FAMILIARIZATIONASME SECTION VIII DIVISION 1
April 2013By. Mufti Fuady
PART U : INTRUDUCTION
Sub Section A : General Requirement (UG) Sub Section B : Requirement Pertaining to
Methods of Fabrication of Pressure Vessel UW : Req. for P/V fab. by Welding UF : Req. for P/V fab. by forging UB : Req. for P/V fab. by Brazing
Subsection C : Requirements pertaining to class materials (UCS)
Mft
GENERAL REQUIREMENT
UG – 1 : scope
Establish General Requirements
Mft
MATERIAL UG 4 : General UG 5 – UG 9
Section VIII requires material test report for plate material only
All other product form are acceptable on the basis of marking as required by the applicable specification
UG 10 Requires Chemical & mechanical properties
be obtained for each material & compare to an approved material
Mft
MATERIAL UG 11 : Pre-fabrication or Pre
performed pressure parts UG 12 : Bolts & Studs UG 13 : Nut & Washer UG 14 : Rod & Bar UG 15 : Product Specification
Mft
DESIGN UG 16 : General
Minimum thickness permitted Pipe under tolerance
UG 17 : Method of Fabrication in Combination
UG 18 : Material in Combination UG 19 : Special Construction UG 20 : Min. Temp. & Impact Test
Requirements UG 21 : Design Pressure
Mft
DESIGN UG 22 : Loading UG 23 : Max. Allowable Stress Values UG 24 : Casting UG 25 : Corrosion UG 26 – UG 34 : Design Pressure vessel UG 35 : Other type of Closure UG 36 – UG 45 : Design concerning
reinforcement for opening UG 46 : Inspection for Opening UG 47 – UG 55 : Design for Braced, Stay
bolts, Ligaments Mft
FABRICATION UG 76 : Cutting and Milling of plate UG 77 : Material Identification UG 78 : Repair on defect material UG 79 : Farming Shell section or Head UG 80 : Tolerances for Cylinder out of
Roundness UG 81 : Tolerances for formed Head UG 82 : Attachment to Pressure Vessel UG 83 : Screw stay requirements
Mft
FABRICATION
UG 84 : Charpy impact Test UG 85 : Heat Treatment
Mft
INSPECTION & TEST UG 90 : General UG 91 : Inspector UG 92 : Access for Inspector UG 93 : Inspection of material UG 94 : marking on material UG 95 : Examination surface during
fabrication UG 96 : Dimensional check UG 97 : Inspection during fabrication
Mft
INSPECTION & TEST UG 98 : Maximum Allowable Working
Pressure UG 99 : Standard Hydrostatic test UG 100 : Pneumatic test UG 101 : Proof Test UG 102 : Test Gauge UG 103 : Non Destructive Test
Mft
MARKING & REPORT UG 115 : general UG 116 : Required Marking (RT/W/HT) UG 117 : Certification of authorization
and code symbol stamps UG 118 : Methods & marking UG 119 : Name Plate UG 120 : Data Reports UG 126 – UG 136 : Pressure Relief
Device UG 137 : Rupture Disk Devices
Mft
REQUIREMENT FOR VESSEL FABRICATED BY WELDING
UW 1 : Scope UW 2 : Service Restriction UW 3 : Welded Joint Category UW 5 : Material UW 8 – UW 9 : Design UW 10 : Post-weld Heat Treatment UW 11 : Radiographic & Ultrasonic
Examination UW 12 : Joint Efficiency
Mft
REQUIREMENT FOR VESSEL FABRICATED BY WELDING
UW 13 : Attachment detail UW 14 : Opening adjacent to Weld UW 15 – UW 20 : Design
Mft
FABRICATION UW 26 – UW 30 : Welding requirement
as per ASME Sec. IX UW 31 : Cutting, Fitting & Alignment UW 32 : Cleaning of Surface to be
welded UW 33 : Alignment tolerance UW 34 : Spin Holes UW 35 : Finished longitudinal &
circumferential joints UW 36 : Fillet Welds
Mft
FABRICATION UW 37 : Miscellaneous welding
requirement UW 38 : Repair of Weld defect UW 39 : Peening UW 40 : PWHT Procedure UW 41 : Sectioning welded joint UW 42 : Surface weld metal build up
Mft
INSPECTION & TEST UW 46 – UW 49 : Verification of
qualification WPS and Welder as per Section IX requirement
UW 50 : NDT on pneumatically tested vessel
UW 51 : radiographic & radioscopic examination for Welded joints
UW 52 : Spot examination for welded joint
UW 53 : Ultrasonic Test for Welded Joints
Mft
MARKING & REPORTS
UW 60 : General
Mft
PRESSURE RELIEF DEVICES
UW 65 : General
Mft
PART UCSRequirement for Pressure Vessel constructed of Carbon & Low Alloy Steels
UCS 1 : Scope
Mft
PART UCS - MATERIAL
UCS 5 : General UCS 6 - UCS 9 : Steel Material UCS 10 : Bolts Material UCS 11 : Nuts & Washers UCS 12 : Bars & Shapes
Mft
PART UCS - DESIGN UCS 16 : General UCS 19 : Welded Joint UCS 23 : Max. Allowable Stress Values UCS 27 : Shell made from pipe UCS 28 : Thickness of Shell under Ext. Press UCS 29 : Stiff. Rings for Shell under Ext. Press UCS 30 : Attach. of Stiffening Rings to Shell UCS 33 : Formed Heads, Press on Convex Side UCS 56 : Requirement for PWHT UCS 57 : Radiographic Examination
Mft
PART UCS – LOW TEMP. OPERATION
UCS 65 : Scope UCS 66 : Material UCS 67 : Impact testing for WPS UCS 68 : Design
Mft
PART UCS – FABRICATION
UCS 75 : General UCS 79 : Forming shell section & Head UCS 85 : Heat Treatment of Test
Specimen
Mft
PART UCS – INSPECTION & TEST
UCS 90 : General
Mft
PART UCS – MARKING & REPORTS
UCS 115 : General
Mft
PART UCS – PRESSURE RELIEF DEVICES
UCS 125 : General