annual plan 2013-14 - uttarakhandspc.uk.gov.in/upload/contents/file-31.pdfthe "krishi karman...
TRANSCRIPT
ANNUAL PLAN 2013-14
MEETING
[
Address by:
Shri Vijay Bahuguna
Hon'ble Chief Minister of Uttarakhand
At
Planning Commission,
Yojana Bhawan, New Delhi
May 23, 2013
Govt. of Uttarakahand
Hon’ble Deputy Chairman Dr.Ahluwalia Ji, Hon’ble
Members and distinguished officers of the Planning
Commission Sir,
I would like to begin by placing on record my gratitude to you
along with Hon’ble Members and officers of the Planning Commission
for the sustained and proactive support and guidance to us in
formulating and implementing the Twelfth Five Year Plan and the
Annual Plan 2012-13.
Based on our performance during the 10th and the 11th Five Year
Plan we visualized a growth rate of 11 percent for the 12th Five Year
Plan for which investment requirement was estimated to be about
Rs.65300 crores but resource constraints forced us to contain our
proposed plan size at Rs. 57252 crores.
However, the Planning Commission has fixed the target of 9
percent growth for our State during the Twelfth Plan Period and
accordingly reduced the Twelfth Plan size, to Rs.45080 crore. This is
only 52.5% above the actual expenditure during the 11th
Five Year
Plan while in case of the central plan there has been 114%
increase. Hence, I would like to request the Planning Commission
to look into this anomaly and rectify it while approving subsequent
annual plan allocations.
Our proposed Annual Plan for the year 2013-14 is before you.
Keeping in view the State’s limited plan resources, the approved 12th
Plan outlay and the minimum investment required to achieve the given
target of 9 percent average annual growth, a rational plan size of Rs.
8500 crore has been proposed for the year 2013-14 . Although the
requirement as per our Twelfth Five Year Plan stands at about
Rs.10,300 crores.
Taking all the factors into consideration we have enhanced our
annual plan outlay marginally by 3.65 percent over the previous year’s
plan which is even less than the Planning Commission’s suggested
minimum 5 % increase and not enough even to meet the price
escalation.
Salient Features
Broadly we have allotted Rs.4639 crore (54.33 percent) of total
outlay to Economic Services which includes PSE resources also,
Rs.3769 crore (44.35 percent) to Social Services and Rs.102 crore
(1.20 percent) to General Services. Due emphasis has been laid on
building socio-economic infrastructure.
Agriculture & Allied Sector
We are aware of the fact that while the growth rate in
manufacturing sector and services sector had been well above the
national average during the Eleventh Five Year Plan, the growth in
agriculture & allied sector remained 3.2% as compared to the national
average of 3.7%.
The main factor behind this low growth rate has been the
diversion of around 3% of agricultural land for industrial and
urbanization purposes during the 11th plan period and that too in the
high productivity region of the State. This loss has been made up
through appreciable increase in productivity despite lower allocations
for the agriculture and allied sectors.
In recognition of the State's efforts we have been bestowed with
the "Krishi Karman Commendation Award" constituted by the Ministry
of Agriculture, Government of India for the year 2011-12 for
registering ever highest production of food grains.
We are committed to foster higher agricultural growth as about
60% of the population is dependent on agricultural activities alone. We
have promulgated the new 'Agricultural Produce Marketing
Committees Act' on the lines suggested by Government of India, which
provides for setting up of Private Mandi Yards and contract farming
besides a number of reform measures. This enables us to take
advantage of a number of centrally sponsored schemes related to
modernization of Mandis as well as establishment of food storage
godowns.
Though we have kept the share of Agriculture and allied sector at
8.15% of the total outlay but we will review the plan shortly to enhance
it to at least 10% of the total outlay and make provisions accordingly in
the supplementary budget so as to enable us to get higher allocation
under Rashtriya Krishi Vikas Yojana.
We need sufficient funding for creation of infrastructure support
to agriculture like ropeways, collection centres, controlled atmosphere
chambers, seeds processing plants, storage godowns etc. With higher
allocation under RKVY we hope to bridge such infrastructure gaps to
some extent.
Horticulture and Fisheries sectors have great potential for
development in Uttarakhand. We are charting out comprehensive
strategy and work plans to realise the same. In this regard we need
higher allocations under centrally sponsored Horticulture Mission For
North East And Himalayan States (HMNEH) and Agricultural
Mechanization Programmes.
Tourism
Being a hilly state with abundance of natural beauty, tourism
holds an important place in shaping the economy of the State. So far,
being a state of religious importance tourism has been largely based on
pilgrimage. Tourism is one sector which holds better prospects for
promoting pro-poor growth than many other sectors. Now we have
worked out a detailed Master Plan for developing new tourism
destinations across the State.
The Tehri Lake is one of the largest manmade lake which
offers ample opportunities for tourism development and income
generation potential to local population and as a pivot of the economic
and social development in the region. State Govt. has a land bank in
excess of 500 Acres around the Lake. The Hon’ble Minister of State,
Planning, Govt. of India also visited the Lake recently and was
impressed of its potential for tourism and desired that a concept note
for its development be presented to the Planning Commission.
Accordingly we have forwarded an infrastructure development plan of
Rs. 550.75 crore for approval and funding from the Planning
Commission.
Special Component Sub Plan/Tribal Sub Plan (SCSP / TSP)
For focused development of the traditionally deprived
sections of society i.e. Scheduled Castes and Scheduled Tribes outlay
proportionate to their population has been separated from the total plan
outlay. Thus 18 percent of total outlay has been apportioned under
SCSP and 3 percent under TSP and is kept at the disposal of the Social
Welfare Department which has been designated as the nodal
department for this purpose and to ensure effective use of given funds
for the welfare and upliftment of these target groups. Monitoring
mechanism has also been put in place to ensure proper use of the funds.
Women & Child Welfare
Women play a major role in the rural economy of the State.
To have their voice in the development programmes their participation
in different level PRIs is being ensured apart from gender budgeting
and plan allocations for women oriented schemes.
The Annual Health Survey Bulletin 2011-12 released
recently, has shown an improvement in the IMR of Haridwar District
which has come down from 72 to 67. Also would like to highlight that
there is a significant drop in the IMR of females in Haridwar from 75
to 70 as compared to males from 68 to 64. The State Govt has made
efforts to tackle this situation of high IMR in Haridwar by
operationalising 1 SNCU (Special New Born Care Unit), 2 NBSU’s
(New Born Stabilization Unit), 1 NRC (Nutrition Rehabilitation
Centre) and training of ASHAs/ANMs in Home Based Neo-Natal
Care focusing on immunization and early breast feeding.
The State’s IMR has also shown a steady decline which now
stands at 36 as per SRS – 2011. Also as per AHS 2012 Bulletin MMR
of the State has gone down from 188 to 162. However, still a lot needs
to be done in the field of institutional deliveries which is getting
hampered due to shortage of doctors and specialists in the State. The
State is trying to address this shortage by opening new Medical
Colleges at Dehradun and Almora and also trying to rope in private
sector by outsourcing of our CHCs. We hope this will help in
addressing the issue of supply of doctors in coming years.
The issue of decreasing child sex ratio is a cause of concern
for which the State has taken some stronger mandatory steps for the
implementation of PCPNDT Act under which State and District Level
PNDT Cells and Inspection and Monitoring Committees have been
formed, State Supervisory Board and District Supervisory authorities
have been activated and all the registered ultra sonography centres
have been inspected with the seizure of 17 machines and suspension of
licenses of 18 centres. All the registered centres have been asked to
compulsorily upload Form- F on the State Health Website and
intensive IEC and awareness activities were also done.
Major Issues
Sir, I had put forward various problems and issues regarding our
plan resources in the last year’s meeting and again in the 57th meeting
of the National Development Council held on 27th December, 2012 but
there has not been much headway in resolving these issues. Hence,
even at the cost of repetition, I would like to reiterate some of them as
they are critically important for the survival of our State and its people.
1- Funding under SCA & SPA
While presenting the State’s Twelfth Five Year Plan and annual
plan 2012-13, I had highlighted the problems and issues faced by our
State in managing the desired finances for plan investment,
appreciating which the Planning Commission had approved Rs.800
crore under Special Plan Assistance (SPA) and Rs.700 crore under
Special Central Assistance (SCA). However, against submission of
Detailed Project Reports (DPR) worth Rs.1378 Crores, which has been
sanctioned by the Planning Commission and against which works have
already been started, we were sanctioned only Rs.300 crores. Thus,
there is a committed liability of Rs.1080 crores. Hence, taking into
account the committed liability, backlog and new Projects, a total of
Rs.1550 crore under SPA and Rs. 1000 crore under SCA is
genuinely expected for the year 2013-14.
2- Non Plan Expenditure :
The non plan expenditure has ballooned from Rs. 6300
crore in 2007-08 to around Rs. 14,000 crores in 2012-13 eliminating
the fiscal space for funding the plan. Given our unique geographical
situation, the economies of scale do not operate here which increases
the per capita cost of service delivery. This has considerably
handicapped our efforts in containing the increasing non-plan
expenditure that was aggravated by wiping out of the Non-Plan
Revenue Deficit Grant by the 13th
Finance Commission.
3- Regional Imbalances:
In the early years of the statehood the development,
particularly in the industrial and construction sectors, concentrated in
plain area which accounts for only about 10% of state’s total area. Hill
area, especially far flung areas, remained plagued with problems of
connectivity, dominance of forest land and its restrictive use, scattered
and low population density coupled with lower infrastructure base.
The successive governments in the State took special care for
delivery of social services and succeeded to some extent in mitigating
the gap in literacy levels and improving health indicators. However,
due to lack of livelihood opportunities and other socio economic
activities people have tended to migrate to the plain areas. This is
evident from the data emanating from 2011 Census, according to which
population in the plains of Haridwar, Udhamsingh Nagar and Dehradun
rose by about 33 percent during the decade against the State’s average
of 19.17 percent. Contrary to this, seven hill districts recorded less than
6 percent growth with Almora(-1.73) and Pauri-Garhwal (-1.51)
posting a negative growth.
The actions of the Union Ministry of Environment and Forests in
bringing entire watersheds covering 4179 sq kms (as they did recently
in the case of Uttarkashi Eco Sensitive Zone) have only served to
further restrict the scope for economic activities in the hills and
condemn the people in the hills to live the lives of second-class citizens
of India. Such notifications are not only being done in a high-handed
manner without any consultation with local people but also against the
unanimous resolution of the State Assembly. In the instant case
(Uttarkashi ESZ) not only have the principles of natural justice been
violated but none of the stated objectives in the notification are borne
out by data available in the government domain.
4- Central Plan Assistance :
Uttarakhand being a Special Category State (SCS) is entitled
for assistance from 30 percent funds earmarked in the total central
assistance. It needs to be considered that while the fund allocation
among general category states are being done according to Gadgil-
Mukherjee Formula, there is adhocism in allocation of central
assistance among Special Category States as it is being distributed
without using any explicit criteria.
The report of the Working Group on State’s Financial
Resources for the 12th Five Year Plan 2012-17 set up by the Planning
Commission has also noted that the percentage share of Uttarakhand
has decreased over the years during the Eleventh Five Year Plan. Even
if we look at the total grant in aid provided by the Centre to Special
Category States during 2012-13 the share of Uttarakhand has been
abysmally poor. While on the whole the average per capita grant
comes to Rs. 6913 for all SCSs, it was the lowest i.e. Rs. 3793 for
Uttarakhand. Further, Himachal Pradesh which has similar topography
but lesser population and better infrastructure created during last 50
years got Rs. 4230.79 crore as Plan Assistance despite its smaller
annual plan size (Rs. 3700 crore). In comparison, Uttarakhand got Rs.
3837 crore against an annual plan size of Rs. 8200 Crore. The Planning
Commission was also generous in sanctioning Rs. 1000 crore in 2011-
12 and Rs. 1400 crore in 2012-13 under SCA & SPA put together to
Himachal Pradesh, while Uttarakhand was discriminately granted only
Rs. 600 crore and Rs. 1000 crore in the respective years. It is therefore
necessary to evolve a separate formula for Special Category States
giving due weightage to area under forests, protected area network,
impact of forest and environment related statutes, disaster proneness
etc. beside the traditional parameters of area, population and
backwardness.
Now the review of Special Category Status to few more States
is being contemplated by the Centre. We hope that our interests will be
safeguarded and the State will be taken into confidence before making
any changes.
5- Funding of Centrally Sponsored Schemes (CSS) on
90:10 basis :
Uttarakhand is likely to suffer a loss of about Rs.700.00
crore in the annual plan 2013-14 due to non-allocation of funds on
90:10 basis under CSS. About 36 CSSs are being funded on the ratio
applicable to general category states, which should have been at par
with other Special Category States. The first year of the 12th Five Year
Plan is already over and the issue is still pending. It is requested that
now all CSSs may be funded on 90:10 basis atleast from this year.
6- Cost of Service Delivery :
Given its topography, the per capita cost of service delivery as
well as per unit capital cost of construction in our State is one of the
highest in the country. For example, the cost of service delivery in the
school education sector is approx. Rs. 16,881 p.a. per child (the highest
in the country) against an all-India average of approximately Rs.
5206/- p.a. per child. Similarly, the per unit construction cost has been
fixed under RMSA @ Rs. 7,000/- sq m whereas the norms under the
State Schedule of Rates (SOR) is almost twice this rate. This is not
taken into consideration under the relevant CSS which follows a one-
size fits all approach. Thus, the scheme which is under 75:25
funding pattern works out to a 50:50 pattern in reality, which
further compounds the issue of non-funding on 90:10 basis.
Similarly PMGSY is stated to be 100 percent Centrally Funded
Scheme. However, the State is required to arrange funds for reasons
like NPV, Compensation for land & buildings, cost and time overrun
due to delay in Forest Clearance by Government of India, payment for
construction of bridges over 50 meter span. Owing to this, PMGSY, a
100% Centrally Sponsored Scheme is working as a 70:30 scheme in
actual practice. This reiterates the point made earlier.
7- Infrastructure Development
Railways: There is a minimal railway network in our State. Given
the current security scenario, this is alarming. I am thankful to the
Centre for accepting our request to construct the Rishikesh-Karnprayag
railway line under the defence project category. This indeed would
strengthen our border security and improve the life of people living in
these areas. However, the pace of construction needs to be stepped up
as this is the only major infrastructure project of the centre in the State.
Work on Roorkee-Muzaffarnagar railway line is also lying in
dormancy. In order to ensure balanced regional development and
strategic border security requirements, sanctioning of Tanakpur-
Bageshwar line under defence project is also necessary.
Given the fact that the State has two sensitive strategic
international borders and it is a Special Category State, the Ministry of
Railways may be asked to prepare a comprehensive Railway
Networking Plan for the State as a Defence Project and stop insisting
on contribution of free land and 75 % Project Cost from the State
Government. Planning Commission may kindly take this up with the
Ministry of Railways.
Roads: Road construction in high hills is an arduous work because of
difficult topography and inclement weather conditions. The
construction of border roads and national highways especially in the
higher regions which are underway as also those which got severely
damaged during previous monsoons also needs to be expedited. I have
also discussed this matter with the Hon’ble Union Home Minister who
has kindly agreed to look into the issue of faster construction of border
roads.
Considering the sensitive international border and the recent
incidents thereon, it is necessary that construction of all border roads be
delinked from the restrictions of the FC Act and special permission be
given to the Border Roads Organisation (BRO) to set up stone crushers
in the higher reaches as also to use stone aggregate etc. available
locally.
Further, keeping in view the suggestion given by Planning
Commission last year, I have issued instructions to PWD to keep the
distance between two points and the length of road to cover this
distance in the ratio of 1:8 or 1:10.
Power : Power generation although undoubtedly the most critical
input because of its overarching impact on all socio-economic sectors
has been facing unnecessary restrictions and many projects are pending
for clearance from the centre while some of them have been forced to
close. Thus against an identified potential of 27,000 MW we have been
able to develop only 3618 MW.
Stalling of our power projects, many of them after proper
clearances has not only shaken investor’s confidence in the Power
Sector but in the entire Public Private Partnership (PPP) initiative in the
State. It has also deprived us of a potential further annual revenue
stream to the tune of Rs. 1651 crore which ought to be given as
recurring annual ACA till these projects are cleared as we have to
purchase electricity for our own use during the peak seasons from
outside on higher rates. Restrictions are now being imposed on Mini-
Hydel Projects (25 MW) on grounds of Eco-Sensitive Zones which
bodes ill for the development of the State.
While the centre has given its nod to the 300 MW Lakhwad
Dam Project which would help improve the power scenario, I would
request for an early decision on other projects languishing for clearance
from the centre.
8- Forest Issues
Despite facing severe disabilities and deprivations on account
of 65% of the total area under forests, our state and its people are
undeterred in their efforts to strengthen its forest and wild life. Our
efforts in this direction are borne out by the total forest area increasing
to 70% due to further survey and mapping of Van Panchayat areas by
the State Forest Department, increase in forest covered area by 1141
Km2, and declaration of a new Sanctuary and a Conservation Reserve
last year.
But herein lies our dilemma. While we are utilizing our
every bit in the interest of the nation even by sacrificing our gains, we
are being denied use of our forest land even for critical infrastructure.
Deputy Chairman Sir, I remember that a couple of years ago in
a letter you had rightly mentioned that Uttarakhand holds ample
opportunities for development by utilizing its rich natural resources
which should be harnessed to generate sustainable growth and
income opportunities for the people but paradoxically, even projects in
progress have been banned on the grounds of protests from certain so-
called religious and environmental activists.
Now to add to our woes, as already mentioned, a notification
has been issued to declare about 4179 sq.km. in Uttarakashi district as
eco sensitive zone, thereby imposing prohibitions and restrictions on
certain activities. This sort of a one-sided prescriptive approach
adopted by the Union Ministry of Forests and Environment baffles us.
While they have not held consultations with the State and have not
responded to the concerns expressed by the State Governments in the
past, they expect us to enforce this unenforceable notification with
Participatory Rural Appraisal.
Why such concern with environment in this State only? The
same river flows through Uttar Pradesh, Bihar and West Bengal. The
environmental stress on the river is greater in these States due to the
pressure of population and industrial activities. Then, why is
Uttarakhand being singled out for this treatment ? Why no eco-
sensitive zones are notified in these States ?
Such ill thought out notifications while ruining the State
economy are also bound to hurt the sentiments of crores of people all
over the country who will now be stopped from entering the Gangotri
Dham (one of the Char Dhams). Eco-Friendly activities like trekking
have been restricted. How will the villager earn his living if he can’t
even walk as this would be covered under trekking ? The prescription
given by the Union Ministry to use traditional architecture would lead
to green felling and also slate mining which are not environment
friendly activities.
We need to understand that the Constitution guarantees the
Right to Equality and Right to Livelihood which implies a Right to a
Dignified life. Before promulgating such notifications having a wide
impact on the economy, law and order and environment of the State,
the Centre should hold extensive discussions with all stake-holders.
9- Urban Growth :
As I have stated earlier, people from the remote and border
areas are tending to settle in plains. During the last decade, large
number of people including the people retired from defence forces
have settled in the periphery of existing larger towns in plains for
whom all urban facilities have to be provided.
Besides, Uttarakhand being a land of pilgrimage and
religious festivals, people from all over the country and abroad visit
the State at different occasions. This floating population soars up to
2-3 times than the native population of the State. Since a larger
number of pilgrims belong to lower economic category and depend
on public utilities only, their transportation, comfortable stay and
safe return puts pressure on our already limited civic amenities and
resources. During Char Dham Yatra and many other seasonal
occasions, creation of additional facilities becomes inevitable for
which extra funds are required.
10- Monsoon Disaster :
Risk management is one of key component of a sustained
development strategy. Our State witnessed unprecedented rains
successively during last three years which wrecked havoc with the
infrastructure created painstakingly during the past one decade. In
addition about 233 villages are on the verge of disaster due to
landslides and need immediate resettlement and rehabilitation. We,
therefore, seek a Comprehensive Road Replacement Package
amounting to Rs. 800 crore and a Resettlement & Rehabilitation
package of Rs. 500 crore in this financial year in the form of ACA.
Our Achievements
Despite all the constraints mentioned above we have been able
to maintain a good track record and have done remarkably well on
many fronts.
1. We have achieved about 13 percent average growth in GSDP
during the Eleventh Five Year Plan which has been rated second
highest among all the States by the Planning Commission.
2. Comparative data between 1999-2000 and 2007-08 of Human
Development Index (HDI) of various states as given in the
national Twelfth Five Year Plan, depicts highest percentage
change (44.54) in Uttrakhand among all states. The HDI in the
State was 0.339 which was lower than the national average
(0.387) in 1999-2000 has exceeded the national average in 2007-
08. However, it is still much lower (0.490) than many states like
Himachal Pradesh (0.652), Goa (0.617), Punjab (0.605), North-
East states (excluding Assam) (0.573), Maharashtra (0.572),
Haryana (0.552) and Gujarat (0.527).
3. Uttarakhand has a Protected Area Network (PAN) of over 15% of
its geographical area as compared to the national average of 4%.
This comprises of 6 National Parks, 7 Wildlife Sanctuaries and 3
Conservation Reserves, including the Nandhaur Wild Life
Sanctuaries and Pawalgarh Conservation Reserve, which were
notified only recently on 14 December, 2012. The Kotri and
Dugadda ranges of Lansdowne Forest Division has been decided
to be declared a buffer zone of Corbett Tiger Reserve. Rajaji
National Park has also been decided to be proposed to be declared
as a Tiger Reserve.
4. The Lansdowne Forest Division acts as a corridor between Rajaji
National Park on the west and Corbett Tiger Reserve on the east.
There has been several evidences and sightings of tigers, elephants
and other wild animals. Hence to have a integrated protection of
the corridor, it has been decided to annex the reserved forests of
Laldhang and Kotdwar ranges of Lansdowne forest division to
Rajaji National Park as a buffer zone and annex the reserved
forests of the Kotri and Dugadda ranges of Lansdowne forest
division as a buffer zone of the Corbett Tiger Reserve. The
Shyampur range of Haridwar forest division has already been
ordered to be annexed under the administration of Rajaji National
Park.
5. To ensure smooth passage of wild animals, it has been proposed to
construct an elevated fly over from Chillar Khal till Shyampur
instead of strengthening the existing forest road from Chilar Khal
to Laldhang. This fly over will reduce the distance from Kotdwar
to Haridwar by 25 Km resulting in saving of fuel, double taxation
at State border of Uttar Pradesh & Uttarakhand and also
decreasing traffic load.
6. Our performance on environment protection has been recognized
by the Planning Commission as the State tops the list of
performing states and union territories in terms of environment
well being.
7. Our performance in literacy has been above the national average.
We have achieved the target of universal enrolment in primary
and are close to achieve it at the secondary level.
8. Public-Private Partnership (PPP) :
Our government has taken several steps to create an enabling
environment to promote investment through PPP. Conceptualisation,
Preparation and implementation of PPP projects requires appropriate
advisory services in terms of preparation of project agreements,
structuring of projects and so on. For this a separate dedicated PPP cell
with services of experts has been put in place in the State. So far 120
projects with estimated cost of Rs. 5746 crore of different sectors have
been taken up of which 12 are now in operation, 14 are under
construction, for 8 bid process has been completed, 29 are under
bidding and 57 are under pipeline. Thus we have initiated the process
with encouraging results which would be further strengthened during
the 12th Five Year Plan.
On our part we are toiling hard to raise our revenues and at the
same time adhering to Fiscal Responsibility and Budget Management
Act in our annual budgets. According to revised estimates Fiscal
Deficit is expected to be 3.09 percent and it is proposed to bring it
down to 2.92 percent in 2013-14 which is within the prescribed limits
of 3.00 percent.
Further, in view of the GSDP growth of about 5 percent at the
national level in 2012-13, fiscal deficit level is targeted at 4.8 percent
in the Union Budget of 2013-14. against the commitment of 5.2 percent
in 2012-13. Under such circumstances the state’s share in central taxes
and allocation in CSSs/grants may also get affected adversely. Even in
2012-13 there has been shortfall of Rs. 116 crore in the share of central
taxes, besides reduced allocations in some central flagship schemes.
Further Rs. 500 crore approved albeit subject to availability of funds,
under Special Plan Assistance were not sanctioned. Sir, I again refer to
your observation quoted earlier, that Uttarakhand has great potential in
terms of natural resources which should be harnessed to generate
sustainable growth and income opportunities for the people, but
ironically all our doors have been closed on this or that pretext. As we
cannot use the forest resources for commercial purpose due to
restrictions of Forest Conservation Act, (read with ESZ), handicapped
for industrial development in the difficult and fragile mountainous
region due to early withdrawal of CIP, cannot develop our hydro power
potential and so on, it is a Hobson’s choice for us to manage our plan
resources.
Also Government of India is now moving towards uniformity
in Taxation across the country, earlier it was VAT and now it is with
GST. This has happened in the case of Transport Sector also where
National Permits, which were earlier issued by the States, were taken
over by the Central government with a consequent loss of Revenue to
the States. Now with the introduction of GST uniformly across the
States it is feared that smaller States will further lose their tax revenue
because of smaller business scale and inflexibility of the new system.
Hence the decision on fixation of minimum annual turnover for
implementation of GST may be left to the jurisdiction of the States.
Despite all the above mentioned handicaps enumerated above we
have tried our best and even Planning Commission has rated the State
as the second best in GDP Growth rates. However, recent
developments like declaration of a large area as Eco-Sensitive Zone
without taking the people of the State & the State Government into
confidence has really demoralised us and decisions like these will be a
great impediment in sustaining our positive growth rates.
Sir, I would request that Planning Commission should bail us out
from this vicious situation by considering giving following grants over
and above Rs 8500 crores proposed plan size:
Green Bonus- Rs. 2000 crores, per annum.
Compensation for Power Projects Stalled due to
Environmental clearances- Rs 1651 crores.
Comprehensive Road Replacement Package- Rs. 800
crores.
Rehabilitation of 233 Villages in Land slide Zones- Rs.
500 crores.
In this backdrop of our performance prospects, problems
and issues relating our State I request you to approve the
presented annual plan and grant the solicited Special Package,
Special Plan Assistance and Special Central Assistance to
enforce our efforts.
Jai Hind.
(Vijay Bahuguna)
23 May, 2013
New Delhi.