Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 1 APPENDIX I FORM 1 (I) Basic Information 1 Name of the Project/s : Gare IV/6 Coal Mine ( Open Cast & Under Ground) (4 MTPA) and 700 TPH (4 MTPA) Coal Washery in proposed area of the GareIV/6 Coal mine of M/s Jindal Steel & Power Limited. 2 S. No. in the Schedule Coal Mine : 1(a) and Coal Washery : 2(a) 3 Proposed capacity/ area/ length/ tonnage to be handled/ command area/ lease area/ number of wells to be drilled Proposed ROM from mine = 4 MTPA Proposed washery throughput = 4 MTPA Area of mine = 381.42 Ha Area of Washery and facilities = 12.52 ha 4 New/ Expansion/ Modernization New 5 Existing capacity/ area etc Nil 6 Category of Project i.e. ‘A’ or ‘B’ “A” for both Coal mine and washery 7 Does it attract general condition? If yes, please specify The project is already category “A”. 8 Does it attract specific condition? If yes, please specify No as not located in any industrial complex/ estate/ SEZ etc. 9 Location Refer Annexure I for location plan Geographical Coordinates (in modified Everest system) :1) Northern Corner: 22 0 9’ 47”.4322 N 83 0 29’ 56’’.8635 E 2) NorthEastern Corner: 22 0 9’ 14”.2488 N 83 0 30’ 21’’.3609 E 3) Southern Corner: 22 0 7’ 58”.7109 N 83 0 29’ 49’’.4764 E 4) Western Corner: 22 0 9’ 8”.0051 N 83 0 29’ 4’’.3174 E

Upload: others

Post on 07-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 1

APPENDIX I FORM 1   

  

(I)   Basic Information   

     

1  Name of the Project/s :  Gare  IV/6  Coal Mine  (  Open  Cast  &  Under Ground)  (4  MTPA)  and  700  TPH  (4  MTPA) Coal Washery  in proposed area of  the Gare‐IV/6 Coal mine of M/s  Jindal  Steel & Power Limited. 

     

2  S. No. in the Schedule  Coal Mine : 1(a) and Coal Washery : 2(a) 

     

3  Proposed  capacity/ area/  length/  tonnage to be handled/ command area/ lease area/ number of wells to be drilled 

Proposed ROM from mine = 4 MTPA 

Proposed washery throughput = 4 MTPA 

Area of mine = 381.42 Ha 

Area of Washery and facilities =  12.52 ha  

     

4  New/ Expansion/ Modernization  New 

     

5  Existing capacity/ area etc  Nil 

     

6  Category of Project i.e. ‘A’ or ‘B’  “A”  for  both Coal mine and washery  

     

7  Does it attract general condition? If yes, please specify 

The project is already category “A”.  

     

8  Does it attract specific condition? If yes, please specify 

No as not located in any industrial complex/ estate/ SEZ etc.  

     

9  Location   Refer Annexure I for location plan 

Geographical  Co‐ordinates  (in  modified Everest system) :‐ 

1) Northern Corner:  220 9’ 47”.4322 N 830 29’ 56’’.8635 E 

2) North‐Eastern Corner:  220 9’ 14”.2488 N 830 30’ 21’’.3609 E 

3) Southern Corner:  220 7’ 58”.7109 N 830 29’ 49’’.4764 E 

4) Western Corner:  220 9’ 8”.0051 N 830 29’ 4’’.3174 E 

 

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 2

  Plot/ Survey/ Khasra no.  Refer Annexure II for list of Khasra and map 

  Village  Lamdarha,  Saraitola,  Gare,  Khamharia, Karwahi  & Tehlirampur 

  Tehsil   Tamnar 

  District  Raigarh 

  State  Chhattisgarh 

     

10  Nearest railway station/ airport along with distance in kms 

Raigarh‐ 45 km 

Raipur –  350 km 

     

11  Nearest town, city, district head quarters along with distance in kms 

Nearest town & District HQ: Raigarh, 45 km 

     

12  Village Panchayats, Zilla Parishad, Municipal Corporation, Local Body (complete postal addresses with telephone nos. to be given) 

Village – Khamharia, Saraitola, Gare, Lamdarha, Tehlirampur & Karwahi.  

Panchayat – Khamharia, Jhinkabahal, Gare & Saraitola 

Circle/Local Body – Tamnar 

Zila Parishad –.Raigarh (Chhattisgarh) 

     

13  Name of the applicant  Jindal Steel & Power Limited 

14  Registered Address  Jindal Centre , 12, Bhikaji Cama Place 

New Delhi – 110 066 

     

15  Address for correspondence : 

  Name  Mr. Anand Goel 

  Designation (Owner/ Partner/ CEO)  Joint Managing Director 

  Address    Jindal Steel & Power Limited,   Jindal Centre,  12, Bhikaji Cama Place, New Delhi  

  Pin Code   110 066. 

  E mail  E mail: [email protected]  

  Telephone no.  011‐41462105

  Fax  011‐26161271 

     

16  Details of Alternative sites examined, if any. Location of these sites should be shown in a Toposheet 

No alternative sites studied as mining is a site specific project according to mineral availability.  

   

 

 

 

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 3

17  Interlinked Projects  1) DRI Plants of Jindal Steel & Power Ltd., Raigarh.  

2) DRI plants of Nalwa Sponge & Iron Ltd. Taraimal. 

     

18  Whether separate application of interlinked project has been submitted? 

Not Applicable as the plants are already operational with requisite clearances 

     

19  If yes, date of submission  Not Applicable 

     

20  If no, reason  Not Applicable 

     

21  Whether the proposal involves approval/ clearance under : if yes, details of the same and their status to be given: 

 

  (a)  The Forest (Conservation) Act, 1980?  Total 93.566 ha forest land involving 51.066 ha of chote jhaad ke jungle and  

42.5 ha of bade jhaad ke jungle. Stage I  Forest Clearance has been accorded on 30.12.2010 

  (b)  The Wildlife (Protection) Act, 1972?  Not Applicable as not within 10 km of a notified area 

  (c)  The CRZ Notification, 1991?  Not Applicable as it is not near shore 

     

22  Whether there is any Government Order/ Policy relevant/ relating to the site? 

No 

     

23  Forest land involved (hectares)  Total 93.566 ha forest involved. Stage I clearance has been accorded on 30.12.2010 

     

24  Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? 

None.  National  Green  Tribunal  has  already given  judgment  for  re‐conduct  of  public hearing. 

  (a)  Name of Court  Not Applicable 

  (b)   Case No.  Not Applicable 

  (c)  Orders/ directions of the Court, if any and its relevance with the proposed project  

Not Applicable 

Capacity  corresponding  to  sectoral  activity  (such  as  production  capacity  for manufacturing, mining  lease  area  and  production  capacity  for mineral  production, area  for mineral  exploration,  length  for  linear  transport  infrastructure,  generation capacity for power generation etc.,) 

 

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 4

(I) Activity  

1.  Construction,  operation  or  decommissioning  of  the  Project  involving  actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) 

 

S. No. 

Information/Checklist confirmation 

Yes/ No 

Details thereof (with approximate quantities /rates,  wherever  possible)  with  source  of information data 

1.1  Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) 

Yes  Mine  : The land use (381.42 Ha), identified in the  form  of  Govt. waste  land,  Gochar  land, forest  land  (Chhote/  bade  jhad  ke  jungle), private agricultural  land will be changed due to  mining  activity,  which  will  be  reclaimed after  completion  of  mining  by  backfill  with overburden  &  fly  ash.  At  present  it  is generally  characterized  by  a  gentle topography with  slope  towards  Kelo  river  in the  east.  However,  it  is  relatively  rugged  in the  area  adjacent  to  Kelo  river  and  south‐western  part  due  to  presence  of  nalas. Elevation  varies  from  250 m  (south‐eastern near  Kelo  river)  to  284  m  (north‐western). Present  topography  is  shown  in Annexure  III and  topography at  the end of mining can be seen in Annexure IV. Washery  :  It will be  located  in north eastern corner of the ML. However, the impact will be limited  since  this  project  will  be  executed within the leasehold area of the mine. 

1.2  Clearance of existing land, vegetation and buildings? 

Yes  93.566  ha  of  chote &  bade  jhaad  ke  jungle will  get  disturbed.  In  the  non  forest  area, bushes and trees planted by farmers will have to be cleared. Existing 16 houses to be shifted as a part of rehabilitation. 

1.3  Creation of new land uses?  

Yes  Infrastructural  facilities/  offices,  excavated area,  plantation,  dumps,  reservoirs,  CHP  & Washery  and  facilities,  power  transmission line, haul roads,  transportation roads, Green Belt,  Safety  zone  ,  Embankment,  Settling Ponds etc. will be created. 

1.4  Pre‐construction investigations e.g. bore houses, soil testing? 

Yes  Exploration  for  estimation  of  coal  reserves has  already  been  done  by  GSI  and  CMPDIL. Detailed  soil  investigations  will  be  done before start of construction of any buildings. 

1.5  Construction works?  Yes  Not  significant as  it will be  required only  for building  and  structure  of  Coal  handling 

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 5

S. No. 

Information/Checklist confirmation 

Yes/No 

Details thereof (with approximate quantities /rates,  wherever  possible)  with  source  of information data 

equipment,  washery,  offices,  reservoir etc.Construction  of  washery  &  other  buildings will change the local topography and drainage for  management  of  which  storm  water drainage will be provided. 

1.6  Demolition works?  Yes  16 houses/ hutments will be demolished 

1.7  Temporary  sites  used  for construction  works  or  housing of construction workers? 

Yes  Local  workers  will  be  deployed,  hence  no arrangement  for  housing  of  construction workers  is  envisaged.  Any  outside  workers will be  accommodated  in  existing    colony of Gare  IV/1 as well as  in  the nearby  colony of Jindal  Power  Ltd  (  about    5  Km  from  the project area). 

1.8  Above  ground  buildings, structures  or  earthworks including  linear  structures,  cut and fill or excavations 

Yes  Construction  of  infrastructure  facilities  for CHP  &  washery  (civil  structure)  and  office building will  be  done which will  disturb  the sheet  flow  of  rain  water.  Excavation  for mining  purpose will  be  carried  out  over  an area of 371.49 Ha. This will be managed by making  provisions  for  storm  water  drains around  built  up  structures,  mine  pits, temporary  dumps  and  backfilling  in excavation. 

1.9  Underground works including mining or tunneling? 

Yes  From 3rd year onwards, underground mining activities will  be  started  and  production will be    commenced  from 8th  year at 0.1MT and will be  increased  to  0.5MT by  10th  year  and from 14th year onwards the production will be 1.00MTPA. 

1.10  Reclamation works?  Yes  All  the excavated area  i.e. 371.49 Ha will be backfilled and reclaimed by the end . 

1.11  Dredging?  No   

1.12  Offshore structures?  No   

1.13  Production and manufacturing processes? 

No  There is no production or manufacturing in the mine or washery. In mine, there will be extraction of coal while in washery raw coal will be washed. 

1.14  Facilities for storage of goods or materials? 

Yes  For  mines,  store  room,  coal  stack  yard, internal dumps  for OB, etc will be there. For washery,  all  products  will  be  stored  in storage bunkers. (1) Clean coal will be stored in    2  X  500  T  capacity  product  bunkers.(ii) Middlings will be stored in 2 X 500 T capacity product bunkers & (iii) Rejects will be stored 

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 6

S. No. 

Information/Checklist confirmation 

Yes/No 

Details thereof (with approximate quantities /rates,  wherever  possible)  with  source  of information data 

in 2 X 300 T capacity storage  bunkers.Sized  raw  coal will  be  stored  in  4  x  1250  T capacity storage bunkers.   

1.15  Facilities for treatment or disposal of solid waste or liquid effluents? 

Yes  Mine 

Top soil to be dumped in topsoil dump and then  reused  for  plantation  and afforestation activities. 

Sludge  from  domestic  wastewater  after composting used as compost/ manure. 

Oil water  separator/  trap  for oil  grease  in workshop effluent. Oil/ grease to be sold to approved  vendors  and  sludge  will  be disposed of in impermeable pits. 

Sludge  created by  the mine water‐settling pond at the surface will be disposed off  in the  backfill  along  with  the  overburden waste. 

Washery 

The middlings  (including  fines)  and  usable rejects will  be  used  for  power  generation. Washery rejects will be disposed off  in  the mines. The  crushed  coal will be washed  in the  heavy  media  cyclone,  Effluent  from various  points  from  cyclone  will  be collected and  treated  in  the  thickener. The thickened  tailing  is  envisaged  to  be dewatered in a belt press while the clarified water is recycled back in the process circuit.

The  Belt  Press will  ensure  better  recovery of Fines thus help  in checking the pollution created by Slurry in most of the Washeries. 

The  coal  washery  will  maintain  the  close water  circuit  operation  with  zero  effluent discharge. 

1.16  Facilities for long term housing of operational workers? 

Yes  The  semi  skilled, unskilled  and  labour  grade manpower  shall  be  hired  from  the surrounding villages and towns.  The  outsider  employees  will  be accommodated in the existing colony of Gare IV/1 as well as in the nearby colony of Jindal Power  Ltd  (about    5Km  from  the  project area). 

1.17  New road, rail or sea traffic during construction or 

Yes  Increase in road traffic due to transportation of  coal  to end use plant, movement of man 

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 7

S. No. 

Information/Checklist confirmation 

Yes/No 

Details thereof (with approximate quantities /rates,  wherever  possible)  with  source  of information data 

operation?  

and  material  to  and  from  mine.Transportation of coal  to  raw coal stockyard in  washery  will  occur  within  the  ML  by dumpers. Within washery, conveyors will be used.  From washery,  clean  coal & middling (including  fines) will be  transported  through road.  Rejects  will  be  dumped  in  mine backfilling. 

1.18  New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?

Yes New  haul  roads  will  be  constructed for transport of coal from mine to washery.  

1.19  Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? 

Yes  Tamnar – Lailunga road passing through ML is proposed  to be diverted along  the boundary of ML. 

1.20  New or diverted transmission lines or pipelines? 

Yes  The power  line passing  through  the western corner  will  be  diverted  along  the  western boundary of the ML . 

1.21  Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers?

Yes  Seasonal nala through the NW part of the ML shall be diverted along the lease boundary.    

1.22  Stream crossings?  Yes  Culverts will be provided wherever  the  road will cross the stream along the boundary 

1.23  Abstraction or transfers of water form ground or surface waters? 

Yes Abstraction of  1346 m3/d  ground water will be  done  to  meet  water  requirement  of workers  (45),  peripheral  villages  (20), sprinkling  (273),  plantation  (100),  vehicle washing  (8) and washery  (900)  . Out of  this, 1281 will  be  from mine water  and  65  from bore  well.  The  seepage  loss  in  mine  is estimated  as  13944  cum/day.  The  balance water  shall  be  discharged  in  the  Kelo  river after settlement at the surface.  

1.24  Changes in water bodies or the land surface affecting drainage or run‐off? 

Yes Seasonal nala through the NW part of the ML shall be diverted along the lease boundary. 

1.25  Transport of personnel or materials for construction, operation or decommissioning? 

Yes  Transportation  of materials  for  construction of infrastructure and buildings will take place primarily  during  construction  period  of  the project.  Thereafter,  transportation  of employed  manpower,  mined  coal  and materials,  as  and  when  required  will  take 

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 8

S. No. 

Information/Checklist confirmation 

Yes/No 

Details thereof (with approximate quantities /rates,  wherever  possible)  with  source  of information data 

place.

1.26  Long‐term dismantling or decommissioning or restoration works? 

Yes  Reclamation  of  excavated  areas  through backfilling and afforestation concurrent with mining. At the end of the life of the mine, the infrastructure shall be dismantled. 

1.27  Ongoing activity during decommissioning which could have an impact on the environment? 

No

1.28  Influx of people to an area in either temporarily or permanently? 

Yes  Proposed  project  will  generate  direct  and indirect employment who will be mostly from surrounding  areas.  Thus, minimum  influx  is expected of the outsiders, who will come and live in the mine colony. 

1.29  Introduction of alien species? 

No

1.30  Loss of native species or genetic diversity? 

No   

1.31  Any other actions?  

No

 2.   Use of Natural resources  for construction or operation of  the Project  (such as  land, 

water, materials or energy, especially any resources which are non‐renewable or  in short supply): 

 

S. No. 

Information/checklist confirmation  

Yes/No 

Details thereof (with approximate quantities /rates, wherever possible) with source of information data 

2.1  Land especially undeveloped or agricultural land (ha) 

Yes  Private land (agriculture)‐ 254.341 Ha Govt. land (grass, road, kotwari, water body etc.) – 33.513 Ha Forest Land (chote & bade jhaad ke jungle, ‐ 93.566 Ha) Total 381.42 Ha  

2.2   Water (expected source & competing users) unit: KLD 

Yes Mines – 381 m³/dayWashery – 900 m³/day Domestic‐ 65.0 m³/day Source : Domestic : Bore well, Industrial: Mines pit.

2.3  Minerals (MT)  Yes Coal

2.4   Construction material – stone, aggregates, sand / soil (expected source – MT) 

Yes  It  is a coal mine. No  large scale construction work will be done other than office buildings, CHP  and Washery.  Stone  and  sand  will  be bought from nearest quarries. 

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 9

S. No. 

Information/checklist confirmation  

Yes/No 

Details thereof (with approximate quantities /rates, wherever possible) with source of information data 

2.5  Forests and timber (source –MT) 

Yes Will  be  bought  from  vendors  for  doors  and windows  construction. Maximum  doors  and windows  will  be  constructed  by  glass, aluminum frame, steel frames, etc. 

2.6  Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW) 

  The  total  connected  load  for  the    Coal washery  including CHP shall be around 8 MW and  2MW  for Mining Operation. The specific power  consumption  for  washing  including CHP  shall  be  around    6.5  kwh  per  Tonne  of raw  coal  throughput.     Approx. 45 KL/D  fuel (diesel) will be consumed. 

2.7  Any other natural resources (use appropriate standard units)

No   

 3.   Use, storage,  transport, handling or production of substances or materials, which 

could  be  harmful  to  human  health  or  the  environment  or  raise  concerns  about actual or perceived risks to human health. 

 

S. No. 

Information/Checklist confirmation 

Yes/No

Details  thereof  (with  approximate quantities/rates,  wherever  possible)  with source of information data 

3.1  Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and  water supplies) 

Yes  Additives  in  washery  washing  circuit. However,  as  the washing  circuit  is  a  closed loop, there  is no effluent discharge from the washery. 

3.2  Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) 

No  No  water  borne  diseases  anticipated  since due  precautions  for  treatment  and  disposal of  waste  water  will  be  taken  from  mines. There  shall  be  no  discharge  from  the  coal washery washing system. 

3.3  Affect the welfare of people e.g. by changing living conditions? 

Yes  The  project  will  create  direct  employment and also indirect employment.  

3.4  Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc., 

Yes  Mining  and  transportation  activity  will generate  SPM  in  ambient  air,  which  can affect health of vulnerable groups. However, with  proper  management  planning  by sprinkling  of  water,  use  of  dust  extractors, developing greenery, etc, the ambient air will be  maintained  clean  and  within  statutory norms.  There  are  no  hospitals  in  the immediate vicinity of the washery or mine as per the Census records. 

3.5  Any other causes  No   

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 10

 4.  Production  of  solid  wastes  during  construction  or  operation  or  decommissioning 

(MT/month)  

S. No. 

Information/Checklist confirmation 

Yes/  No 

Details  thereof  (with  approximate quantities/rates,  wherever  possible)  with source of information data 

4.1  Spoil, overburden or mine wastes 

Yes  Total 153.31 Mcum of OB and 1.86 Mcum of top soil will be generated by opencast mining which will be used for backfilling in the mine.  

4.2  Municipal waste (domestic and or commercial wastes) 

Canteen  waste  will  be  generated  @  40 kg/day  or  12TPA  ,  Waste  from  sweepings (leaves etc) will be about 20kg/d2qay or 6TPA and  Pit  head  septic  tanks will  produce  22.5 kg/day  (6.75)  TPA  solid  waste.  The  organic component  of  all  the  above  will  be composted and used as manure. 

4.3  Hazardous wastes (as per Hazardous Waste Management Rules) 

Yes  Used oil/  spent oil under category 5.1,  from transformers, DG sets, machinery, etc will be generated periodically and sold to authorized recycling agencies. 

4.4  Other industrial process wastes Yes The  coal  washery  will  produce  about  1.02MTPA  washed  coal  &  2.34 MTPA middlings including  coal  fines,  which  will  be  used  for power  generation.  Around  0.64  MTPA  Rejects will  be  generated  from  the washery which will be dumped into the mine with the OB. However, usable rejects will be utilized in power generation.  Washing  workshop  waste  will  be  generated @20 kg/day.    

4.5  Surplus product  No   

4.6  Sewage sludge or other sludge from effluent treatment 

Yes Pit head septic tanks will produce 22.5 kg/day solid waste. 

4.7  Construction or demolition wastes 

Yes  No  construction  work  other  than  offices, store, workshop, washery, etc. is anticipated. The waste  from construction and demolition of houses will be meager and will be used for road  construction  within  the  premises  and for  filling  any  low‐  lying  areas  within  the premises or backfilled/ dumped. 

4.8  Redundant machinery or equipment 

Yes Metallic scraps are recycled in Raigarh plant.

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 11

S. No. 

Information/Checklist confirmation 

Yes/  No 

Details  thereof  (with  approximate quantities/rates,  wherever  possible)  with source of information data 

4.9  Contaminated soils or other materials 

No

4.10  Agricultural wastes  No   

4.11  Other solid wastes  No   

 5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) 

 

S. No. 

Information/Checklist confirmation 

Yes/No 

Details  thereof  (with  approximate quantities/rates,  wherever  possible)  with source of information data 

5.1  Emissions from combustion of fossil fuels from stationary or mobile sources 

Yes  Fossil fuel (diesel) will be used in operation of machinery.  The  consumption  will  be approximately 45 KL/D.  Fossil  fuel  will  be  used  in  DG  sets  for generation of power in case of power failure. Electricity  will  be  used  to  operate  the washery machinery

5.2  Emissions from production processes 

Yes  The  production  process  will  involve excavation, which  will  generate  dust  at  the site.  In  washery,  the  crushing  of  coal  will generate  dust;  effective  dust  suppression system will be incorporated. 

5.3  Emissions from materials handling including storage or transport 

Yes  The  emissions  are  included  in  production emission above. Automobiles  to be used  for raw and washed coal will contribute to the air pollution by exhaust emissions, which will be reduced  by  proper maintenance  of  vehicles. The  storage  of  coal  and  its  handling  will contribute to the fugitive emission which will be  mitigated  by  water  spraying,  dust extractors etc. 

5.4  Emissions from construction activities including plant and equipment 

Yes The emissions are  limited  to  construction of offices  and  infrastructure  etc  and  will  be short  term and  can be  countered by  regular water  spraying.  Some  vehicle  emission  will also be there. Both types of pollutants will be for a limited period of time. 

5.5  Dust or odours from handling of materials including construction materials, sewage and waste 

Yes  Dust emissions are  limited to construction of offices and  infrastructure etc. As the sewage will be treated in septic tanks at the pit head, no  odour  is  anticipated  except  during periodic desludging. 

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 12

S. No. 

Information/Checklist confirmation 

Yes/No 

Details  thereof  (with  approximate quantities/rates,  wherever  possible)  with source of information data 

5.6  Emissions from incineration of waste 

No No  incineration  processes  within  the proposed ML. 

5.7  Emissions from burning of waste in open air (e.g. slash materials, construction debris) 

No  No  burning  process  within  the  lease  area. However  coal  can  burn  as  a  result  of spontaneous combustion or accidental fire. 

5.8  Emissions from any other sources 

No

6.  Generation of Noise and Vibration, and Emissions of Light and Heat:  

S. No. 

Information/Checklist confirmation 

Yes/No 

Details  thereof  (with  approximate quantities/rates,  wherever  possible)  with source  of  information  data  with  source  of information data 

6.1  From operation of equipment e.g. engines, ventilation plant, crushers 

Yes  HEMM will be  required  for excavation of OB and  coal.  These  are  high  noise  generating machinery  in  the  range of 60‐100 dB  (A)  for which noise proof air conditioned cabins will be  provided  for  operator.  Noise  pollution from  crushers,  screens  and  various components of the washery will be there  for which  suitable  measures  will  be  taken  to maintain  level  within  the  stipulated standards. 

6.2  From industrial or similar processes 

No Mining and washery equipment as above.

6.3  From construction or demolition 

Yes  Marginal and temporary. 

6.4  From blasting or piling Yes Noise and  vibration will occur,  the quantum of which  is  subject  to  strata  under  blasting. Ground  vibration  study  will  be  separately commissioned  for  assessment.  During construction  limited  piling  work  will  be undertaken. 

6.5  From construction or operational traffic 

Yes The  plying  of  trucks  will  increase  noise  to about 60‐75 dB(A) for that instant in ambient air. 

6.6  From lighting or cooling systems 

No  Heat generated only  in  immediate vicinity of light bulb, ACs, chillers and other equipment. 

6.7  From any other sources  No   

    

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 13

7.  Risks of contamination of  land or water from releases of pollutants  into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: 

 

S. No. 

Information/Checklist confirmation 

Yes/ No 

Details  thereof  (with  approximate quantities/rates,  wherever  possible)  with source of information data 

7.1  From handling, storage, use or spillage of hazardous materials 

No  The  hazardous  material  is  transformer  oil under  category  5.1, which will  be  stored  in leak  proof  drums  and  kept  on  impervious floor  with  shed.  Oil  separators  with impervious drains will be provided to prevent any  land/  water  contamination.  Hence,  no contamination anticipated. 

7.2  From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) 

Yes  There  shall  be  discharge  of  excess  mine seepage  water  into  the  natural  drain  after settlement  of  solids  in  the  surface.  The sewage will be  led  to  the  septic  tank where the  overflow,  after  treatment will  be  led  to soak  pit. Workshop  effluent  will  be  passed through OWS and  settling  tank and  recycled completely.  In  washery,  the  effluent  from various points  in  the circuit will be collected and  treated  in  the  thickener.  The  thickened tailing  is envisaged to be dewatered in a belt press  while  the  clarified  water  will  be recycled  back  in  the  process  circuit. Treatment will be based on the closed water circuit operation with zero effluent discharge. 

7.3  By deposition of pollutants emitted to air into the land or into water 

Yes Mine: Dust suppression will be carried out by means of sprinkling on the haul roads, dumps, reclaimed area, mine faces and top soil dump. Covered vehicle will be used  for any material transport.  The  deposition  of  particulate matter  on  the  surrounding  vegetation  can occur, which will get washed off during  rains and  can  be  washed  periodically.  Mine seepage  water  will  be  discharged  in  the natural drain. After pumping from mine sump to the surface water reservoir, the settlement of  suspended  solids  will  be  done  and  then only  the  water  discharged  to  the  natural drain. Washery  :  Atmospheric  pollution  may  be from discharge of coal  into  receiving hopper, at  coal  crushing  unit,  transfer  points  and during screening. Effective steps will be taken to quench the dust.  

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 14

S. No. 

Information/Checklist confirmation 

Yes/No 

Details  thereof  (with  approximate quantities/rates,  wherever  possible)  with source of information data 

Conveyors,  transfer  points  etc.  will  be covered/  provided  with  enclosures.  The crushers will be provided with enclosures and with  adequate water  sprinkling  arrangement using  fine atomizer nozzles. Mist  Spray’s will be  installed  and  provide  healthy  working conditions. Zero discharge is envisaged; hence no pollutants deposition  into water and  land is anticipated. 

7.4  From any other sources  No   

7.5  Is there a risk of long term build up of pollutants in the environment from these sources? 

No  Dust  falling  on  land/  plants  will  easily  be washed  off  during  rains  or  can  be  washed periodically. Hence no risk of  long term build up.

 8.  Risk of accidents during construction or operation of the Project, which could affect 

human health or the environment  

S. No. 

Information/Checklist confirmation 

Yes/No 

Details  thereof  (with  approximate quantities/rates,  wherever  possible)  with source of information data 

8.1  From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances 

No  Risk  can  be  from  blasting  which  will  be practiced  before  excavation  of  coal  and OB and  also  from  fire  which may  break  out  in coal  stock  files. Raw  coal bunkers  can  catch fire  when  improperly  stored,  hence,  fire fighting measures will be  taken. Appropriate On  site Emergency Plan will be planned and executed. 

8.2  From any other causes  No

8.3  Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? 

No  The project falls under Zone‐III which is not under actively seismic zone. The project area is not prone to floods, landslides or cloudburst etc. 

        

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 15

9.  Factors which  should  be  considered  (such  as  consequential  development) which could  lead  to environmental effects or  the potential  for cumulative  impacts with other existing or planned activities in the locality 

 

Sl. No. 

Information/Checklist confirmation 

Yes/ No 

Details thereof (with approximate quantities/rates, wherever possible) with 

source of information data 

9.1  Lead to development of supporting. Facilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: 

   

  supporting infrastructure (roads, power supply, waste or waste water treatment, etc.) 

Yes  The  establishment  of  the  project  will  lead  to establishment  of  wide  metalled  roads  to  and around  the mine. Borewell water will be made available to peripheral villages.  

  housing development  Yes  With  the  establishment  of mine  colony,  small clusters  of  houses,  shops  and  informal  sector kiosks will  come  up  around  it  to  cater  to  the colony’s requirements. The existing villages will upgrade their housing with money earned from employment  or  from  compensation  in  lieu  of land. The affected people  (16 households) will be  resettled  with  new  housing  and  new infrastructure at suitable location. 

  extractive industries  No   

  supply industries  No   

  other  No   

9.2  Lead to after‐use of the site, which could have an impact on the environment 

Yes  The post mining  land use has been planned as per mine closure plan. The excavated area will be backfilled and planted with  trees. Thus,  the after use of the site will be “plantation” and of a better  quality  than  the  present  chote &  bade jhaad  ke  jungle  that  the  mine  excavation  is intending to disturb.  

9.3  Set a precedent for later developments 

No

9.4  Have cumulative effects due to proximity to other existing or planned projects with similar effects 

Yes  The adjoining industries are: 

NAME OF MINE AND PLANT  DIST. AND DIR. 

1. Gare IV/1 of JSPL 3.45 KM, ESE

2. Gare IV/ 2& 3 of JPL  East of  Kelo River 

3. Gare IV/4 of Jayswal Neco  1.8 KM East 

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 16

Sl. No. 

Information/Checklist confirmation 

Yes/No 

Details thereof (with approximate quantities/rates, wherever possible) with 

source of information data 

Ltd. 

4. Gare IV/5 of Monet Ispat Co. Ltd

2.5 KM (Kelo River), E

5. Gare IV/7 Raipur Alloys  Adjoining NE

6. Gare IV/8 of Jayswal Neco   Adjoining NW

7. Gare Palma Sector‐ II of Mahatamil Collieries Ltd. 

Adjoining SW 

8.Operational 1000 MW TPP and Proposed 2400 MW Thermal Power Plant of JPL  

4.26 km, SW

9. Jamkhani coal block of Bushan Ltd. 

7.8 km, ESE 

10. 4 x 135 MW DCPP of   JSPL 

3.5 km, ESE 

 

 (II) Environmental Sensitivity 

    (Refer Annexure V for 15 Km study area map) 

S.No.  Areas  Name/ Identity 

Aerial  distance  (within  15  km.) Proposed project location boundary 

1   Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value 

Nil   

2  Areas which are important or sensitive for ecological reasons ‐ Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests 

  None  exist  which  are    important  or sensitive  for  ecological  reasons  ‐ Wetlands, watercourses or other water bodies,  coastal  zone,  biospheres, mountains.  However,  Forests  are located as under.  

Gare P.F.  Within ML  

Jamkhani R.F  8 km E 

Tolge R.F  5 km NE 

Silot R.F  1.49 km NE 

Deodanagar R.F  8 km N 

Barkachhar R.F  9 km  S 

Deogaon R.F  9 km SW 

Bendra R.F.  2.52 km SE 

3  Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over 

Nil   

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 17

S.No.  Areas  Name/Identity 

Aerial  distance  (within  15  km.)Proposed project location boundary 

wintering, migration 

4  Inland, coastal, marine or underground waters 

Kelo River  Along the east boundary of ML 

5  State, National boundaries  Orissa state boundary 

About 7.7 kms East from ML boundary. 

6  Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas 

Dry season motorable road connecting Lailunga – Tamnar ‐ Raigarh 

Passes through ML 

7  Defence installations  Nil

8  Densely populated or built‐up area  None  Densely  populated  or  built  up  area doesn’t exist. Only villages and colonies in the study area as per list in Annexure VI and map in Annexure V 

9   Areas occupied by sensitive man‐made land uses (hospitals, schools, places of worship, community facilities) 

Yes None  in mine lease area.   Hospitals,  Schools, Community  facilities are  present within  10  km  of  the  study area. 

10  Areas containing important, high quality or scarce resources  (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 

Nil    

11   Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded) 

Nil   

12   Areas susceptible to natural hazard which could cause the project to present environmental problems  (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) 

Nil

     

Form I - 4 MTPA Gare IV/6 Mines & Washery of M/s JSPL 19

 LIST OF ANNEXURES 

 

Annexure No.    Description 

   

I  Location map 

II  Khasra list and map 

III  Present surface plan of ML 

IV  Conceptual Plan 

V  15 km study area 

VI  Amenities in 10 km radius 

VII  Terms of Reference for EIA studies 

   

ANNEXURE : 3-1

SL.NO. VILLAGETRIBAL LAND

NON-TRIBAL LAND GOVT.LAND

FOREST LAND TOTAL

CHOTE JHAR KA JANGAL

BADE JHAR KA JANGAL

1 GARE 89.732 57.238 3.681 42.434 27.397 220.4822 KHAMHARIA 14.487 22.376 11.227 0 15.103 63.1933 LAMDARHA 34.453 0.5 15.8 0 0 50.7534 SARAITOLA 13.704 0.817 1.865 0 0 16.3865 KARWAHI 1.076 14.551 0 8.632 0 24.2596 TAHILIRAMPUR 2.747 2.66 0.94 0 0 6.347

TOTAL 156.199 98.142 33.513 51.066 42.5 381.42

SL.NO. District Tahasil VILLAGE Khasra Nos. Tribal Non-Tribal GOVT.LAND TOTAL G. Total

1 Raigarh Gharghoda GARE Enclosed 89.732 57.238 3.681 150.651 150.6512 KHAMHARIA Do 14.487 22.376 11.227 48.09 48.093 LAMDARHA Do 34.453 0.5 15.8 50.753 50.7534 SARAITOLA Do 13.704 0.817 1.865 16.386 16.3865 KARWAHI Do 1.076 14.551 0 15.627 15.6276 TEHLIRAMPUR Do 2.747 2.66 0.94 6.347 6.347

TOTAL 156.199 98.142 33.513 287.854 287.854

SL.NO.Name of Forest Division

Name of Forest range VILLAGE

Khasra No. (Revenue Forest)

Chote Jhar Ke Jangal (Revenue Forest)

Compartment No. (P.F.)

Bade Jhar Ke Jangal (P.F.) Total

1 Raigarh Tamnar GARE

4/1,94/1a,113/1a,113/6,113/7,113/8,113/9,113/10,121/2,174/1 (P),162/3(P),162/1(P) 42.434 669 27.397 69.831

2 KHAMHARIA 0 669 15.103 15.1033 LAMDARHA 0 0 04 SARAITOLA 0 0 0 05 KARWAHI 155 8.632 0 8.6326 TAHILIRAMPUR 0 0 0 0

TOTAL 51.066 42.5 93.566

DETAILES OF LAND IN COAL BLOCK GARE IV/6

DETAILES OF REVENUE LAND IN COAL BLOCK GARE - IV/6

DETAILES OF FOREST LAND IN COAL BLOCK GARE - IV/6

ivaturi.rao
Text Box
Annexure -2

Annexure-2- Map

Gare IV/6 Coal Block of Jindal Steel & Power Ltd. [1/5]

VILLAGE WISE AMENITIES IN THE STUDY AREA AS PER CENSUS 2001 CODE NAME OF VILLAGE EDUCATION Medical DRINKING WATER POWER P & T COMMUN- BANKS / CULTURAL APPR. TO INCOME EXPENCES SUPPLY ICATION SOCIETIES FACILITY VILLAGES (Rs. Lc) (Rs. Lc.) DISTRICT : SUNDARGARH TEHSIL : HEMGIR 00375300 Mendra P-1 ALH(>10),MCW(>10), W,TK,HP ED,EO PO(0-5), BS(0-5), COM(5-10), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(0-5) RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00375400 Jamkani P-1 ALH(0-5),MCW(0-5), W,TK,HP ED PO(0-5), BS(5-10), COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- PHC(0-5) Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00375600 Girisima P-1 ALH(>10),MCW(>10), W,TK,HP NA PH-1 BS(5-10), COM(5-10), CV(>10), MR-1,FP-1 -- -- PHC(>10) RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) DISTRICT : RAIGARH TEHSIL : LAILUNGA 00347400 Lamdand P-1,M-1,ALC-1 AYD-1,PHS-1,CHW-1 W,TK,TW,HP ED,EAG PO(0-5), BS-1, COM(>10),COP(>10), CV(>10), MR-1 930 921 Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) TEHSIL : GHARGHODA 00358700 Kudhurmauha P-1 ALH(>10),MCW(>10), W,TK,HP ED PO(5-10), BS(>10), COM(>10),COP(>10), CV(>10), FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00359000 Tilaipali P-1 ALH(>10),MCW(>10), W,HP ED,EAG PO(0-5), BS(>10), COM(>10),COP(>10), CV(>10), FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00359100 Naya Rampur P-1 ALH(>10),MCW(>10), W,HP ED,EAG PO(0-5), BS(5-10), COM(>10),COP(>10), CV(>10), FP-1 -- -- PHC(>10) Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00359300 Bichinara P-1 ALH(>10),MCW(>10), W,TK,HP ED,EAG PO-1 BS(5-10), COM(>10),COP(>10), CV(>10), MR-1 -- -- PHC(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00359400 Raikera P-1,M-1,S-1 PHS-1 W,TK,TW,HP ED PH-1 BS(5-10), COM(>10),COP(>10), CV(>10), MR-1 -- -- RS(>10), SPCL(>10), NW(>10) STAU(>10) 00359500 Pelama P-1,M-1 ALH(>10),MCW(>10), NA ED PO(5-10), BS(>10), COM(>10),COP(>10), CV(>10), PR-1 -- -- PHC(>10) Ph(5-10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00359600 Uraba P-2,M-1,S-1,SS-1 PHS-1,CHW-1 W,HP ED PO-1 BS-1, COM(>10),COP(>10), CV(>10), MR-1 45000 40000 RS(>10), SPCL(>10), NW(>10) STAU(>10) 00359700 Hinjher P-1 ALH(>10),MCW(>10), W,HP ED PO(0-5), BS(0-5), COM(>10),COP(>10), CV(>10), MR-1,FP-1 35000 30000 PHC(>10) Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00359800 Jarhidih P-1 ALH(>10),MCW(>10), W,HP ED PO(0-5), BS(0-5), COM(>10),COP(>10), CV(>10), MR-1,FP-1 25000 21000 PHC(>10) Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00359900 Lalpur P-2 ALH(>10),MCW(>10), W,HP ED PO(0-5), BS(0-5), COM(>10),COP(>10), CV(>10), MR-1,FP-1 25000 22000 PHC(>10) Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00360000 Kharra P-1 PHS-1 W,HP,R ED PO(0-5), BS(0-5), COM(>10),COP(>10), CV(>10), MR-1,FP-1 40000 35000 Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00360100 Maduadumar P-1,ALC-1 ALH(>10),MCW(>10), W,TW,HP ED,EAG PO(0-5), BS(0-5), COM(>10),COP(>10), CV(>10), MR-1,FP-1 30000 25000 PHC(>10) Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00360200 Banjhikhol P-1 ALH(>10),MCW(>10), W,HP NA PO(5-10), BS(5-10), COM(>10),COP(>10), CV(>10), FP-1 20000 18000 PHC(>10) Ph(5-10) RS(>10), SPCL(>10), NW(>10) STAU(>10)

AN

NEXU

RE : VI

CODE NAME OF VILLAGE EDUCATION Medical DRINKING WATER POWER P & T COMMUN- BANKS / CULTURAL APPR. TO INCOME EXPENCES SUPPLY ICATION SOCIETIES FACILITY VILLAGES (Rs. Lc) (Rs. Lc.)

Gare IV/6 Coal Block of Jindal Steel & Power Ltd. [2/5] [gare-6.dbf]

00360300 Semijor P-1 ALH(>10),MCW(>10), W,TK,HP ED,EAG PH-1 BS(5-10), COM(>10),COP(>10), CV(>10), MR-1,FP-1 25000 20000 PHC(5-10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00360400 Chirwani P-1 ALH(>10),MCW(>10), W,HP NA PO(5-10), BS(5-10), COM(>10),COP(>10), CV(>10), MR-1,FP-1 25000 20000 PHC(>10) Ph(5-10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00360500 Sakta P-1 ALH(>10),MCW(>10), W,HP,R EA PO(0-5), BS(0-5), COM(>10),COP(>10), CV(>10), MR-1 -- -- PHC(5-10) Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00360600 Bhalumuda P-1 ALH(>10),MCW(>10), W,TK,HP EA PO(0-5), BS(0-5), COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00360700 Dholnara P-1 ALH(>10),MCW(>10), W,TK,TW,HP EA PO(5-10), BS-1, COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- PHC(0-5) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00360800 Bajarmuda P-1,M-1 ALH(>10),MCW(>10), W,TK,TW,HP EA PH-1 BS-1, COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- PHC(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00360900 Karwahi P-1 ALH(>10),MCW(>10), W,TK,TW,HP EA PO(0-5), BS(>10), COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00361000 Khamahariya P-1 PHS-1,CHW-1 W,TK,TW,HP EA PH-1 BS-1, COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- RS(>10), SPCL(>10), NW(>10) STAU(>10) 00361100 Milupara P-2,M-1 ALH(>10),MCW(>10), W,TK,TW,HP,R EA PO-1,PH-1 BS(5-10), COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- PHC(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00361200 Lamdarha P-1 ALH(>10),MCW(>10), W,HP,R EA PO(5-10), BS(0-5), COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00361300 Kondkel P-1,M-1 PHS-1,CHW-1 W,TK,HP EA PO(5-10), BS(5-10), COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00361600 Kerakhol P-1 CHW-1 HP ED PO(5-10), BS(>10), COM(>10),COP(>10), CV(>10), MR-1 -- -- Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00361700 Chirramuda P-1 CHW-1 W,HP ED,EAG PO(0-5), BS(>10), COM(>10),COP(>10), CV(>10), MR-1 -- -- Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00361800 Banai P-1,M-1 PHS-1,CHW-1 W,HP ED,EAG PO-1,PH-1 BS(5-10), COM(5-10), CV(>10), PR-1 -- -- RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00362000 Barkaspali P-1 CHW-1 HP ED,EAG PO(0-5), BS(5-10), COM(5-10), CV(>10), MR-1 -- -- Ph(0-5) RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00362100 Uttar Regaon P-1 CHW-1 W,TK,TW,HP EA PO(5-10), BS(0-5), COM(>10),COP(>10), CV(>10), FP-1 8000000 300000 Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00362200 Kolam P-1,M-1,S-1,SS-1 CHW-1 W,TK,TW,HP EA PO-1 BS(0-5), COM(>10),COP(>10), CV(5-10), MR-1,FP-1 60000 40000 RS(>10), SPCL(5-10), NW(>10) STAU(>10) 00362300 Chitwahi P-1 CHW-1 W,TK,HP EA PO(0-5), BS-1, COM(5-10), CV(5-10), MR-1 50000 35000 Ph(5-10) RS(>10), COP(5-10), SPCL(5-10), NW(>10) STAU(>10) 00362400 Dolesara P-1,M-1 CHW-1 W,TK,TW,HP EA PO-1 BS-1, COM(5-10), CV(>10), MR-1 90000 60000 RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00362500 Dakshin Regaon P-1,M-1 CHW-1 W,TK,TW,HP EA PO(0-5), BS(0-5), COM(0-5),COP(0-5), CV(>10), MR-1 95000 80000 Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00362700 Salihabhanttha P-2,ALC-1 CHW-1 W,TK,TW,HP EA PO(0-5), BS-1, COM(0-5),COP(0-5), CV(5-10), PR-1 95000 85000 Ph(0-5) RS(>10), SPCL(5-10), NW(>10) STAU(>10)

AN

NEXU

RE : VI C

ontd..

CODE NAME OF VILLAGE EDUCATION Medical DRINKING WATER POWER P & T COMMUN- BANKS / CULTURAL APPR. TO INCOME EXPENCES SUPPLY ICATION SOCIETIES FACILITY VILLAGES (Rs. Lc) (Rs. Lc.)

Gare IV/6 Coal Block of Jindal Steel & Power Ltd. [3/5] [gare-6.dbf]

00362900 Deogarha P-2,M-1,ALC-1 PHS-1 W,HP ED PO-1 BS(5-10), COM(5-10), CV(>10), MR-1 150000 130000 RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00363000 Patrapali P-1,ALC-1 ALH(5-10),MCW(>10), W,HP ED PO(0-5), BS(5-10), COM(5-10), CV(>10), MR-1 15000 15000 PHC(5-10) Ph(5-10) RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00363200 Mauhapali P-1,M-1,ALC-1 ALH(5-10), W,TK,TW,HP ED PO-1 BS(5-10), COM(5-10), CV(>10), MR-1 30000 30000 MCW(5-10),PHC(5-10) RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00366300 Jarekela P-2,M-1 PHS-1,RMP-1,CHW-1 W,TK,HP,R EA PH-1 BS(5-10), COM(5-10), CV(>10), MR-1 -- -- RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00366500 Basanpali P-1 CHW-1 W,TK,TW,HP,R EA PH-1 BS(0-5), COM(5-10), CV(5-10), MR-1,FP-1 -- -- RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00366600 Gorhi P-1,M-1 PHS-1,CHW-1 W,TK,HP ED PO(0-5), BS(0-5), COM(>10),COP(>10), CV(>10), PR-1,MR-1, -- -- Ph(>10) RS(>10), SPCL(>10), FP-1 NW(>10) STAU(>10) 00366700 Tamnar P-4,M-2,S-1,SS-1 ALH-1,AYH-1,ALD-1, T,W,TK,TW,HP,R,C,L EA PO-1 BS-1, COP-1,ACS-1 CV(>10), PR-1,MR-1, -- -- AYD-1,MCW-1,MH-1, RS(>10), SPCL(>10), FP-1 CWC-1,HC-1,PHC-1, NW(>10) STAU(>10) PHS-1,FWC-1 00366800 Budiya P-1,ALC-1 ALH(0-5),MCW(0-5), W,TK,HP,R ED PO-1 BS(0-5), COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- PHC(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00366900 Bagbadi P-1,ALC-1 ALH(5-10), W,TK,HP,R ED PO(0-5), BS(5-10), COM(>10),COP(0-5), CV(>10), MR-1,FP-1 -- -- MCW(5-10),PHC(5-10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00367000 Kunjemura P-1,M-1,S-1,SS-1 PHS-1,CHW-1 T,W,HP,R EA PH-1 BS(5-10), COM(5-10), CV(>10), PR-1,MR-1, -- -- RS(>10), COP(5-10), SPCL(>10), FP-1 NW(>10) STAU(>10) 00367100 Kosampali P-1 CHW-1 W,HP EA PO(0-5), BS(0-5), COM(>10),COP(0-5), CV(>10), FP-1 -- -- Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00367200 Gare P-1 RMP-1,CHW-1 W,TW,HP,R EA PH-1 BS-1, COP-1,ACS-1 CV(>10), MR-1,FP-1 -- -- RS(>10), SPCL(>10), NW(>10) STAU(>10) 00367300 Pata P-2,ALC-1 CHW-1 W,TK,TW,HP EA PH-1 BS-1, COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- RS(>10), SPCL(>10), NW(>10) STAU(>10) 00367600 Sarasmal P-1 CHW-1 W,HP EA PO(0-5), BS(0-5), COM(>10),COP(0-5), CV(>10), MR-1,FP-1 -- -- Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00367700 Tihli Rampur P-1 CHW-1 W,HP,R EA PO(0-5), BS(0-5), COM(5-10),COP(0-5), CV(>10), MR-1,FP-1 -- -- Ph(5-10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00367800 Aamgaon P-2 ALH(>10),MCW(>10), W,TK,TW,HP EA PO-1 BS(0-5), COM(>10),COP(0-5), CV(>10), MR-1,FP-1 -- -- PHC(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00367900 Janjgir P-1 ALH(>10),MCW(>10), W,TK,HP,R EA PO(0-5), BS(5-10), COM(>10),COP(5-10), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00368000 Tapranga P-1 ALH(>10),MCW(>10), W,TK,TW,HP ED,EAG PO(0-5), BS(0-5), COM(>10),COP(>10), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00368100 Tangarghat P-1,M-1 ALH(>10),MCW(>10), W,TK,HP ED,EAG PO-1 BS(5-10), COM(>10),COP(5-10), CV(>10), MR-1,FP-1 -- -- PHC(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00368200 Dongamauha P-1 ALH(>10),MCW(>10), W,TK,TW,HP ED,EAG PO(0-5), BS(0-5), COM(>10),COP(0-5), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10)

AN

NEXU

RE : VI C

ontd

CODE NAME OF VILLAGE EDUCATION Medical DRINKING WATER POWER P & T COMMUN- BANKS / CULTURAL APPR. TO INCOME EXPENCES SUPPLY ICATION SOCIETIES FACILITY VILLAGES (Rs. Lc) (Rs. Lc.)

Gare IV/6 Coal Block of Jindal Steel & Power Ltd. [4/5] [gare-6.dbf]

00368300 Telaipara P(0-5),M(0-5), ALH(>10),MCW(>10), W,HP ED PO(0-5), BS(5-10), COM(>10),COP(5-10), CV(>10), FP-1 -- -- C(>10) PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00368400 Dhaurabhatha P-1,M-1,S-1,SS-1 ALH(>10),MCW(>10), W,TK,TW,HP EA PO-1 BS-1, COM-1,ACS-1 CV(>10), MR-1,FP-1 -- -- PHC(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00368500 Nagramuda P-1 ALH(>10),MCW(>10), W,TK,HP ED,EAG PO(0-5), BS(0-5), COM(>10),COP(0-5), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00368600 Baljor P-1 ALH(>10),MCW(>10), W,HP,R ED PO(0-5), BS(5-10), COM(>10),COP(5-10), CV(>10), FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00368700 Jhinku Bahal P-1 ALH(>10),MCW(5-10), W,TK,HP ED PO(0-5), BS(5-10), COM(>10),COP(5-10), CV(>10), MR-1,FP-1 -- -- PHC(5-10) Ph(5-10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00368800 Libara P-1,M-1 ALH(>10),MCW(5-10), W,TK,R ED PO-1 BS(0-5), COM(>10),COP(0-5), CV(>10), MR-1,FP-1 -- -- PHC(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00368900 Jharna P-2 ALH(>10),MCW(5-10), W,TK,HP ED PO(0-5), BS(0-5), COM(>10),COP(0-5), CV(>10), MR-1,FP-1 -- -- PHC(5-10) Ph(5-10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00369000 Raipara P-1 ALH(>10),MCW(>10), W,TK,HP ED PO(0-5), BS(5-10), COM(>10),COP(0-5), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(5-10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00369100 Samkera P-3,M-1 ALH(>10),MCW(>10), W,TK,HP ED PO-1 BS(5-10), COM(>10),COP(0-5), CV(>10), MR-1,FP-1 -- -- PHC(5-10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00369200 Gourbahari P-2 ALH(>10),MCW(5-10), W,TK,HP ED PO(0-5), BS(0-5), COM(>10),COP(5-10), CV(>10), MR-1,FP-1 40000 39000 PHC(5-10) Ph(5-10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00369300 Mahloi P-2,M-1,S-1 PHS-1,CHW-1 W,TK,HP,R EA PO-1 BS(5-10), COM(5-10), CV(>10), MR-1,FP-1 -- -- RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00369400 Deogaon P-1 CHW-1 W,TK,HP NA PO(0-5), BS(0-5), COM(0-5),COP(0-5), CV(>10), MR-1,FP-1 -- -- Ph(0-5) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00369600 Amalidhondha P-1 ALH(>10),MCW(5-10), W,TK,HP NA PO(0-5), BS(5-10), COM(5-10), CV(>10), MR-1,FP-1 -- -- PHC(5-10) Ph(5-10) RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) 00369800 Jobaro P-1 ALH(>10),MCW(>10), W,TK,HP ED PO(0-5), BS(0-5), COM(>10),COP(5-10), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00370500 Khurus Lenga P-2 ALH(0-5),MCW(>10), W,HP ED PO(0-5), BS-1, COM(0-5),COP(0-5), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(>10) RS(>10), SPCL(>10), NW(>10) STAU(>10) 00370900 Bijana P-1,M-1 ALH(0-5),MCW(>10), W,HP ED PO(0-5), BS(5-10), COM(5-10), CV(>10), MR-1,FP-1 -- -- PHC(>10) Ph(>10) RS(>10), COP(5-10), SPCL(>10), NW(>10) STAU(>10) Source : Village directory, Census of India, 2001

AN

NEXU

RE : VI C

ontd

Gare IV/6 Coal Block of Jindal Steel & Power Ltd. [5/5]

A B B R I V A T I O N S

1. EDUCATION : P Primary school M Middle school S Secondary school SS Senior secondary school C Collage IS Industrial school TS Training school ALC Adult literacy class/centre O Other educational facilities 2. MEDICAL ALH Allopathic hospital AYH Ayurvedic hospital UNH Unani hospital HMH Homeopathic hospital ALD Allopathic dispensary AYD Ayurvedic dispensary UND Unani dispensary HMD Homeopathic dispensary MH Maternity home CWC Child welfare centre MCW Maternity and child welfare centre HC Health centre PHC Primary health centre PHS Primary health sub centre FWC Family welfare centre TB T.B. centre NH Nursing home CHW Comunity health workers RMP Registered private medical practitioners SMP Subsidised medical practitioner O Other medical facilities 3. DRINKING WATER T Tap water W Well water TK Tank water TW Tubewell water HP Hand pump R River water C Canal L Lake S Spring O Other drinking water sources 4. POWER SUPPLY ED Power for Domestic purpose EAG Power for Agriculture EO Power for Ind./Comm. purpose EA Power for all purposes 5. POST AND TELEGRAPH PO Post Office TO Telegraph Office PTO Post & Tele. Office PH Telephone 6. COMMUNICATION BS Bus Stop RS Railway Station NW Navigable waterways 7. BANKS / CREDIT SOCIETIES COM Commercial bank COP Cooperative bank NACS Non agricultural credit societies ACS Agricultural credit societies OCS Other credit societies 8. CULTURAL FACILITIES CV Cinema / Video hall SPCL Sports club STAU Stadium/Auditorium 9. APPROACH TO VILLAGE PR Pucca road MR Mud road FP Footpath NR Navigable river NC Navigable canal NW Navigable waterways (other than river & canal)

TOTAL AMENITIES AVAILABLE IN THESE VILLAGES

1. EDUCATION : Primary school : 90 Middle school : 24 Secondary school : 7 Senior secondary schools : 5 Adult Literacy Centre : 9 2. MEDICAL Allopathic Hospital : 1 Ayurvedic hospital : 1 Allopathc dispensary : 1 Ayurvedic dispensary : 2 Metarnity and child welfare : 1 Maternity home : 1 Child welfare centre : 1 Health centre : 1 Primary health centre : 1 Primary health sub-centre : 13 Family welfare centre : 1 Regd. Pvt. Medi. practiotioner: 2 Comunity health workers : 25 3. DRINKING WATER : Tap Water : 2 Well water : 71 Tank Water : 46 Tube Well Water : 22 Hand Pump : 72 River water : 16 Canal water : 1 Lake water : 1 4. POWER SUPPLY : Power for Domestic purpose : 41 Power for Agriculture : 13 Power for other purpose : 1 Power for all purposes : 28 5. POST AND TELEGRAPH : Post Office : 16 Telephone : 12 6. COMMUNICATION : Bus Stop : 13 7. BANKS/CREDIT SOCIETIES : Commercial bank : 1 Cooperative banks : 2 Agricultural credit society : 3 8. CULTURAL FACILITIES : : Nil 9. APPROACH TO VILLAGE : Pucca road : 6 Mud road : 63 Footpath : 56

Source : Village directory, Census of India, 2001

AN

NE

XU

RE

: XVIII C

ontd. A

NN

EXUR

E : VI Contd

Annexure‐VII  

Terms of Reference for EIA studies 

 

The  proposed  “Gare  PalmaIV/6  block  coal mine”  located  in  at  about  10km North  of  Tamnar  tehsil  of  Raigarh  district  of  Chhattisgarh  state.    The  total mine  lease  area  is 381.42 Ha. Out of  381.42 Ha,  93.566 Ha  is  forest  land designated  as Chhote  jhad  ke Jungle  and  Bade  Jhad  ke  Jungle  .  The  Land  of  lease  area  lies  within  the  villages Lamdarha, Saraitola, Gare, Khamharia , Tehlirampur and Karwahi. 

This proposed mine having an ML area of 381.42 Ha  is planned  for 4.00 MTPA.   Coal Washery and facilities is also proposed to be established within the ML area of Gare IV/6 adopting heavy media cyclone process. The  capacity of washery will be 700TPH  (4.00 MT/Annum). 

Jindal  Steel  &  Power  Limited  and  Nalwa  Sponge  Iron  Limited,  registered  under Companies Act, 1956 have been allotted by Central Government  for mining coal  from Gare‐IV/6 Block and supply it on an exclusive basis to their e sponge iron plants situated at Raigarh and Taraimal respectively. 

Gare IV/6 obtained for Terms of Reference for EIA studies on 28‐03‐2007 in accordance with EIA notification 2006.     Draft EIA  report was prepared based on  summer  season 2006  data  and  Public  hearing  was  conducted  on  05‐01‐2008  by  CECB.    After  due considerations in various EAC meetings, MoEF has accorded Environmental clearance on 18‐05‐2009.  

However, National Green Tribunal  (NGT) has set aside the Environmental Clearance  in its order 20‐04‐2012 with a directive to  reconduct the public hearing  by taking steps  as required under the law. 

 Incompliance to the same  it  is proposed to prepare EIA–EMP report, submit for Public Hearing  and  seek  Environmental  Clearance  from  the  Ministry  of  Environment  and Forests  (MoEF),  New  Delhi  as  per  the  EIA  Notification  of  September  2006  and  its subsequent amendments. The scope proposed in the TOR is as follows: 

  1.0 DATA GENERATION: 

The EIA‐ EMP Report  shall be  in accordance with     Terms of Reference  for Coal Mine   Opencast cum underground and coal washery     prescribed by MoEF. The data  for  the same shall be based on 

1) Baseline data of earlier  EIA–EMP report  as submitted for Public hearing  2) Recent data collected for the adjoining coal mines of  Gare IV/2 & IV/3 and Gare 

IV/1 

3) One month filed sampling 

Additionally, all the data /information as furnished to MoEF during appraisal process  in various EAC meetings from time to time such as,  

i. Hydrogeology and Status of Ground Water Resources 

ii. Ground Water  Conservation , Recharge Plan  and Monitoring Plan 

iii. Habitat Management & Restoration Plan 

iv. Socio Economics Status based on UNDP’s Human Development Indices 

  

1.1 AUGMENTATION DATA     One month base line environmental data will be generated by MOEF/ NABL accredited 

laboratory as given in Table 1.  

TABLE 1:  DATA GENERATED  

Sl. No.  Description  No. of locations  Total No of samples 

 1.0  

  

AIR Ambient air monitoring (24 hourly samples), twice a week for one month  Parameters : PM10, PM2.5, SO2, NOx 

8 (one in core zone and 7 in buffer 

zone) 

 64 

 

1.1    

 

Meteorological parameters measured at hourly duration simultaneously at one air monitoring station for one months. Parameters : a.  Wind speed, direction b.  Relative humidity c.  Temperature d.   Rainfall 

1  30 days 

 2.0  WATER Water /effluents sample collected various locations (surface and ground water) in core and buffer zone (10 km radius) Parameters : drinking water as per IS 10500 or effluents as per schedule VI of EPR 

upto 10  upto 10 

3.0  SOIL   2  2 

4.0  NOISE Hourly readings taken for 24 hours (Leq) 

10  10 sets 

5.0  TRAFFIC DENSITY  1  1 sets 

   

2.0  DATA COLLECTION  

The EIA study shall be carried for the mine (core zone) and area within 10.0 km radius (buffer zone), both of which comprise the ‘study area’. The following data, through field survey  and  other  sources,  shall  be  collected  by  various  agencies  and  specialists  of different expertise for preparing the EIA/EMP for the proposed Mine and Washery with related facilities. 

 i  Study of fauna, flora, forests and cropping pattern. ii  Major habitats, ecologically sensitive areas, biosphere reserves, wildlife 

sanctuaries within 15 km of the project site. iii  Major industries and places of historical/ archaeological importance  iv  Land use pattern within core zone and buffer zone v  Geo‐hydrological aspects based on available data from various secondary 

sources.  vi  Demography and Socio‐economic based on last available Census data for 

entire study area vii  Relevant meteorological data, for previous decades from India 

Meteorological Department (IMD) viii   Identification of water bodies, hills, roads etc. ix   In case of operational plant, emissions data and details of implemented 

pollution control systems    3.0   PREPARATION OF EMP     The EMP includes the following details    a  Study of the reports like Geological report, FR for mine  regarding the project.    b   Present Environmental Setting     The base  line data  generated  and  collected  as per para  1.0  and  2.0 has been 

used to establish the present environmental scenario.    c  Identification, prediction and evaluation of Anticipated Environmental Impacts 

due to the Proposed Mine and related facilities      The environmental impacts would be anticipated in core and buffer zone on: 

‐  Topography 

‐  Climate 

‐  Water Quality (Surface/Ground) 

- Hydro‐geological Regime 

- Air quality 

‐  Noise Levels 

‐  Flora and Fauna (terrestrial, aquatic) 

‐  Traffic density 

‐  Land‐Use 

‐  Socio‐Economic Conditions 

‐  Habitat 

‐  Health, culture, human environment including public health, occupational health and safety 

‐  Sensitive Places/Historical Monuments 

‐  Aesthetics and Visual intrusion  

The impacts would be anticipated based on experience of similar projects and success of this mine operation during the past. 

 d  Proposed Environmental Safeguards and Monitoring Mechanism   Relevant  guidelines,  as  per  Environmental  Impact  Assessment  (EIA) Notification  no. 

S.O. 1533 dated September, 2006 and its amendments till date under the Environment (Protection) Act, 1986, will be kept in mind while spelling out mitigation measures. The following aspects would be covered.  

   The following aspects have been covered  

i  Reclamation of areas disturbed during construction but not required for any activity during operation. 

ii  Measures to control the surface and ground water pollution due to various effluents to be discharged  

iii  Measures to control air pollution due to proposed activities/ operation. 

iv   Green belt development and identification of flora species which can be planted in and around the project 

v   Measures to contain noise pollution and mitigate adverse impact on workers and habitat in core and buffer zone 

vi  Pronounce the improvement in socio‐economic conditions and benefits the people will get on implementation of the project 

vii   Measures to control health hazard of workers and surrounding population 

viii   Total and specific cost of implementation of pollution control measures 

ix  Environmental monitoring, implementation organization and feedback mechanism to effect mid course corrections. 

x  Summary of impact due to displacement, if any xi.  Solid Waste Management 

   The experience of  similar project(s) will be made use of  for envisaging  the pollution 

control measures by pronouncing the success in the past.