SHIFT2RAIL JOINT UNDERTAKING
ANNUAL ACTIVITY REPORT 2014
Approved by the S2R Governing Board, on 31 March 2015, in accordance with
Article 20 of the Statutes of the S2R JU annexed to Council Regulation (EU) No
642/2014 and with Article 20 of the Financial Rules of the S2R JU.
2
Contents
Contents .................................................................................................................................................. 2
FACTSHEET .............................................................................................................................................. 4
INTRODUCTION ....................................................................................................................................... 6
1 OPERATIONS .................................................................................................................................... 7
1.1 Key objectives 2014 and associated risks ................................................................................ 7
1.1.1. Preparatory actions for S2R JU autonomy ...................................................................... 7
1.1.2. Development of the strategic Master Plan ..................................................................... 8
1.1.3. Call for Associated Members of the S2R JU .................................................................... 9
1.2 Research activities ................................................................................................................. 11
1.3 Calls for proposals and grant information ............................................................................. 11
1.4 Progress against KPIs / Statistics (Annex C) ........................................................................... 12
1.5 Operational budget execution .............................................................................................. 12
2 SUPPORT ACTIVITIES ..................................................................................................................... 12
2.1 Communication activities ...................................................................................................... 12
2.2 Legal and financial framework .............................................................................................. 13
2.3 Budgetary and financial management .................................................................................. 14
2.4 Procurement and contracts ................................................................................................... 15
2.5 Housing, IT and logistics ........................................................................................................ 15
2.6 Human Resources .................................................................................................................. 15
3 GOVERNANCE ................................................................................................................................ 16
3.1 Governing Board .................................................................................................................... 16
3.2 Executive Director ................................................................................................................. 17
3.2.1. States Representatives Group ............................................................................................. 17
3.2.2. Scientific Committee ........................................................................................................... 19
3.3 Innovation Programme’s Steering Committees .................................................................... 19
3.4 European Railway Agency ..................................................................................................... 19
4 INTERNAL CONTROL FRAMEWORK ............................................................................................... 19
4.1 Financial Procedures ............................................................................................................. 19
4.2 Ex-ante Controls on operational Expenditure ....................................................................... 20
4.3 Ex-post Control of Operational Expenditure and Error Rates Identified .............................. 20
4.4 Audit of the European Court of Auditors .............................................................................. 20
4.5 Internal Audit ......................................................................................................................... 20
3
4.6 Risk management .................................................................................................................. 20
4.7 Compliance and effectiveness of Internal Control ................................................................ 20
5 MANAGEMENT ASSURANCE ......................................................................................................... 21
5.1 Assessment of the Annual Activity Report by the Governing Board ..................................... 21
5.2 Elements supporting assurance ............................................................................................ 21
5.3 Results from audits during the reporting year and follow up of previous audits ................. 21
5.4 Reservations .......................................................................................................................... 21
5.5 Overall conclusion ................................................................................................................. 21
6 OBJECTIVES AND MAIN MILESTONES FOR 2015 ........................................................................... 21
7 DECLARATION OF ASSURANCE ...................................................................................................... 22
8 ANNEXES ........................................................................................................................................ 23
ANNEX A Organisational chart of the S2R JU .................................................................................... 23
ANNEX B Establishment plan ............................................................................................................. 24
ANNEX C Indicators and Scoreboard of KPIs ..................................................................................... 25
ANNEX D Draft Annual accounts ....................................................................................................... 36
4
FACTSHEET
Name Shift2Rail Joint Undertaking (S2R JU)
Objectives
The Shift2Rail Joint Undertaking (S2R JU) is a new public-private partnership in the rail sector, providing a platform for cooperation that will drive innovation in the years to come. The S2R JU will pursue research and innovation activities in support of the achievement of the Single European Railway Area and improve the attractiveness and competitiveness of the European rail system.
Shift2Rail will contribute to:
• a 50 % reduction of the life-cycle cost of the railway transport system (i.e. costs of building, operating, maintaining and renewing infrastructure and rolling stock);
• a 100 % increase in the capacity of the railway transport system;
• a 50 % increase in the reliability and punctuality of rail services (measured as a 50 % decrease in unreliability and late arrivals).
Founding Legal Act Council Regulation (EU) No 642/2014 of 16 June 2014
Executive Director Mr Christos ECONOMOU, Executive Director Ad Interim
Governing Board
EC members:
Mr João AGUIAR MACHADO, Chair, DG MOVE Director General
Mr Rudolf STROHMEIER, DG RTD Deputy Director General
EC alternates:
Ms Magda KOPCZYNSKA, DG MOVE Director C
Ms Manuela SOARES, DG RTD Director H
Industry members (until 31/12/2014):
Mr Nicolas Castres-Saint-Martin (ALSTOM)
Mr Giovanni Bocchetti (ANSALDO STS)
Mr Josef Doppelbauer (BOMBARDIER)
Mr José Gortazar (CAF)
Mr Jerry England (NETWORK RAIL)
Mr Roland Edel (SIEMENS)
Mr Christian Gregoire (THALES)
Mr Bo Olsson (TRAFIKVERKET)
Industry alternates:
Mr Daniel Cadet (ALSTOM)
Mr Antonio Ruggieri (ANSALDO STS)
Mr Markus Dengler (BOMBARDIER)
Mr Aitor Galarza (CAF)
5
Mr Andrew Doherty (NETWORK RAIL)
Mr Lars Bergmann (SIEMENS)
Mr Yves Perreal (THALES)
Mr Christer Löfving (TRAFIKVERKET)
Other participants:
Mr Christos Economou (Executive Director ad Interim of the S2R JU
Observers
Mr Richard Lockett / Ms Sarah Young (European Railway Agency)
Mr Jaime Martinez Real (Chairman of the States Representatives Group)
Other bodies
Scientific Committee
States Representatives Group
Programme Office of the Executive Director
Innovation Programmes' Steering Committees
Staff 4 (On-going staff recruitment)
2014 Budget Voted budget EUR 988 800. EUR 494 400 of contributions collected.
Budget
implementation Administrative expenditure only
Grants No grants were signed in 2014
Strategic Research
Agenda
The draft Shift2Rail Master Plan was approved by the S2R JU Governing Board on 24 September 2014 (http://ec.europa.eu/transport/modes/rail/doc/2014-09-24-draft-shift2rail-master-plan.pdf). The Commission adopted a proposal for a Council Decision endorsing the Shift2Rail Master Plan on 16 December 2014.
Call implementation Number of calls launched in 2014: No calls for proposals were launched in 2014.
A call for Associated Members to the S2R JU was issued on 6 October 2014.
Number of applications submitted: 43
Number of eligible applications: 40
The call is a two-stage procedure. The evaluation of the first-stage submissions should
be finalised in Q1 2015. The second stage will then be launched with a view to
finalising membership negotiations in the autumn of 2015.
Participation,
including SMEs
Total n° of participations in funded projects: N.A. as no grant agreements were signed
in 2014.
6
INTRODUCTION
The Shift2Rail Joint Undertaking (S2R JU) is a new public-private partnership for rail research,
providing a platform for the rail sector as a whole to work together with a view to driving innovation
in the years to come. Officially established on 7 July 2014, the S2R JU will pursue research and
innovation activities in support of achieving the Single European Railway Area and improving the
attractiveness and competitiveness of the European rail sector. It seeks to provide a platform for rail
equipment manufacturers, infrastructure managers, railway undertakings, rail research organisations
and all other relevant stakeholders to work together and coordinate their R&I efforts with a view to
driving innovation in the years to come.
The S2R JU will manage an estimated budget of at least €920 million (for the period 2014-2024) to
coordinate Research & Innovation activities in the rail sector. The budget will be split between the EU
and the industrial partners participating in the S2R JU.
The activities of the S2R JU will benefit all actors in the rail sector. It will help boosting the
competitive edge of the rail supply industry, opening new market perspectives and offering
significant employment and export opportunities. Railway undertakings, infrastructure managers and
public transport operators will benefit from innovations that drastically reduce infrastructure and
operating costs, which should ensure better value for the subsidies paid to rail operators by national
governments.
Shift2Rail aims to deliver:
a reduction, by up to 50%, in the life-cycle cost of railway transport (i.e. costs of building,
operating, maintaining and renewing infrastructure and rolling stock);
an overall increase in capacity of up to 100% and
an overall increase in reliability of up to 50% in the different rail market segments.
More generally, it should support the Union's policy of making rail a more attractive mode, as part of
the overall objectives of increasing transport capacity, reducing congestion and reducing oil use for
climate change and fuel security reasons.
7
1 OPERATIONS
1.1 Key objectives 2014 and associated risks
The Shift2Rail Joint Undertaking ('S2R JU') was officially established on 7 July 2014 following the
adoption by the Council of Regulation (EU) N°642-2014 establishing the Shift2Rail Joint Undertaking
on 16 June 2014 ('S2R Regulation').
There were three main objectives for the S2R JU in 2014:
Preparatory actions for S2R JU autonomy: As a newly established JU, activities in 2014 were
principally focused on the setting up of the S2R JU, including putting in place an appropriate
governance structure and fulfilling all the preparatory actions to lead to the operational
independence of the S2R JU;
Development of the strategic Master Plan: It was essential to rapidly develop this key
strategic document due to the fact that the adoption procedure foreseen in Article 1(4) of
Annex I to the S2R Regulation is lengthy (the document first needs to be approved by the
Governing Board, then endorsed by the Council, acting on a proposal from the adopted by
the Governing Board, before being adopted by the Governing Board), and yet is a key pre-
requisite for the call for associated members to the JU and the adoption of the first S2R JU
annual work plans, in accordance with Article 2 of Annex I to the S2R Regulation;
Implementation of the call for associated members of the S2R JU: In accordance with Article
4(4) of Annex I to the S2R Regulation, the first call for associated members to the S2R JU had
be launched within three months at the latest following the establishment of the S2R Joint
Undertaking (i.e. by 7 October 2014 at the latest).
1.1.1. Preparatory actions for S2R JU autonomy
Achieving operational autonomy is a lengthy process that requires the fulfilment of a series of criteria
under which the Commission could agree with the JU on the day of the latter's capacity to implement
its own budget.
These criteria include the establishment of the bodies of the S2R JU (as listed in Article 5 of the S2R
Statutes, namely, the Governing Board, Executive Director, Scientific Committee and States
Representatives Group), the adoption of basic legal, administrative and financial documents,
procedures and budgets, the recruitment of key staff and the finalisation of housing arrangements.
An overview of the main actions undertaken in 2014 relating to these criteria can be found in the
following sections of the document.
Until achieving operational autonomy (i.e. achieving the capacity to implement its own budget), the
S2R JU remains under the responsibility of the European Commission and all its initial operations are
run by the Commission, in collaboration with the other founding members (Article 19 of the Council
Regulation establishing the S2R JU).
8
In accordance with the same article, the Commission designated an interim Executive Director of the
S2R JU on 9 July 2014 to exercise the duties that are assigned to the Executive Director in the S2R
Regulation.
The interim Executive Director is assisted by a limited number of Commission officials. He may
authorise all payments covered by the appropriations provided in the annual budget of the S2R JU,
once approved by the Governing Board, and conclude agreements, decisions and contracts, including
staff contracts following the adoption of the S2R JU's staff establishment plan.
The autonomy of the S2R JU is planned for the 3rd quarter of 2015 when all autonomy criteria are
planned to be met.
The date for achieving autonomy of the JU is technically contingent on the deployment of a
dedicated ABAC accounting system, which, in turn, is conditional on the recruitment of a number of
key staff, including the S2R JU Executive Director.
The main risks associated to the autonomy of the S2R JU are therefore related to possible delays in
the recruitment of the S2R JU Executive Director and to the deployment of a functioning ABAC
environment. To manage these risks, close scrutiny on the appointment and ABAC related processes
has been established by DG Mobility & Transport. A Service level Agreement has been signed
between the JU and the relevant Commission service (DG BUDG) setting up a timetable for the
implementation of ABAC in 2015.
1.1.2. Development of the strategic Master Plan
In accordance with Article 1(4) of the S2R Statutes, the S2R JU had to develop a Shift2Rail strategic
Master Plan, defining the priority research and innovation activities to drive innovation in the rail
sector in the long term, and structured around the five following thematic areas or 'Innovation
Programmes’ (‘IPs’):
IP1: Cost-efficient and Reliable Trains, including high capacity trains and high speed trains;
IP2: Advanced Traffic Management & Control Systems;
IP3: Cost-efficient, Sustainable and Reliable High Capacity Infrastructure;
IP4: IT Solutions for Attractive Railway Services;
IP5: Technologies for Sustainable & Attractive European Freight.
Given the Master Plan's status as the key strategic document to focus all EU-funded R&I efforts in the
future, as well as a reference document for the call for associated members and for the first S2R JU
annual work plans, the main risks associated to the development of the Master Plan were related to
possible delays in the adoption procedure and to the need to ensure broad stakeholder adherence to
the document.
In light of these challenges, the founding members of the S2R JU, including the Union, elaborated a
first draft of the Master Plan, in consultation with the European Railway Agency (ERA) and the
European Rail Research Advisory Council (ERRAC) Technology Platform already in the first two
quarters of 2014.
9
Numerous individual meetings with sector representatives were also held, and a public consultation
meeting held on 20 June 2014, to which close to 200 stakeholders took part. The consultation
revealed that the draft of the Master Plan as elaborated by the founding members was well balanced
and broadly supported.
On 24 September 2014, the Governing Board of the S2R JU approved the Master Plan1. On the basis
of this stable document, it was possible to launch the call for associated members. Furthermore, the
Commission adopted a proposal for a Council Decision endorsing the Shift2Rail Master Plan on 16
December 2014. It is expected that the Council will endorse the Master Plan in Q1 2015.
The Master Plan is a living document that may be updated by the Governing Board of the S2R JU
once the associated members have been selected and the Governing Board of the S2R JU reaches its
full composition (i.e. including representatives of selected associated members as foreseen in Article
6 of the S2R Statutes).
1.1.3. Call for Associated Members of the S2R JU
A crucial milestone in 2014 was the launch of the call for the selection of associated members to the
S2R JU. Indeed, in accordance with Article 4 of Annex I of the Council Regulation establishing the S2R
JU, the first call for associated members had to be launched at the latest three months after the
establishment of the S2R JU.
In agreement with the Governing Board of the S2R JU, the Commission successfully launched the call
on 6 October 20142.
The call document (Ref. S2R JU/AM/01/20143) listed the conditions and procedures for applications,
as well as a detailed list of selection and evaluation criteria. The deadline for applications was 12
November 2014 and the Commission received 43 applications. These included 27 applications by
single legal entities (SLEs) and 16 applications on behalf of consortia, so that a total of 127 entities
applied. 7 applications were made by stakeholders from the rail operating community (ROC), i.e.
railway undertakings (RU), infrastructure managers (IM) or urban operators (URBAN) either as SLEs
or consortia. The research community (research centres or universities) was also rather well
represented in applications either as SLEs or consortia. Finally, there were 4 applications from SMEs
as single entities and a further 18 SMEs were involved in consortia.
The following table provides information on the representation of SMEs, the research community, the rail operating community and large industry, among the entities applying.
Organisation type SMEs ROC (RU / IM /
Urban) RESEARCH CENTRES
/ UNIVERSITIES LARGE
INDUSTRY TOTAL
Total number of entities 22 23 33 49 127
Share of total applications 17% 18% 26% 39% 100%
1 http://ec.europa.eu/transport/modes/rail/doc/2014-09-24-draft-shift2rail-master-plan.pdf
2 Commission Decision N° C(2014) 7084 final
3 http://ec.europa.eu/transport/modes/rail/news/doc/2014-10-06-shift-to-rail-call/2014-10-06-call-associated-member-s2rju.pdf
10
In terms of geographical representation, there were significantly more applications from entities established in EU-15 countries than in the central and eastern Member States, as seen in the graph below.
Finally, all Innovation Programmes (IPs) identified in the draft S2R Master Plan4 were covered by applicants, as were, to a lesser extent, the Cross-Cutting Activities (CCA). Overall, the sum of proposed contributions on indirect actions (projects) reached M€ 474, i.e. a more than three-time over-subscription compared to the expected overall contribution from associated members to the JU foreseen in the S2R Regulation (M€ 150). Generally all IPs were largely "over-subscribed", in particular IP2, IP3 and IP5. As indicated in the following table, almost three quarters of the applicants' proposed contributions were concentrated on IP1, IP2 or IP3.
CCA IP1 IP2 IP3 IP4 IP5 Total
CONSORTIA 2 7 4 10 2 6 16
SLEs 4 12 14 6 9 7 27
Total 6 21 20 18 11 13 43
Amount of the proposed own contributions
(indirect actions)
M€ 7 M€ 135 M€ 111 M€ 105 M€ 43 M€ 73 M€ 474
Percentage (compared to the
total commitment) 1,5% 28,5% 23,4% 22,1% 9,2% 15,4% 100,0%
The evaluation procedure of the first stage of the call was initiated in November 2014 and is
expected to be completed in March 2015.
The main risk associated to this procedure is to ensure a non-discriminatory and transparent process,
that enables the Commission to make the final decision on a manageable number of associated
members to the S2R JU, that provide for the key capabilities required to to implement the S2R
Master Plan, while also ensuring geographical balance, as well as balanced participation of SMEs, of
4 http://ec.europa.eu/transport/modes/rail/shift2rail_en.htm
11
the research community and of actors from the entire rail value chain, including from outside the
traditional rail sector, in accordance with Article 4(4) of Annex I to the S2R Regulation.
In order to ensure that this was the case, the Governing Board of the JU, who is tasked with the
transparent evaluation of applications, in accordance with Article 4(2) of Annex I to the S2R
Regulation, decided to delegate the evaluation to independent experts. The evaluation process has
therefore been centrally managed by the Commission, with regular reports to the Governing Board.
1.2 Research activities
As the Shift2Rail JU is currently in its set-up phase, it has not yet begun any research activities. The
first calls or invitations for proposals are expected to be published in 2015.
However, in drafting and approving the first version of the Shift2Rail Strategic Master, the S2R JU has
already made progress on further defining the objectives of the different innovation programmes
and the associated priority research areas.
Furthermore, the S2R JU invited the founding members other than the Union to submit technical proposals to
the Shift2Rail multiannual action plan on 25 September 2014, with a deadline of 10 November 2014.
The evaluation by independent experts of these technical submissions was organised in December 2014, with a
view to elaborating a scoping paper for the draft Shift2Rail multiannual action plan, to serve as a reference
document for the second stage of the selection procedure for associated members. The scoping paper
represents a first draft prioritisation of the activities foreseen in the Master Plan, taking into account the S2R
JU's available budget for the period 2014-2024.
1.3 Calls for proposals and grant information
The S2R JU did not launch any calls or invitations for proposals in 2014.
However, a call for proposals was launched by the Commission under its Work Programme 2014-
2015 of Horizon2020, and specifically under the Challenge “Smart, green and integrated transport”,
call “Mobility for Growth”, topic 2 "Rail". The call included the three following topics for a maximum
budget of EUR 52 million:
MG.2.1-2014.I²I – Intelligent Infrastructure
MG.2.2-2014. Smart rail services
MG.2.3-2014. New generation of rail vehicles
Although this call was launched by the Commission, the work programme specified that “the
selected proposals will contribute to the objectives of the initiative to be implemented under a
public-private partnership (Shift2Rail) as they will later be integrated into the activities of this
partnership”.
Furthermore, Article 4 of the S2R Regulation foresees that the management of these projects may be
taken over by the S2R JU once it achieves the operational capacity to implement its own budget.
The first stage of the 2014 call was closed on 18 March 2014. A total of 33 proposals were received,
of which two were ineligible. The proposals were evaluated remotely, by independent experts, from
14th April 2014 – 23rd May 2014.
12
Following the first stage evaluation, a total of 13 proposals were invited to stage 2. The deadline for
second stage submissions was 28 August 2014. All 13 proposals were successfully submitted by the
applicants by this deadline and were deemed eligible. The proposals were evaluated by independent
experts from 15 September to 14 October 2014, first remotely, then centrally in Brussels. A decision
of the Commission on the list of projects to be funded and reserve lists will be adopted at the
beginning of the year 2015.
1.4 Progress against KPIs / Statistics (Annex C)
Since the S2R JU was established in mid-2014, the definition of the Key Performance Indicators (KPIs)
was not completed by December 2014. A draft list of KPIs has been elaborated by the Commission
aiming at the establishment of 3 groups of indicators, namely:
Horizon 2020 Key Performance Indicators5 common to all JTI JUs;
Indicators for monitoring H2020 Cross-Cutting Issues6 common to all JTI JUs;
Key Performance Indicators specific for S2R JU.
In future, the Annual Work Plans will provide KPIs. They will clearly set out how the planned activities
will contribute to the achievement of objectives set, listing the respective KPIs and taking into
account the allocated resources and the identified risks.
Furthermore, one of the core tasks of the S2R JU will be to develop a model to monitor the progress
towards the objectives laid down in the S2R Regulation. It will develop a suitable methodology for
gathering and exploiting the necessary data to measure these impacts, and for assessing the optimal
combination of technology developments to achieve these KPIs.
1.5 Operational budget execution
Since no grants were signed by the S2R JU during 2014, no operational budget has been executed.
2 SUPPORT ACTIVITIES
2.1 Communication activities
A number of communication activities were organised to ensure political and public awareness about
the S2R JU's activities. As new Joint Undertaking, the main objective was to foster awareness towards
EU and national policy makers, as well as stakeholders of the railway sector.
A major point of attention in communication activities was the need to ensure the involvement of
stakeholders from the entire rail value chain, including actors from outside the traditional rail sector,
from the very start of the process, in defining the R&I strategy of the S2R JU.
5 (based on Annex II to Council Decision 2013/743/EU)
6 (based on Annex III to Council Decision 2013/743/EU)
13
To this end, the Commission organised a large number of meetings and exchanges with stakeholders
in the railway sector (such as UNIFE (rail supply industry), CER (incumbent railway undertakings), UIP
(wagon keepers), EIM (independent infrastructure managers), UITP (urban transport operators) and
EPTO (private passenger transport operators)) on the content of the Shift2Rail strategic Master Plan.
This consultation process was rounded off by the organisation of a major stakeholder consultation
meeting on 20 June 2014, to which close to 200 stakeholders took part.
The Commission and the Interim Executive Director of the S2R JU also participated in meetings and
conferences organized in Brussels and in some EU Member States in order to disseminate
information about S2R JU activities, in particular:
Participation in the JU-JTI call launch on 9 July 2014 – Shift2Rail was associated in the event
for the launch of the activities of all seven European Joint Undertakings.
Participation in the InnoTrans international faire trade organised in Berlin in September
2014.
Presentations to the ERRAC plenary session of November 2014 and to the ERRAC Permanent
Advisory Groups in July 2014.
Participation in the Spanish Shift2Rail Information Day in Madrid in October 2014, marking
the launch of the call for Associated Members.
Presentations within various rail and/or research stakeholder fora (UNIFE general assembly
June 2014, CLORA (Club des Organismes de Recherche Associés), etc.
A fact-sheet was also produced and disseminated during the launch of the S2R JU on July 9. It gathers
general information as well as facts and figures about S2R JU activities.
The DG MOVE website has been regularly updating its content related to all activities executed
during 2014: organisation of events, publication of the S2R Master Plan, launch of the S2R JU call for
associated members, S2R JU governance members, S2R JU vacancies, frequently asked questions
section, etc.
The S2R JU has also initiated in 2014 the procedure for the purchase and creation of a visual identity
and communication materials (www.shift2rail.org website, etc.). Following discussions in the
Governing Board, it was decided to engage in a dialogue with the JU industry partners, in particular
UNIFE, to organise the purchase (transfer of ownership) of the existing website, logo, social network
accounts, which have been created by the S2R promoters during the preparatory phase. This process
is expected to be completed in 2015.
2.2 Legal and financial framework
The legal framework refers to:
Council Regulation (EU) N°642/2014 of 16 June 2014 establishing the Shift2Rail Joint Undertaking
(OJ L 177, 17.6.2014, p. 9).
Regulation (EU) No 1291/2013 of the European Parliament and of the Council of 11 December
2013 establishing Horizon 2020 — the Framework Programme for Research and Innovation for
the period 2014-2020 and repealing Decision No 1982/2006/EC (OJ L 347, 20.12.2013, p. 104), as
well as Regulation (EU) No 1290/2013 of the European Parliament and of the Council of 11
14
December 2013 laying down the rules for participation and dissemination in Horizon 2020 (OJ L
347, 20.12.2013, p. 81).
The Financial Rules of the S2R JU, as adopted by the Governing Board of the S2R JU on 30 July
2014.
2.3 Budgetary and financial management
The Governing Board of the S2R JU adopted its yearly budgets for 2014 and for 2015 on 15 October
2014. The budgets consist of the statements of revenue and expenditure for each year, together with
the staff establishment plans.
The total budget of the S2R JU for 2014 was EUR 998 800, split equally among the Commission and
the non-Commission members, to cover staff costs and administrative expenditures only. No
operational budget was included as the JU did not launch any research and innovation actions in
2014. The adopted budget was in fully line with the initial estimates from the Commission regarding
the budgetary needs during the JU's start-up phase7.
In accordance with Article 19 of the S2R Regulation, the Executive Director ad Interim of the S2R JU
and the European Commission were in charge of executing the S2R JU budget in 2014.
This meant that payments to third parties (beneficiaries, suppliers, staff) were carried out by the
Commission from the JU budget lines and administered following the provisions of the Financial
Regulation. All financing decisions, budgetary commitments, legal commitments were co-signed by
the JU’s legal representative – Interim Executive Director – and the Commission’s authorising officer
by delegation.
In terms of execution of the administrative budget for 2014, the following points should be noted:
The budget needs of the S2R JU were lower than expected due, among others, to the fact that
DG MOVE accommodated the S2R JU free of charge during the start-up phase, until the S2R JU
obtains its own premises. Costs related to the rental of buildings, movable property, IT
infrastructure and equipment, etc. were therefore postponed until 2015.
The late adoption of the budget 2014 meant that the first financial commitments of the
Commission on behalf of the S2R JU could only take place at the end of the year, thereby
resulting in a limited number of payments in 2015. The main payments in 2014 were in relation
to the payment of first staff members taking the office in late 2014, as well as the payment of
meeting costs (Governing Board meetings, meeting of the States Representatives Group and
expert meetings for the evaluation of applications under the call for associated members);
As regards the payment of the 2014 contributions of the founding members to the administrative
expenditures of the JU, the Governing Board agreed that these payments should be claimed by
the JU in 2015 in addition to the 2015 contributions, due to the limited needs in 2014.
2.4 Procurement and contracts
In 2014, S2R JU did not launch any procurement procedures. 7 COM(2013) 922 final
15
2.5 Housing, IT and logistics
In the context of the "initial actions" as described in Article 19 of the S2R Regulation, the staff of the
S2R Joint Undertaking is currently located in the premises of DG MOVE and benefits from its IT and
logistical infrastructures.
The interim Executive Director initiated actions in 2014 aiming to identify appropriate office space in
Brussels. After investigating different alternatives, it was decided to house the S2R JU in the same
building as the other previously established Joint Undertakings, such as Clean Sky, IMI or FCH in the
"White atrium" building, located at 56 Avenue de la Toison d'Or in Brussels.
The related rental contract is expected to be signed in early 2015 and the S2R JU will benefit from
similar conditions to the other JUs.
This decision is in line with the Commission Communication "la politique d'installation des services
de la Commission à Bruxelles et à Luxembourg"8, which clearly recommends the gathering of EU
services in a smaller number of larger buildings. In particular, this can be done by enabling EU
services to increase their "share" in buildings where they rent only part of the building.
This option has the advantage of allowing for the development of clear synergies between the JUs
(same IT infrastructure, shared meeting rooms, shared IT and other support services, same secured
connection with Commission building, etc.).
2.6 Human Resources
In addition to the recruitment process for the Executive Director, the S2R Joint Undertaking initiated
on 10 July 2014 two procedures to recruit the first staff of the JU, namely 3 Programme Managers
and 1 Accounting Officer. The vacancy notices were published on the website of EPSO and the
website run by the Shift2Rail promoters.
Four recruitment processes were completed in 2014 and two members of the staff (programme
officers) already took office in November and December 2014. An additional programme officer as
well as the accountant of the JU, who also had been recruited, will take office in January 2015.
In accordance with the staff establishment plan, the recruitment of the JU staff will continue to
progress in 2015 with a view to have the team complete by 2016. Service level Agreements have
been signed with the relevant Commission services (DG HR and PMO) aiming to facilitate the
recruitment, remuneration, training, etc. of the JU staff.
3 GOVERNANCE
In accordance with Article 5 of Annex I of the Council Regulation establishing the S2R JU, the bodies
of the S2R Joint Undertaking are: (a) the Governing Board; (b) the Executive Director; (c) the Scientific
Committee; (d) the States Representatives Group.
8 COM(2007)501
16
3.1 Governing Board
The Governing Board of the JU was formally established after the 8 Founding Members of the S2R JU
other than the Union listed in Annex II to the S2R Regulation (rail equipment manufacturers Alstom,
Ansaldo STS, Bombardier, Construcciones y Auxiliar de Ferrocarriles (CAF), Siemens and Thales, and
infrastructure managers Network Rail (UK) and Trafikverket (SE)) formally accepted the S2R Statutes
and once all founding members, including the Union, nominated their representatives and alternate
representatives to the Board.
In accordance with the S2R Regulation, the JU Governing Board is currently composed of two
representatives from the Commission and one representative from each of the founding members of
the S2R Joint Undertaking other than the Union. Once the procedure for selecting associated
members will be completed and the Steering Committees for each Innovation Programme (IP) have
been formed, the number of representatives in the Governing Board will be extended to include
representatives from the Associated Members, on the basis of the shortlists proposed by the IP
Steering Committees. .
In line with the provisions of the S2R Statutes, a representative of the European Railway Agency and
the chairperson of the States Representatives Group have also been invited to attend meetings of
the Governing Board as observers and take part in its deliberations, but with no voting rights.
The composition of the Governing Board in 2014 is as follows:
Main representative Alternate
EUROPEAN COMMISSION (DG MOVE) João Aguiar Machado Magda Kopczynska
EUROPEAN COMMISSION (DG RTD) Rudolf Strohmeier Manuela Soares
ALSTOM Nicolas Castres-Saint-Martin Daniel Cadet
ANSALDO STS Giovanni Bocchetti Antonio Ruggieri
BOMBARDIER Josef Doppelbauer Markus Dengler
CAF José Gortazar Aitor Galarza
NETWORK RAIL Jerry England Andrew Doherty
SIEMENS Roland Edel Lars Bergmann
THALES Christian Gregoire Yves Perreal
TRAFIKVERKET Bo Olsson Christer Löfving
Three meetings of the Governing Board were organised in 2014:
30 July 2014
15 October 2014
16 December 2014
Asides from dealing with the preparation and adoption of all the basic legal, administrative and
financial documents required with a view to achieving operational autonomy, the Board worked on
preparing the Shift2Rail Strategic Master Plan, which sets out the research and innovation priorities
of the S2R JU and on the implementation of the call for Associated Members to the S2R JU.
The following decisions were approved by the Board:
17
Decision N°1/2014 - Rules of procedure of the Governing Board of the Shift2Rail Joint
Undertaking: The document circulated prior to the meeting was approved subject to some
minor amendments agreed during the meeting (see point 4 below).
Decision N°2/2014 - Financial rules of the Shift2Rail Joint Undertaking: The document
circulated prior to the meeting was approved with no amendments (see point 5 below).
Decision N°3/2014 - Approval of the Shift2Rail Strategic Master Plan (decision taken by
written procedure)
Decision N°4/2014 - The budget and establishment plan of the S2R JU for 2014 and for 2015
Decision N°5/2014 - A decision in principle of the establishment of user requirements
working groups, a system integration working group and an implementation and deployment
working group. These groups will assist the JU in fulfilling its objectives and promoting an
inclusive approach to the widest range of stakeholders. The Governing Board tasks the
Executive Director with initiating the process for drafting the terms of reference of these
groups and making a proposal for the procedure and timing of their establishment.
Decision N°6/2014 - The process and criteria for selection of the Shift2Rail Scientific
Committee members. The Governing Board tasks the Executive Director with publishing the
call for the expressions of interest for the selection of Members of the Scientific Committee
of the Shift2Rail Joint Undertaking by 22 October.
3.2 Executive Director
In accordance with Article 19 of the S2R Regulation, the European Commission has appointed an
Executive Director ad Interim, Mr. Christos Economou from DG MOVE on 09 July 2014.
In parallel, the recruitment process for the position of Executive Director was also launched on 25
July 2014 (vacancy notice COM/2014/10363). The vacancy notice was published on the website of
EPSO and the website run by the Shift2Rail promoters. The deadline for applications was 22
September 2014. 44 applications were received. The selection procedure for this position is still
ongoing and is expected to be completed by mid- 2015.
3.2.1. States Representatives Group
Following the entry into force of the S2R Regulation, Members States and countries associated to the
Horizon 2020 framework programme were asked to nominate their representatives to the States
Representatives Group, in accordance with Article 14 of the S2R Statutes. To date, the 27 countries
have nominated representatives to the Group. The list is as follows:
Country Name First Name Organisation
Albania Gjermeni Leonidha Deputy Administrator of the Albanian Railways
Austria Krautsack Sarah Austrian Federal Ministry for Transport, Innovation and Technology
Belgique Geens Peter FOD Mobiliteit en Vervoer
Croatia Lazor Damir Ministry of Maritime Affairs, Transport and Infrastructure
Cyprus Lambrinos Michael Public Works Department, Ministry of Communications & Works
18
Czech Republik Haltuf Miroslav Independent expert, H - Comp consulting
Denmark Selsmark Niels Danish Transport Authority
Estonia Haidak Toomas Ministry of Economic Affairs and Communications
Finland Hilska Lassi Ministry of Transport and Communications
France Cheron Christophe Ministère de l'Écologie, du Développement durable et de l'Énergie
Germany Küpper Wolfgang Head of Unit LA 10, Railway Policy, at the Federal Ministry of Transport and Digital Infrastructure
Greece AGIASOGLOU Stefanos Ministry of Infrastructure, Transport and Networks
Hungary Gecse Gergely Ministry of National Development - Department for Transport Infrastructure
Italy Violi Alessandro Ministero delle Infrastrutture e dei Trasporti - Dipartimento Trasporti nel Gruppo consultivo a supporto dell'impresa comune Shift2Rail
Latvia Riekstiņš Māris Deputy Director of the Department of Railway, Ministry of Transport
Lithuania Tamulis Vidmantas
Head of the Railway Transport Division of the Water and Railway Transport Policy Department of the Ministry of Transport and Communications
Luxembourg Poeker Jeannot Inspecteur Principal
Netherlands van der Burg
Rob Ministry of Infrastructure and Environment, department Rail Transport
Norway Rognes Ingunn Norwegian Ministry of Transport and Communications
Portugal
Afreixo Nunes da Cruz
José Manuel Instituto da Mobilidade e dos Transportes, I.P.
Romania Anoaica Dragoş Ministry of Transport
Slovakia Magdechová Katarína Ministry of Transport, Construction and Regional Development of the Slovak Republic
Slovenia Pregl Miloš Ministry of Infrastructure
Spain Martínez Real Jaime Ministry of Transport
Turkey Ay Mustafa TUBITAK
Ukraine Kulachok Volodymyr Head of Division of Economic Analysis in Rail Sector / ministry of Infrastructure
United Kingdom Brown Chris Rail Technical International and Safety Team of the Rail Executive of the Department for Transport in the UK
A first meeting of the States Representatives Group was organised on 16 October 2014 in Brussels.
The States Representatives Group adopted its rules of procedures at its first meeting. It also
proceeded with the election of the Chair and Vice-Chair persons. In December 2014, the SRG also
adopted by written procedure a list of recommended nominees for the Scientific Committee.
3.2.2. Scientific Committee
The S2R Joint Undertaking launched the selection procedure of its Scientific Committee on 21
October 2014 through the publication of an open call for expression on interest, in accordance with
Article 13 of the S2R Statutes. The call document (Ref. S2R JU/SC/01/20149) lists the eligibility
9 http://ec.europa.eu/transport/modes/rail/news/doc/2014-10-22-shift-to-rail-call/call-members-scientific-
committee.pdf
19
conditions, evaluation and selection criteria and procedures for applications. The deadline for
applications was 22 December 2014.
The call was published on the website of DG MOVE and the website of the S2R promoters
(www.shift2rail.org). In accordance with the S2R Regulation, the call was also advertised through the
ERRAC technology platform, the European Railway Agency and the States Representatives Group,
who were invited to nominate potential candidates.
61 applications were received in response to the call, of which 55 were male applicants and 6 were
female applicants. The applications were received from applicants representing 17 different EU
Member States and 5 non-EU Member States. Among these, 24 candidates received nominations
from the States Representatives Group and/or ERRAC.
1 application was deemed ineligible. 1 application was deemed inadmissible. The selection panel will
complete the evaluation of the application in the first months of 2015 and the S2R Scientific
Committee is expected to be established in the first half of 2015.
3.3 Innovation Programme’s Steering Committees
The Shift2Rail Regulation foresees the establishment of Steering Committees for each Innovation
Programme (Article 11 of the Statutes). However, these will only be established once the associated
members have been selected. Each Steering Committee will have to adopt its rules of procedure,
based on a common model approved by the Governing Board.
3.4 European Railway Agency
Article 12 of the Shift2Rail Statutes clarifies the areas of cooperation between the Shift2Rail Joint
Undertaking and the European Railway Agency. A number of meetings have been organised with the
staff of ERA during the drafting of the Master Plan. Moreover, ERA has been present in all meetings
of the S2R Governing Board, in which it participated as an observer (cf. 3.1).
4 INTERNAL CONTROL FRAMEWORK
4.1 Financial Procedures
As the S2R JU has not yet obtained its financial autonomy, the budgetary and financial management
of the S2R JU is integrated in EC DG Mobility and Transport financial management, according to the
Commission's financial procedures. The S2R JU manual of Financial Procedures will be prepared in
line with Article 17(3) of the financial rules of the S2R JU and incorporated to the ABAC
Implementation. The main purpose of the document is to describe the financial circuits, identify
actors and detail check lists on the implementation of S2R JU budget. The financial circuits will take
into account the structure of S2R JU and the risks associated with the management environment.
They will be established in order to standardise the mandatory steps of the processing of financial
transactions.
20
4.2 Ex-ante Controls on operational Expenditure
No operational expenditures were executed in 2014, thus no ex-ante controls on these were
implemented.
4.3 Ex-post Control of Operational Expenditure and Error Rates
Identified
N.A.
4.4 Audit of the European Court of Auditors
N.A.
4.5 Internal Audit
N.A.
4.6 Risk management
During 2014 S2R JU risk management was integrated in EC DG Mobility and Transport Risk
management.
Within the Commission Risk Management is defined as:
"A continuous, proactive and systematic process of identifying, assessing, and managing risks in line
with the accepted risk levels, carried out at every level of the Commission to provide reasonable
assurance as regards the achievement of the objectives".
Practically, risk management is about taking the necessary time to identify and carefully assess
potential problems (risks) that could affect the execution of the organisation's activities and the
achievement of its objectives. The risks are prioritised according to their relative significance, and
actions are taken to reduce them to a "tolerable" level. Hence, the aim is neither to avoid risks at all
costs, nor to reduce the risk to zero. Indeed, a certain degree of risk-taking is necessary to keep the
organisation dynamic.
For background information, see the Communication to the Commission - "Towards an effective and
coherent risk management in the Commission services" (SEC(2005)1327).
4.7 Compliance and effectiveness of Internal Control
The Internal Control Standards and the Internal Control Framework are under preparation.
The Internal Control Framework (ICF) will aim to help the JU to address different types of
management issues and risks, so that reasonable assurance regarding the proper execution of the
whole operational system can been gained.
Internal Control Standards will be based on the same principles as applied by the Commission and
adapted to the JU's context and specificities. The JU's ICS will have to be adopted by the Governing
21
Board and provide generic management principles and set out the minimum requirements for the
control activities.
5 MANAGEMENT ASSURANCE
5.1 Assessment of the Annual Activity Report by the Governing Board
The Annual Activity Report 2014 was sent to the Governing Board on 4 March 2015 and the Executive
Director presented the report during the Governing Board meeting on 31 March.
The Board is of the opinion that this documents sets out the relevant highlights of the
implementation of the 2014 activities of the Joint Undertaking from both an administrative and
operational point of view. The accuracy and completeness of the various activities had been
improved during the initial set-up phase of the JU carried out by the European Commission. This
document clearly reports on the achievements of the objectives set for the first year: the level of
achievement is considered satisfactory.
5.2 Elements supporting assurance
5.3 Results from audits during the reporting year and follow up of
previous audits
5.4 Reservations
5.5 Overall conclusion
6 OBJECTIVES AND MAIN MILESTONES FOR 2015
Activities in 2015 will principally be focused on completing the establishment of the S2R JU, including
further preparatory actions to lead to the operational independence of the S2R JU, as well as the
continuation of activities started in 2014 with a view to launching the JUs first activities.
In particular, the JU is expected to finalise the recruitment procedure for the Executive Director of
the JU, and to recruit other key staff members (Head of Programme, legal officer, financial assistant,
communications officer, HR assistant, etc.).
The implementation of the ABAC system should also progress, enabling the JU to achieve financial
autonomy, subject to the conditions provided for under Article 19 of the S2R Regulation (initial
actions). At the same time, the JU will normally move into the White Atrium building, a further step
towards its administrative and operational autonomy. .
23
1 ANNEXES
ANNEX A Organisational chart of the S2R JU
24
ANNEX B Establishment plan
Staff population 2014* 2015**
Est
abli
shm
ent
pla
n p
ost
s
Officials
AD
AST
AST/SC
TA
AD 14 1 1
AD 9 1 2
AD 8
1
AST
AST/SC
Total 2 4
Exte
rnal
Per
sonnel
CA GFIV 2 5
CA GF III 1 3
CA GF II 1 2
CA GFI
Total CA 4 10
SNE
Structural service
providers
TOTAL 6 14
External staff for
occasional
replacement
* Staff population in voted EU Budget
** Staff population in Draft EU Budget
25
ANNEX C Indicators and Scoreboard of KPIs
TABLE I
Horizon 2020 Key Performance Indicators1 common to all JTI JUs
Co
rre
spo
nd
en
ce t
o g
en
era
l A
nn
ex
1
Key Performance Indicator Definition/Responding to
question Type of data required Data to be provided by
Baseline at the start of H2020
(latest available)
Target at the end of H2020
Automated
IND
UST
RIA
L LE
AD
ERSH
IP
12
SME - Share of participating SMEs introducing innovations
new to the company or the market (covering the period
of the project plus three years);
Based on Community Innovation Survey (?). Number and % of participating SMEs that have
introduced innovations to the company or to the market;
Number of SMEs that have introduced innovations;
H2020 beneficiaries through project reporting
n.a. [new approach
under H2020]
50%
Yes
13 SME - Growth and job creation in participating SMEs
Turnover of company, number of employees
Turnover of company, number of employees;
H2020 beneficiaries through project reporting
n.a. [new approach
under H2020]
to be developed based on FP7 ex-post
evaluation and /or first H2020 project
results
Yes
SOC
IETA
L
CH
ALE
NG
ES
14 Publications in peer-reviewed high impact journals in the
area of the JTI
The percentage of papers published in the top 10% impact
ranked journals by subject category.
Publications from relevant funded projects (DOI: Digital Object Identifiers); Journal
impact benchmark (ranking) data to be collected by commercially available bibliometric databases.
H2020 beneficiaries through project reporting;
Responsible Directorate/Service (via access to appropriate
bibliometric databases)
n.a. [new approach
under H2020]
[On average, 20 publications per €10 million funding (for
all societal challenges)]
Yes
1 (based on Annex II to Council Decision 2013/743/EU)
26
Co
rre
spo
nd
en
ce t
o g
en
era
l A
nn
ex
1
Key Performance Indicator Definition/Responding to
question Type of data required Data to be provided by
Baseline at the start of H2020
(latest available)
Target at the end of H2020
Automated
15 Patent applications and patents awarded in the area
of the JTI
Number of patent applications by theme; Number of awarded
patents by theme
Patent application number H2020 beneficiaries through project reporting;
Responsible Directorate/Service (via
worldwide search engines such as ESPACENET, WOPI)
n.a. [new approach
under H2020]
On average, 2 per €10 million funding
(2014 - 2020) RTD A6 Yes
16 Number of prototypes testing activities and clinical trials2
Number of prototypes, testing (feasibility/demo) activities,
clinical trials
Reports on prototypes, and testing activities, clinical trials
H2020 beneficiaries through project reporting
n.a. [new approach
under H2020]
[To be developed on the basis of first
Horizon 2020 results]
Yes
17 Number of joint public-private publications in
projects
Number and share of joint public-private publications out of all
relevant publications.
Properly flagged publications data (DOI) from relevant
funded projects
H2020 beneficiaries through project reporting;
Responsible Directorate/Service (via DOI
and manual data input-flags)
n.a. [new approach
under H2020]
[To be developed on the basis of first
Horizon 2020 results]
Yes
18* New products, processes, and methods launched into the
market
Number of projects with new innovative products, processes,
instruments, methods, technologies
Project count and drop down list allowing to choose the type processes, products,
instruments, methods, technologies
H2020 beneficiaries through project reporting
n.a. [new approach
under H2020]
[To be developed on the basis of first
Horizon 2020 results] Yes
EVA
LUA
TIO
N
NA
Time to inform (average time in days) all applicants of the
outcome of the evaluation of their application from the
final date for submission of completed proposals
To provide applicants with high quality and timely evaluation
results and feedback after each evaluation step by implementing and monitoring a high scientific
level peer reviewed process
Number of days (average) Joint Undertaking
FP7 latest know results?
Yes
2 Clinical trials are IMI specific
27
Co
rre
spo
nd
en
ce t
o g
en
era
l A
nn
ex
1
Key Performance Indicator Definition/Responding to
question Type of data required Data to be provided by
Baseline at the start of H2020
(latest available)
Target at the end of H2020
Automated
NA
Time to inform (average time in days) successful applicants
of the outcome of the evaluation of their
application from the final date for submission of completed proposals
Number of days (average) Joint Undertaking
FP7 latest know results
Yes
NA
Redress after evaluations To provide applicants with high quality and timely evaluation
results and feedback after each evaluation step by implementing and monitoring a high scientific
level peer reviewed process
Number of redresses requested
Joint Undertaking
FP7 latest know results
GR
AN
TS NA
Time to grant measured (average) from call deadline to signature of grants
To minimise the duration of the granting process aiming at
ensuring a prompt implementation of the Grant Agreements through a simple
and transparent grant preparation process
Cumulatively in days Average under H2020 (days) TTG < 270 days ( as %of GAs
signed)
Joint Undertaking (automatized)
n.a. [new approach
under H2020]
Yes
NA
Time for signing grant agreements from the date of informing successful applicants (average values)
Average under H2020 (days)
Joint Undertaking
n.a. [new approach
under H2020]
Yes
AU
DIT
S
NA Error rate % of common representative
error; % residual error CAS n.a. [new
approach under H2020]
Yes
NA
Implementation of ex-post audit results
Number of cases implemented; in total
€million; ´of cases implemented/total cases
CAS n.a. [new approach
under H2020]
Yes
28
Co
rre
spo
nd
en
ce t
o g
en
era
l A
nn
ex
1
Key Performance Indicator Definition/Responding to
question Type of data required Data to be provided by
Baseline at the start of H2020
(latest available)
Target at the end of H2020
Automated
PA
YM
ENTS
NA
Time to pay (% made on time)
-pre-financing - interim payment
-final payment
To optimize the payments circuits, both operational and
administrative, including payments to experts
Average number of days for Grants pre-financing, interim
payments and final payments;
Average number of days for administrative payments;
Number of experts appointed
Joint Undertaking
FP7 latest know results
-pre-financing (30 days)
- interim payment (90 days)
-final payment ((90days)
Yes
HR
NA
Vacancy rate (%) % of post filled in, composition of the JU staff 3
Joint Undertaking
n.a. [new approach
under H2020]
JU E
FFIC
IEN
CY
NA
Budget implementation/execution:
1. % CA to total budget 2. % PA to total budget
realistic yearly budget proposal, possibility to monitor and report
on its execution, both in commitment (CA) and payments (PA), in line with sound financial
management principle
% of CA and PA Joint Undertaking
100% in CA and PA
Yes
NA
Administrative Budget: Number and % of total of late
payments
realistic yearly budget proposal, possibility to monitor and report
on its execution in line with sound financial management
principle
Number of delayed payments % of delayed payments (of
the total)
Joint Undertaking
Yes
NOTES: 18* This indicator is not a legally compulsory one, but it covers several additional specific indicators requested for more societal challenges by the services in charge.
3 Additional indicators can be proposed/discussed with R.1 and/or DG HR
29
TABLE II
Indicators for monitoring H2020 Cross-Cutting Issues4 common to all JTI JUs
Co
rre
spo
nd
e
nce
in t
he
ge
ne
ral
An
ne
x 2
Cross-cutting issue
Definition/Responding to question Type of data required Data to be provided by
Data to be provided
in/to
Direct contributio
n to ERA
Automated
2
Wid
en
ing
the
par
tici
pat
ion
2.1 Total number of participations by EU-28 Member State Nationality of H2020 applicants & beneficiaries (number of )
H2020 applicants & beneficiaries at the submission and grant agreement signature stage
JU AAR RTD
Monitoring Report
YES Yes
2.2 Total amount of EU financial contribution by EU-28 Member State (EUR millions)
Nationality of H2020 beneficiaries and corresponding EU financial contribution
H2020 beneficiaries at grant agreement signature stage
JU AAR RTD
Monitoring Report
YES Yes
NA Total number of participations by Associated Countries Nationality of H2020 applicants & beneficiaries (number of )
H2020 applicants & beneficiaries at the submission and grant agreement signature stage
JU AAR RTD
Monitoring Report
YES Yes
NA Total amount of EU financial contribution by Candidate Country (EUR millions)
Nationality of H2020 beneficiaries and corresponding EU financial contribution
H2020 beneficiaries at grant agreement signature stage
JU AAR RTD
Monitoring Report
YES Yes
3
SMEs
par
tici
pat
ion
3.1 Share of EU financial contribution going to SMEs (Enabling & industrial tech and Part III of Horizon 2020)
Number of H2020 beneficiaries flagged as SME; % of EU contribution going to beneficiaries flagged as SME
H2020 beneficiaries at grant agreement signature stage
JU AAR RTD
Monitoring Report
Yes
4 (based on Annex III to Council Decision 2013/743/EU)
30
Co
rre
spo
nd
e
nce
in t
he
ge
ne
ral
An
ne
x 2
Cross-cutting issue
Definition/Responding to question Type of data required Data to be provided by
Data to be provided
in/to
Direct contributio
n to ERA
Automated
6
Ge
nd
er
6.1 Percentage of women participants in H2020 projects Gender of participants in H2020 projects
H2020 Beneficiaries through project reporting
YES Yes
6.2 Percentage of women project coordinators in H2020 Gender of MSC fellows, ERC principle investigators and scientific coordinators in other H2020 activities
H2020 beneficiaries at the grant agreement signature stage
YES Yes
6.3 Percentage of women in EC advisory groups, expert groups, evaluation panels, individual experts, etc.
Gender of memberships in advisory groups, panels, etc.
Compiled by Responsible Directorate/ Service/Joint Undertaking based on existing administrative data made available by the CSC
YES
7
Inte
rnat
ion
al
coo
per
atio
n
7.1 Share of third-country participants in Horizon 2020 Nationality of H2020 beneficiaries H2020 beneficiaries at the grant agreement signature stage
JU AAR RTD
Monitoring Report
YES Yes
7.2 Percentage of EU financial contribution attributed to third country participants
Nationality of H2020 beneficiaries and corresponding EU financial contribution
H2020 beneficiaries at the grant agreement signature stage
JU AAR RTD
Monitoring Report
YES Yes
31
Co
rre
spo
nd
e
nce
in t
he
ge
ne
ral
An
ne
x 2
Cross-cutting issue
Definition/Responding to question Type of data required Data to be provided by
Data to be provided
in/to
Direct contributio
n to ERA
Automated
9
Bri
dgi
ng
fro
m d
isco
very
to
mar
ket
5
9.1 Share of projects and EU financial contribution allocated to Innovation Actions (IAs)
Number of IA projects Project Office – at GA signature stage he/she will be required to flag on SYGMA. Responsible Directorate/Service (WP coordinator)/Joint Undertaking - via tool CCM2
JU AAR RTD
Monitoring Report
Yes
9.2 Within the innovation actions, share of EU financial contribution focussed on demonstration and first-of-a-kind activities
Topics properly flagged in the WP; follow-up at grant level
Responsible Directorate/Service (WP coordinator)/Joint Undertaking - via tool CCM2
JU AAR RTD
Monitoring Report
Yes
NA Scale of impact of projects (High Technology Readiness Level)
Number of projects addressing TRL6 between…(4-6, 5-7)?
Joint Undertaking JU AAR RTD
Monitoring Report
11
Pri
vate
se
cto
r
par
tici
pat
ion
11.1 Percentage of H2020 beneficiaries from the private for profit sector
Number of and % of the total H2020 beneficiaries classified by type of activity and legal status
H2020 beneficiaries at grant agreement signature stage
JU AAR RTD
Monitoring Report
Yes
11.2 Share of EU financial contribution going to private for profit entities (Enabling & industrial tech and Part III of Horizon 2020)
H2020 beneficiaries classified by type of activity; corresponding EU contribution
H2020 beneficiaries at grant agreement signature stage
JU AAR RTD
Monitoring Report
Yes
12
Fun
d
ing
for
PP
Ps
12.1 EU financial contribution for PPP (Art 187) EU contribution to PPP (Art 187) Responsible Directorate/Service/
JU AAR RTD
Yes
5 This indicator (9.2) is initially intended to monitor the Digital Agenda (its applicability could be only partial)
6 TRL: Technology Readiness Level
32
Co
rre
spo
nd
e
nce
in t
he
ge
ne
ral
An
ne
x 2
Cross-cutting issue
Definition/Responding to question Type of data required Data to be provided by
Data to be provided
in/to
Direct contributio
n to ERA
Automated
Monitoring Report
12.2 PPPs leverage: total amount of funds leveraged through Art. 187 initiatives, including additional activities, divided by the EU contribution
Total funding made by private actors involved in PPPs - in-kind contribution already committed by private members in project selected for funding - additional activities (i.e. research expenditures/investment of industry in the sector, compared to previous year)
Joint Undertaking Services
JU AAR RTD
Monitoring Report
13
Co
mm
un
icat
ion
and
dis
sem
inat
ion
13.3 Dissemination and outreach activities other than peer-reviewed publications - [Conferences, workshops, press releases, publications, flyers, exhibitions, trainings, social media, web-sites, communication campaigns (e.g radio, TV)]
A drop down list allows to choose the type of dissemination activity. Number of events, funding amount and number of persons reached thanks to the dissemination activities
H2020 Beneficiaries through project reporting
JU AAR RTD
Monitoring Report
YES Yes
14
Par
tici
pat
ion
pat
tern
s o
f
ind
epen
den
t ex
pe
rts
14.2 Proposal evaluators by country Nationality of proposal evaluators Responsible Directorate/Service/Joint Undertaking in charge with the management of proposal evaluation
14.3 Proposal evaluators by organisations' type of activity Type of activity of evaluators' organisations
Responsible Directorate/Service/Joint Undertaking in charge with the management of proposal evaluation
YES
33
Co
rre
spo
nd
e
nce
in t
he
ge
ne
ral
An
ne
x 2
Cross-cutting issue
Definition/Responding to question Type of data required Data to be provided by
Data to be provided
in/to
Direct contributio
n to ERA
Automated
NA
Par
tici
pat
ion
of
RTO
s an
d
Un
iver
siti
es
Participation of RTO7s and Universities in PPPs (Art 187 initiatives)
Number of participations of RTOs to funded projects and % of the total Number of participations of Universities to funded projects and % of the total % of budget allocated to RTOs and to Universities
H2020 beneficiaries at the grant agreement signature stage
JU AAR RTD
Monitoring Report
YES Yes
NA
Eth
ics
The objective is ensuring that research projects funded are compliant with provisions on ethics efficiently
% of proposals not granted because non-compliance with ethical rules/proposals invited do grant (target 0%); time to ethics clearance 5target 45 days)8
Responsible Directorate/Service/Joint Undertaking
JU AAR RTD
Monitoring Report
Notes:
* H2020 applicants - all those who submitted H2020 proposals
*H2020 beneficiaries - all those who have signed a H2020 Grant Agreement
*Responsible Directorate - DG RTD Directorates and R&I DGs family in charge with management of H2020 activities
*Services -Executive Agencies and other external bodies in charge with H2020 activities
*Project officer - is in charge of managing H2020 projects in Responsible Directorate/Service including Executive Agencies
7 RTO: Research and Technology Organisation 8 Data relates to pre-granting ethics review. This time span runs in parallel to granting process.
34
TABLE III
Draft Key Performance Indicators specific for the S2R JU
# Key Performance Indicator Objective
Data to be provided by
Baseline at the start of H2020
Target at the end of H2020
Automated
S2R
1
% reduction in the costs of developing, maintaining, operating and renewing infrastructure and rolling stock and increase energy efficiency compared to "State-of-the-art"
Reduce the life-cycle cost of the railway transport
system JU "State-of-the-art" 2014 > 50 % No
2
% increase the capacity of railway segments to meet increased demand for passenger and freight railway services compared to "State-of-the-art" 2014
Enhance the capacity of the railway transport system
JU "State-of-the-art" 2014 100% No
3 % decrease in unreliability and late arrivals compared to "State-of-the-art" 2014
Increase in the quality of rail services
JU "State-of-the-art" 2014 > 50% No
4
Reduce noise emissions and vibrations linked to rolling stock and respectively infrastructure compared to "State-of-the-art" 2014
Reduce the negative externalities linked to
railway transport JU "State-of-the-art" 2014 > 3 - 10 dBA No
5 Number of TSI open points closed compared to "State-of-the-art" 2014
Enhance interoperability of the railway system
JU "State-of-the-art" 2014 > 20-30% No
6 Number of Integrated Technology Demonstrators (ITDs) and System Platform demonstrations
Improve market uptake of innovative railway solutions
through large-scale demonstration activities
JU tbd in the Multi Annual
Work Plan Yes
35
# Key Performance Indicator Objective
Data to be provided by
Baseline at the start of H2020
Target at the end of H2020
Automated
7
Share of the fund allocated to the
different Innovation Programmes and to
cross-cutting themes
Ensure that funding covers the railway system as a
whole JU n.a. n.a. No
8 Percentage of topics resulting in signature of GA
Ensure a sufficiently high call topics success rate
JU n.a. > 90% Yes
9 % of resources consumption versus plan (members only)
WP execution by members - resources
JU n.a. > 80% Yes
10 % of deliverables available versus plan (members only)
WP execution by members - deliverables
JU n.a. > 80% Yes
36
ANNEX D Draft Annual accounts
The S2R JU has not yet obtained its financial autonomy. Thus, the financial transactions relating to the JU are integrated in the Annual Accounts of the European Commission.