Page 1: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

April 21, 2010

Barbara C. Jordan Elementary School Update

Presented by

Page 2: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

• SafetyBarbara Jordan Incident Rate 0.00 with 17,792 hours worked- Construction Industry Average Incident Rate in 2008 was 4.7- (recordable or lost time) = [(number of recordable or lost time injuries) x 200,000]/(number of hours)

• Quality- 8 non-conformance issues written to date and have been remediated

• Schedule- CPM Schedule is developed and contractor comments are being incorporated prior to CPM submission - 21 weather days to date but appears to be incorporated into the schedule logic- Current Completion Date: February 23, 2011

• MBE/WBE Minority Workforce- MBE Goal 15% Barbara Jordan to Date 24%- WBE Goal 5% Barbara Jordan to Date 4%- Minority Workforce Goal 10% Barbara Jordan to Date 47.07%

Page 3: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by
Page 4: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by
Page 5: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by
Page 6: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

Barbara C. Jordan Building Underground (Looking North)

Plumbing Underground was started February 16 and completed March 3

Page 7: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

Barbara C. Jordan water line was started March 4

(Looking West)

Page 8: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

Steel Erection started March

Page 9: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

Mock-ups started on March 18 – can be seen from 82nd Street

Page 10: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

Load Bearing Masonry started March 19 in the Gym

Looking North

Page 11: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

Electrical wall rough-in and underground started March 19

Page 12: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

Mechanical hangers started April 9

Page 13: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

Safe Entry (Overhead Protection) and recent steel erection progress (South Elevation)

Page 14: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

What’s Next?• Concrete Slabs –

- Concrete elevated slab pours will start tomorrow - Concrete slab-on-grade will start April 29 - Concrete slabs to complete by May 21

• Structural Steel –- Roof screen steel will start upon completion of elevated slab pours- Roof deck will be placed after roof screen framing is erected- Gym and Cafeteria bar joists erection will start April 30

• Plumbing – - Water service will be completed to the building- In-wall plumbing rough-in will start in 1st floor restrooms after slab pour

Page 15: April 21, 2010 Barbara C. Jordan Elementary School Update Presented by

• Electrical –- Electric in wall erection will start with wall framing

• Masonry –- Load Bearing Masonry in Gym and Cafeteria will complete April 30

• Building Enclosure Program- Mock-up sun screen brackets will be installed the week of April 26- Mock-up air/moisture barrier and detailing will be started the week of May 3- Exterior Building studs will start the week of May 3

• Interior - Interior partitions will start the week of May 3