application for resource consent under section 88 of the...
TRANSCRIPT
Application No: 37549 and LR-213194 Page 1
Application for Resource Consent under Section 88 of the Resource Management Act 1991 by Auckland Council (formerly North Shore City Council) to construct a 40m long pedestrian bridge and associated activities over the Wairau Creek, Milford, to occupy part of the common marine and coastal area with the bridge, and use it for public access purposes.
TO: Resource Consent Hearing Commissioners
FROM: Sam Morgan – Senior Consents and Compliance Advisor- Coastal DATE: 26 March 2012 NOTE: This report sets out the advice of the reporting planner. This report has yet to be considered by the Panel of Commissioners delegated by the Council to determine this application. The recommendation is not the decision on this application. A decision will only be made after the Commissioners have considered the application and heard the applicant and any submitters.
1.0 APPLICATION DESCRIPTION
1.1 Application and Property Details
Application Number (s): 37549 and LR - 2131943
Reporting Officer: Sam Morgan – Senior Consents and Compliance Advisor- Coastal
Site Address: The CMA spanning the Wairau Creek and the esplanade/road reserve between Inga/ Beach Road and Milford Reserve
Applicant's Name: Auckland Council (formerly North Shore City Council)
Lodgement Date: 11 May 2010
Notification Date: 17 September 2010
Application No: 37549 and LR-213194 Page 2
Submissions Close Date: 15 October 2010
Number of Submissions Received:
59 in support
98 in opposition
47 submitters wish to be heard
1.2 Locality Plan
Figure one – approximate location of footbridge and temporary mooring (lay-over) area.
1.3 Application Documents (Plans and Reference Documents)
Approximate location of footbridge and temporary
mooring area
Application No: 37549 and LR-213194 Page 3
The plans and reference documents associated with the application are:
Report: Dated 5 May 2010, ‘Wairau Stream Pedestrian Bridge Assessment of Environmental Effects’. Prepared by: Beca Carter Hollings & Fraser (Beca).
Dated 2 June 2010, ‘Wairau Stream Weir – Assessment of Environmental Effects’. Prepared by: Beca.
Dated 28 July 2010, ‘Wairau Stream Pedestrian Bridge – Further Information’. Prepared by: Beca.
Correspondence: Dated: 6 September 2010, titled ‘Wairau Stream Pedestrian Bridge – section 92 Response’.
Dated: 19 October 2010, titled ‘Wairau Stream Pedestrian Bridge – section 92 Response (2)’.
Dated: 17 August 2011, titled ‘Wairau Stream Pedestrian Bridge – Supplementary Information’.
Dated: 22 December 2011, titled ‘Wairau Stream Pedestrian Bridge – Second Supplementary Information Letter.
Plans: Dated: January 2010, ‘Wairau Stream Footbridge, Proposed footbridge and general arrangement sheet 1.’ Dwg. No. 4242890-R-001, Rev. A. Drawn by BECA.
Dated: January 2010, ‘Wairau Stream Footbridge, Proposed footbridge and general arrangement sheet 2.’ Dwg. No. 4242890-R-002, Rev. A. Drawn by BECA.
Dated: 14 April 2010, ‘Wairau Bridge, Indicative plan for temporary mooring area.’ Dwg. No. 4242890-C-100, Rev. A. Drawn by BECA.
Dated: 14 April 2010, ‘Wairau Bridge, Temporary mooring area.’ Dwg. No. 4242890-C-101, Rev. A. Drawn by BECA.
1.4 Adequacy of Information
Application No: 37549 and LR-213194 Page 4
It is considered that the information submitted by the applicant is sufficiently
comprehensive to enable the consideration of the following matters on an informed basis:
a) The nature and scope of the proposed activity as it relates to the regional plan and
district plan.
b) The extent and scale of any adverse effects on the environment.
c) Persons who may be adversely affected.
d) The requirements of the relevant legislation.
e) A request for further information under section 92 of the RMA was made on 11
May 2010 prior to notification.
f) A subsequent section 92 request was made 13 August 2010 in response to issues
raised through the notification process. The final submission of information
addressing these issues was received on 25 August 2011.
1.5 Report and Assessment Methodology
The application has been prepared to a good standard incorporating a number of expert
assessments. In recognition of the standard of this application, this report will not
unnecessarily repeat descriptions or assessments made in the application. A separate and
independent assessment of the application has been undertaken on behalf of the Auckland
Council, as the consent authority, to review technical aspects as required. Where
descriptions or assessments provided on various aspects of the proposal are agreed, the
report simply confirms agreement with those aspects. If there are differences in opinion or
matters that need more assessment, consideration or discussion in the report or indeed
there are matters that are considered inaccurate, incorrect or that have been missed or
there is disagreement with opinion or approaches, the report will detail these assessments
and opinions (of Council experts) where relevant. Where appropriate, extracts from the
application material or from the Council expert reports will be included to enable this report
and assessment to be clearly understood.
This assessment relies upon reviews and advice from the following experts on behalf of the
Auckland Council and specialist officers. These assessments are attached in Appendix 2 of
this report:
Mt. Hobson Group- Landuse Planner- Nick Mathieson
Application No: 37549 and LR-213194 Page 5
Auckland Transport- Traffic Engineer- Warren Budd
Auckland Council’s Marine Scientist - Dr Jarrod Walker;
LA4 – Landscape Architects – Rob Pryor; and Tonkin and Taylor Limited – Richard Reinen-Hamill.
2.0 EXECUTIVE SUMMARY
2.1 Auckland Council (the applicant) seeks resource consents under the Auckland Council
Regional Plan (Coastal) (coastal plan) and Auckland Council District Plan (North Shore
Section) (district plan)to construct a 40m long pedestrian bridge over the Wairau Creek
connecting Inga / Beach Road with Milford Reserve. The applicant seeks to occupy part of
the common marine and coastal area with the bridge and to use the bridge for the purpose
of public access.
Associated with the construction of the bridge will be the construction of a temporary
mooring (lay-over) area in the Wairau Creek seaward of the proposed bridge and install
navigation markers. In order to construct the temporary mooring area it will be necessary to
dredge approximately 500m3 of sediment from 102m2 of the Wairau Creek. The applicant
seeks occupation of the part of the common marine and coastal area with the temporary
mooring area and to use it for laying-over vessels.
The applicant seeks resource consent to lay electrical cables across the bed of the Wairau
Creek, to occupy part of the common marine and coastal area with the cables and the use
of the cables to connect the bridge to an appropriate power supply.
The applicant seeks resource consent to undertake ancillary work within the esplanade/road
reserve at Inga/Beach Road and Milford Reserve to accommodate the construction of the
bridge and associated electrical and mechanical equipment and the erection of signs and a
lighting column.
The individual physical effect of the activities for which consent is being sought under the
regional and district plans have been assessed as being no more than minor.
The resource consent applications sought are considered to be consistent with the objective
and policies of the New Zealand Coastal Policy Statement 2010, the Hauraki Gulf Marine
Application No: 37549 and LR-213194 Page 6
Park Act 2000, the Auckland Council Regional Policy Statement, the Auckland Council
Regional Plan (Coastal) and the Auckland Council District Plan (North Shore Section). It is
recommended that consent be granted subject to conditions, subject to any new or contrary
evidence being presented at the hearing.
3.0 THE PROPOSAL, SITE AND LOCALITY DESCRIPTION
3.1 Proposal
The applicant has applied to construct a pedestrian bridge approximately 4 metres seaward
of an existing weir, across the Wairau Creek. The proposed bridge is to be 3 metres wide
and will span approximately 40 metres over the Wairau Creek, connecting Inga/Beach Road
and Milford Reserve. Approximately 36 metres of the bridge length will be situated within the
CMA. The remainder of the bridge will be located in the esplanade/road reserve at
Inga/Beach Road and Milford Reserve. The proposed bridge will incorporate a 9 metre long
vertical lifting span which will be situated above the existing access channel in the centre of
the Wairau Creek.
The original application sought that the bridge operate based on tidal movements with the
bridge remaining in the upright position for approximately 3 hours either side of high tide
and down the remainder of the time. Through the application process this operational
procedure has been changed to an ‘on-demand’ system. This means the lifting span will rise
at the request of boat users either entering or exiting the marina. When boats are not using
the channel, the bridge will be in the down position so pedestrians will be able to cross the
CMA between Inga/Beach Rd. and Milford Reserve.
In order assist navigation through the lifting span it is proposed to install 3 navigational
markers leading up to and through the gap in the bridge. The 300mm diameter timber
markers will protrude approximately 3 metres above the seabed and 1.5 above MHWS.
Approximately 8 fender piles will be installed on the eastern and western sides of the bridge
to protect the bridge piles from potential damage by vessels.
The bridge will incorporate lighting on the handrails that will be fitted facing down to
illuminate the bridge deck at night. Lighting will also be installed in the bottom of the lifting
Application No: 37549 and LR-213194 Page 7
span in order to assist navigation past the weir and bridge at night.
Electrical ducting will be placed under the creek bed to connect the eastern bridge lighting,
warning systems and gate mechanics to a power supply located on the Inga/Beach Road
side of the creek. The applicant has advised that the electrical ducting is to be grouted in a
trench in the creek bed. These works will be carried out during low tide. The structure will
consist of a 200mm square wide trench excavated across the main navigational channel.
A 30 metre long temporary mooring (lay-over) area will be provided along the eastern bank
of the Wairau Creek, seaward of the proposed bridge. That area will provide a lay-over area
for boats intending, but unable to pass the bridge when the bridge is down or if two boats
meet each other whilst trying to navigate the channel. It will include two 10m x 2m concrete
platforms for vessels to rest on. In order to facilitate the mooring area, the applicant
proposes to install 11 timber mooring poles and dredge approximately 500m3 of the Wairau
Creek to a depth of 0.5 below chart datum, the same depth as the existing adjacent access
channel.
Earthworks of approximately 135m2 will be undertaken in the Milford Reserve to
accommodate the construction of the bridge and associated electrical and mechanical
equipment. Ancillary works will involve the erection of signs in the esplanade/road reserve
at Inga/Beach Road and Milford Reserve advising the public of the operation of the bridge
together with a lighting column in the Milford Reserve.
An existing concrete footpath traverses along and across part of the Wairau Creek
connecting the roadside footpath on Inga Road across the creek, and up to a footpath within
Milford Reserve. The path is only exposed during periods of low tide. The applicant has
advised that despite maintenance attempts, the path is often slippery and is deemed to be a
health and safety hazard, and use of it is now discouraged. The applicant advises that the
retention or removal of the path is dependent on whether resource consent is granted to
construct the footbridge. The applicant in a letter to the ARC dated 28 July 2010 has
advised that that part of the footpath that is below MLWS will be removed if resource
consent is granted to construct the footbridge. If the pedestrian bridge is not constructed
the applicant proposes, to retain the footpath, subject to resource consents being issued.
Application No: 37549 and LR-213194 Page 8
3.2 Site, locality, catchment and environs description
The application site and surrounding environment is described in detail in section 4.0 of the
AEE and in the landscape and visual assessment accompanying the AEE prepared by
Stephen Brown Environments Ltd.
Of particular relevance is the following comment from the AEE.
“Wairau Stream is, for the most part, a highly modified urban watercourse within a heavily
engineered and constrained alignment. Development of the Milford Reserve, the Milford
Marina and Brian Byrnes Reserve, have eroded the streams natural character to a point
where only the coastal escarpments to the north of the creek mouth retain any real natural
character”.
The Milford Marina occupies approximately 3 hectares of the creek to the south of the
proposed bridge. Wairau Creek between the location of the proposed footbridge and the
Inga Road Bridge, has been dredged and structurally retained and provides approximately
225 marina berths for mainly small (approximately 8 – 10m) boats. Other man-made
structures in the vicinity of the marina include slipways, jetties, pontoons and pile moorings.
Tidal influence on Wairau Creek has been controlled by the existing weir at the entrance of
the marina.
Land development in the vicinity of the proposed footbridge is mainly concentrated to the
east and west along Craig Road and Inga/Beach Road. Two reserves are located in the
vicinity of the site, namely Brian Byrnes Reserve and Milford Reserve. The immediate area
also includes a number of local services as well as established residential neighbourhoods
comprising Milford and Crown Hill.
That part of Wairau Creek hat comprises the marina is classified in the coastal plan as a
Marina Management Area and the creek that connects the marina to the sea is identified as
a General Management Area.
Overall the proposed footbridge and associated activities are to be considered in the
context of an environment which has been modified by urban development.
Application No: 37549 and LR-213194 Page 9
3.3 Background
The applicant has advised that a pedestrian link across the Wairau Creek will “reduce
open space deficiency affecting residents to the north and west of Milford Reserve”. The
reporting planner’s understanding of this is that the footbridge is aimed at improving
access to existing areas of open space. The applicant has allocated funds in the Long
Term Council Community Plan (LTCCP) towards consenting of a pedestrian bridge
across the Wairau Creek.
On 14 September 2006, following community consultation, the Community and Parks
Committee of the former North Shore City Council (NSCC) approved changes to the
Milford Reserve Management Plan which states:
“A bridge structure may be provided across the Wairau Stream in keeping with, and
sensitive to, the needs of both the marina and reserve users. Any access ways to such a
structure shall have a minimum impact on the environment and open space of the
reserve”.
The applicant has advised that the design of the bridge has been undertaken in
conjunction with the public consultation that has been on-going since 2004. This is when
the NSCC commissioned the development of a number of functional concepts for the
crossing of the Wairau Creek. As a result, seven concepts were put to the public for
comments. Following stakeholder consultation an opening bridge near the weir was
selected.
In February 2007, NSCC commissioned Beca to further develop the winning concept
design and submit a cost estimate for the construction of the bridge. On-going
refinement of the proposal has resulted in the submission of the present proposal.
3.4 Other Consents No other consents are required.
Application No: 37549 and LR-213194 Page 10
4.0 REASONS FOR THE APPLICATION
Resource consents are required under the provisions of the following Regional Plan and
District Plan. 4.1 Regional Plan 4.1.1 Operative Regional Plan – Auckland Council Regional Plan (Coastal)
Consent is required under the following provisions of the Auckland Council Regional Plan: Coastal.
Erection of the footbridge
Rule 12.5.18: The erection of the footbridge (which is not provided for in any other rule contained in chapter 12 and is not located in a Coastal Protection Area 1) is a discretionary activity;
Rule 10.5.9: occupy part of the common marine and coastal area with the footbridge is a discretionary activity;
Rule 11.5.5: The use of the footbridge for public access purposes in the CMA is a discretionary activity;
Laying of power cables
Rule 12.5.18: The laying of electrical ducting in a chase across the creek bed, is a discretionary activity;
Rule 10.5.9: occupy part of the common marine and coastal area with the electrical cables is a discretionary activity;
Rule 11.5.5: The use of the cabling in association with the operation of the footbridge is a discretionary activity;
Dredging of Wairau Stream
Rule 15.5.10: dredging of up to 500m3 of sediment from the seabed (capital works) for the purpose of providing the temporary mooring (lay-over) area is a discretionary activity.
Construction of a temporary mooring (lay-by) area
Rule 24.5.5: Moorings including the vessel proposed to be moored and their occupation (outside the Mooring Management Area, but not within any
Application No: 37549 and LR-213194 Page 11
Coastal Protection Area 1 or Special Activity Area) is a discretionary activity.
Rule 11.5.5: The use of the temporary mooring (lay-over) area is a discretionary activity;
Rule 12.5.18: The erection of the concrete pads associated with lay-over area (which is not provided for in any other rule contained in chapter 12 and is not located in a Coastal Protection Area 1) is a discretionary activity;
Note that installation of the proposed navigation markers is considered a permitted activity under rule 12.5.4.
4.2 District Plan
4.2.1 Operative District Plan – Auckland Council District Plan (North Shore Section)
The erection of the bridge and associated mechanical and electrical equipment in the
Coastal Conservation Area is a controlled activity under Rule 8.4.1.1.
The erection of the bridge and associated mechanical and electrical equipment in the
Recreation 2 Zone and the Road Zone is a non-complying activity under Rule 3.10.2.2.
The undertaking of 135m2 of earthworks, and associated site works within the foreshore
yard associated with the erection of the bridge and lighting pole, which is a non-
complying activity is a non-complying activity under Rule 9.4.1.5.
The erection of signs in the Road Zone are a discretionary activity under Rule 13.4.2.
The erection of signs in the Recreation 2 Zone are a permitted activity under Rule
13.4.1.9.
The erection of a light and associated pole, within the Recreation 2 Zone and Coastal
Conservation Area is a non-complying activity under Rule 19.5.1.
4.3 Status of the Application
Where more than one activity is involved, as in this case, and those activities are inextricably linked, (again as in this case) the general rule is that the activities should be bundled.
It is considered that the applications sought under the regional and district plans are
Application No: 37549 and LR-213194 Page 12
sufficiently interrelated that they should be considered together in the interest of integrated resource management.
Overall the application is a Non-Complying Activity.
5.0 NOTIFICATION AND SUBMISSIONS
5.1 Notification
The application was publicly notified on 17 September 2010 at the request of the applicant in accordance with section 95A(2)(b) of the RMA.
5.2 Submissions
At the close of the submission period, total of 154 submissions were received with a
further three submissions received after the close of submissions. The late submissions
were G Shaw (one day late), J Revill and Takapuna Residents Association ( three days
late).
The decision on whether to extend the closing date for submissions rests with the
Hearing Commissioners pursuant to section 37 of the Act and the factors that must be
considered in making this decision are:
a) the interests of any person who, in Council’s opinion, may be directly affected by
the waiver;
b) the interests of the community in achieving adequate assessment of the effects
of the proposal, and
c) Council’s duty under s21 of the Act to avoid unreasonable delay.
A later section of this report will address the above matters and make a recommendation
to the Hearing Commissioners.
A total of 59 submissions supported the application and 98 opposed the application. A
total of 47 submitters have stated that they wish to be heard.
A summary of the issues raised in submissions together with the relief sought by the
submitters is set out below:
Application No: 37549 and LR-213194 Page 13
Please note that the information set out below is only a summary of the key issues
raised in submissions. Please refer to the full set of submissions as required. These are
attached in Appendix 3 to this report.
The following tables identify the following:
• the issues raised in submissions in terms of the key issues; and
• details any relief sought.
Summary of Submissions in Opposition
Issues Raised
(1) The bridge is an unnecessary expense – 29 submissions;
(2) Adverse visual and landscape effects of the bridge in the upright position – 26
submitters;
(3) More cost efficient to upgrade the existing access on the established footpaths
along Beach Road and Inga Road to Milford Reserve – 26 submissions;
(4) Lack of information regarding the operation of the bridge, maintenance and back-up
systems to deal with malfunctions – 25 submissions;
(5) On-going costs of maintenance will be borne by rate payers – 20 submissions;
(6) The bridge will impede the on-going management and access to the marina – 15
submissions;
(7) The bridge will be a hazard to navigational safety – 15 submissions;
(8) Increased car parking effects in the vicinity of the marina and Milford Reserve – 14
submissions;
(9) Adverse noise and lighting effects associated with the bridge warning systems – 12
submitters;
(10) Lack of details in regard to a management plan for the lay-over area and the
allocation of responsibility in the event of a bridge failure – 11 submissions;
(11) The bridge will create problems for pedestrian safety – 10 submissions;
(12) The bridge will only benefit a small minority of resident – nine submitters;
(13) The bridge will prevent access to the marina by the dredging barge – seven
submissions;
(14) The bridge will be liable to vandalism – seven submissions;
(15) The bridge will only be available to pedestrians for a limited time due to the extent
Application No: 37549 and LR-213194 Page 14
of time it will be in the upright position – six submitters;
(16) Conflict between boaties navigating the Wairau creek and pedestrians accessing
the reserve over the bridge – five submissions;
(17) The lay over area is inadequate in length to accommodate boats stranded in the
event of the bridge malfunctioning – five submissions;
(18) Lack of information regarding who is responsible for maintenance dredging of the
lay over area – one submission;
Summary of Submissions in Support
Issues Raised
(1) The bridge will enhance the accessibility of the beach – 19 submitters;
(2) The bridge fulfils a promise made to residents when the previous bridge was
demolished - 19 submitters;
(3) The bridge will enhance the Te Araroa - coastal walkway – 12 submitters;
(4) General support for the bridge however, no specific reasons mentioned – 11
submitters.
(5) The bridge will improve the amenity of the built environment – 10 submitters;
(6) The bridge will encourage walking and cycling – nine submitters;
(7) The bridge will relieve congestion on local roads and parking pressure around the
beach and reserves – six submitters;
(8) The bridge will provide a safer pedestrian access to Milford Reserve when
compared to the current situation (along Inga and Beach Road) – five submitters;
(9) The bridge will replace an existing footpath running across the bed of the Wairau
Creek which is unsafe and dangerous – three submitters;
(10) The provision of a temporary lay over area will improve safety for boaties accessing
the marina – two submitters; and
(11) The bridge will reduce the time taken to access the beach – one submitter;
Relief Sought
Submitters opposing the applications sought the following relief:
• The applications be either refused, withdrawn or not proceed further and
alternative options be considered;
Application No: 37549 and LR-213194 Page 15
• The applications be declined but dredging and improving the cill be allowed;
• The applications be withdrawn unless access for the marina for boaties could be
maintained for a period of 3 hours either side of high tide;
• Ensure that if the bridge fails it should default to the upright position so as not to
restrict access to the marina; and
• Provide an alternative route around the marina to the Milford Reserve and the
beach for pedestrians.
A number of submitters supporting the applications sought the following relief
• A revised design for the bridge be sought in regard to its width and lifting
mechanism;
• A silent LED screen be used to warn pedestrians and other users when the
bridge is about to be moved;
• A condition be imposed allowing the bridge to be left in the down position longer
than currently proposed when major events are being held in the adjoining
reserve;
• A revised bridge operation methodology be considered reducing the amount of
time the bridge is in the upright position to 1 hour either side of high tide; and
• A condition be imposed allowing the bridge operation methodology to be
reviewed within 3 years.
Three late submissions have been received from Takapuna Residents Association, G W Shaw
and J N Revill. Takapuna Residents Association and G W Shaw oppose the applications. While
J N Revill gave conditional support, suggesting that the bridge be reduced in width to 2.5m.
Application No: 37549 and LR-213194 Page 16
6.0 CONSIDERATION OF APPLICATION
6.1 Statutory Considerations
When considering an application for a non complying activity the consent authority must
have regard to Part 2 of the RMA (“Purposes and Principles” – sections 5 to 8), and
sections 104, 104B and 104D of the RMA.
Subject to Part 2 of the RMA, when considering an application for resource consent and
any submissions received a council must, in accordance with section 104(1) of the RMA
have regard to:
• any actual and potential effects on the environment of allowing the activity;
• any relevant provisions of a NES, other regulations, national policy
statement, a New Zealand coastal policy statement; a regional policy
statement or proposed regional policy statement; a plan or proposed plan;
and
• any other matter a council considers relevant and reasonably necessary to
determine the application.
Section 104(2) allows any effects that may arise from permitted activities set out in a
NES or a plan to be excluded from the assessment of effects related to the resource
consent. This is known as the permitted baseline test. The ‘baseline’ constitutes the
existing environment (excluding existing use rights) against which a proposed activity’s
degree of adverse effect is assessed. Generally it is only the adverse effects over and
above those forming the baseline that are relevant when considering whether the effects
are minor. It is at the Council’s discretion whether to apply the assessment of the
permitted baseline to any proposal. Essentially, the consent authority may disregard an
adverse effect of any activity on the environment if a NES or an operative plan (or an
operative rule in a proposed plan) permits an activity with that effect.
When considering an application for resource consent, the consent authority must not
Application No: 37549 and LR-213194 Page 17
have regard to trade competition or the effects of trade competition [section 104(3)(a)(i)]
or any effect on a person who has given their written approval to the application [section
104(3)(a)(ii)].
Under section 104B a consent authority may grant or refuse consent for a non
complying activity and, if it grants the application, may impose conditions under section
108 of the RMA.
Section 104D sets out the ‘threshold test’ for non-complying activities. A consent
authority may only grant consent to a non complying activity if it is satisfied that the
adverse effects on the environment are minor, or the activity will not be contrary to the
objectives and policies of the relevant plan or proposed plan. If either of the limbs of the
test has been passed then the application is able to be considered for approval subject
to consideration under section 104 of the RMA.
Section 108 provides for consent to be granted subject to conditions and sets out the
kind of conditions that may be imposed.
All considerations are subject to Part 2 of the RMA, which sets out the purpose and
principles that guide this legislation. This means the matters in Part 2 prevail over other
provisions of the RMA or provisions in planning instruments (e.g. regional plans) in the
event of a conflict. Section 5 states the purpose of the RMA and sections 6, 7 and 8 are
principles intended to provide additional guidance as to the way in which the purpose is
to be achieved.
The application of section 5 involves an overall broad judgement of whether a proposal
will promote the sustainable management of natural and physical resources. The RMA’s
use of the terms “use, development and protection” are a general indication that all
resources are to be managed in a sustainable way, or at a rate which enables people
and communities to provide for their social, economic, and cultural wellbeing, and for
their health and safety, while sustaining the potential of natural and physical resources
to meet the reasonably foreseeable needs of future generations, safeguarding the life-
supporting capacity of air, water, soil and ecosystems, and avoiding, remedying and
mitigating any adverse effects of activities on the environment. The enabling and
management functions found in section 5(2) should be considered of equal importance
Application No: 37549 and LR-213194 Page 18
and taken as a whole.
Sections 6, 7 and 8 of the RMA provide further context and guidance to the constraints
found in section 5(2)(a),(b) and (c). The commencing words to these sections differ,
thereby laying down the relative weight to be given to each section.
Section 6 of the RMA sets out the matters of national importance which need to be
recognised and provided for and includes among other things and in no order of priority,
the protection of outstanding natural features and landscapes, the protection of areas of
significant indigenous vegetation and significant habitats of indigenous fauna, and the
protection of historic heritage. In the case of this particular proposal the following
matters are considered relevant: the preservation of the natural character of the coastal
environment and the maintenance and enhancement of public access to and along the
coastal marine area. Relevant matters are considered in the evaluation section of this
report.
Section 7 of the RMA requires the consent authority to give particular regard to those
matters listed in the section. Section 7 matters are not expressly ranked in order of
priority. Therefore, all aspects of this section are to be considered equally. In the case
of this particular proposal the following matters are considered relevant: the efficient use
and development of natural and physical resources and the maintenance and
enhancement of amenity values, maintenance and enhancement of the quality of the
environment. Relevant matters are considered in the evaluation section of this report.
Section 8 of the RMA requires the consent authority to take into account the principles of
the Treaty of Waitangi. This section of the RMA recognises the relationship of Tangata
Whenua with natural and physical resources and encourages active participation and
consultation with Tangata Whenua. Any relevant matters are considered in the
evaluation section of this report.
Application No: 37549 and LR-213194 Page 19
6.2 Section 104(1)(a) Actual and potential effects on the environment 6.2.1 Effects that must be disregarded
A) Any effect on a person who has given written approval to the application
In this case, no written approvals were provided by the applicant which could be
considered in terms of section 104(3).
6.2.2 Effects that may be disregarded – Permitted Baseline Assessment
Case law has established that the permitted baseline refers to the existing
environment and potential environment, which is comprised of what could be
undertaken by way of unimplemented resource consents and what could be
undertaken as of right (i.e. permitted by the relevant planning documents) but
which are not fanciful. The Council may disregard affects which the coastal plan
and district plan permit. Section 104(2) enables the consent authority to disregard
an adverse effect of an activity on the environment if a plan permits an activity with
that effect.
A description of the site and its surroundings is set out above and there are no
relevant unimplemented consents in respect of the site.
In this case, the types of effects associated with the construction of the proposed
bridge and lay-over area and the undertaking of earthworks are such that the
permitted baseline does not provide a useful comparison for the purpose of
discounting effects
6.2.3 Assessment of Effects
The following assessment of the adverse effects of the proposed coastal works on
the environment addresses the actual and potential adverse effects of the activity,
and distinguishes between the adverse effects of the proposed works and those that
may arise as a result of a permitted activity.
The policy framework and matters for discretion in the coastal plan is used as the
context for assessing the potential adverse environmental effects that may arise
Application No: 37549 and LR-213194 Page 20
from the proposed activities within the CMA. Similarly, the policy framework and
relevant assessment criteria of the district plan are applied to all matters associated
with the erection of the bridge, signage and associated earthworks.
It is considered that those areas where effects may arise in the CMA are generally
related to landscape and natural character, ecology and water quality, navigation
and safety, public access, cultural heritage, historic heritage, construction effects,
noise effects and cumulative effects. The following comments are therefore made in
respect of these matters.
In summary, it is considered that the adverse effects of the proposal on the
environment are likely to be no more than minor.
Effects on Landscape and Natural Character
Twenty six submitters raised issues around the landscape and visual impact of the
project. Rob Pryor of LA4 Landscape Architects was commissioned in late 2010 to
assess and review the proposal’s impact upon the local landscape and natural
character values. This assessment has been updated in accordance with the
changes to the proposed operational methodology, and a letter detailing the change
in effect is included in Appendix 2. It is considered, that with the bridge being in the
lowered position for longer amounts of time, the effects upon landscape and natural
character values will be no more than minor.
Natural Features (including coastal processes) and Ecological Values Effects
Tidal movements and fluctuating stream flows are the dominant natural processes
operating within the lower portion of Wairau Creek. These processes have been
altered by the placement of the weir at the entrance to Milford Marina. The weir acts
to focus and regulate the tidal and stream flows around the mouth of the Wairau
Creek. Further, the natural processes and features have been affected by the wall
lining the southern bank of the creek and the groynes at the very seaward end of
the creek. These serve to train the stream flow and control any natural fluctuations
that would be expected to occur in a setting such as this. The proposed bridge’s
piles would likely have little impact upon the functioning of natural processes that
currently exist. The proposed dredging of the lay-over berths and associated
Application No: 37549 and LR-213194 Page 21
mooring piles will likely not impact upon tidal current flows in Wairau Creek, due to
relatively the shallow depth and position within the channel of the proposed lay-over
berths. Further, significant sedimentation is not expected to occur in this portion of
Wairau Creek, where tidal flows are near peak.
The applicant has provided an assessment of the proposal against the local coastal
processes. A review of this assessment was undertaken by Richard Reinen-Hamill
(Tonkin and Taylor) and questions raised as part of a section 92 request for further
information. These issues were adequately addressed through this process and it is
considered that overall the proposal would have a no more than minor impact upon
local coastal processes.
Similarly most of the natural ecosystems around the proposed site have been
altered by the modifications noted above. An assessment of the proposal’s impact
upon the local ecology was provided by Coast and Catchment Ltd. on behalf of the
applicant. A review of the application has been undertaken by Dr. Jarrod Walker
(Auckland Council) who raised matters around the local ecology for a section 92
further information request. The matters were addressed adequately and overall it
is considered the proposal would have a no more than minor impact upon the
surrounding ecological values.
Public Access Effects
Submissions were put forward in favour and in opposition for the proposal with
respect to public access issues. However the majority of submitters commenting on
public access were in support of the proposal because it is perceived to enhance
access to the beach and reserve, and will provide a safer route for pedestrians than
what is currently available.
The primary intent of the project is to enhance and facilitate safe public access
across Wairau Creek. Use of the bridge will be restricted by vessel movements in
and out of the Milford Marina. The restriction on whilst being demand-based use will
be limited to periods around high tide and will likely fluctuate according to weather,
seasonally, time of day and through the week.
Overall, it is considered that the proposal will be an improvement to public access
Application No: 37549 and LR-213194 Page 22
opportunities within the area.
Navigation and Safety Effects – aids to navigation, signage etc
22 submissions raised concerns about the proposed bridge affecting navigational
access to and from the marina. The Auckland Council Harbourmasters office has
reviewed the application and the revised operational methodology in order to
assess the impact upon navigation and safety. Within the Navigation and Safety
report (Appendix 2) it is noted that navigation of the channel to and from Milford
Marina is limited by the width of the channel and the weir hold water within the
marina at low tides. It is recognised that the bridge open span is aligned with the sill
and therefore does not impact upon the existing navigation setting. The addition of
a lay-over area is seen to aid in the navigation of the narrow channel. Overall, it is
considered that proposal will have a no more than minor impact upon Navigation
and Safety issues.
Cultural Heritage and Tangata Whenua Values Effects
Three cultural heritage sites are located within the vicinity of the proposed bridge.
These are associated with a historic swimming pool, a pill box and the site of the
previous footbridge. The proposal is set away from these features and will likely not
have any impact upon them.
The North Shore City Council Iwi committee were consulted with regards to the
proposal at a Hui held at the North Shore City Council offices on 17th February
2010. Support for the project was provided at this time.
It is considered that effects upon Cultural Heritage and Tangata Whenua values will
be no more than minor.
Construction Effects
Some disturbance of the foreshore and seabed is to be expected during
construction, but the proposed methods are designed to minimise these impacts.
Construction is expected to take approximately 6 months, with the main bridge
piers and deck elements being constructed offsite to reduce the onsite construction
time. The majority of work is planned to be undertaken from the Milford Reserve to
Application No: 37549 and LR-213194 Page 23
minimise the impact on the CMA and road users on the opposing bank. The main
area of disturbance from works to the CMA will be during pile boring, dredging
operations and digging the trench for the electrical cabling. The applicant is
proposing to produce a construction management plan to provide details of
mitigation measures. This is to be submitted to the resource consent manager for
approval. This will be required to address navigation within the channel and noise
generated over the construction period. It is considered that the impact on the CMA
from construction effects to be no more than minor.
The site works required to establish the eastern and western abutments are fairly
limited, and would result in the disturbance of approximately 135m2 of earth. Whilst
specific methodologies have not been devised, the applicant states that measures
in accordance with the Council’s Technical Publication 90 (TP90) would be
implemented to ensure that any silt runoff is appropriately controlled and
contained. Such measures would be submitted for Council approval prior to
construction works commencing. This approach has been reviewed by the
Council’s Development Engineer, Ms Ann Rammo, who is supportive of it.
With respect to stability, a comprehensive geotechnical investigation has been
undertaken in order to gain an understanding of the underlying soil conditions. The
nature of the soils encountered is such that the report recommends that bored
piles to a depth of 7m are utilised in order to allow for stable abutments on the
eastern and western sides of the bridge to be constructed. Ms Rammo has
reviewed the bridge design and is satisfied that it has been designed to
accommodate the geotechnical recommendations.
It is considered that any potential adverse effects can be avoided and/or mitigated
through the implementation of, and compliance with, appropriate silt management
and geotechnical methodologies. As a result, the level of adverse effects in
respect of site works above MHWS is considered to be less than minor in nature.
Traffic
The proposal has been reviewed by Auckland Transport Traffic Engineer, Mr
Warren Budd, who is agreeable in principle to the proposal. Mr. Budd has met on-
site with the applicant’s Traffic Engineer. Mr Budd is satisfied that there is sufficient
Application No: 37549 and LR-213194 Page 24
space to allow for a design that will integrate appropriately with Beach Road and
Milford Reserve. This includes the provision of an appropriate median refuge and
kerb realignments. A condition is recommended requiring all detailed design issues
to be submitted and approved prior to construction commencing. The measures
proposed would ensure that any adverse vehicular, pedestrian and cyclist traffic
safety issues are suitably addressed, which have been raised as concerns within
some of the submissions received.
With respect to construction traffic, a compound yard is proposed at the western
end of Craig Road, with temporary haul roads proposed between it and the bridge
site. This yard would provide an area for vehicle parking and the storage of
associated materials. Its location is considered appropriate, as it would minimise
disruption for vehicles accessing Milford Beach and Reserve, whilst ensuring it is
reasonably accessible to the development site.
Turning to vehicle movements, those associated with workers would occur during
the morning and evening peaks and would be of little significance given that
numbers would be low. Truck movements would occur throughout the day, but
again, are unlikely to be of significant volume. The removal of soil from the site,
which includes dredging works, would require approximately 100 truck
movements. Spread out over the 1-2 weeks required for soil extraction works,
these movements would also be of little consequence. It is noted that some of the
works would need to be undertaken from the western side of Wairau Creek. This
has the potential to disrupt traffic flows along Beach Road and Inga Road.
Accordingly, and in order ensure all relevant construction traffic issues are suitably
addressed, a condition requiring the submission of a construction traffic
management plan is recommended. Mr Budd is comfortable with this approach
and endorses the construction traffic comments outlined above.
Mr Budd raised no concerns with respect to increased parking along Inga Road, as
raised in submissions. From a planning perspective it is unclear how such issues
would arise. Furthermore, it is also unclear as to how such a scenario would result
in adverse environmental effects if on-street parking is already readily available. It
is therefore considered that adverse parking effects will not result from this
proposal.
Application No: 37549 and LR-213194 Page 25
Accordingly, subject to conditions in respect of the detailed design of the bridge
(and its interface with the road and reserve environments) and construction traffic
management, it is considered that adverse traffic related effects would be less
than minor.
Visual Amenity
The proposed bridge is for both pedestrian and cyclist shared use. The 3m width is
the minimum recommended by the relevant design standards and is acceptable.
The larger visual amenity issues are dealt with in the assessment against
landscape value under taken by Rob Pryor discussed above.
The signage proposed would be small in size (0.5m2 in area) and would contain
information with respect to the operation of the bridge. Given the unconventional
nature of the bridge and the potential safety concerns, such signage is considered
necessary and would accord with the amenities reasonably expected by users.
Subject to the final design of the signage being approved by Council, any related
adverse visual effects would be insignificant.
The lighting proposed along the bridge would be incorporated into the underside of
the hand rails, which ensures that it would be complementary in design and that
any potential light spill is minimised. The light on the northwestern corner of Milford
Reserve would improve visibility for boats navigating Wairau Creek at night, and
would again be positioned to ensure undue light spill does not result. The light
warning system associated with the operation of the bridge would, according to the
applicant, be designed to comply with the relevant lighting standards of the District
Plan. Comments received from the Council’s Environmental Health Officer, Ms
Fiona Eames, concur that the light levels are likely to comply with District Plan
standards, but she recommend that the lighting be reviewed once it has been in
operation for three months. It is recommended to include this as a condition of
consent. This is considered to suitably addresses the submissions received that
raise lighting concerns.
In summary, any adverse visual amenity or costal character effects that may result
as a consequence of the establishment and operation of the bridge and its
Application No: 37549 and LR-213194 Page 26
associated signage and lighting would be minor in nature.
Recreation Values
The provision of a bridge over the Wairau Creek is provided for within the Milford
Reserve Management Plan (MRMP). As outlined in the submitted AEE, the MRMP
was updated in September 2006 to allow for the possible development of a bridge,
provided it is in keeping with, and sensitive to, the needs of users of the marina
and reserve and has minimal impact on the environment and open space
character of the reserve.
It is noted that the bridge would provide a barrier to users of the marina, any
impediment would be minimal given its proposed raising function. Any resultant
delays pedestrian access would be minimal and more than off-set by the
enhanced access to the reserve from those properties to the west of Beach Road
and Inga Road, with people from these areas currently having to take a much
longer route along Omana Road and Craig Road. I note that a number of the
submissions received also highlight the access improvements that would result.
As noted above, the nature of the bridge would be appropriate in terms of bulk,
scale and design. Any intrusion into the reserve is minimal, relating only to the
eastern abutment and interface. Overall, the bridge would have minimal impact on
the environment and open space nature of the reserve.
Accordingly, it is considered the proposal is consistent with the provisions of the
MRMP and that the overall effect on recreational values would be positive. A
condition is, however, recommended to ensure that any adverse effects related to
construction works, and especially traffic movements within the reserve, are fully
remediated upon completion of the development.
Noise
The levels of acceptable noise set within the coastal plan are above those within
the district plan. Therefore it is considered appropiraite to consider noise effects
under the district plan only. The AEE states that noise from the warning system
would not exceed those set out in Section 10 of the district plan, which allows for
Application No: 37549 and LR-213194 Page 27
levels of between 40dBA L10 and 50dBA L10 at a residential boundary depending
on the time of day. The operation of the alarm would be varied depending on the
time of day, with its duration and sound level reduced as required.
This noise assessment has also been reviewed by Ms Eames. Ms Eames notes
that the nearest residential receiver is approximately 50m away, but that noise
may travel further than otherwise expected given the open nature of the area and
the elevation of the closest houses. That being said, Ms Eames has recommended
that this be reviewed and confirmed after three months of operation. It is
suggested that this be included as a condition of consent to negate any possible
adverse noise effects would fall within the permitted limits of the District Plan, or
could be adjusted to do so. Again, this also addresses the submissions received
that raise noise related concerns.
Effects Conclusion
In summary, it is considered, on balance, that any adverse actual and potential
effects on the environment with respect to site works, traffic, visual amenity and
recreation values and noise would be minor and could be remedied or mitigated to
an appropriate level through the imposition of recommended conditions. In addition,
positive effects would result, being improved public access to Milford Reserve and
Beach.
Application No: 37549 and LR-213194 Page 28
6.3 Section 104(1)(b)(i) and (ii) Relevant provisions of National Environmental Standards and other regulations
There are no NES or other regulations in effect that apply to this application.
6.4 Section 104(1)(b)(iii) Relevant provisions of National Policy Statements
There are no National Policy Statements relevant to this application.
6.5 Section 104(1)(b)(iv) Relevant provisions of the New Zealand Coastal Policy
Statement (NZCPS)
The purpose of the NZCPS is to state policies in order to achieve the purpose of the
RMA, in relation to the coastal environment of New Zealand.
The proposal is considered to be consistent with those relevant NZCPS objectives listed
below:
Objective 2- To preserve the natural character of the coastal environment and protect
natural features and landscape values through:
• recognising the characteristics and qualities that contribute to natural character,
• natural features and landscape values and their location and distribution;
• identifying those areas where various forms of subdivision, use, and
development would be inappropriate and protecting them from such activities;
and
• encouraging restoration of the coastal environment.
Objective 4- To maintain and enhance the public open space qualities and recreation
opportunities of the coastal environment by:
• recognising that the coastal marine area is an extensive area of public space
for thepublic to use and enjoy;
• maintaining and enhancing public walking access to and along the coastal
marine area without charge, and where there are exceptional reasons that
mean this is not practicable providing alternative linking access close to the
coastal marine area; and
Application No: 37549 and LR-213194 Page 29
• recognising the potential for coastal processes, including those likely to be
affected by climate change, to restrict access to the coastal environment and
the need to ensure that public access is maintained even when the coastal
marine area advances inland.
Objective 6- To enable people and communities to provide for their social, economic, and
cultural wellbeing and their health and safety, through subdivision, use, and development,
recognising that:
• the protection of the values of the coastal environment does not preclude use
and development in appropriate places and forms, and within appropriate
limits;
• some uses and developments which depend upon the use of natural and
physical resources in the coastal environment are important to the social,
economic and cultural wellbeing of people and communities;
• functionally some uses and developments can only be located on the coast or
in the coastal marine area;
• the coastal environment contains renewable energy resources of significant
value;
• the protection of habitats of living marine resources contributes to the social,
economic and cultural wellbeing of people and communities;
• the potential to protect, use, and develop natural and physical resources in the
coastal marine area should not be compromised by activities on land;
• the proportion of the coastal marine area under any formal protection is small
and therefore management under the Act is an important means by which the
natural resources of the coastal marine area can be protected; and
• historic heritage in the coastal environment is extensive but not fully known,
and vulnerable to loss or damage from inappropriate subdivision, use, and
development.
The relevant policies of the NZCPS for this proposal are the preservation of the natural
character of the coastal environment and the protection of natural features (Policy 1); the
recognition that the provision of infrastructure is an activity important to the social,
economic and cultural well-being of people and communities; maintain and enhance
public open space and to promote the efficient use of occupied space (Policy 6(2)(a, b,
Application No: 37549 and LR-213194 Page 30
and e)); to avoid significant adverse effects and avoid, remedy, or mitigate other adverse
effects of activities on natural features and natural landscapes in the coastal environment
(Policy 15(a, b)); to maintain and enhance walking access linkages between public open
space areas in the coastal environment (Policy 18(c)); and maintain and enhance public
walking access to, along and adjacent to the coastal marina area (Policy 19(1)(2c)).
It is considered that in the context of the existing coastal environment and the above
assessment of the effects of the proposed activities on the environment, the proposal is
not contrary to the provisions of the NZCPS. The construction of the pedestrian bridge
and the occupation of the CMA with the proposed bridge will not have significant
adverse effects on the above matters, and will have beneficial effects in terms of public
access and recreational use in the coastal environment. The bridge will create a
walking linkages between existing areas of open space and the coastal environment
thereby enhancing recreational opportunities of the coastal environment. The operation
of the bridge will not adversely affect the continued occupation of the CMA by the Milford
Marina and its on-going use by boaties and the proposed operation methodology will
have no more than minor adverse effects on navigation and will be an efficient use of
the CMA. The dredging of the Wairau Creek and the provision of a temporary mooring
(lay over) area will not have significant adverse effects on the coastal environment,
amenity values, or on the enjoyment of the coast by the public. The proposal is
considered to be an appropriate use and development of the Wairau Creek. Any
adverse effects on the coastal environment can be avoided, remedied or mitigated.
Some restriction on public access during construction works is required to ensure public
safety, however, overall the proposal enhances public access to the CMA.
Hauraki Gulf Marine Park Act 2000 ( HGMPA)
When considering an application for resource consent within the Hauraki Gulf, its
islands, and catchments, a consent authority must have regard to sections 7 and 8 of the
HGMPA. These sections must be treated as a New Zealand coastal policy statement.
Section 7 recognises the national significance of the Hauraki Gulf, its islands and
catchments, while section 8 outlines the objectives of the management of the Hauraki
Gulf, its islands and catchments. The objectives are intended to protect, maintain and
where appropriate enhance the life supporting capacity of the environment of the Gulf
and its islands.
The objectives are broad-based and are intended to protect, maintain and where
Application No: 37549 and LR-213194 Page 31
appropriate enhance the life supporting capacity of the environment of the Hauraki Gulf
and its islands.
The matters to be considered in terms of the HGMPA are not dissimilar to those arising
under the NZCPS, and accordingly the conclusions reached in the preceding section of
this report are considered to be equally relevant to the HGMPA. In particular, it is
considered that the proposed works associated with the construction of the bridge and
lay over area will not adversely affect the life supporting capacity of the gulf and the
proposed development and activities will provide a social, economic and recreational
benefit for people and communities. Some parts of the coastal environment will be made
more accessible via the pedestrian bridge. It is therefore considered that the proposal
would not be contrary with sections 7 and 8 of the HGMPA.
There is potential for tension to occur between the natural character values of the wider
area and the provision of the bridge and lay over area. However the proposals are within
a modified environment and of a scale (based on their minor effect on marine ecological
values) whereby it is considered, on balance, to maintain the overall amenity and values
of the Hauraki Gulf. Furthermore, it is considered that it minimises the potential adverse
effects on the life supporting capacity of the Hauraki Gulf in so far as utilising a site that
is already modified and does not contain any unique or special ecological or landscape
features.
Overall, it is considered that in context of the nature of the proposed activity, the site and
locality characteristics, and the above assessment of effects of the proposed activity on
the environment, the proposed development and activities, would not be contrary to the
provisions of the HGMPA.
Application No: 37549 and LR-213194 Page 32
6.6 Section 104(1)(b)(v) Relevant provisions of the Auckland Council Regional Policy Statement
The Auckland Council Regional Policy Statement (policy statement) is a strategic
document which sets out the direction for managing the use, development and
protection of the natural and physical resources of the Auckland region. This
document became operative in 1999.
The strategic objectives and policies of the policy statement provide a framework to
achieve the integrated, consistent and co-ordinated management of the Region’s
resources.
Under the policy statement matters related to environmental protection such as the
coastal environment, have specific objectives, policies and methods to achieve
sustainable and integrated management of major natural and physical resources in
the region. The focus of this section is on the appropriateness of the proposed
facilities and activities in terms of their function in assisting economic growth and
achieving strategic objectives of the policy statement, particularly those related to
Part 2 of the RMA.
As noted in the AEE, Chapters 2 (Strategic Objectives), 7 (Coastal Environment) of
the policy statement are relevant in assessing the applications.
Chapter 2 of the policy statement provides a regional perspective in setting the
strategic direction. Issue 2.3.6 discusses the significance of Auckland’s coastal
environment and in particular the need to maintain or enhance public access to the
coast. Strategic objective 2.5.1(4) discusses the balancing of retaining coastal
natural character with use and activity within the coastal environment. The proposal
is considered consistent with Chapter 2 as the intent of the proposal is to promote
further public access (pedestrian) whilst maintaining the existing public access (water
access). The proposal is situated in an existing area of high modification and
designed to minimise the impact upon natural character.
Chapter 7 of the policy statement provides direction on matters within the coastal
environment. The proposal is consistent with issues 7.2.1, 7.2.2, 7.2.4 and 7.2.6 and
objectives 7.3(1), 7.3(3), 7.3(6) and 7.3(7). Policy 7.4.4 (1) discusses the importance
Application No: 37549 and LR-213194 Page 33
of preserving natural character and lists a range of issues to be considered. The
design, operational methodology, and site help to negate the impact of the proposal
upon the area’s natural character values.
Policy 7.4.10 discusses the appropriateness of developments in the coastal
environment, citing a range of issues and values to consider which include natural
character, public access, amenity, and efficient use. The proposal is considered to be
consistent with 7.4.10 (1, 2i, 2ii, 2iii, 2iv, 2vii and 7) because it seeks to maintain and
enhance existing public access and amenity values, while considering natural
character and efficient use of the coastal environment. Importantly, the proposal
does so whilst maintain navigational access to and from the marina.
Having considered the relevant provisions of the policy statement, it is concluded that
the proposal is to a large extent consistent with the relevant provisions. The
proposed coastal works and structure are of a scale that can be accommodated
without significant changes to the existing natural character and use of the
surrounding coastal environment.
6.7 Section 104(1)(b)(vi) Relevant provisions of the relevant regional/district plan(s) objectives, policies and rules
The Plans applying to this proposal are set out in Sections 4.1 and 4.2 above.
6.7.1 Relevant objectives and policies
The following objectives and policies of the coastal plan and district plan are considered
relevant:
6.7.2.1 Auckland Council District Plan (North Shore Section)
The relevant objectives and policies are as follows:
8.3.1 Coastal Conservation
Objective
To protect the natural character, public access, cultural heritage values, ecology and
Application No: 37549 and LR-213194 Page 34
landforms of the coastal environment.
Policies
1. By defining the Coastal Conservation Area.
2. By applying a building set back or foreshore yard as a buffer between the
coastline and development to the extent necessary to:
- protect the natural character of the coastal environment, including its soft
green edge, the physical landform, natural features, vegetation and ecological
systems
- protect the water quality of the coastal environment and the habitats that it
sustains
- provide for the operation of naturally occurring processes
- keep open the existing and foreseeable opportunities for future esplanade
reserves and strips
- maintain and enhance landscape and amenity values
- protect the value the coastline has to tangata whenua
- reduce potential hazards resulting from natural processes and subsequent
changes in landform
- manage the cumulative effects of the activities of property owners in the
coastal environment.
3. By restricting development and structures on the beach areas and other coastal
areas of high public use of the city so as to protect the natural character and
high recreational values of these areas, except where these structures are
needed for public safety.
6. By ensuring that the effects of any buildings or any structures, including erosion
control works and stormwater outlets, within the coastal environment do not
Application No: 37549 and LR-213194 Page 35
adversely affect natural values or natural character.
8. By ensuring that development and activities in the Coastal Conservation Area
do not adversely affect the proper functioning of ecosystems, or adversely
affect the natural coastal environment.
10. By using activity and development controls within the Coastal Conservation
Area so as to avoid or mitigate pollution or sedimentation of coastal waters, and
avoid, remedy or mitigate any adverse effects on the amenity value of the
coastal environment.
13. By providing for shoreline walkways and reserves, to and around the foreshore
where these do not significantly conflict with environmental or cultural heritage
values or public safety and security or lead to the erosion of sensitive
landforms.
14. By controlling the location of any development and associated activities on land
adjacent to the foreshore to ensure that the opportunity for the provision of
waterborne transport, and the ready public access to such transport, is not
compromised.
Comment
The level of works within the Coastal Conservation Area is relatively small, and act to
support the main portion of the bridge structure which is within the CMA. That being
said, the bridge is consistent with the form of development anticipated within the
coastal environment and has been designed in an appropriate manner, through the
use of suitable materials and simple design features. As such, it would not have an
undue adverse effect on the natural character of the coastal environment.
Appropriate measures would be implemented to ensure that sediment generated
during the construction process is appropriately controlled and contained. This would
ensure that undue sedimentation of coastal waters would not result and that the
proper functioning of ecosystems would not likely be adversely affected. Any
resultant adverse effects would, in any case, be temporary in nature.
The bridge would provide improved access to coastal amenities, whilst ensuring that
Application No: 37549 and LR-213194 Page 36
the passage of waterborne transport is not unduly compromised. While the bridge
would be visually prominent when in its upright position, this would only be for limited
periods of time, which ensures that any adverse visual effects would be temporary in
nature.
No known cultural heritage or landscape features would be adversely affected.
9.3.1 Protection of the Environment
Objective
To avoid, remedy or mitigate the adverse effects of subdivision and development on
the environment, including the physical environment, biota, amenity values and
landscape.
Policies
1. By retaining significant landscape features, vegetation and wildlife habitats as
they provide amenity value, diversity in the landscape and habitat
2. By ensuring that soil/sediment runoff resulting from vegetation clearance and
earthworks is controlled in order to avoid, remedy or mitigate adverse effects on
amenity and habitat.
3. By ensuring that new subdivision and development recognises existing natural
features and landscapes and that the form of development reflects the
character and environmental qualities of the location.
4. By ensuring that new subdivision and development recognises, and is
compatible with, the character and amenity values of existing development.
5. By ensuring that subdivision and development is designed and located such
that it does not cause or contribute to, and/or be significantly affected by,
natural hazards such as flooding, subsidence and erosion.
6. By ensuring the integrated management of resources by requiring that land use
and development avoid, remedy or mitigate any adverse effects on natural and
Application No: 37549 and LR-213194 Page 37
physical resources which manifest themselves within or beyond the immediate
location and across jurisdictional boundaries.
Comment
The proposed site works are minimal in scale, involving excavations to establish the
bridge abutments. Accordingly, they would not adversely affect the visual integrity of
the landscape. The implementation of appropriate site management devices would
ensure that any silt run-off is suitably controlled and transfer into the surrounding
environment, including the CMA, is minimised.
As all works would be undertaken in accordance with geotechnical
recommendations, with foundations being deep enough to ensure they are secured
into solid ground. This would ensure the bridge is structurally sound and not
susceptible to subsidence.
There is no evidence to suggest that the bridge would contribute to or be affected by
natural hazards, or that the land use elements would result in adverse effects within
the CMA.
13.3 Signs
Objective
1. To ensure that signage does not create a traffic hazard.
2. To ensure that signs do not adversely affect the visual amenity of the
surrounding environment.
Policies
1. To require signs to be designed and located so that they do not detrimentally
affect traffic safety.
2. To control the adverse affects of signs, having regard to the amenity standards
and context of the particular environment in which they are located, on the
basis of the various zones defined in the Plan.
Application No: 37549 and LR-213194 Page 38
3. To ensure that promotional signage does not hinder the functioning of
informational signage.
Comment
The signs are considered necessary given the need to inform users as to the
operation of the bridge, particularly with respect to its lifting function.
The limited size of the signs and their association with a larger bridge structure would
ensure that the visual amenity values of the site and surrounding area are not
adversely affected.
The proposed signage has been reviewed by the Auckland Transport Traffic
Engineer, who has not raised any concerns with respect to the creation of a traffic
hazard. It is further noted that the proposed signs would not interfere with the
function of informational signage.
19.3.3 Management of the Effects of Activities and Development
Objective
To ensure that open space is used and developed in a manner which is compatible
with its function and character, and with the amenities of adjoining residential areas.
Policies
1. By limiting the use of open space to recreation and community activities, having
regard to their intensity of use and other generated effects, the function and
character of the open space and the provisions of the relevant approved
Reserve Management Plan.
3. By placing controls on the size, design and siting of buildings so as to avoid,
remedy or mitigate any adverse effects on the function and character of the
open space, and on the amenity of surrounding areas.
4. By the Council as landowner ensuring that buildings are designed and sited to
complement the function and character of the open space.
Application No: 37549 and LR-213194 Page 39
9. By imposing controls on floodlighting.
10. By the preparation of management plans for each open space gazetted as
public reserve under the Reserves Act 1977, to determine the specific purposes
of the reserve and, where appropriate, the priorities for its development.
19.4.2 Recreation 2 (Neighbourhood Activities) Zone
Objective
To provide for open spaces throughout the residential areas of the city which serve
local resident needs for recreation and community activities, and visual amenity.
Policies
1. By recognising the land in this zone as a recreational resource for low key,
everyday recreation and community activities.
2. By restricting the range of activities and associated development to a type and
which allows recreational and community use of the open space, while retaining
its visual amenity and compatibility with adjacent residential development.
Comment
The proposed bridge would provide enhanced access to the Milford Reserve and
beach areas and is considered compatible with the character of these recreational
spaces. Furthermore, as noted in section 5.1, it accords with the provisions of the
Milford Reserve Management Plan which envisages an appropriately designed
bridge structure across the Wairau Creek. The subject bridge is considered to fulfil
this provision.
As noted above, the bridge would be of an appropriate form, scale and design and
would complement the function of the adjoining reserve area by providing improved
public access.
The level of lighting proposed would be subtle and would allow the bridge and
associated areas of Wairau Creek to be safety used during night-time hours. In
Application No: 37549 and LR-213194 Page 40
addition, it would comply with the permitted lighting levels stipulated by the District
Plan.
The control of light spill and noise from the bridge warning mechanisms in
conjunction with its appropriate design and scale would ensure that the amenity
values of the neighbouring residential area are suitably provided for.
Conclusion
Based on the evaluation above, the proposed development is considered to be
consistent with the relevant objectives and policies of the Auckland Council District
Plan (North Shore Section).
6.7.2.2 Auckland Council Regional Plan (Coastal)
Natural Character (Chapter 3)
Objective 3.3.1 and Policy 3.4.1 state that natural character of the coastal environment
shall be preserved and protected from inappropriate use and development, by avoiding,
remedying or mitigating the adverse effects of such on the elements and features which
contribute to the natural character of the coastal environment. Policy 3.4.3 states that in
assessing the actual or potential adverse effects of subdivision, use and development
including cumulative effects, regard shall be had to the relevant policies in Chapters 4, 5,
6 and 8.
As has been described in the natural character effects assessment of this report, the
proposed bridge and associated lay-over area is to be located in an area with highly
modified natural character. The proposed bridge and associated lay-over area are within
an area already modified by the marina and surrounding development. Further changes
to the operational methodology are proposed to lessen any impact upon natural
character. Accordingly, it is considered that the proposal is consistent with the provisions
of Chapter 3.
Landscape (Chapter 4)
Objective 4.3.2 is to maintain and enhance the diversity, integrity and landscape quality
of the coastal environment. Policy 4.4.3 states in areas with less than regional landscape
Application No: 37549 and LR-213194 Page 41
value the use and development shall be of a scale, design and location to avoid adverse
effects on key landscape elements, feature and patterns. Policy 4.4.4 recognises the
contribution of the built environment to the environment when considering proposals in
the CMA near coastal settlements. 4.4.5 states that in assessing the cumulative effects
in the CMA on landscapes values, particular regard shall be had to ensuring where
practicable, that development is of an appropriate scale, location and design which
encourages its integration with the type and intensity of development in the adjacent
area.
The wider coastal environment surrounding Wairau Creek has no landscape significance
assigned to it. The proposed location of the bridge and associated lay-over area is set
within a background of urban development including housing, reclamations, recreational
parkland and a marina. It is specifically located at the edge of a landscape change, and
therefore considered that its location is in keeping with the values highlighted above.
Further the proposed operational methodology has been put forward to mitigate possible
effects upon the area’s landscape. Therefore, it is considered the proposal is consistent
with Chapter 4.
Natural Features and Ecosystems (Chapter 5)
Objective 5.3.1 is to protect the dynamic functioning of physical coastal processes, and
5.3.2 is to protect the integrity, functioning and resilience of ecosystems within the
coastal environment. Policy 5.4.4 states that any development in areas not identified as
Coastal Protection Areas 1 and 2 should avoid, remedy or mitigate adverse effects on
indigenous vegetation, habitats, natural features, and ecological and physical processes.
Policy 5.4.5 states that regard shall be had to protecting the physical integrity
functioning, educational, scientific, and amenity values of any natural features.
The applicant and subsequent reviews have demonstrated that the proposal will have no
more than minor effect on the existing marine ecology and coastal processes.
Furthermore, the proposal will not affect any indigenous vegetation, habitats or natural
features. Accordingly the proposal is considered to be consistent with the objective and
policies of Chapter 5.
Application No: 37549 and LR-213194 Page 42
Nga Take Takutai Turu Mo Tangata Whenua- Coastal Matters of Significance to
Tangata Whenua (Chapter 6)
Objective 6.3.1 is to recognise that the CMA has characteristics of special spiritual,
historical, and cultural significance to Tangata Whenua. Objective 6.3.2 is to sustain the
mauri of natural and physical resources of the coastal environment, and to enable
provision for the social, economic and cultural wellbeing of Maori. The policies of chapter
6 endeavour to achieve these objectives through recognising and protecting ancentral
taonga in the plan and involving iwi in the resource management process.
In accordance the intent of the policies and objectives of this chapter the applicant
worked with the NSCC Iwi Committee through the development of the proposal. The
committee was supportive of the proposal. For this reason, it is considered, that the
proposal is consistent with Chapter 6.
Public Access (Chapter 7)
Objective 7.3.1 is to maintain and enhance public access to, along, and within the CMA.
Policy 7.4.1 recognises that public access to, along, and within the CMA should be
maintained or enhanced except where it is necessary to restrict access.
In this case, the applicant proposes to improve public access to an area of beach
reserve while maintaining the existing access through the CMA. Accordingly it is
considered that the proposal is consistent with the provisions of Chapter 7.
Cultural Heritage (Chapter 8)
Objective 8.3.1 is to preserve and protect significant maritime cultural heritage sites in
the coastal environment. Policy 8.4.6 states that use and development in the CMA
should consider any effect on resources recognised as having historical or cultural value,
and where practical should avoid, remedy or mitigate any adverse effects on these
resources.
Three items of cultural significance have been identified within the vicinity of the
proposal, including the footprint of the former bridge. The proposed site of the bridge and
lay-over area is located as such that no effect upon these items is expected. Therefore it
Application No: 37549 and LR-213194 Page 43
is considered that the proposal is consistent with the provisions of Chapter 8.
Subdivision, Use and Development (Chapter 9)
Objective 9.3.1 is to enable appropriate subdivision, use and development in the coastal
marine area, recognising that the CMA is a finite resource. Policy 9.4.1 recognises
subdivision, use and development shall be considered appropriate dependent upon the
natural and physical resources of the CMA.
The proposal is situated in an area of high coastal development and modification, whilst
taking into account the natural and physical resources of the area. The proposed bridge
is constrained in size to that necessary to meet its purpose. Therefore the proposal is
considered to be efficient use of the CMA and consistent with the provisions of Chapter
9.
General (Chapter 10)
Objective 10.3.1 is to provide for appropriate use and development in the CMA.
Objective 10.3.2 is to ensure that efficient use is made of the CMA. Objective 10.3.3 is
to maintain where appropriate the open space nature of the coastal environment.
Policy 10.4.1 states that use and development which maintains or enhances public use
and enjoyment of the CMA shall be encouraged. Policy 10.4.2 directs that any proposal
for use and development shall have regard to maintaining or enhancing recreational use
of the CMA. Policy 10.4.3 states that use and development of the CMA shall be
considered more appropriate where the environment has already been highly modified
by human activities or located in areas where development already exists. Policy 10.4.5
states that any proposal for use and development shall be located, designed and
constructed to complement, as far as practicable, the character of the environment in
which it is located, and where practicable be consistent with relevant resource
management strategies of adjoining territorial authorities. Policy 10.4.10 considers that
occupation of part of the common marine and coastal area shall be considered
inappropriate unless occupation is necessary for the proper functioning of the activity.
It is considered that this proposal is consistent with the objectives and policies of
Chapter 10 as the project is to improve public access between Milford Reserve and
Application No: 37549 and LR-213194 Page 44
surrounding suburbs, improve local coastal walkway linkages whilst maintaining
navigation access to and from Milford Marina, and hence enhance public access and
recreation values in terms of policies 10.4.1 and 10.4.2. Policy 10.4.3 is met as the
proposal will be located within the context of a highly modified coastal environment and
maintains the primary focus on recreational related activities.
Policy 10.4.10 relates to occupation of part of the common marine and coastal area.
The area to be occupied is the minimum necessary for the safe operation of the bridge
and associated structures.
Overall, it is considered that the proposal is consistent with the provisions of Chapter 10.
Activities (Chapter 11)
The proposed bridge across Wairau Creek and associated lay-over area will introduce
permanent structures and a range of temporary construction activities into the CMA.
Accordingly, the general provisions relating to the activities in the CMA, as contained in
Chapter 11 are relevant. These are set out as follows:
Objective 11.3.1:
To provide for a wide range of appropriate activities in the coastal
marine area.
Objective 11.3.2:
To ensure that efficient use is made of the coastal marine area.
Policy 11.4.1:
Activities in the coastal marine area which are not permitted activities
by this chapter shall generally be considered appropriate where:
a i there is a functional need to undertake the activity in the
coastal marine area; or
ii they are ancillary to an activity which has a functional need
Application No: 37549 and LR-213194 Page 45
to locate in the coastal marine area; or
iii no reasonable or practicable alternative location exists
including any location outside of the coastal marine area; or
iv the activities are for the cultural and traditional needs of
Tangata Whenua; and
b any landward development associated with the activities in the
coastal marine area can be accommodated; and
c any adverse effects on the environment can be avoided,
remedied or mitigated.
Comment
In this case, it is considered the proposed bridge and associated lay-over area is an
efficient use of the CMA as it improves the public access across and to the CMA, as
well valued coastal recreation space. The scale of the proposed upgrade is considered
appropriate, given the long standing coastal modification within the area.
It is considered that the proposed bridge and associated lay-over area has a functional
need to be located in the coastal environment as it would facilitate and enhanced the
use of Milford Reserve and the CMA, and that the landward components of the
proposed development can be accommodated, and moreover have been considered.
Accordingly, it is considered that the proposal is consistent with the provisions of
Chapter 11.
Structure (Chapter 12)
The proposed bridge and associated lay-over area will provide for better pedestrian
access across Wairau Creek and will introduce new structures within the CMA.
Accordingly, a series of general objectives and policies related to structures contained
in Chapter 12 are relevant to consider. The following are considered relevant:
Objective 12.3.1:
Application No: 37549 and LR-213194 Page 46
To provide for appropriate structures in the coastal marine area, while avoiding,
remedying, or mitigating adverse effects on the environment.
Policy 12.4.1:
Subject to the limitations stated in Policies 12.4.2 to 12.4.14, structures in the
coastal marine area shall generally be considered appropriate where:
a (i) no reasonable or practicable alternative location exists having regard
to the efficient use and development of natural and physical
resources; or
(ii) the structure is proposed for the cultural and traditional needs of
Tangata Whenua;
b the purpose for which the structure is required cannot reasonably or
practicably be accommodated by existing structures in the coastal marine
area; and
c efficient use will be made of the coastal environment by using the
minimum area of the coastal marine area necessary for the structure; and
d the structure will not have a significant adverse effect on the adjoining
land.
Policy 12.4.3:
Structures in the coastal marine area should as far as practicable, be of an
appropriate scale, design, colour and location so as to avoid, remedy or mitigate
adverse effects on the coastal environment.
Policy 12.4.4:
Structures for public or multiple use shall be considered more appropriate than
the erection of new structures for individual use.
Application No: 37549 and LR-213194 Page 47
Policy 12.4.5:
Structures shall be avoided where they will modify, other than for the purpose of
maintaining intrinsic heritage values, damage, or destroy a site, building, place
or area scheduled for preservation in Cultural Heritage Schedule 1.
Policy 12.4.12:
Structures shall be designed and located taking into account relevant dynamic
coastal processes, including the possibility of sea level rise.
Comment
It is considered that the proposed design of the bridge is appropriate for the following
reasons:
(i) The bridge and associated lay-over area are located to minimise its impact on
natural character;
(ii) The proposal does not impact on the operation of vessels operating within
Wairau Creek;
(iii) As confirmed by the respective landscape and visual effects experts, the design
and location of the proposed bridge will have minor effects on existing landscape
and visual amenity values;
(iv) Iwi have been consulted through development of the proposal;
(v) The physical integrity of nearby Cultural Heritage sites will not be impacted upon,
and nor will the wider heritage landscape values;
(vi) The design of the bridge and associated lay-over area has taken account existing
coastal processes; and
(vii) Overall, it is considered that the proposed structures would be an efficient use of
the CMA.
Accordingly, it is considered that the proposal is consistent with the provisions of
Chapter 12.
Dredging (Chapter 15)
The proposed dredging of the Wairau Creek seabed to create a lay-over area requires
Application No: 37549 and LR-213194 Page 48
consideration of the objectives and policies of Chapter 15. The following are considered
relevant:
Objective 15.3.1:
To provide for appropriate dredging in the coastal marine area, while remedying
or mitigating adverse environmental effects.
Policy 15.4.3:
The redevelopment of existing navigation channels, wharves, piers and berths,
and the development of new facilities should be designed and located so that the
need for both capital works and maintenance dredging is either avoided or
minimised as far as practicable, where this does not result in additional adverse
environmental effects.
Policy 15.4.5:
Proposals for dredging shall generally demonstrate that:
a) there are no practicable alternative methods, locations or designs for the
activity which would avoid or reduce the need for dredging; and
b) the dredging will be undertaken at times of the day, or year that will avoid, as
far as practicable, remedy or mitigate adverse effects on the environment,
particularly on:
(i) the growth and reproduction of marine and coastal vegetation and the
feeding, spawning and migratory patterns of marine and coastal fauna,
including bird roosting,nesting and feeding; and
(ii) recreational use of the coastal marine area;and
(iii) other established activities and structures located in the coastal marine
area which are likely to be affected by the dredging; and
c) the dredging will not give rise to more than short duration and localised
turbidity, or disturbance to surrounding sediments, and does not result in
Application No: 37549 and LR-213194 Page 49
permanent long term adverse effects on the surrounding environment; and
d) the dredging will avoid significant adverse effects on biota caused by the
release of contaminants;and
e) the dredging will not be likely to cause or exacerbate coastal erosion either
within the coastal marine area or on adjacent coastal land; and
f) the dredging will not result in the permanent loss of any habitat of a rare or
endangered species.
Policy 15.4.6:
Where appropriate, as part of any consent granted for dredging, the grantee
shall be required to:
a) mitigate, as far as practicable, adverse effects of the dredging activity, in
particular sediment disturbance and the release of contaminants into the
surrounding environment;
b) monitor the dredging activity to a level commensurate with the expected scale
of adverse environmental effects, to determine that unacceptable adverse
environmental effects are not occurring; and
c) have in place contingency plans to remedy or mitigate any unacceptable
adverse effects that may arise from the dredging activity.
Policy 15.4.7:
The ARC will have regard to information obtained from resource consents
granted for similar forms of dredging in the coastal marine area in:
a) assessing the effects of maintenance dredging under Policy 15.4.5; and
b) determining the relevance of all matters listed in Policy 15.4.5; and
c) determining the criteria for any monitoring programme.
Application No: 37549 and LR-213194 Page 50
Comment
The proposed dredging is considered appropriate for the following reasons:
1. The area to be dredged is considered to be the minimum to achieve its stated
purpose of aiding navigation to Milford Marina.
2. No maintenance dredging is expected to be required.
3. No significant natural features or coastal ecology has been identified to be
affected.
4. Any adverse effects can be mitigated by appropriate construction methods, to be
confirmed by the submission of a construction management plan as a condition
of consent.
5. Local coastal processes are not expected to be impacted upon.
Therefore it is considered that the proposed dredging of a lay-over area is consistent
with the objective and policies of Chapter 15.
Moorings (Chapter 24)
The proposed creation of a lay-over area in the Wairau Creek requires consideration of
the objectives and policies of Chapter 24. The following are considered relevant:
Objectives 24.3
24.3.1 To concentrate moorings into defined locations while avoiding as far as
practicable, remedying or mitigating adverse effects on the environment.
24.3.2 To avoid, as far as practicable, conflicts between moorings and other
activities in the coastal marine area.
24.3.3 To ensure that efficient use is made of the coastal marine area.
Policy 24.4.2:
Moorings shall be avoided where they will:
a) result in more than minor modification of, or damage to, or the destruction of the
Application No: 37549 and LR-213194 Page 51
values of any Coastal Protection Area 1 or Tangata Whenua Management Area; or
b) modify, damage or destroy a site, building, place or area scheduled for
preservation in Cultural Heritage Schedule 1.
Policy 24.4.4
New moorings outside the Mooring Management Areas shall be generally
considered inappropriate unless:
a) there is no Mooring Management Area in close proximity to the proposed
mooring site that has available space; and
b) there are compelling reasons why a mooring outside a Mooring Management
Area is necessary; and
c) it can be demonstrated that short term anchorage as opposed to a permanent
mooring is not a practicable option; and
d) the mooring and any moored vessel will not adversely affect the navigation and
safety of other vessels; and
e) the mooring and any moored vessel will not adversely affect other recreational
use of the coastal marine area, including the short term anchorage of other
recreational vessels; and
f) the mooring and any moored vessel will not adversely affect the operation of any
existing activity or any activity that has been granted resource consent; and
g) there are no practicable land-based storage options; and
h) the mooring and any moored vessel will not restrict public access to and along
the coastal marine area.
Policy 24.4.5:
In addition to Policies 24.4.3 and 24.4.4, any proposal for a mooring shall
demonstrate how visual and amenity values of the area have been maintained or
Application No: 37549 and LR-213194 Page 52
enhanced to the greatest extent practicable.
Policy 24.4.6:
Moorings within Special Activity Areas shall be avoided.
Policy 24.4.7:
A mooring or a mooring area should be established only where it can be
demonstrated that the site is suitable in terms of wave, tide, and wind conditions,
particularly during storm events.
Policy 24.4.8:
Sufficient provisions should be made for land-based facilities associated with new
Mooring Management Areas, or extensions to Mooring Management Areas.
Policy 24.4.9:
In assessing any proposals for moorings consideration shall be given to boat
storage systems which avoid using space in the coastal marine area.
Policy 24.4.10:
Mooring areas which are adjacent to land of high amenity and recreational value
should be managed so as to maintain easy access to that land.
Policy 24.4.11:
Notwithstanding Rule 35.5.1, noise associated with the mooring of vessels in the
coastal marine area should as far as practicable be avoided or minimised. This
includes noise from halyard slap and general maintenance and operational
activities.
Comment
The proposed mooring area is considered appropriate for the following reasons:
Application No: 37549 and LR-213194 Page 53
1. The intent of creating the mooring/ lay-over area is to aid in the navigation of the
tide restricted Wairau Creek.
2. Short term anchorage in this space is not practicable given the tidal velocities
and width of the channel.
3. The intent of the lay-over area is to provide temporary berthing during times
when navigation into the Milford Marina is not possible.
4. It is in close proximity to a marina area, and therefore visually it will appear a
minor extension of an already established activity.
5. No other mooring space will be impacted upon.
6. No land based or other boat storage options are practicable.
Therefore, it is considered that the proposed creation of a mooring space/ lay-over area
is consistent with the objective and policies of Chapter 24.
Conclusion
Overall, it is considered that the proposal is consistent with the coastal plan. In
particular it allows for the enhancement and maintains public access to and along the
CMA, whilst the design is intended to minimise its impact upon natural character,
landscape values, cultural heritage, natural features and ecosystems and therefore it is
considered to be efficient use of the CMA.
Application No: 37549 and LR-213194 Page 54
6.8 Section 104(1)(c) Any other matters considered relevant and reasonably necessary to determine the application
Section 104(1)(c) requires that any other matter the consent authority considers relevant
and reasonably necessary to determine the application be considered. In this case the
Milford Reserve Management Plan (MRMP) is considered relevant.
The provision of a bridge over the Wairau Creek is provided for within the MRMP. As
outlined in the applicant’s AEE, the MRMP was updated in September 2006 to allow for
the possible development of a bridge, provided it is in keeping with, and sensitive to,
the needs of users of the marina and reserve and has minimal impact on the
environment and open space character of the reserve. After considering the actual and
potential adverse effects likely to be generated by the proposal, it is considered that the
proposal is considered to be consistent with the MRMP.
6.8.1 Submissions
All of the submissions received by Council in the processing of this application have
been reviewed and considered in the overall assessment of effects in this report.
Council’s specialists have also reviewed the relevant submissions as required and
incorporated comments into their assessments accordingly. Many of these submissions
raised similar issues and have been dealt with generically in the body of this report.
Those that have raised specific resource management matters and points of clarification
have been specifically addressed in the assessment of actual and potential effects
contained in section 6 of this report.
6.12 Section 104D Particular restrictions for Non-complying Activities
Pursuant to section 104D of the RMA if a proposal is a for non-complying activity then it
must pass at least one of the tests of either section 104D(1)(a) or section 104D(1)(b)
before an application can be assessed to make a decision under section 104B of the
RMA. If the application fails both tests of section 104D then the application must be
declined.
Application No: 37549 and LR-213194 Page 55
It is considered that subject to appropriate conditions of consent, the proposal satisfies
the threshold test of section 104D(1)(a) and 104D(1)(b) because, as demonstrated in
section 6.2.3 of this report the adverse effects on the environment will be no more than
minor and the proposal will not be contrary to the objectives and policies of coastal plan
and district plan as concluded in section 6.6 of this report. From the above section 104D
assessment it can be concluded that the application meets both of the tests of section
104D of the RMA. Therefore the application can be assessed against the provisions of
section 104B of the RMA and a substantive decision made.
6.13 Consideration of Part 2 (Purpose and Principles) of the RMA
Section 5 of Part 2 of the RMA identifies the purpose of the RMA as being the
sustainable management of natural and physical resources. This means managing the
use of natural and physical resources in a way that enables people and communities to
provide for their social, cultural and economic well-being while sustaining those
resources for future generations, protecting the life supporting capacity of ecosystems,
and avoiding, remedying or mitigating adverse effects on the environment
Section 6 of the Act sets out a number of matters of national importance which need to
be recognised and provided for, and includes among other things and in no order of
priority, the protection of outstanding natural features and landscapes, the protection of
areas of significant indigenous vegetation and significant habitats of indigenous fauna,
and the protection of historic heritage.
Section 7 identifies a number of “other matters” to be given particular regard by a council
in the consideration of any assessment for resource consent, and includes the efficient
use of natural and physical resources, and the maintenance and enhancement of
amenity values. Section 8 requires a council to take into account the principles of the
Treaty of Waitangi. Overall the proposal is considered to meet the relevant provisions of
Part 2 of the RMA as the proposal achieves the purpose of the RMA being sustainable
management of natural and physical resources.
Application No: 37549 and LR-213194 Page 56
6.14 Lapsing of Consent
Section 125 of the RMA provides that if a resource consent is not given effect to within
five years of the date of the commencement (or any other time as specified) it
automatically lapses unless the consent authority has granted an extension. In this case,
it is considered five years is an appropriate period for the consent holder to implement
the consent due to the nature and scale of the proposal.
6.16 Duration of Consent
It is considered appropriate to set a term of 35 years for the occupation of the CMA
under coastal consent 37549 because it is the maximum term afforded under the RMA,
and the structure present little risk of future environmental impact, beyond those already
discussed. Further, a term of 5 years is considered appropriate for the construction of
the bridge under coastal consent 37549.
6.17 Conclusion
Overall, it is considered that the proposal meets the overriding sustainable management
purpose of the Act. The project will be undertaken within a modified environment and is
consistent with the adjacent and surrounding uses.
The proposal will:
• enhance public access across and to the coastal environment whilst having no
more than minor adverse effects on access to and from the Milford Marina..
• The environmental effects of the proposal are considered to be no more than
minor, and importantly there will be no significant adverse effects from the
proposal such that the consent should be declined.
• The proposal is consistent with the relevant objectives and policies of the
NZCPS, HGMPA, the Regional Policy Statement, coastal plan and district plan.
Application No: 37549 and LR-213194 Page 57
7.0 RECOMMENDATION AND CONDITIONS
7.1 Recommendation 1
Late Submissions
Subject to new or contrary evidence being presented at the hearing, it is recommended
that pursuant to Section 37 and 37A of the RMA, the time limit for the receipt of
submissions be waived to accept the late submission(s) of Takapuna Residents
Association, G W Shaw and J N Revill for the following reason:
• No person will be prejudiced by the acceptance of the late submission.
• The submissions assist in achieving an adequate assessment of the proposal,
and
• The submissions were received within three days of the submission closure date
and did not delay the processing of the application.
It is considered that granting a waiver will be consistent with the participatory intention of
the Act.
7.2 Recommendation 2
Subject to new or contrary evidence being presented at the hearing, it is recommended
that pursuant to sections 104, 104B, 104D, and 108 of the RMA, consent is granted to
the non-complying activity application by Auckland Council to authorise the construction
of a pedestrian bascule bridge and associated boat lay-over area at Wairau Creek
(Consent Application 37549 and LR-213194).
The reasons for this decision are as follows:
(a) In terms of section 104(1)(a) of the RMA, the effects upon coastal processes,
natural character, landscape values, coastal ecology, and cultural heritage are
no more than minor.
(b) In terms of section 104(1)(b) of the RMA, the proposal is consistent with
objectives and policies of both the coastal plan and district plan.
(c) In terms of section 104(1)(c) of the RMA, other relevant matters, the proposal is
Application No: 37549 and LR-213194 Page 58
consistent with the Milford Reserve Management Plan.
7.3 Conditions
General Conditions
1. Pursuant to section 36 of the Resource Management Act 1991, this consent (or
any part thereof) shall not be exercised until such time as all charges in relation
to the receiving, processing and granting of this resource consent are paid in full.
2. The activities permitted by this consent shall be carried out in accordance with the
documentation submitted in support of the applications as identified below:
Report: Dated 5 May 2010, ‘Wairau Stream Pedestrian Bridge
Assessment of Environmental Effects’. Prepared by: Beca
Carter Hollings & Fraser (Beca).
Dated 2 June 2010, ‘Wairau Stream Weir – Assessment of
Environmental Effects’. Prepared by: Beca.
Dated 28 July 2010, ‘Wairau Stream Pedestrian Bridge – Further
Information’. Prepared by: Beca.
Correspondence: Dated: 6 September 2010, titled ‘Wairau Stream Pedestrian
Bridge – section 92 Response’.
Dated: 19 October 2010, titled ‘Wairau Stream Pedestrian
Bridge – section 92 Response (2)’.
Dated: 17 August 2011, titled ‘Wairau Stream Pedestrian Bridge
– Supplementary Information’.
Dated: 22 December 2011, titled ‘Wairau Stream Pedestrian
Bridge – Second Supplementary Information Letter.
Plans: Dated: January 2010, ‘Wairau Stream Footbridge, Proposed
footbridge and general arrangement sheet 1.’ Dwg. No.
Application No: 37549 and LR-213194 Page 59
4242890-R-001, Rev. A. Drawn by BECA.
Dated: January 2010, ‘Wairau Stream Footbridge, Proposed
footbridge and general arrangement sheet 2.’ Dwg. No.
4242890-R-002, Rev. A. Drawn by BECA.
Dated: 14 April 2010, ‘Wairau Bridge, Indicative plan for
temporary mooring area.’ Dwg. No. 4242890-C-100, Rev. A.
Drawn by BECA.
Dated: 14 April 2010, ‘Wairau Bridge, Temporary mooring area.’
Dwg. No. 4242890-C-101, Rev. A. Drawn by BECA.
3. Consent to undertake the construction of the bridge and lay-over area shall expire
on 19 April 2017 unless it has lapsed, been surrendered or been cancelled at an
earlier date pursuant to the Resource Management Act 1991.
4. Consent to occupy the CMA with a bridge and lay-over moorings shall expire on
19 April 2047 unless it has lapsed, been surrendered or been cancelled at an
earlier date pursuant to the Resource Management Act 1991.
5. No vessels shall berth in the lay-over area for a period greater than twelve hours.
6. At least 40 working days prior to the commencement of construction works the
consent holder shall submit a final detailed operation plan, for the approval of the
manager. This shall include but not be limited to the following:
a. Schedule and process of the bridge operation sequence;
b. Details of detection mechanisms and alert signals for both bridge users and
vessels;
c. Details and locations of the CCTV system to enable the remotely located
bridge operator to have full view of both vessel traffic and the bridge
d. The VHF Channel and mobile number available for vessels to demand a
bridge operation;
e. The method of Bridge Operation management during special events in Milford
Reserve and official regattas or races organised by the Milford Mariners
incorporated or Milford Cruising Club, including outside the hours of daylight;
f. The period and method for review of the Operations Management Plan
g. Liaison plan with Milford Marina representatives.
Application No: 37549 and LR-213194 Page 60
Construction Conditions
7. At least 15 working days prior to the commencement of construction works on the
site, a detailed construction management plan for works in the CMA, shall be
submitted for the approval of the Manager.
The purpose of the construction management plan is to ensure that all works are
undertaken in a manner which avoids remedies or mitigates potential adverse
effects during construction works. The construction management plan shall
specify, but not necessarily be limited to the following matters:
a. Final mechanical and structural design of bridge and associated structures.
b. Final design for bridge and road interface zone.
c. Construction timetable;
d. Site management, including details of:
• Site access
• Storage of fuels and lubricants (these should be bunded or contained in
such a manner so as to prevent the discharge of contaminants from
spillages)
• Heritage site management
• Maintenance of machinery and plant to minimise the potential for leakage of
fuels and lubricants
• Dust nuisance
• Confirmation that no equipment or machinery is cleaned, or refuelled in any
part of the CMA; and
e. Traffic management plan.
f. Methods to ensure compliance with noise standards.
g. Construction remediation plan.
h. Dredging method and management plan.
6. The Manager shall be notified in writing of the proposed date of commencement of
the proposed works covered by this consent, at least 10 working days prior to the
proposed start date.
7. The general public shall be forewarned of any restrictions on the use Wairau Creek
by public notice in the local press and signage to the entrance to the ramp of Inga
Application No: 37549 and LR-213194 Page 61
Road, and/or by other appropriate methods.
8. The method and location of disposal of potentially contaminated surface sediments
removed from the Wairau Creek prior to dredging, piling and as a result of the
removal of the existing path shall be subject to approval by the Auckland Council
prior to these works commencing.
9. For the duration of the works, the site shall be maintained in good order. The
consent holder shall, as far as practicable, remedy all damage and disturbance
caused by vehicle traffic, plant and equipment to the seabed, to the satisfaction of
the Manager.
10. All machinery and equipment shall be removed from the CMA at the completion of
each days works and/or when the incoming tide dictates that work must cease
(except that appropriately stored on a work vessel or platform above MHWS). No
refuelling of machinery or equipment shall be undertaken within the CMA.
11. Within 1 week following the completion of the works, all damage and disturbance to
the seabed and reserve land shall be remedied and all equipment, surplus soil and
construction materials removed, to the satisfaction of the Manager, such that any
remaining disturbance of the foreshore and seabed is able to be rectified by the
operation of natural processes within 7 days.
12. All practicable steps shall be taken to minimise sediment loading and increased
turbidity in the coastal marine area due to the construction works. All erosion and
sediment control measures used on site shall be in accordance with ARC Technical
Publication 90 (Erosion and sediment control guidelines for land disturbing activities
in the Auckland Region).
13. All works in the coastal marine area shall be restricted to the hours between 7.30am
to 6.00pm Monday to Saturday, and between 1 April and 30 November (to avoid
peak recreational use periods). No work shall occur on Sundays or Public Holidays.
Post Construction Conditions
14. The Manager shall be notified in writing of the date of completion of the works,
within 2 weeks of the completion date.
15. Within one month of the completion of the proposed works, the Consent Holder
shall supply to the Auckland Council a complete set of “as built” plans. All
correspondence shall be marked to the attention of the Coastal Consents and
Compliance Co-ordinator, Auckland Council.
Application No: 37549 and LR-213194 Page 62
16. The Consent Holder shall also provide a copy of the “as built” plans to the
Hydrographic Office (Chief Hydrographer, National Topo/Hydro Authority, Land
Information New Zealand, Private Box 5501, Wellington) within one month of the
completion of the works.
17. Following 90 days of continuous operation the consent holder shall provide a review
of the operational procedures. The review shall cover, but not be limited to, the
following matters:
i. A statement from a suitably qualified and experienced person evaluating the
level of noise emitted from the audible bridge warning system, and
commenting upon compliance with the District Plan permitted
levels/standards.
ii. A statement from a suitably qualified and experienced person evaluating the
level of light emitted from all lighting, including the visual bridge warning
system and commenting upon compliance with the District Plan permitted
levels/standards.
iii. Feedback from representatives of Milford Mariners Incorporated, Castor Bay
Residents and Ratepayers Association, the Harbourmaster, the Bridge
Operators, and any other relevant groups on methods to improve the
operational efficiency of the bridge for all users.
iv. A record of daily bridge operations.
Maintenance Requirements
18. The structure permitted to occupy the CMA by this consent shall be maintained in a
good and sound condition, and any repairs that are necessary shall be made,
subject to obtaining any necessary resource consents.
Extent of Occupation
19. The right to occupy part of the coastal marine area shall not be an exclusive right,
and the Consent Holder shall at all times permit all persons to use the structures
identified in the plans for the purpose of providing public access along the coastal
marine area.
Application No: 37549 and LR-213194 Page 63
Review Condition
20. The conditions of this consent may be reviewed by the Manager, pursuant to
Section 128 of the RMA, by giving notice pursuant to Section 129 of the RMA, in
May 2011 and every two years thereafter in order:
i. To deal with any adverse effect on the environment which may arise
from the exercise of the consent and which it is appropriate to deal with
at a later stage; or
ii. To deal with any other adverse effect on the environment on which the
exercise of the consent may have an influence.
Advice Notes
1. The provisions of Section 116 of the RMA determine when a resource consent may
commence, unless a later date is stated as a condition of consent. The details of S116
are summarised in the attached letter issued with this consent.
2. Section 124 of the RMA sets out the provisions that allow a Consent Holder to
continue to exercise a resource consent while applying for a new consent for the same
activity.
3. Section 125 of the RMA relates to the lapsing of consents. This resource consent
lapses on the date specified in the consent or, if no date is specified, 5 years after the
date of commencement of the consent, unless the consent is given effect to or other
criteria contained within S125 are met.
4. This consent may be transferred to another party, pursuant to Sections 136 and 137 of
the RMA, if the consent holder notifies the ARC in writing of their intention to do so.
5. It is the responsibility of the consent holder to comply with all relevant provisions of the
Building Act 1994.
6. Payment of any administrative charge fixed in accordance with Section 36(1) of the
Resource Management Act 1991, or any additional charge shall be required pursuant
to Section 36(3) of the Resource Management Act 1991 in respect of this consent.
7. During the construction period, the Consent Holder shall comply with the noise
restrictions in Rule 35.5.5 of the Auckland Regional Plan: Coastal and the relevant
Application No: 37549 and LR-213194 Page 64
District Plan.
8. The consent holder shall not carry out, modify, extend, alter or reconstruct any works
in the part of the coastal marine area subject to this consent without first obtaining any
other resource consents for such works which are required.
8.0 OFFICERS RECOMMENDATION
8.1 Adequacy of Information
It is considered that the information submitted with the application is sufficiently
comprehensive to enable the consideration of the following matters on an informed basis:
a) The level of information provides a reasonable understanding of the nature and
scope of the proposed activity as it relates to the district and coastal plan.
b) The extent and scale of any adverse effects on the environment are able to be
assessed.
c) Persons who may be adversely affected are able to be identified.
Report Prepared by: Sam Morgan
Title of Reporting Officer:
Senior Consents and Compliance Advisor -
Coastal
Signed:
Date: 27 March 2012
Report Release by: Alan Moore
Title Team Leader- Coastal
Signed:
Date: 27 March 2012