April 1, 2008TPTF

Early Delivery SystemsStatus

Daryl Cote

Page 2: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

2TPTF4/1/2008 2

Agenda

• EDS 2 – Release 3: State Estimator

• TSP Dashboard• Load Status• Wind• QSE Dashboard• SE results (March vs Feb)

– EDS 2 Release 4: NOMCR• EDS 3

– Release 5: SCED– Release 6: LFC– Release 7: CRR

• EDS 4– Release 8: Coms– Release 9: DAM / RUC / SASM

Page 3: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

3TPTF4/1/2008 3

TSP Dashboard

Page 4: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

4TPTF4/1/2008 4

Convergence Rate

MVAR tolerance remains at 30. Working to identify reactive curves that need to be adjusted so that MVAR can be set to 15 also

Page 5: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

5TPTF4/1/2008 5

Load Status

Page 6: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

6TPTF4/1/2008 6

EDS 2 – Wind Output from QSEs

This data is required to support AWS

TrueWind’s forecast tuning

Page 7: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

7TPTF4/1/2008 7

QSE Dashboard

Page 8: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

8TPTF4/1/2008 8

State Estimator 30 day Comparison

Metric Zonal 2-28 Zonal 3-27 Nodal 2-28 Nodal 3-27

Buss Observability 98.1 98.0 94.7 95.3

Branch with MW measurement mismatches across 2 endsLine Only

Line >5 74 81 89 104

Line >15 14 17 29 25

Line >25 3 4 14 9

Max 68.7 38.4 -219.4 -98.1

Page 9: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

9TPTF4/1/2008 9

State Estimator 30 day Comparison II

Measurement Availability

Zonal 2-28 Zonal 3-27 Nodal 2-28 Nodal 3-27

Analog MeasurementsAvailable Mapped-Non SI%

95.5 95.9 88.6 90.0

Topology Monitoring

UnitForced Remove

3 2 34 27

LoadForced Remove

14 16 22 34

Page 10: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

10TPTF4/1/2008 10

Next Steps

• Complete Telemetry Reporting

• Remedy Application issues

• ERCOT build redundant servers at Met Center

Page 11: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

11TPTF4/1/2008 11

Release 4 – NMMS / NOMCR

2007 2008Sep Oct Nov Dec Jan Feb

R4: NOMCR / Network Model verificationE2 R4NOMCR Checkout Network Model Verification

NMMS/NOMCR overview training has been completed by the market participants Citrix connections and digital certificates have been successfully installed and validated for

100% of the market participants Onsite NMMS training and scripted scenario execution completed by:

AEP, Rayburn, STEC, and College Station Onsite training to occur week of 4/7 for:

CenterPoint & Greenville Onsite training to occur week of 4/14 for:

Austin Energy, Garland, CPS San Antonio All MP to complete onsite training week of 5/19

Page 12: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

12TPTF4/1/2008 12

EDS SLA Metrics

This data only describes HW. March number should include applications.Reports are posted at: http://nodal.ercot.com/readiness/index.html EDS - SLA Metrics Summary (February 2008)

Page 13: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

13TPTF4/1/2008 13

Release 5 - SCED

2007 2008

SCED R5.1 SCED R5.3: RT ICCP SCED R5.4: LMP Post

Sep Oct Nov Dec Jan Feb

SCED R5.2E3 R56-month LMP PostingRT ICCP

EDS 3 Release 5 Exit Criteria % Complete

Comments

Daily submissions of COP, TPO, and OS ~90% •Temporary performance fix to be included in MMS3 •Average submissions are in the 90% range•Issue encountered with MMS caused outage from 3/19 to 3/26; SPPs still not being published•Upgrade of EMS broke EMS – MMS; resolved on 3/26

SCED Inputs verified: HRL, LRL, SURAMP, SDRAMP, HDL, LDL; GTBD, ICCP

90%(80%)

GTBD within ~200 MW of Zonal

SCED Outputs verified: QSE’s ability to receive Resource Base Points and LMPs via ICCP

90%(60%)

Base Point and LMPs (with 5 decimals being sent over ICCP)

Base Point and LMP calculation verified for Resources with Offer Curves or Output Schedules

100%(100%)

Reports 100%(100%)

Reports related to SCED are available in draft form on MIS and https://nodaleds.ercot.com/nodalercot/readiness/reports/publicreports.html

LMPs verified for Reasonability and posted to MIS for Market Participant review 100%

(100%)

Completed on Feb 15th. The calculation of the LMPs are reasonable given the input data, but the input data needs improvement.

Legend: % in parentheses are from the 2/22 TPTF update

Page 14: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

14TPTF4/1/2008 14

Recent Issues with LMPs

• Poor quality of ICCP data will cause SE & TCM to not publish results to MMS; therefore stale LMPs & BPs or uniform LMPs

• EMS – MMS interface shuts down daily (reported Oracle issue); therefore stale LMPs & BPs

• COP / TPO / OS submissions to SCED are sufficient

EMS MMS

Market Participant

Starting in Mid-April, ERCOT will contact MPs Real-Time desks when data issues cause SE / TCM failures. This will be done 24x7

1 2

3

1

2

3

Page 15: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

15TPTF4/1/2008 15

Release 6 - LFC

2008Jan Feb Mar Apr May Jun

E3 R6 R6.1: ACE & RLC

EDS 3 Release 6.1 Exit Criteria % Complete Comments

Test Time Scheduled (Phase 1 and 2) 100%(100%)

Dates have been set with all QSEs with Resources.

Completed Test Form Received back from MP 100%(80%)

All QSEs tested

RLC Validation Completed 100%(71%)

Full completion pending regression test of SPR 1643 and 2211

Emergency Base-Point Validation Completed 100%(33%)

ERCOT issue has been resolved and QSEs that conducted testing when the issue existed have been contacted to setup a regression test

EM05 verify ACE Performance TBD%(0%)

Data submitted to TPTF for review

Legend: % in parentheses are from the 2/22 TPTF update

R6.2: QSE Testing R6.3: TST

Page 16: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

16TPTF4/1/2008 16

Release 6 - LFC

2008Jan Feb Mar Apr May Jun

E3 R6 R6.1: ACE & RLC

EDS 3 Release 6.2 Exit Criteria % Complete Comments

Testing time scheduled 100%(0%)

6.2 pre-test conducted (dry-run) 20%(0%)

Garland P&L, NRG, STEC, Suez

Individual QSE UDBP and Regulation 10%(0%)

Garland P&L, STEC

Constant Frequency Operation Test 10%(33%)

Garland P&L, STEC

Responsive Reserve Service Schedule Test 10%(0%)

Garland P&L, STEC

Legend: % in parentheses are from the 2/22 TPTF update

R6.2: QSE Testing R6.3: TST

~ 50% of the AS schedules and responsibilities being provided accurately via ICCP. 6.3 testing can not commence without this data.

QSEs wishing to accelerate their 6.2 test date are encouraged to do so.

Page 17: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

17TPTF4/1/2008 17

LFC 6.3 pre-Test

• Prior to R6.3 (total system test) the market desires an open loop test to validate SCED dispatch. Approach to accomplish this:– QSEs w/ Resources submit Excel files with EOC, OS, INC/DEC

on 4/8 that deconstruct Zonal activities for Operating period 4/7 7-9am

– Perform open loop test on 4/25 from 7-9am– Perform open loop test on 5/5 from 10-noon– Perform open loop test on 4/12 from 4-6pm

• ERCOT to provide QSEs with settlement impact resulting from OOME and Local Balancing had units followed SCEB BP

• Please refer to details provided during the 3/14 workshop: http://www.ercot.com/calendar/2008/03/20080314-EDS3-6.html

Page 18: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

18TPTF4/1/2008 18

Target Dates for 6.3 Tests

• Week of June 16th – 2 hour test

• Week of July 7th – 8 hour test

• Week of July 28th – 48 hour test

Page 19: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

19TPTF4/1/2008 19

Release 7 - CRR

EDS 3 Release 7 Status % Complete Comments

Release 7.1 Connectivity and Submissions 100%(0%)

56 of 71 completed tests

Release 7.2 Scripted Monthly Auction 100%(0%)

50 participants successfully submitted bids (91% participation)

Release 7.3 unscripted Monthly Auction 100%(0%)

40 participants successfully submitted CRR Market Credit Limit (71% participation)43 participants successfully submitted self-created bid portfolios (75% participation)39 participants participated in bilateral trade activity – initiated or accepted trades (69.64% participation)Readiness Metric CRR3 Completed

Jan 08 Feb 08 Mar 08 Apr 08 May 08Dec 07CRR – R7.0 CRR – R7.1 CRR – R7.2 CRR – R7.3 CRR R7.4 CRR – R7.5 (TBD)

Jan 08 Feb 08 Mar 08 Apr 08 May 08Dec 07 Jan 08 Feb 08 Mar 08 Apr 08 May 08Dec 07CRR – R7.0 CRR – R7.1 CRR – R7.2 CRR – R7.3 CRR – R7.5 (TBD)

Release 7.4 Scheduled to begin 4/7; possibility of delayed completionCRR team to discuss configuration limitations with TPTF on 4/2

Legend: % in parentheses are from the 2/22 TPTF update

Page 20: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

20TPTF4/1/2008 20

EDS 4 Release 9.1

2008Jan Feb Mar Apr May Jun

E4 R9 R9.1: DAM/RUC Submission Testing R9.3: R9.4: DAM/ Adj Period, RT

R9.2: Outage Scheduler

Legend: % in parentheses are from the 2/22 TPTF update

Those not completed with 9.1 will be Red for Readiness Metric MP8 after 3/31.

EDS 4 Release 9.1 Exit Criteria % Complete

Comments

Intent to Participate Sent 86%(83%)

Sign-Up Testing Window Scheduled 86%(81%)

See next slide

MP8 - QSE Ability to Submit Transactions Via MIS

86%(32%)

MP9 – QSE Ability to Submit Web Service Transactions

100%(23%)

Of those who indicated desire to use Web Services

Page 21: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

21TPTF4/1/2008 21

EDS 4 Release 9.1

Ambridge Energy* AquilaCitadel Energy ProductsClearview Electric Glacial Energy Kansas City Power and Light

National Power Company Sitara Energy Texpo Power Urban Energy Source WCW International

QSEs that have not signed up for a testing window for EDS4 (as of COB 3/28/08)

Page 22: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

22TPTF4/1/2008 22

EDS 4 Release 9.2

2008Jan Feb Mar Apr May Jun

E4 R9 R9.1: DAM/RUC Submission Testing R9.3: R9.4: DAM/ Adj Period, RT

R9.2: Outage Scheduler

Legend: % in parentheses are from the 2/22 TPTF update

Release 9.2 Kickoff webex conducted on 3/27Testing to occur from 4/15 through 6/13

EDS 4 Release 9.2 Exit Criteria % Complete

Comments

Test Window Scheduled Market notice sent requesting TSPs and QSEs with Resources schedule a test window by 4/4. 10 MPs have responded to date (as of 3/31)

Completed Scripted Testing

Participate in Performance testing

Participate in Dual Entry days (prior to 168hr test)

Page 23: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

23TPTF4/1/2008 23

EDS 4 Release 9 timeline as showed in the approved handbook

Feb Mar Apr May Jun JulJan Aug

9.1 - DAM/RUC Submission testing

9.3 - Initial DAM/RUC Exec

9.4 - Exec DAM, Adj Period, RT Ops

9.5 - Pre-Test for 168 hour test

• Final assembly and testing of all deliveries, integration and functionality• Implement final MMS delivery to include Baseline 1 and 2 changes• Testing of relevant portions of MIS/EDW/Extracts• Test of EECP, DST, Compliance monitoring and tools• Execute DAM without any significant error of DAM for 7 consecutive

days and provide settlement statements • Execute two Operating Days without interruption along the full market

timeline with no critical failures• ERCOT and QSEs execute nodal timeline in parallel to zonal market

• Begin Adj Period activities – SASM/HRUC• Submit all transactions for DAM, Adj Period and RT Ops• Download reports for DAM/DRUC/HRUC/SASM• Performance testing of DAM• Stub data as needed for DAM, Adj Period and RT activities• Execute market timeline for 7 consecutive days

• QSEs submit transactions to DAM/RUC• Post pre-DAM/RUC exec data (A/S Obligations, LF)• Execute DAM and RUC• Test MMS integration with NMMS and EMS • Communicate results to QSEs (MIS and notifications)• Test QSE ability to receive notifications, prices, awards• Stub in other data as needed

• DAM/RUC database for MP EDS Activities• Verify QSEs ability to submit, modify,

cancel, and retrieve submission items using MIS/User Interface and/or Web Services

• MMS2• DAM / RUC Submission Items • MMS2

• CIM Integration• EMS-MMS Integration

• MMS3 (MMS2 + SASM, CIM Imp)• MMS4• Settlements integration• All Integration points addressed• MIS/EDW Integration

Page 24: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

24TPTF4/1/2008 24

Proposed revisions to EDS 4 Release 9 timeline

Feb Mar Apr May Jun JulJan Aug

9.1 - DAM/RUC Submission testing

9.3 - Exec DAM/RUC/SASM

9.4 – Integration and Preparation for 168 hour test

• Final assembly and testing of all deliveries, integration and functionality• Implement final MMS delivery to include Baseline 1 and 2 changes• Performance testing of DAM• Execute DAM, DRUC, HRUC, SASM • CIM Integration between NMMS, MMS and EMS • Test of EECP, DST, Compliance monitoring and tools• Testing of relevant portions of MIS/EDW/Extracts• Execute DAM without any significant error of DAM for 7 consecutive

days and provide settlement statement • Execute two Operating Days without interruption along the full market

timeline with no critical failures• ERCOT and QSEs execute nodal timeline in parallel to zonal market

• DAM/RUC database for MP EDS Activities• Verify QSEs ability to submit, modify,

cancel, and retrieve submission items using MIS/User Interface and/or Web Services

• QSEs submit transactions to DAM/RUC• Post pre-DAM/RUC exec data (A/S Obligations, LF)• Execute DAM and RUC• Communicate results to QSEs• Test QSE ability to receive notifications, prices, awards• Stub in other data as needed• Execute SASM/HRUC capabilities in May 08

• MMS2• DAM / RUC Submission Items

• MMS3 • CIM Data Stub

• MMS4• Settlements integration• All Integration points addressed• MIS/EDW Integration

MMS 3 and MMS 4 will be deployed earlier to the EDS environment to enable market testing

Page 25: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

25TPTF4/1/2008 25

What does it mean for ERCOT and MPs

Feb Mar Apr May Jun JulJan Aug9.1 - DAM/RUC Submission testing 9.3 - Exec DAM/RUC/SASM 9.4 – Integration and Preparation for 168 hour test

• MMS2• EIP• MMS UI

• MMS 3• Stub CIM + other

data• EIP Awards query• MMS UI upgrades

• MMS 3• EIP Notifications• UI Notifications• MMS-OS Integration

• EMS-NMMS-MMS Integration

• Implement last EMS delivery

• MMS-CMM integration

• MIS• CDR• Compliance

monitoring

• Submit, modify, retrieve, cancel bids and offers

• Submit transactions to DAM and RUC

• Download DAM Awards

• Participate in DAM, Adj period and RT Ops testing

• Receive DAM Award notifications

• Validate Settlements stmts

• Participate in DAM performance test

• Verify new Day Ahead and RT reports

• Extract support• Adapt to Baseline1/2

Market Submission changes in MMS4

• Participate in DAM and settlement of 168 hour test

• Participate in DST and Failover testing

• Participate in EECP test

• Provide environment for uploading bids and offers

• Execute DAM / RUC• Enable downloads of

awards• Produce DAM

settlement stmts

• Execute DAM / RUC/HRUC/SASM

• Produce DAM settlement stmts

• Enable notifications

• Conduct DAM performance test

• Run market timeline for 7 consecutive days

• Conduct 168 hour test of DAM

• EECP• DST and Failover• Compliance

monitoring

• MMS 4• EMS-MMS

Integration• MMS - S&B

Integration• MMS - NMMS

integration• CSI

• Execute DAM / RUC/HRUC/SASM

• Implement B1 & B2 submission items

• Settlements Integration

Current day reports and EDW extracts will be deployed according to the DAG schedule

ERC

OT

Mar

ket

Part

icip

ant

Page 26: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

26TPTF4/1/2008 26

A Go-Live Plan is being developed that will encompass key activities/actions post the successful completion of the 168-Hr test

Key Elements of the plan include: ERCOT and Market Participant engagement expectations Communications and ongoing health checks during the go-live period Phased staging of production submission during cut-over Planned regression test of Nodal LFC Software environment controls (migration freeze) Contingency planning and guidelines for switch of control back to zonal

Next Steps Target Completion Date

Complete ERCOT review April 7th

Present to TPTF for Vote May 5th

Present to TAC for Vote June 5th

Present to BoD June 17th

Page 27: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

27TPTF4/1/2008 27

EDS Deliverables

DAM/RUCR9.4

EECP Go-Live DST

Post for TPTF Comment

Apr 25 Apr 7 April 10 May 8

Comment Close May 1 Apr 14 April 24 May 16TPTF Vote May 5 Apr 21 May 5 May 22/23

Legend: indicates completion

Page 28: April 1, 2008 TPTF Early Delivery Systems Status Daryl Cote

28TPTF4/1/2008 28

Questions?