arup may 2020 - lbbd
TRANSCRIPT
Dagenham Dock (BRPS and New Market) - ES Volume II Appendix 4-2 : Cooling Water
System – Stage 1 Design Summary
ARUP
May 2020
City of London Corporation
Barking Power Station
Decommissioning
Cooling water system – Stage 1 design summary for Environmental Statement
Issue | 15 May 2020
This report takes into account the particular
instructions and requirements of our client.
It is not intended for and should not be relied
upon by any third party and no responsibility
is undertaken to any third party.
Job number 268591
Ove Arup & Partners Ltd
13 Fitzroy Street
London
W1T 4BQ
United Kingdom
www.arup.com
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02. COOLING WATER SYSTEM
DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Document verification
Job title Barking Power Station Decommissioning Job number
268591
Document title Cooling water system – Stage 1 design summary
for Environmental Statement
File reference
Document ref
Revision Date Filename Cooling Water System S1 Design Summary Final.docx
Draft 15 May
2020
Description Final issue
Prepared by Checked by Approved by
Name Mark Button Clon Ulrick Simon Delves
Signature
Issue 15 May
2020
Filename Cooling Water System S1 Design Summary Final.docx Description Final issue
Prepared by Checked by Approved by
Name Mark Button Clon Ulrick Simon Delves
Signature
Filename Description
Prepared by Checked by Approved by
Name
Signature
Filename Description
Prepared by Checked by Approved by
Name
Signature
Issue Document verification with document
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Contents Page
Executive summary 1
1 Scope 2
1.1 Extent of assets assessed 2
1.2 Structure of report 2
2 Desk assessment - the assets 4
2.1 Documents reviewed 4
2.2 Understanding of the assets 4
3 Relevant licences and agreements 20
3.1 Documents reviewed 20
Understanding of key issues 20
4 Decommissioning Scope 28
4.1 Key drivers 28
4.2 Potential solutions 29
Decommissioning methodology 29
5 29
5.1 Buildability and safety 29
6 Hanson Aggregates Consultation 30
7 References 30
Appendices
– Documents reviewed
- Licences and deeds extracts
- Consultation with Regulatory Authorities
- Decommissioning Scope and Methodology
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B1
Executive summary
This report summarises the work carried out by Arup as stage 1 of the barking
power station cooling water system decommissioning. This report is intended to
support the Environmental Statement, and to set out the design development that
is pertinent to the Environmental Impact Assessment (EIA).
The proposed scope of decommissioning has been agreed. It is to completely fill
the intake tunnel but only partially fill the outfall tunnel. The outfall structure will
be demolished but the intake structure left in place.
Pre- application consultation has taken place with the river regulators. The
regulators have raised no objections to the proposed works.
The proposed decommissioning methodology has been agreed for the outfall
structure: underwater cutters will be used which avoids the need for a coffer dam.
If possible, the tunnels will be filled without man entry; but it has not yet been
demonstrated whether this is feasible. Man-entry would require proof that the
water inflow was manageable, and that the tunnel is in safe condition. It might
also require secondary access shafts (s). The feasibility of the two alternative
approaches will be tested in stage 2 by means of a pump test and consultation with
contractors.
The above information has been summarised in briefing notes which have been
provided to other consultants in the project team for an EIA addendum, and for
consultation with planning authorities and affected landowners.
We include a decision matrix which summarises key decisions made and
identifies further decisions required for the next steps in stage 2.
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B2
1 Scope
1.1 Extent of assets assessed
Barking power station is to be decommissioned in order to redevelop the site as a
market place or alternatively for other industrial uses
This report considers the following parts of the cooling water system: See Figure
1:
• Intake and outfall tunnels
• Intake
• Outfall
• Combined shaft
It does not include the cooling recirculation system or the cooling water culverts
within the site. These will be dealt with under other packages.
Figure 1: Plan view of the Cooling Water System that is included in the decommissioning
scope of works (Figure from Ref. 1)
1.2 Structure of report
This initial scoping report includes:
• Section 2: Desk assessment of information provided and gap analysis
• Section 3: Licenses and Agreements
• Section 4: Decommissioning Scope
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B3
• Section 5: Decommissioning Methodology
• Section 6: ECI contractor consultation
• Section 7: EIA Screening
• Section 8: Hanson Aggregates Consultation
• Section 9: Summary of Progress
• Section 10: Residual Risks and Opportunities
• Section 11: Next Steps
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B4
2 Desk assessment - the assets
2.1 Documents reviewed
A schedule of documents reviewed is in Appendix B
The existing structures at the Power Station site were also visually inspected at a
site visit on 13th of June 2019.
2.2 Understanding of the assets
2.2.1 Intake Shaft & Structure
See Figure 2 to Figure 5. The intake shaft comprises of 65mm thick, 5m internal
diameter steel tube sections 3m long, bolted together at internal flanges. This was
to form a watertight stand-alone caisson, which during construction would
facilitate TBM removal. The caisson is lined with precast concrete segments, with
the annulus between the concrete segments and steel shaft being filled with mass
concrete.
The intake shaft is topped with a reinforced concrete lozenge shaped headwork
structure. The 94 tonnes lozenge-shaped intake headworks are located below the
existing structure of Jetty No 4. The jetty provides protection for the intake head
structure. The intake headwork has 6mm screens to prevent fish getting into the
intake pipes.
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B5
Figure 2: Intake – plan underneath jetty – [Source: CoLC records]
Jetty No.4
supports
Intake structure
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B6
Figure 3: Intake- section [Source: CoLC records]
Jetty No. 4
Intake
structure
Intake shaft
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B7
Figure 4 structure: Intake- isometric view [Figure from Ref. 2]
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B8
Figure 5: Intake shaft [Source: CoLC records]
2.2.2 Outfall shaft & structure
See Figure 6 to Figure 8. Like the intake shaft, the outfall shaft comprises of
65mm thick, 5m internal diameter steel tube sections 3m long, bolted together at
internal flanges to form a watertight stand-alone caisson. The caisson is lined with
precast concrete segments, with the annulus between the concrete segments and
steel shaft being filled with mass concrete
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B9
At the top of the outfall shaft, a 40 tonnes precast concrete, circular headwork is
positioned.
The outfall structure is located within the Thames river about 600m from the north
bank. It consists of a platform supported by 8 piles, which are located on the
vertices of the octagon. The outfall space frame consists of truss panels. The
outfall structure is surrounded by large floating fenders. Its primary function is to
protect the outfall shaft from accidental collision with ships, to support a platform
that facilitates dewatering and filling of tunnels in the permanent case and to
support a temporary platform during construction.
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B10
Figure 6: Outfall structure- plan [Source: CoLC records]
Figure 7: Outfall structure- section [Source: CoLC records]
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B11
Figure 8: Outfall shaft
2.2.3 Dewatering Caps
Within the intake and outfall headworks, there is a steel dewatering cap, which
consists of steel frame and plate. During station operation, the caps are supported
by the upper deck of the headworks. During tunnel dewatering, the caps are
rotated to allow the support brackets to pass through slots in the headwork upper
deck. The cap is then lowered to form a watertight seal (plug) in the shaft. The cap
details are shown in Figure 9.
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B12
Figure 9: Dewatering cap at intake and outfall
2.2.4 Cooling Water Tunnels
See Figure 10 to Figure 12. The intake and outfall tunnels are constructed of pre-
cast concrete segmental linings of 3.35m internal diameter and 3.71m external
diameter, with a 180mm lining thickness. The intake tunnel is 627m length and
the outfall tunnel 1165m. The tunnel linings comprise six trapezoidal segments
with Ethylene Propylene Diene Monomer (EPDM) gaskets installed around their
edges to provide a waterproofing joint. The tunnel lining segments consist of
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B13
reinforced concrete with conventional steel reinforcement cage and concrete grade
C40/50.
We were not able to trace any as built cross section drawings of the tunnels, so the
above description relies on secondary reports.
Figure 10: Plan and long section of tunnels
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B14
Figure 11: Tunnel adjacent to pumping station
Figure 12: Image inside tunnel under construction [Image from Ref. 2]
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B15
2.2.5 Combined Intake/ Outfall Shaft
See Figure 13 to Figure 15. The combined shaft is located on the main station site
and is used to house two 3m internal diameter pipes, which connect the cooling
water tunnels to the pump station. The initial shaft lining was made as a caisson
with precast, reinforced concrete segment rings but due to failure of the temporary
works, it was redesigned as an in situ concrete diaphragm wall shaft, with an
approximate ID of 8m. Steel piles are installed in the shaft and the void between
shaft and pipes is filled with lightweight, foamed concrete.
Figure 13: Combined shaft at Pump Station – plan at base of pump station
[Source: CoLC records]
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B16
Figure 14: Combined shaft at pump station section through shaft [Source: CoLC records]
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B17
Figure 15: Combined shaft- elevation [Source: CoLC records]
2.2.6 Combined Pump Station & Seal Pit
The pump station includes a circular reinforced concrete wall with internal walls
and other features. See Figure 16 and Figure 17. The circular diaphragm caisson
excavation support consists of a 1.02m thick reinforced concrete wall. The
internal diameter of the caisson wall is 44.3m. It is formed of 24 interlocking
panels. The general toe level of the wall is at -18m OD but this extends down to -
21m OD adjacent to the combined shaft. On the inside of the diaphragm wall, a
500mm thickness inner lining wall has been placed. The inner lining wall is fixed
to the diaphragm wall with drill-in anchors. Most of the internal elements (walls,
slabs, beams and plant support or housings) are in-situ concrete. Some elements
have been constructed with pre-cast concrete and structural steelwork.
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B18
Figure 16: Pump station – plan [Source: CoLC records]
Figure 17: Pump station- section [Source: CoLC records]
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B19
2.2.7 Condition of the Assets
2.2.7.1 Intake/Outfall Tunnels
Two condition surveys of the water tunnels were conducted back in 2000 and
2010, in accordance with the ten-year inspection period for the cooling water
system, as identified by Balfour Beatty. The year 2000 survey inspected the first
100m of the outfall tunnel and the chainages between 450m-600m in the intake
tunnel. The survey revealed evidence of marine growth in the tunnels and layers
of silt with a thickness of 10mm. Possible deflections in the tunnel lining could
not be picked up by the survey. The 2010 survey also identified marine growth
and silt in the tunnels. Holes in the tunnel lining were also identified, which could
indicate a deterioration in the tunnel condition. After the cessation of the pump
station operation back in 2014, a dewatering cap was installed on the outfall shaft,
sealing the tunnels from the river and isolating the water within. Dewatering tests
showed that the tunnels get recharged after the water is fully pumped out.
Inspection of the cap revealed no obvious signs of damage that could justify water
ingress through the cap. Therefore, it is likely that water ingress could occur
through the tunnel lining itself or through the outfall shaft.
2.2.7.2 Above Ground Structures
A walk-over survey dated back in 2015 by Atkins found that the above ground
assets are in generally good condition, with no obvious signs of structural
deterioration. The key areas of consideration, taking account of decommissioning
options, are:
• Outfall shaft marine structure: the eight concrete filled steel piles,
which form part of the outfall structure will not be able to be removed in a
single lift due to their large size and weight. Therefore, they will need to
be cut into pieces and then removed
• Intake Shaft & Jetty No 4: the intake shaft is located under the Jetty No
4, which is owned by Hanson Aggregates. The jetty can be accessed by a
bridge from the adjacent Hanson Aggregates site. This jetty is a Grade II
listed structure and load restrictions of 3tonnes and 10tonnes have been
imposed on the access bridge and jetty respectively. This might have
implications on the decommissioning works on the intake shaft.
• Cooling Water Pump Station: there is no direct ground level access to
the combined intake/outfall shaft in the cooling water pump station.
Modification to the existing water retention tanks may be required if
decommissioning works are to be serviced from this area.
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B20
3 Relevant licences and agreements
3.1 Documents reviewed
The consents and licenses that have been reviewed are presented in the Appendix
A.
Understanding of key issues
There are at least 14 stakeholders that will require an agreement or license for
works to the cooling water system. There are at least 15 existing licenses to be re-
negotiated.
There are still some gaps in information: 1) Planning Consents (?), 2) 4 land
owners’ Deeds of Grant 3) Water discharge license 4) plans shown land
ownership of PLA, Crown Estates and National Power Plc
There appears to be a conflict of interpretation between PLA and Crown Estates
regarding the decommissioning of the river works- PLA wrote informally “Works
that are held on a RWL need to be removed in their entirety otherwise any works
that remain need to be retained on a license-any of the tunnels/shafts/piles
extending over MHW and are not removed will need to be retained on a River
works license” They also indicated informally that demolition to 1m below river
bed level may be acceptable. Conversely, Crown Estates reportedly want the
outfall structure and tunnel underneath their property to be removed.
The deeds of grant of 6 land Owners mention “safe” or “harmless” regarding the
state of tunnels after cease of operation of the Power Station- This poses a risk of
interpretation: “In the event that the power station shall cease to be operational
for a continuous period of 4 years at the end of such 4 year period to render the
Authorised Tunnel harmless in accordance with the then current safety
standards”
“In the event the Power Station ceases to operate for a continuous period of 4
years, at the end of such period, BPL shall clean out the Authorised Tunnel Cap
and fill the same with materials which will Render the Authorised Tunnel safe,
such materials to accord with the then current safety standards”
Jetty No 4 is a listed structure. Listed Building Consent will be required for any
significant works to the intake structure
Key Opportunities
PLA and EA both have indicated informally that it may be acceptable to them to
grout up the shafts (only) and not the tunnels
Key Risks to programme
The volume of agreements/licences suggests a high programme risk.
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B21
A dredging licence will may be required for removal of intake or outfall structure.
This would add considerably to the consents process duration
The duration of There is risk of anan EIA
3.1.1 PLA
PLA are landowners of north bank and are responsible for navigation on the river
Existing Licences/Agreements:
There is an existing licence combined with The Crown Estates (see extracts on
Error! Reference source not found.). A river works licence for any changes and
for any residual assets in the river will be required. Important information relevant
to the river works license is listed below:
• River work license with PLA and the Crown estate to construct and retain
two tunnels/intakes/outfalls is for 30 years (starting from 1992)-It expires
in 2022.
• River Works License is owned only by BPL and cannot be assigned to a
3rd party
• On expiry or sooner termination of the license, BPL must remove the
River Works and make good the airspace above and the river bed to the
reasonable satisfaction of PLA- If BPL does not comply, PLA will carry
out the necessary works and charge BLP
• Hogen Lovells note that in the deed there is no option to make safe or
leave the River Works in Situ.
Consultation:
In 2015 Atkins consulted with the PLA on decommissioning the cooling water
system. Arup and CoLC re- consulted with PLA on 5th of August 2019. See
Appendix C for the PLA Meeting of Minutes.
Key Issues:
• Structures are to be cut down to approximately one metre below existing
river bed level; however, the exact depth needs to be confirmed by the
PLA consents manager, depending on the riverbed condition.
• PLA are comfortable in principle to retain the existing intake structure
• A River Works License will be required for retained structures under the
river
• A new licence would still be a combined PLA and Crown Estates licence.
PLA will take the lead, as PLA own more of the affected land in the tidal
Thames. The new licence will cover the financial aspects for both PLA
and Crown Estates.
• In addition, a Marine Licence will be required from the MMO
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B22
• The PLA/MMO Concordat is under renewal. PLA will take the lead, but
CoLC/Arup should consult with MMO in parallel. PLA are happy to
support the process. Arup should be consistent and apply the same
information to PLA and MMO
• Although it is a matter for the PLA’s Estates Team (and the Crown Estate)
it is likely that the existing annual licence fee would be reduced to reflect
less infrastructure after decommissioning and non-usage of the
infrastructure.
• PLA have 3 months to reach a decision from the date of receipt of the
applications for a licence, otherwise application is deemed refused. There
is a potential for delay in finding agreement from all parties
• Works on the Intake Shaft must be organised in a way so as to protect the
Jetty No.4 structure, which is listed as a safeguarded wharf by PLA
• Outfall shaft must be removed to at least 1m below construction river bed
level, which is approximately 2.5-3m below current river bed level
• Works that are held on a RWL need to be removed in their entirety
otherwise any works that remain need to be retained on a license-any of
the tunnels/shafts/piles extending over MHW and are not removed will
need to be retained on a River works license. (Appendix J-correspondence
Atkins-PLA)
• PLA recognise the benefits from complete removal of the outfall structure
but would not require its removal
• Dredging- would need a separate approval from PLA
• Scour protection- this would need to be recorded for navigation purposes if
it remains on the river bed
• PLA do not have any special requirements regarding the infill material of
the tunnels and shafts.
3.1.2 The Crown Estates –
The Crown Estates Commissioners are landowners of south bank of the river (See
Figure 18)
Existing licences/Agreements.
There is a joint River Works License with PLA (see Section 3.1.1 above). A new
licence will be required for the residual assets retained on their land
Consultation:
CoLC reported verbally on previous communication between the City of London
and the Crown Estate Commissioners
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B23
Key Issues:
• As reported by CoLC, the Commissioners are expecting CoLC to fully
remove all the assets in The Crown Estates land, including removing the
shaft to full depth and the outfall tunnel. However, this will be impractical
to achieve.
Figure 18: Land Ownership Plan – Yellow: Crown Estates & Red: Unregistered Land
claimed by PLA (Source: received by PLA on 05/08/2019)
Deloitte, which is the CoLC planning consultant is responsible for the
consultation with The Crown Estate Commissioners. At the moment of writing
this report, we are not aware of the status of this consultation.
3.1.3 Environment Agency
The Environment Agency (EA) is responsible for all works in river, intake and
extraction and contamination risks everywhere (river and on land). The EA was
formerly the National River Authority (NRA).
Existing Licenses/Agreements:
Existing flood defence licences with the NRA, which is now the EA, are listed
below:
• Abstraction licence with NRA (original in 1992 and later in 2001) we
understand that this also includes licence to discharge.
• Consent to construct an outfall marine structure at River Thames (Consent
to Works)
• Consent to construct an intake structure at River Thames
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B24
• Consent to construct an Outfall Tunnel under the flood defence river wall
• Consent to construct an Intake Tunnel under the flood defence river wall
• Environmental Permit for prevention of Pollution (EA)
(non-relevant: Existing Consent to discharge Trade Effluent into the sewers to
the Dagenham Breach with Thames Water Utilities)
Consultation:
Atkins consulted informally with the EA in 2015 to discuss decommissioning
options. Arup and CoLC consulted with EA on 12th September 2019, see EA
Minutes of Meeting and briefing note in Appendix C
Key Issues:
• The decommissioning proposals are considered low risk for EA statutory
comments. Flood risk level is not expected to be an issue
• The EA indicated no issues of principle to the outline proposals in Atkins
assessment.
• The EA is interested in knowing the construction methodology that will be
followed for the outfall structure demolition (underwater operations,
cofferdam)
• The EA may be concerned about groundwater or river water
contamination from any grouting operation. The fill material of the tunnels
and shafts should ensure that no water migration occurs between the river
and the chalk aquifer
• The EA would not object to small rock scour protection being left at the
river bed, if it is small rocks. However, if there is a gabion or other form of
mattress, EA would need to investigate this matter further
• The EA referred to the local planning authorities for EIA consultation
• If a Marine License is obtained, there is no requirement for EA flood
activity environmental permit for works below MHWS, as the MMO
Marine License addresses the EA requirements
• Environmental Permit will be required for the landward works that are
located within 16m distance in plan from the flood defences.
• An Environmental Permit might be required if new discharges or
connections through the flood defences are constructed.
• An Environmental Permit will be needed for any decommissioning option
The EA stated that a licensing application might be required if:
• temporary works structures are required over the river walls
City of London Corporation Barking Power Station DecommissioningCooling water system – Stage 1 design summary for Environmental Statement
| Issue | 15 May 2020
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\268000\268591-00 BARKING POWER STATION REMEDIATION\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\02.
COOLING WATER SYSTEM DECOMMISSIONING\EIA APPENDIX REPORT\COOLING WATER SYSTEM S1 DESIGN SUMMARY FINAL.DOCX
Page B25
• for river works access for transporting material (e.g. conveyor belts, jetty
use)
3.1.4 Marine Management Organisation (MMO)
The MMO is responsible for granting a Marine Licence for any works below tidal
waters.
Existing Licenses/Agreements:
There are no existing licenses/agreements; the MMO didn’t exist back in 1992.
Consultation: Arup and CoLC consulted with the MMO on 10th September
2019.- see MMO Minutes of Meeting and briefing note in Appendix C.
Key Issues:
• Marine Licence is required for any works below the MHWS (mean high
water springs) under the Marine and Coastal Access Act 2009
• Any marine license application must include a detailed methodology of the
demolition/removal of structures and any mitigations proposed. MMO
expressed concern about environmental impacts of the construction works
(migratory fish, birds, designated areas nearby, navigational issues,
pollution on Thames)
• Potential requirement for an EIA under the Marine and Coastal Act 2009
• Timescales for MMO licences are very uncertain. The timescale will
extend substantially if a dredging licence or EIA is required MMO
MMO said a dredging licence might be required if:
• scour protection is removed. MMO clarified that this might not
specifically be a marine license for dredging activities, but it would be a
licensable marine activity under MCCA, 2009 (e.g. Removal activities)
• It is impossible to extract the outfall structure piles from the river bed and
excavation is required-This depends on the volumes of excavated
material. MMO clarified that there are certain exemptions that apply for
low dredge volumes, but these have specific criteria
3.1.5 Local Planning Authorities
Barking and Dagenham is the local planning authority for north bank up to mid-
river, where the intake structure is located.
The outfall is in Bexley borough council jurisdiction (see