September 13, 2016

THE ROAD TO HARBOR BRIDGE:Achieving Environmental Clearance on

a Major Project for the State of Texas

October 11, 2016

September 13, 2016

Richard O’Connell

Associate General Counsel

Christopher Amy,

Environmental Specialist

September 13, 2016

US 181 Harbor Bridge Project

3

Constructed 1956-1959

Replacing the existing US 181

Harbor Bridge and

approaches over the Corpus

Christi Ship Channel.

2005-2007 Project Scoping

2010 FHWA determined EIS

developed under SAFETEA-LU

Procedures

2011 Published NOI to

prepare EIS

FHWA the lead Federal agency

with TxDOT as the joint lead

agency for the project

EPA, HUD & USCG were

Cooperating AgenciesCourtesy of Corpus Christi Caller Times

September 13, 2016

US 181 Harbor Bridge Project

4

September 13, 2016

Harbor Bridge Public Involvement

5

Public Hearing Store Front Meetings

September 13, 2016

Developing Harbor Bridge Mitigation

6

September 13, 2016

Developing Harbor Bridge Mitigation

7

TxDOT and FHWA Commitments to

the Neighborhood

Implement Recreational

Enhancements

– Implement park mitigation

– Construct hike & bike trails

Noise Mitigation

Host Job Fairs

Provide Information on Workforce

Support

Develop Northside Neighborhood

Livability Plan

– Develop Historical Record of

neighborhoods

– Identify neighborhood needs and ideas

September 13, 2016

The FEIS was published in November 2014

In March of 2015, FHWA received a complaint under Title VI of the Civil Rights Act

US 181 Harbor Bridge FEIS

September 13, 2016

US 181 Harbor Bridge FEIS

September 13, 2016

ROD signed January 8, 2016

Record of Decision

September 13, 2016

Voluntary Resolution Agreement

11

September 13, 2016

Voluntary Resolution Agreement

12

September 13, 2016

Community Advisory Board (CAB)

Meetings Monthly

• Where: (Oveal Williams Senior Center)

• First Meeting was held May 12th

Meetings will be professionally facilitated;

Open to the public;

• Citizens provide input during the public comment period

TxDOT responsibilities

– Collaborate with CAC on implementation of Agreements:

• Voluntary Acquisition

• Relocation Benefits

• Voluntary Restrictive Covenant

• Tenant relocation at D.N. Leathers

• 4(f) mitigation for T.C. Ayers and H.J. Williams Parks

– Document Meetings with CAB for update to FHWA

13

September 13, 2016

Lessons Learned