I-95 BRUCKNER
EXPY
PELHAM PKWY
HUTCHINSON RIVER PKWY
X731.27 – BRUCKNER ACCESS AND CONNECTIVITY IMPROVEMENTS
DATE: 04/10/2019
2
Agenda• Background• Project status• Next steps • Schedule• Questions & Answers
3
Project Area – Bronx
N
PELHAM PKWY
THROGS NECK EXPRESSWAYCROSS BRONX
EXPRESSWAY
BRONX RIVER PARKWAY
HUTCHINSON RIVER PARKWAY
BRUCKNER EXPRESSWAY
4
Project Goals
• Address peak hour recurring congestion on the northbound I-95 in the vicinity of the Pelham Parkway interchange
• Enhance safety
• Improve access to Co-Op City from the northbound Hutchinson River Parkway
• Improve pedestrian and bicycle paths (shared use paths)
5
Project Focus AreaBruckner Expy./ Pelham Parkway Interchange
N
PELHAM PKWY
HUTCHINSON RIVER PKWY
I-95 (BRUCKNER EXPY)
PELHAM BAY PARK
I-95(NEW ENGLAND
THRUWAY)
GUN HILL RD
CO-OP CITY
AMTRAK/METRO-NORTH RAILROAD
BRUCKNER BLVD
PELHAM BAY
SUBWAY STATION # 6 TRAIN
METRO-NORTH CO-OP CITY STATION
(FUTURE)
BRONX VICTORY
MEMORIAL
6
N
HUTCHINSON RIVER PARKWAY
BAY PLAZA SHOPPING CENTER
BARTOW AVENUE
CO-OP CITY
HUTCHINSON RIVER
Project Focus AreaHutchinson River Parkway near Bartow Ave.
7
NEW RAMP FROM PELHAM
PARKWAY
ADDITION OF A TRAVEL LANE
(4 LANES TOTAL)
NEW TRAFFIC SIGNAL
RAMPS TO BE REMOVED
NEW ACCELERATION
LANE
NEW SIGNALIZED INTERSECTION
RAMP TO BE REMOVED
NEW SIGNALIZED INTERSECTION
Proposed Work (Interchange)N
8
Proposed Work (HRP / Bartow Ave.)N
NEW RAMP FROM HUTCHINSON
RIVER PARKWAY
NEW SIGNALIZED INTERSECTION
BAY PLAZA SHOPPING CENTER
CO-OP CITY
HUTCHINSON RIVER
9
NB HRP Access to Co-op City – Existing and Proposed
Current path from NB HRP to Co-Op City
New route from NB HRP to Co-Op City after construction
N
I-95 BRUCKNER
EXPY
PELHAM PKWY
HUTCHINSON RIVER PKWY
CO-OP CITY
BAY PLAZA MALL
10
Impacts and Mitigation
• Impactso Land for new ramps
o Removal of mature trees
• Mitigationso Documentation of historic features
o Planting of new trees
o Interpretive sign on history
11
Project Status• Completing preliminary design phase, advancing to final design
• Draft Design Report/Environmental Assessment and Individual Section 4(f) document has been completed.
o Adverse impact on Bronx Victory Memorial Grove
o Adverse impact on Pelham Bay Park
• Coordinated with New York City Department of Transportation (NYCDOT) to obtain concurrence for the project
• Coordinated with New York State Thruway Authority (NYSTA) to produce Right Of Way acquisition maps
• Coordinated with New York City Department of Parks and Recreation. (NYCDPR)
12
Next Steps• Final design phase• Coordination required with the following agencies
o Federal Highway Administration (FHWA)o New York State Thruway Authority (NYSTA)o New York State Department of Environmental Conservation (NYSDEC)o New York City Department of Environmental Protection (NYCDEP)o New York City Department of Parks and Recreation (NYCDPR)o New York State Historic Preservation Office (SHPO)o New York City Department of Transportation – Division of Street Lighting and
Traffic Signalso Metropolitan Transportation Authority – New York City Transit
• Utilities : Consolidated Edison (Con Ed), Verizon, Riverbay Corporation,New York City Fire Department (FDNY), Intelligent Transportation Systems (ITS)
• Anticipated permitso NYSDEC SPDES General Permito NYCDPR Construction Permito NYCDOT-OCMC Permit
13
Project Schedule• Design Approval – Summer 2019• 90%Plan– Spring 2020• Final Plans– Summer 2020• Bids Due – Fall 2020• Construction Starts – Late Fall 2020• Construction – 18 to 24 months
14
Construction Staging• 5 stages • Roadways and shared-use paths will be
constructed concurrently• All mainline lanes and shared use paths will be
open during all stages of construction