AFFORDABLE HOUSING

BWEYOGEREREGALAXY APARTMENT

Work Progress Photos From 1ST To 15TH NOV 2015

Painting work almost complete

Pavement, Compound wall & Security Cabin almost complete

Terrace – Plumbing work, color, flooring almost complete

Flooring Painting & Cleaning in Staircase & Lobbies complete

Internal Painting & Cleaning complete

Kitchens ready with Tiles, Plumbing etc complete

Flooring, coloring, electrical, plumbing, cleaning etc complete in all Apartments

All doors fixed in place and provided with latest locks &

handles

ToiletsBedroomsBalconies complete in all

respectToilets complete in all respect