Test Strategies in Agile Projects
2(29)
Contents
Agile development and testing
Test methods, tools and planning
Definition of Done
User Stories
Test ideas and guidelines
Test charters and exploratory
testing
Logging and reporting
When to stop testing
3(29)
Agile Development
Focus on rapid delivery of business value
Reducing risks
Continuous planning and feedback
Value demonstrated
Self-organizing teams
4(29)
Agile Testing
An iterative process from a customer's perspective
Testing is performed early and often
Testers are part of the development team
“User Stories” are tested
Close cooperation with developers and customers
Continuous integration and regression tests
All test results are logged
Defects are reported
5(29)
Scrum Overview
Product Backlog
Sprint Backlog
Daily
Sprint
Meeting
Sprint2 – 4 WeeksSprint
Plan
Risk
Analysis
Retrospective
Release
Plan Definition
of Done
Task Board
Burndown Chart
Release
Criteria
6(29)
Agile Testing Quadrants
Functional Tests
Examples
Story Tests
Prototypes
Simulations
Exploratory Testing
Scenarios
Usability Testing
UAT
Alpha/BetaQ2 Q3
Q1 Q4Unit Tests
Component
Tests
Performance
& Load Testing
Security Testing
“ility” Testing
Automated
& Manual
Automated Tools
Business-Facing
Technology-Facing
Supp
ort
ing the T
eam E
valu
ate
Pro
duct
Manual
Bri
an
Mari
ck's
agile
te
sting
matr
ix
7(29)
Find out what the Customer Values the Most
Importance
Weight %
Customer
SatisfactionQuality Attribute
User/Customer Value Analysis
Priority
IW / CS
4. Performance 20 1,1 18
2. Availability 15 0,8 18
1. Reliability 30 0,9 33
5. Service Level 10 1,0 10
6. Maintainability 5 0,8 6
3. Usability 20 1,1 18
Summary: 100 % X=0,96
Also analyze the complexity of the system including all valid and prioritized combinations of features and platforms
Risk/Cost
of failure
Supplier
costs
Customer
costsX < 1: Less satisfied
X > 1: More satisfied
High Critical
High Critical
Medium High
High Critical
High High
Medium Low
8(29)
Test Methods and Techniques
Requirements based testing
Design based testing
Risk based testing
Exploratory testing
Error guessing
Taxonomy based testing
Attack based testing
Model based testing
Scenario based testing
Combinatorial testing
Value based testing
Prototyping
9(29)
Three Different Views
User What do the user want to do with the system?
System What should the system be capable of doing?
Risks What problems may occur?
10(29)
How to Explore and Learn
11(29)
Test Planning
What
Why
Who
Where
When
How
Dependencies
Risks
Prio
Time
12(29)
Useful Tools for Agile Testinghttp://www.opensourcetesting.org/ http://www.satisfice.com/tools.shtml
Allpairs Test Case Generation Tool for combinatory testing
PICT Generation of combinatorial tests using orthogonal
arrays http://www.pairwise.org/tools.asp
Perlclip Testing of text fields or documents with different kinds
of stressful inputs
SpectorPro Logging/recording of all activities on a PC
http://www.spectorsoft.com/
TestExplorer Session based ET http://www.testexplorer.com
Session Tester An exploratory testing tool for managing and recording
session-based testing http://sessiontester.openqa.org/
Resource Viewer Is intended for viewing of resources in executable files
http://www.glocksoft.com/resource_viewer.htm
Rasta Keyword Driven Test Automation
http://rasta.rubyforge.org/index.html
List of Testing Tools: http://www.aptest.com/resources.html
13(29)
Definition of Done
Feature Story(-ies) or product backlog item(s)
Sprint A collection of features developed within a Sprint
Release Potentially shippable parts
Example, feature overview:
User management
Add new
Delete
ListSort
Paging
Search
Tags
Smart search
Regular expressions
Clone
Edit
14(29)
Definition of Done – Unit Level
Test Aspect Criteria for Done
Structure based testing
100% Software Design and Module Specifications covered
100% Statement Coverage of the source code
Boundary Value Analysis Testing
Equivalence Classes and Input Partitioning Testing
All Test Cases passed and no remaining faults to be corrected
All code reviewed
Known weaknesses described
Component testing reported (including obtained test coverage)
Integration testing
Internal and external interfaces in the sub-system covered by verifying protocols and syntax in all messages
More than 40% of all tests are negative test cases
15(29)
Definition of Done – Functional Level
Test Aspect Criteria for Done
Functional testing
100% requirements coverage.
100% coverage of the main flows in the operational scenarios.
100% of the highest risks covered.
100% of externally observable system states covered.
100% of externally observable failure modes covered.
Operational manuals tested.
All failures found are reported.
Boundary Values, Equivalence Classes and Input partitioning testing made for all input data.
All combinations of input and output parameters and values covered (pair-wise coverage).
16(29)
User Stories 1(2)
Card:
As a registered user, I want to log in, so I can access subscriber content
Conversation: User Login
Username:
Password:
LoginRemember me
[Message] Forgot password?
Store cookie if
ticked and login
successful
User’s email address,
Validate format
Authenticate against SRS
using the new web service
Go to forgotten password page
Display message here if not successful.
(See confirmation scenarios on the next page)
17(29)
User Stories 2(2)
Confirmation:
Success Valid user logged in and referred to the home page
a) Valid user name and password
b) “Remember me” ticked – Store cookie/automatic login next time
c) “Remember me” not ticked – Manual login next time
d) Password forgotten and a correct one is sent via email
Failure Display message:
a) “Email address in wrong format”
b) “Unrecognized user name, please try again”
c) “Incorrect password, please try again”
d) “Service unavailable, please try again”
e) Account has expired – refer to account renewal sales page
18(29)
Test Questions
- Which user/usage goals should be met?
- What user problems should be solved?
- Which user benefits should be achieved?
- Why does the orderer/customer want the system?
- Who are the customer(s) and the target user group?
- Which functions and characteristics are included?
- What are the most common and critical parts of the functionality from the users point of view?
- Are there any performance requirements included?
- What is an acceptable response time for the users?
- How tolerant should the system be to faulty input or user actions?
19(29)
Test Ideas
What do we need to find out about the system?------------------------------
1 What happens if …………………………………..?
2 What should happen when ………………………..?
3 Will the system be able to fulfil all its requirements?
4 What are the expectations and needs from the customer?
5 In what way may the system fail?
6 What problems were found in the previous release?
7 Are the requirements and the input specifications possible to
understand and test (sufficient testability)?
8 Will the system be reliable and resist failure in all situations?
9 Will the system be safe in all configurations and situations
it will be used?
10 How easy is it for real users to use the system?
11 How fast and responsive is the system?
12 Is it easy to install (and configure) onto its target platform?
13 How well does it work with external components and configurations?
14 How effectively can the system be tested (e.g. can log files be read)?
20(29)
Guidelines for Agile Testing 1(2)
1. Test in pairs
2. Prepare test charters in advance
3. Use exploratory testing
4. Build tests incrementally
5. Use test design patterns
6. Perform keyword/data driven tests
21(29)
Guidelines for Agile Testing 2(2)
7. End-to-end testing
8. Scenario based testing
9. Use automation for test data generation and execution
10.Frequent regression testing
11.Documentation testing
12.Log everything you do
22(29)
Test Charter 1(3)
Actor < Type of user >
Purpose < Describe the function, web page , test idea, … to be tested >
Setup < Preconditions i.e. concerning HW, content of data base(s),.. >
Priority < Importance of risk, function, web page, …. >
Reference(s) < Requirement, risk, test ideas, … >
Data < Whatever is needed for the activities, files >
Activities < A list of actions and test ideas >
Oracle notes < How to evaluate the product for correct results >
Variations < Alternative actions and evaluations >
Test Charter no # and <title>
23(29)
Test Charter 2(3)Test Charter 1: Analyze the copy/paste function of pictures
Actor: Normal user.
Purpose: To evaluate if the copy/paste function of pictures works in our word processor together with the most commonly used word processors on the market (Word, Power Point., etc.) and other programs where pictures can be inserted in the copy buffer for copy/paste operations in the PC. The purpose is also to see that no information is lost or corrupted.
Setup: A Dell PC with 2 Gb memory, our word processor, the Microsoft Office package professional and the home edition 2003 patch level xx, PDF reader version 7.1, Notepad version 4, Internet Explorer version 7, Opera version 5, Mozilla……etc. (the setup might be common for several charters and can therefore be described and referred to instead of repeating the same information in every charter).
Priority: High, because this function is used very frequently both within our own word processor, but also between other word processors and programs, the user may want to copy/paste pictures with ours.
Reference: Requirement abc_1 in document Def-07:034 revision R1.1. Risk number 3 from the risk assessment held on April 4 2007 regarding the copy function, which is documented and followed up in the document Rsk-07:012.
Data: A variety of pictures with different resolutions, both vector graphics as well as bit mapped pictures. The pictures could be photos or figures in web browsers for example. Complex pictures are also included and pictures which might be copy protected in some way.
24(29)
Test Charter 1: Analyze the copy/paste function of pictures, continued….
Activities: 1. Copy/paste a picture in our word processor from one location to another in the same document.
2. Copy/paste a picture to and from our word processor into/from Word, PowerPoint and Excel.
3. Copy a picture into our word processor from a variety of the mostly used Web browsers.
4. Copy/paste a picture to/from the most commonly used web site building tools such as Dreamweaver from Adobe.
5. Copy a picture from a PDF document using Acrobat Reader into our word processor.
6. Try to copy a write protected picture from the web or other source into our word processor.
7. Try to copy/paste a variety of non readable and some readable ASCII-characters or corrupted pictures.
Oracle Look if the size of the pasted picture changed on the screen (it should not).
notes: Check if there is any loss in the resolution of the picture especially when you copy and paste from other programs to or from ours.
Check which is the highest resolution picture that can be copied and how that affect the system.
Check for memory leaks and how much memory the copy/paste operation takes from the system and how that affects the use of other programs. Other programs should not slow down or be affected in any way.
Print pasted pictures to see if there are any differences in color, resolution or any other anomaly.
Variations:Try out (and find) the boundaries of how large pictures are possible to copy/paste.
Perform copy/paste with a large number of items in the copy/paste buffer in your PC.
Try to fill the copy/paste buffer to its limit and then copy/paste a picture and see what happens.
Try the longest file name of the picture you can type before making the copy/paste. You may use the tool Perlclip (download from http://www.satisfice.com/tools/perlclip.zip) to generate file names with a million characters or more if you want.
Test Charter 3(3)
25(29)
Exploratory Test Execution
1. Observe
2. State questions
3. Form hypothesis
4. Design the experiment
5. Test the hypothesis
6. Draw conclusions
7. State additional questions
The scientific approach
26(29)
A Program can Fail in many Ways
System
under
test
Program state
System state
Intended inputs Monitored outputs
Configuration and
system resources
Input from other cooperating
processes, clients or servers
Program state, including
uninspected outputs
System state
Impacts on connected
devices/system resources
Output to other cooperating
processes, clients or servers
27(29)
Exploratory Test Execution Logging
Use a logging tool:
Log everything you do
Information is traceable
Complement with an API logger/sniffer
Your notes show your reasoning while testing
Exploratory testing requires good logging
28(29)
Medium
Medium
High
Low
Low
Current
risk
level
Q
ass.
3
2
1+
2+
0
W 6
High
Pause
Blocked
High
None
Current
test
effort
Medium
High
High
Medium
Low
Initial
Risk
Level
Medium
High
High
Medium
Low
Needed test
effort
IR1212 under investigation.1+1+1+11Area 4
Crashes, IR123451+11Area 3
On track, no faults.221+11Area 2
Feature(s) not yet delivered
from design and integration.
Definition of Done not
fulfilled for functional testing.
No testing possible.
00Area 1
3
W 5
2+
W 4
2+
W 3
2
W 2
1
W 1
Configuration problems.Area 5
CommentsTest
area
Test effort and perceived Quality Level – Including risks and test coverage
Test Reporting
29(29)
All planned/required Test Charters/sessions and characteristics tests have been run and passed according to the current risk areas/levels and where faults have been found. The coverage objectives have been reached that were stated in the test goals (e.g. System Requirements, User Stories).
CoverageTesting should stop when:
• The probability of remaining faults has been reduced to a level that can be accepted by the customer.
• No open priority A Incident Reports.
• The systems’ risk level is within acceptable limits (i.e. no critical risks remain unsolved).
• The Definition of Done for all testing activities have been fulfilled.
• The product values have been demonstrated and accepted (i.e. implicit and explicit quality attributes are satisfied).
Quality
When the agreed ship date has been reached.
Time
When to Stop Testing