aps profile company
TRANSCRIPT
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
2 Email: [email protected]
Summary Introduction:
Name : Arshia Petro Santa Khavar Mianeh (APS)
Company Type : Private
Grading : Grade 3 on Oil and Gas / Grade 4 on Construction
Economy Code : 411394313547
Board of Directors : A.Abnoos – M.Moslemi – M.Tavasoli – M.Eskandari
Chairman : A.Abnoos
Managing Director : M.Moslemi
Tel No. : +9821 8856 3849, +9821 8856 3859, +9821 8837 9173, +9821 8837 9178
Fax No. : +9821 8856 3861
Central office Address : Apartment No.3 , Third floor, Building No.162, Darya Blvd, Between Paknegad and Motahari, Gharb County , Tehran.
Yard Address : 37 Km, West Bandar Abbas
Email Address : [email protected]
Web Site : www.aps-oie.com
Scope of Work : We are a General Contractor performing turnkey projects, project management and project development in all oil & gas, petrochemical power plants both National and International. We are performing all Engineering services, Fabrication plans, Research plans in all our permitted fields, also all Consultant & Construction services for petrochemical complex, Oil & Gas Refineries & Petrochemical plants. Arshia Petro Sanat fulfill all Oil & Gas pipeline projects, Water pipelines, Auxilary facilities of power plants, in both on shore & off shore, Ship Repairing, Excavation, Earth filling, Drilling, Installation & Commissioning, Project control & planning, Technical support services for Administrative & Contractual proposals, Making consortium with similar companies, feasibility studies, Engineering & Procurement, Implementation of Management systems & Strategic Management, Risk Management, Contract Management & Project Management for Oil & Gas and petrochemical, would be in our scope of work.
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
3 Email: [email protected]
History :
Arshia Petro Sanat Khavar Mianeh (APS) started activity as a Fabrication Subcontractor called Abnoos,
in year 1997, in Lordegan city.
The objectives of this group had been summarized in, offering a new method of services to Oil & Gas
Contractors/Clients and did its best with fulfilling projects on time, satisfying the clients, being capable
in forming expert project teams as well as, project cost’s control. In South Pars Phase 14, platform has
been rolled up by this small group in 20 days period successfully.
We have achieved precious experiences over the years in all aspects of EPCI oil / Gas, petrochemical &
power plants.
This subcontracting company, just because of its patriotism, aimed to develop the country industry
and changed totally to a Company named :Arshia Petro Sanat Khavar Mianeh , in year 2008. One of
the main reasons for this company was the company accurate management to achieve the best
economical way to do the projects in a safe mode. We have started to go ahead in our way to develop.
We also achieved the Grading for Oil & Gas and construction in 2014 for performing our projects in
ideal way.
Vision :
Arshia petro Sanat, with reliance to its abilities for accomplishment of all on shore & off shore construction projects with high quality and in a minimum time proceeded to go head in Engineering, Procurement and Construction of all on shore & off shore structures & equipments to help our country’s self development. We will ascertain this, by the help of our capable & formidable experts and modern technology & equipment.
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
4 Email: [email protected]
Competitive advantages :
APS, has been created an experienced team to assist the economical and industrial organizations’ managers and clients for going ahead to development in both onshore and offshore fields. We have achieved a precious experience over the years, to fabricate, installation, testing and commissioning as with support of applying required modern equipments. We owe our reputation from capable managers and experts in our company, which are one of our main funds. The basic objective of our management team is customer’s satisfaction; we are presenting high quality services to our customers and clients. In fact, our executive, monitoring and safety systems allow us to reach our goals to present ideal services in a cost effectiveness way with high quality level. In other hand, our experienced dynamic personnel and management ,facilitate the way to achieve our objectives in this regard. Accomplishment the projects in minimum period in a high quality level with being cost effectiveness, achieving our customer’s satisfaction and ability to do different projects simultaneously are the major signs of our company ability to perform the job in a best way. The following items are the witness of our competitive advantages:
- High financial strength : To perform the 1188000000000 Rials Project in 4 years.
- High level QA/QC management : Obtaining the international certificates: ISO/TS29001:2010, ISO9001:2008, ISO14001:2004
OHSAS18001:2007, HSE-MS Main bearing and bearing support with 4 meters diameter on installed piece in SPM
project. - Performing the project in minimum period :
Fabrication of 2 sets of tripods for south pars phases 14 with 1000 tons weight in 30 days. Structure fabrication of deck B for south pars phase 14 in 3 months. Construction of 4 sets jackets for south pars phase 14 with 8000 tons weight in 150 days. Construction of tripods and piles for phase 19A, 19C, with 3000 tons weight in 90 days. Construction of tripods and piles for projects south pars phase 20, 21 with 1200 tons in 60
days. Construction of mechanical part for the first SPM in Iran in 7 months. Hook up operation for phase 12 platform in 60 days.
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
5 Email: [email protected]
Company Abilities
Aligned with realization of appropriate infrastructures for sustainable development of our country, through outsourcing the projects to private sector, we are proud to support the clients with our potential abilities. Our domain services includes: all management services, engineering, procurement of material and equipments, projects management in Oil / Gas, petrochemical and power plants.
Our scope of work includes below:
All fixed equipment construction such as pressure tanks, storage tanks, heat exchanges, chemical packages, towers, …
All Oil & Gas platforms structures. All platforms ancillaries such as: jackets / tripods, bridges, flares, piles,.. Air conditioning systems installation on all Oil / Gas platforms. Oil & Gas platforms piping. Hydro test activities on pipelines and storage tanks. Civil operation of Oil & Gas platforms, Electrical, instrument operation for Oil & Gas platforms. Offshore & onshore Oil and Gas pipelines. Offshore cable lying. Internal inspection and Hydro test in Oil & Gas pipelines. Sea fastening and load out operations. Hook up operation. Offshore installation of jacket, piles, platforms installation. Precommissioning / commissioning. Vessels periodic maintenance on dry dock or floating dock on the supervision of clients. Subsea inspection and video recording. Subsea repair and maintenance of vessels & main structures. Offshore structures maintenance & development. Paint / sand blasting of marine & submarine projects. Anode installation projects on offshore & onshore pipelines.
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
6 Email: [email protected]
Codified procedures in Arshia petro Sanat Khavar Mianeh :
No. Procedure Name Applicable in
1 Management strategic procedure
The objective of this procedure is to clarify communication methods of top management with company downstream process and projects, in order to monitor its effectiveness to go along company main goals.
2 Quality management system This procedure is prepared to clarify the quality management system’s policy as well to determine the managers & personnel responsibilities in company.
3 HSE
This procedure is to define : - To decrease the accident / incident to minimum level. - To decrease the environmental pollutants to minimum level. - To decrease the wastage in processes to minimum level and gain the favorable output. - Finally analysies the HSE data and monitoring improvement is happened or not.
4 Project Control Procedure
This procedure is to define : - Project management contains activity such as initiating,
planning, executing, controlling, and closing the work of a team to achieve specific goals and meet specific success criteria base on PMBOK standard.
- Project management software in our company base on Primavera P6 and Microsoft Project Server 2013.
- All projects are managed by Project Management Office (PMO) since 2013
5 Training procedure This procedure is prepared to ensure the managers and personnel’s competence, and the competence include / education / training / skills and experiences.
6 Continuous improvement procedure
The procedure goal is to implement corrective measures and preventive actions for performing continuous improvement to eliminate the problems and fix deficiencies.
7 Business development & CRM procedure
This procedure is to define an administrative method to describe relationship and/ communication with potential customers / clients, obtaining projects from clients, and how to keep in touch with them. The methods of customer’s satisfaction and its measurement would be described in this procedure.
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
7 Email: [email protected]
No. Procedure Name Applicable in
8 Analysis and overview procedure This procedure objective is to analyze company performance, method statements and procedures within a specified period in order to increase productivity.
9 Value engineering procedure This is an efficient method to identify and remove unnecessary costs and short implementation time and optimization of projects.
10 Human resource management procedure
The purpose of this procedure is to implement the policies and goals of organizations and individuals in the area of staff.
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
8 Email: [email protected]
Integrated Management System Policy :
Arshia Petro Sanate Khavar Mianeh, utilized the specialized human resources, advanced systems and
know-how in the world, is active in Offshore Oil & Gas Projects.
This Company is a general Contractor (G.C) performing turnkey projects, management contract (MC),
Engineering, Procurement & Construction (E.P.C), also provides consulting services.
In order to promote the quality & quantity of the projects, environmental protection, sanitation &
safety rules observation in work place based on:
ISO/TS29001:2010,ISO 9001:2008,ISO14001:2004,OHSAS18001:2007,HSE-MS
Hereby declare the outlines of Integrated Management System as follows:
Increasing the competitive ability with fair prices
Efficient use of all resources and reduce costs on the projects
Endeavor for customers’ satisfaction, identification of beneficiaries & supp0ly their needs in
accordance with legal rules
Pollutant prevention for environmental protection through continuous improvement
Promotion of personnel’s technical , scientific & HSE level through detail planning for related
training courses
Ensuring compliance with observation of legal rules,standards,clients’ requirements
Prevent and reduce occupational diseases and accidents by identifying and assessing risks in
order to keep health human resources
Establishment & preservation of IMS standards in company & achieving our mentioned objectives, is
related to all personnel’s cooperation & the top management of company hereby declare his
commitment toward the legal compliances for objectives determination and implementation.
This IMS Policy would be overviewed in specified period by top management.
M.Moslemi
Direct Manager
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
9 Email: [email protected]
Certificates
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
10 Email: [email protected]
HSEQ Certificates :
1- Certificates of Jas.ANZ- Australia from Jul 2013 until Jul 2016
ISO 9001 : 2008 ISO 14001 : 2004 ISO 29001 : 2010 OHSAS 18001 : 2007 HSE-MS
2- Certificates of qcb- Italia from Jul 2016 until Jul 2019
ISO 9001 : 2008 ISO 14001 : 2004 ISO 29001 : 2010 OHSAS 18001 : 2007 HSE-MS
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
11 Email: [email protected]
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
12 Email: [email protected]
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
13 Email: [email protected]
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
14 Email: [email protected]
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
15 Email: [email protected]
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
16 Email: [email protected]
Grading Certificate :
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
17 Email: [email protected]
Clients Satisfaction :
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
18 Email: [email protected]
Clients Specifications’:
No. Clients Name Contact Person
Contract Scope Address
1 ISOICO Mr.Hafezpour Construction of 2 Bridges, 2 Jackets of SPD-14B/SPD-14A & Flares of SPD-14A, B, C, D
37 km of West Bandar Abbas,ISOICO Yard
2 Arman Sazeh Aryan
Co. Mr.Arzoughi Constructin of jacket A, D S.P.phase 14
37 km of West Bandar Abbas,ISOICO Yard
3 Mobin Sazeh
Gostare Khalije fars Mr.Abbaspour
Construction & Installation of sea fastening for jacket C, S.P phase 14
37 km of West Bandar Abbas,ISOICO Yard
4 Mobin Sazeh
Gostare Khalije fars Mr.Abbaspour
Construction & Installati0n of sea fastening for jacket B, S.P phase 14
37 km of West Bandar Abbas,ISOICO Yard
5 Bahr Gostareshe
Hormoz Shipbuilding co.
Mr.Ghasemizadeh Operation of main structure & ancillaries for
Deck B, S.P.phase 14 37 km of West Bandar
Abbas,ISOICO Yard
6 Mobin Sazeh
Gostare Khalije fars Mr.Abbaspour Operation of platforms 07, 08 Hendijan field
37 km of West Bandar Abbas,ISOICO Yard
7 Mobin Sazeh
Gostare Khalije fars Mr.Abbaspour
Piping operation for 07, 08 platforms of hendijan field
37 km of West Bandar Abbas,ISOICO Yard
8 Arvand Poolad Faraynd Int.Co
Mr.Mamjad Construction & Installation of One SPM Khorramshahr, Yard
No.3, IOEC
9 IOEC Mr.Jazayeri Construction of tripods, flares, piles of S.P
phase 19C Khorramshahr, Yard
No.3, IOEC
10 Arvand Poolad Faraynd Int.Co
Mr.Mamjad Construction of tripods, flares, piles of S.P
phase 19A Khorramshahr, Yard
No.3, IOEC
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
19 Email: [email protected]
Experiences
South Pars Gas Field Development Oil Field Development
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
20 Email: [email protected]
South Pars Gas Field Development :
Phase 12
SPM (Single Point Mooring)
Construction
Hook up operation
Phase 19
Construction of Ancillaries Part C
Construction of Ancillaries Part A
Phase 14
Piping operation
Electrical System & Instrument
Operation
Construction of Platform
Construction of Platform Jackets
Construction of Ancillaries
Phase 20 & 21
Construction of Ancillaries
Construction of Platform
Phase 15&16
4 Inch onshore pipeline
32 Inch onshore pipeline
Phase 17&18
4 Inch onshore pipeline
32 Inch onshore pipeline
Hook Up & Pre-Commissioning
17B
Hook Up & Pre-Commissioning
18B
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
21 Email: [email protected]
Phase 12 :
SPM Construction
Client Arvand Poolad farayand Co./IOEC Location Khorramshahr Duration 9 months
Nowadays, The marine terminal as one of the best ways to load oil and its derivatives with respect to the minimum cost compared with loading docks, always have been in center of attention & interest to apply. As,the Marine Terminals ( SPM,single point mooring ) have been already interested by Iranian clients, some of the local companies entered to Engineering, Procurement & Fabrication of SPMs. APS Co. according to the priority of the subject & for support of Islamic Country development initiated the project of one Single Point Mooring Fabrication & commissioning for South Pars Phase 12 as IOEC subcontractor. Fabrication of this SPM in Khorramshahr yard is accomplishing as a complete National Project.
Hook up Operation project for platform C, S.P.Phase 12 Client IOEC
Location South Pars Free Zone Duration 2 months
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
22 Email: [email protected]
Phase 14 :
Piping Operation of S.P.Phase 14 Platform Client Mobin Sazeh Gostar
Location Bandar Abbas Duration 12 months
Electrical System & Instrument Operation for S.P.Phase 14 platforms
Client Mobin Sazeh Gostar Location Bandar Abbas Duration 12 months
Construction of platform B,S.P Phase 14 project Client Bahr Gostaresh Ship building Co
Location Bandar Abbas Duration 4 months
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
23 Email: [email protected]
Construction of Jackets A,D,S.P.Phase 14 Client ISOICO
Location Bandar Abbas Duration 90 days
Construction of Jackets B,C,S.P.Phase 14 Client ISOICO
Location Bandar Abbas Duration 5 months
Ancillaries of S.P Phase 14 project Client Nadim Gostaresh Khalij Fars
Location Bandar Abbas Duration 4 Months
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
24 Email: [email protected]
Phase 15 & 16 :
32 ,4 Inch pipeline project , South Pars Phases 15,16
Client IOEC Location Booshehr Duration 6 months
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
25 Email: [email protected]
Phase 17 & 18 :
32,4 Inch pipeline project, South pars Phases 17,18 Client IOEC
Location Booshehr Duration 7 months
Hook up operation project for platform B, S.P.Phase 17 & 18 Client Bahr Gostaresh Ship building Co
Location Bandar Abbas Duration 4 months
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
26 Email: [email protected]
Phase 19 :
Construction of tripods,Bridges,piles & flares of S.P Phase 19C
Client IOEC Location Khorramshahr Duration 7 months
Construction Project for tripods, bridges & piles of S.P.Phase 19A Client Arvand Poolad Farayand
Location Khorramshahr Duration 7 months
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
27 Email: [email protected]
Phase 20 & 21 :
SPD20 Platform Construction Project for S.P.Phase 20, 21 Client IOEC
Location KHorramshahr Duration 7 months
Ancillaries Construction project , S.P.Phase 20, 21 Client Arvand Poolad Farayand
Location Khorramshahr Duration 5 months
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
28 Email: [email protected]
Oil Field Development :
Hendijan
Development of Platforms 07,08
Piping Platforms 07, 08
Electrical & Instrument
Platforms 07, 08
Engineering & Pre Commissioning
Platforms 07, 08
Hengam
Construction of Platform
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
29 Email: [email protected]
Hendijan Field :
Piping project for platforms 07, 08 Hendijan Field Client Mobin Sazeh Gostar
Location Bandar Abbas Duration 12 months
Development of Platforms 07,08 project Client Mobin Sazeh Gostar
Location Bandar Abbas Duration 8 months
Electrical System & Instrument operation for Platforms 07,08 project Client Mobin Sazeh Gostar
Location Bandar Abbas Duration 11 months
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
30 Email: [email protected]
Engineering and Pre Commissioning platforms 07, 08 Hendijan Field Client Mobin Sazeh Gostar
Location Bandar Abbas Duration 12 months
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
31 Email: [email protected]
Hengam Field :
Other Project :
ABOOZAR GAS FLOW INCREASE PROJECT Client Petro Sahel Ofogh Kish/PEDCO
Location KHARK ISLAND Duration 6 months
Construction and installation Hengam oil platform Client Mobin Sazeh Gostar
Location Bandar Abbas Duration 12 months
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
32 Email: [email protected]
Completed Projects:
Discription Client Location Storage tanks piping Bana Gostar Co Bandar Abbas
Structure fabrication & piping Zolal Iran Co. Mahshahr
Structure fabricating & piping Mehvarsazan Co. Mahshahr
Pipng for Maroon Petrochimi Mehvarsazan Co. Mahshahr
Kharg Oil port renovation project include piping, structure & pile driving
Tehran Berkli Kharg Island
Lavan jetty structure fabrication includes piping, structure & pile driving
NIOPDC Lavan
Structure fabrication & piping Ramshir Co Assaluyeh
Structure fabrication & piping Yegan Foolad Co Assaluyeh,Phases 6,7,8
16 inch pipeline project from Abadan to Darkhoin Tasdid offshore development co
Khoozestan
Engineering,construction & installation of 2 Hinge Flange for Aboozar 1200 vessel
I O E C Khorramshahr
Engineering,construction & Installation of Moldering system on Aboozar 81 vessel
I O E C Khorramshahr
Construction & Installation of Sea fastening for Bahregnsar
I O E C Khorramshahr
Ancillary construction for S.P.9,10 phases IOEC / MSM Khorramshahr
Piping for Bahregansar,P.P I O E C Khorramshahr
Heli Deck construction for S.P Phases 9,10 IOEC/MSM Khorramshahr
Bahregansar Platforms Load out IOEC Khorramshahr
Dorood & Foroozan Renovation & revamping project IOOC/RGD Dorood & Foroozan Oil Field
Renocatin & revamping of IOOC Platforms IOOC/RGD Persian Gulf
Ancillaries Structure Fabrication of S.P.Phase 16 ISOICO/ASA Bandar Abbas
Skid beam Fabrication/Weighing support ISOICO/ASA Bandar Abbas
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
33 Email: [email protected]
Technical Ability
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
34 Email: [email protected]
Company Organization Chart :
Managing Director
Technical Consultants
Legal advisers
Market DevelopmentManagement
Execution Management
Procurement Management
QC / QA Management
Financial and Administrative Management
Engineering Manager
PMO
Order Engineering
Sales Engineering
Quality Control
Quality Assurance
Management Office
HSEQ Management
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
35 Email: [email protected]
Key personnel List :
No. Name Academic Degree Position Experience
1 M.Moslemi BS in Mechanic Engineering Managing Director 12 years
2 A.Kamali khah MS in Mechanic Engineering Technical Consultant 17 years
3 R.Hosseinpour MS in International Law Lawyer Consultant 10 years
4 A.Akbari BS in Mechanic Engineering Commercial Manager 20 years
5 E.Basakha BS in Industrial Engineering Construction Manager 12 years
6 J.Imani BS in Civil Engineering Engineering Dep. Manager 20 years
7 A.Afshang BS in Mechanic Engineering Strucural Dep. Manager 11 years
8 M.Sasani BS in Mechanic Engineering Piping Dep. Manager 15 years
9 A.Khodabakhsh BS in Electrical Engineering Elec and Ins Dep. Manager 12 years
10 H.Jalalifar MS in Mecateronic Commissuning Dep.
Manager 10 years
11 A.Samyari BS in Mathematics PMO Manager 11 years
12 S.Salahshoor BS in Mechanic Engineering Q/C Manager 10 years
13 J.Atashkar BS in Industrial Manager HSE Manager 20 years
14 B.Sohrabi BS in Industrial Engineering Market Development
Manager 10 years
15 Z.Eskandari BS in Acounting Admi. And Financial
Manager 13 years
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
36 Email: [email protected]
Equipment List :
No. Equipment Name Quantity Specification Property Type 1 Crane 2 50 tons Self Property 2 Crane 3 30 tons Self Property 3 Crane 3 25 tons Self Property 4 Crane 5 10 tons Self Property 5 Trailer 2 Self Property 6 Flooring Tractor 3 Self Property 7 Tractor 4 Self Property 8 Forklift 3 5.5 tons Self Property 9 Forklift 3 3.5 tons Self Property
10 Bus 5 Self Property 11 Mini Bus 8 Self Property 12 Nissan-Saypa-Mazda Pick up 4 Self Property 13 pasenger car 10 Self Property 14 Motor cycle 3 125 cc Self Property 15 Water Tank 2 Self Property 16 Compressor 5 Self Property 17 Rectifyer 230 Self Property 18 Water Tank 4 5000 liter Self Property 19 Gazoline Tank 2 20000 liter Self Property 20 Gazoline Tank 2 3000 liter Self Property 21 Container 10 6 meters Self Property 22 Container 8 12 meters Self Property 23 Residential (Conex) 22 12 meters Self Property 24 Residential 11 Self Property 25 Oven 5 Self Property 26 Manual Oven 300 Self Property 27 Grinding Machine 350 Self Property 28 Mini Grinding machine 300 Self Property 29 Saypa Diesel water tank 1 Self Property 30 Color inspection equipment 3 Self Property 31 Rail cutting machine 10 Self Property 32 Manual cutting machine 80 Self Property 33 Circular cutting machine 30 Self Property 34 Chain bevel cutting machine 25 Self Property 35 Banding machine(4 inch) 2 Self Property
36 Diesel Electric Generator 10 Self Property
37 Electrical Panel 00 Self Property
38 Welding Cable 10000 Self Property
39 3 phase cable 0000 Self Property
40 Chain Block 00 1-8 tons Self Property
41 Jack 00 5-50 tons Self Property
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
37 Email: [email protected]
42 Hydrolic Jack 0 50 tons Self Property
43 Hydrolic Jack 0 100 tons Self Property
44 Sand Blasting Pot 9 Self Property
45 Digital Grinding Machine 80 00 Self Property
46 Airless 7 Self Property
47 Water jet machine 4 7550 b Self Property
48 Magnet Drill 4 Self Property
49 Scaffolfing pipe 0000 6 meters Self Property
50 Scaffolding panel 7000 4,6 meters Self Property
51 Scaffolding fastener 00000 Self Property
52 Topography Camera 0 Self Property
53 Air Capsule (tank) 000 Self Property
54 Gas Capsule (tank) 100 Self Property
55 Termometer 0 Self Property
56 Welding Inspection
Equipment 0 Self Property
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
38 Email: [email protected]
Codes & Standards Related to Quality Control
1. GENERAL INTERNATIONAL SPECIFICATION AND STANDARDS
API Spec 5L Line pipe
API SPEC 2B API Specification for Fabrication of Structural Steel Pipe
API SPEC 2C Specification for Offshore Pedestal Mounted Cranes
API RP 2L Planning, Designing & Constructing Heliports for Fixed Offshore Platforms
API Spec 6D Pipeline valves (gate, plug, ball and check valves) -
API Std 1104 Welding of Pipelines and Related Facilities
ASME B16.5 Pipe flanges and flanged fittings (NPS ½ through NPS 24)
ASME B31.3 Process piping
ASME B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids
ASME B31.8 Gas transmission and distribution piping system
ASME PV Code 8 Div. 1 Boiler and Pressure Vessel Code - Pressure Vessels
ISO 9000/9001 Quality systems
MSS SP-75 Specification for high test wrought butt welding fittings
NACE MR01-75 Petroleum and natural gas industries—Materials for use in H2S-containing
environments in oil and gas production
ANSI AW WA D100 Welded Steel Tanks for Water Storage
API Spec 2C Offshore Cranes
API Std 650 Welded Steel Tanks for Oil Storage
ASME Sec. II Material Specification
ASME Sec. V Non-Destructive Examination
ASME Sec. IX Welding and Brazing Qualifications
ASTM 370 Testing Of Materials
AWS D1.1/D1.1M Structural Welding Code
AWS D1.1 Structural Welding Code – Steel
AWS A2.4 Symbols for Welding and NDT
AWS A3.0 Welding Terms and Definitions
EN 10204 Metallic Products-Types of Inspection Documents
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
39 Email: [email protected]
2. SPECIFIC INTERNATIONAL PIPING SPECIFICATION AND STANDARDS
ASME B16.9 Factory-made wrought steel butt welding fittings ASME B16.10 Face-to-face and end-to-end dimensions of valves ASME B16.11 Forged fittings, socket-welding and threaded ASME B16.20 Metallic gaskets for pipe flanges – Ring joint, Spiral-wound and Jacketed ASME B16.21 Non metallic flat gasket for pipe flanges ASME B16.25 Butt welding ends ASME B16.34 Valves - Flanged, threaded and welding ends ASME B16.36 Steel Orifice Flanges ASME B16.48 Steel line blanks ASME B18.2 Square, hexagonal bolts and nuts ASME B36.10M Carbon steel pipe ASME B36.19M Stainless steel pipe API RP 5L Specification for Line Pipe. EEMUA 142 Acoustic insulation of pipes, valves and flanges EEMUA 144 90/10 Copper Nickel Alloy Piping for Offshore Applications - Specification - Tubes
Seamless and Welded EEMUA 145 90/10 Copper Nickel Alloy Piping for Offshore Applications – Specification – Flanges
Composite and Solid EEMUA 146 90/10 Copper Nickel Alloy Piping for Offshore Applications – Specification – Fittings ISO 10474 Steel products – inspection documents MSS SP 43 Wrought Stainless Steel Butt-Welding Fittings MSS SP 53 Quality Standards for Steel Castings for Valves, Flanges, Fittings and Other Piping
Components MSS SP 54 Quality Standards for Steel Castings for Valves, Flanges, Fittings and Other Piping
Components MSS SP 55 Quality Standards for Steel Castings for Valves, Flanges, Fittings and Other Piping
Components MSS SP 61 Pressure Testing of Steel Valves NACE MR0175/ISO 15156 Petroleum and Natural Gas Industries Parts 1/2/3: Material for use in H2S containing Environments in Oil and Gas Production - 2004 TC 2
2008 Corrigenda Corrigenda Pack – 2005
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
40 Email: [email protected]
3. SPECIFIC INTERNATIONAL PIPELINE STANDARDS
API RP 1111 Design, Construction, Operation and Maintenance of Offshore Hydrocarbon Pipeline API 1104 Welding of Pipelines and Related Facilities ASME B16.47 Large Diameter Steel Flanges (NPS 26 thru NPS 60) BS 4515-1(2009) Welding of Steel Pipelines on Land and Offshore DNV OS-F1 01 Submarine Pipeline Systems ISO 15590-1 Induction Bends, Fittings and Flanges for Pipelines Part 1: Induction Bends MSS SP-44 Steel Pipeline Flanges
4. SPECIFIC INTERNATIONAL STRUCTURAL STANDARDS
API RP 2A-WSD Planning, Designing and Construction of Fixed Offshore Platforms Working Stress
Design
API RP 2B Fabrication of Structural Steel Pipe
API RP 2X Ultrasonic and Magnetic Examination of Offshore Structural Fabrication and
Guidelines for Qualification of Technicians
API RP 2H Carbon manganese steel plate for offshore platform tubular joints.
API RP 2MT1 As -rolled carbon manganese steel plate with improved toughness for offshore
structures.
API RP 2W Specification for Steel Plates for Offshore Structures, Produced by Thermo Mechanical
Control Processing (TMCP).
API RP 2Y Specification for Steel Plates, Quenched-and-Tempered, for Offshore Structures.
API RP 5Z Recommended Practice for Preproduction Qualification for Steel Plate for Offshore
Structures.
API RP 2Z Preproduction qualification for steel plates for offshore structures
American Society for Testing and Materials (ASTM)
A6 Std. Specification for general requirements for rolled structural steel bars, plates, shapes and sheet piling
A36 Specification for Structural Steel. A53 Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless. A106 Specification for Seamless Carbon Steel Pipe for High-Temperature Service A131 Specification for Structural Steel for Ships. A194 Carbon and Alloy Steel Nuts for Bolts for High Pressure and High Temperature Service. A325 Standard Specifications for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum
Tensile Strength. A370 Standard Test Methods and Definitions for Mechanical Testing of Steel Products. A500 Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural
Tubing in Rounds and Shapes. A537 Specification for Pressure Vessel Plates, Heat-Treated, Carbon-Manganese-Silicon Steel. A572 Specification for High-Strength, Low-Alloy Columbium-Vanadium-Steels of Structural
Quality. A578 Specification for Straight-Beam Ultrasonic Examination of Plain and Clad Steel Plates for
Special Applications. A633 Specification for Normalized High-Strength Low-Alloy Structural Steel.
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
41 Email: [email protected]
A709 Standard Specification for Carbon and High-Strength Low Alloy Structure Steel Shapes, Plates and Bars and Quenched and Tempered Alloy Structure Steel Plates for Bridges.
American Welding Society (ANSI/AWS)
D1.1 Structural Welding Code Steel AWS A3.0 Welding Terms and Definitions
British Standards Institute (BSI)
BS 5762 Methods for Crack Tip Opening Displacement (CTOD) Testing
European Standards (EN)
EN 10025 Hot rolled products of non-alloy structural steels and their technical delivery conditions EN 10225 Weld able structural steel for fixed offshore structures – Technical delivery conditions EN 10029 Tolerances on dimensions, shape and mass for hot rolled steel plates 3mm thick or above EN 10045 Charpy Impact Test on Metallic Materials EN 10113 Hot Rolled Products in Weld able Fine Grain Structural Steels EN 10002 Tensile Testing of Metallic Materials
5. SPECIFIC INTERNATIONAL PAINTING & COATING STANDARDS
ISO 209-1 Wrought aluminium and aluminium alloys – Chemical composition and forms of products. Part 1: Chemical composition
ISO 1512 Paints and varnishes – sampling of products in liquid or paste form ISO 2063 Metallic and other inorganic coatings – Thermal spraying-Zinc, aluminium and their alloys ISO 2431 Paint and varnishes – Determination of flow time by use of flow cups ISO 2808 Paint and varnishes – Determination of film thickness ISO 2811-1 Paint and varnishes – Determination of density ISO 4624 Paint and varnishes – Pull tests for adhesion ISO 4628-1,2,3,4 Paint and varnishes – Evaluation of degradation of paint coatings ISO 7253 Paint and varnishes – Determination of the resistance to neutral salt spray ISO 8501-1 Preparation of steel substrates before application of paints and related products – Visual
assessment of surface cleanliness – Part 1: Rust grades and preparation grades of uncoated steel substrates and steel substrates after overall removal of previous coatings
ISO 8502-1 Preparation of steel substrates before application of paints and related products – Tests for the assessment of surface cleanliness – Part 1: Field test for soluble iron corrosion products
ISO 8502-2 Preparation of steel substrates before application of paints and related products – Test for the assessment of surface cleanliness- Part 2: Laboratory determination of chloride on cleaned surfaces
ISO 8502-3 Preparation of steel substrates before application of paints and related products – Test for the assessment of surface cleanliness – Part 3: Assessment of dust on steel surfaces prepared for painting (pressure-sensitive tape method)
ISO 8502-4 Preparation of steel substrates before application of paints and related products – Test for the assessment of surface cleanliness – Part 4: Guidance on the estimation of the probability of condensation prior to paint application
Doc No : APS/BD-CP001
Rev No. 03
Rev Date 2016/09/06
Arshia Petro Sanat Khavar Mianeh
(APS)
Profile Company
Web site: https://aps-oie.com
42 Email: [email protected]
ISO 8503-1 Preparation of steel substrates before application of paints and related products - Surface roughness characteristics of blast steel substrates – Part 1: Specifications and definitions for ISO surface profile comparators for the assessment of abrasive blast cleaned surfaces.
ISO 8503-2 Preparation of steel substrates before application of paints and related products – Surface roughness characteristics of blast cleaned steel substrates – Part 2: Method for the grading of surface profile abrasive blast cleaned steel – Comparator procedure
ISO 8504-2 Preparation of steel substrates before application of paints and related products – Surface preparation methods – Part 2: Abrasive blast cleaning
ISO 8504-3 Preparation of steel substrates before application of paints and related products – Surface preparation methods – Part 3: Hand and power tool cleaning
ISO 1005 Quality management: guidelines for quality plans ISO 14918 Thermal spraying – Approval testing of thermal sprayers ISO 14922-2 Thermal spraying – Quality requirement of thermally sprayed structures ISO 11124-2 Preparation of steel substrates before application of paints and related products –
Specifications for metallic blast cleaning abrasives chilled iron grit ISO 1124-3 Preparation of steel substrates before application of paints and related products –
Specifications for metallic blast cleaning abrasives – High carbon cast steel and grit ISO 11126-3 Preparation of steel substrates before application of paints and related products –
Specifications for metallic blast cleaning abrasives – Copper refinery slag ISO 11126-7 Preparation of steel substrates before application of paints and related products –
Specifications for metallic blast cleaning abrasives – Fued aluminium oxide ISO11126-10 Preparation of steel substrates before application of paints and related products-
specifications for non-metallic blast cleaning abrasive-Almandite Granet ISO 19840 Paint and varnishes – Corrosion protection of steel structures by protective paint systems.
Measurements of, and acceptance criteria for the thickness of dry films on rough surfaces ISO 6272 Paints and varnishes – Falling weight resistance (impact) ISO 3248 Paints and varnishes – Determination of the effect of heat ASTM C 868 Test method for chemical resistance of protective linings ASTM D 4940 Standard test method for conductivity analyses of water soluble contamination of blasting
abrasives ASTM D 4285 Standard test method for indicating oil or water in compressed air ASTM D 5162 Standard practice for discontinuity (holiday) testing of non-conductive protective coating
on metallic substrates ASTM E 96 Test methods for water vapour transmission of materials BS 4800 Paint colours for building purposes BS 3900 F10 Methods of test for paints – Determination of resistance to cathodic disbonding of coatings
for use in marine environments RAL Colour cards