Page 1: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

ATHABASCA UNIVERSITY

LEAN SOFTWARE DEVELOPMENT AND INFORMATION TECHNOLOGY

THE TOYOTA WAY

BY

PAUL MAH

A Master’s Essay submitted in partial fulfillment

Of the requirements for the degree of

MASTER OF SCIENCE in INFORMATION SYSTEMS

Athabasca, Alberta

February, 2008

© Paul Mah, 2008

Page 2: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

i

DEDICATION

To my loving wife Cindy, Mom who was always there for me, and Dad who

taught me to always do my best.

Page 3: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

ii

ABSTRACT

The software industry is plagued with many problems, such as high cost,

low quality, project failures, and missed deadlines. To overcome these

shortcomings, Lean as pioneered by Toyota is proposed as the way to improve

upon software development and Information Technology by making them Lean.

This becomes even more important as organizations adopt Lean, expects

Information Technology to adopt Lean.

As organizations becomes Lean, there exists new opportunities for

Information Technology to develop new software for these Lean organizations,

and this will be examined as well.

Finally a literature search is conducted to find the current state of using

Lean within the software industry to see what kind of impact it has on solving

software industry problems as a gauge to the success of this proposal.

Page 4: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

iii

ACKNOWLEDGEMENTS

I would like to thank all the faculty and staff in the Master of Science in

Information Systems program at Athabasca University’s School of Computing

and Information Systems, especially my supervisor Dr. Qing Tan, reviewer Dr.

Richard Johnston, and chair Dr. Fuhua (Oscar) Lin.

I would also like to thank Mary Poppendieck who has opened my eyes to Lean

Software Development, when she gave a speech at the Calgary Agile Method

User Group meeting, and for Taiichi Ohno, the person who created the Toyota

Production System, and thus the idea of Lean.

Finally I would like to thank my wife Cindy who supported me in my endeavor, my

Mom who is always so caring, and my Dad who is my mentor.

Page 5: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

iv

TABLE OF CONTENTS

DEDICATION.........................................................................................................i

ABSTRACT........................................................................................................... ii

ACKNOWLEDGEMENTS.................................................................................... iii

TABLE OF CONTENTS....................................................................................... iv

LIST OF FIGURES .............................................................................................. ix

CHAPTER I - INTRODUCTION............................................................................1

Statement of Purpose........................................................................................1

Research Problem or Question.........................................................................2

Assumptions of the Master’s Essay...................................................................2

Significance.......................................................................................................3

Limitations .........................................................................................................3

Definition of Terms............................................................................................4

Lean...............................................................................................................4

Kaizen............................................................................................................4

Delimitations......................................................................................................5

Organization of Master’s Essay.........................................................................5

Disclaimer .........................................................................................................6

CHAPTER II – TOYOTA AND LEAN ....................................................................7

Toyota, The Birth of Lean..................................................................................7

CHAPTER III – THE TOYOTA WAY...................................................................11

Long Term Philosophy ....................................................................................11

Establish Customer Defined Value..................................................................12

Page 6: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

v

Create Continuous Process Flow.................................................................... 14

Overproduction ............................................................................................14

Waiting.........................................................................................................15

Unnecessary Transport or Conveyance ......................................................15

Over Processing..........................................................................................15

Excess Inventory .........................................................................................15

Unnecessary Movement ..............................................................................15

Defects ........................................................................................................15

Unused Employee Creativity........................................................................15

Use Pull Systems ............................................................................................16

Heijunka ..........................................................................................................16

Muda............................................................................................................17

Muri..............................................................................................................17

Mura ............................................................................................................17

Value Stream Mapping....................................................................................18

Culture of Quality............................................................................................. 20

Thoroughly Explore Alternative Solutions........................................................21

Standardized Task ..........................................................................................23

Use Visual Controls to Make Problems Visible................................................24

Use Reliable Technology ................................................................................24

Grow Leaders..................................................................................................25

Develop Exception People and Teams ...........................................................27

Respect and Challenge Partners and Suppliers..............................................29

Page 7: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

vi

Genchi Genbutsu ............................................................................................31

Decisions by Consensus .................................................................................32

Become a Learning Organization.................................................................... 32

CHAPTER IV – APPLICATION OF LEAN TO SOFTWARE DEVELOPMENT

AND INFORMATION TECHNOLOGY ................................................................ 35

Long Term Philosophy ....................................................................................36

Establish Customer Defined Value..................................................................37

Create Continuous Process Flow.................................................................... 38

Overproduction ............................................................................................38

Waiting.........................................................................................................39

Unnecessary Transport or Conveyance ......................................................39

Over Processing..........................................................................................39

Excess Inventory .........................................................................................40

Unnecessary Movement ..............................................................................41

Defects ........................................................................................................41

Unused Employee Creativity........................................................................42

Use Pull Systems ............................................................................................42

Heijunka ..........................................................................................................43

Value Stream Mapping....................................................................................44

Culture of Quality............................................................................................. 45

Thoroughly Explore Alternative Solutions........................................................47

Standardized Task ..........................................................................................48

Use Visual Controls to Make Problems Visible................................................49

Page 8: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

vii

Use Reliable Technology ................................................................................51

Grow Leaders..................................................................................................52

Develop Exception People and Teams ...........................................................53

Respect and Challenge Partners and Suppliers..............................................56

Genchi Genbutsu ............................................................................................56

Decisions by Consensus .................................................................................57

Become a Learning Organization.................................................................... 57

Lean Scrum.....................................................................................................58

CHAPTER V - LEAN OPPORTUNITIES FOR INFORMATION TECHNOLOGY 60

Kanban - Information Flow ..............................................................................65

Global Production Centre................................................................................66

Andon..............................................................................................................67

Check List ....................................................................................................... 68

Lean and Simulation........................................................................................68

Manufacturing Agent-Based Emulation System ..............................................69

CHAPTER VI – LITERATURE SEARCH ON APPLYING LEAN TO SOFTWARE

DEVELOPMENT AND INFORMATION TECHNOLOGY .................................... 70

Innovation in Software Development Process By Introducing Toyota

Production System..........................................................................................70

Learning to Love Lean IT ................................................................................72

Lean Software For The Lean Aircraft ..............................................................73

Introducing Lean Principles with Agile Practices at a Fortune 500 Company..74

Scrum and CMMI Level 5: The Magic Potion for Code Warriors.....................76

Page 9: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

viii

Summary of Literature Search on Applying Lean to Software Development and

Information Technology...................................................................................77

CHAPTER VII - CONCLUSIONS AND RECOMMENDATIONS .........................78

Conclusions.....................................................................................................78

Recommendations ..........................................................................................79

Suggestions for Further Research...................................................................79

REFERENCES ...................................................................................................80

APPENDIX A ~ GLOSSARY............................................................................... 88

Page 10: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

ix

LIST OF FIGURES

Figure 1 Value Stream Mapping .........................................................................18

Page 11: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

1

CHAPTER I

INTRODUCTION

Statement of Purpose

The software industry is plagued with many problems such as project

failures, missed deadlines, high costs, and poor quality with no real solution to

resolve this in sight (The Standish Group, 1995). One way to solve these

problems is to borrow from the concept of Lean from the Toyota Motor

Corporation.

Software development has long borrowed from other industries. For

example, the idea of software engineering came from the engineering discipline.

Despite engineering has been around for quite a while, there too has been

failures in engineering, so one should not borrow from the engineering discipline

verbatim. Instead, one has to look at where engineering is practiced successfully,

and borrow from that. One such successful organization is Toyota where it has

up to 80% valued added engineering activity to design, and manufacture an

automobile (Kennedy, 2003). Toyota today, is poised to be the number one

automobile manufacturer (CBC News, 2008). Toyota did it the Toyota Way.

When the Toyota concepts were introduced to North America, and Europe, it was

referred to as Lean, because Toyota were able to design, and produce motor

vehicles with less resources, more quality, and faster than any other motor

vehicle companies (Womack, Jones & Roos, 1990). It is the principles of Toyota

Page 12: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

2

which should be brought to the software industry to make software development

and Information Technology Lean, and thus become more successful.

Research Problem or Question

For this Master’s Essay, a literature search is conducted on the principles

of Toyota and the concepts of Lean as they are the cornerstone to Toyota’s

success.

To make the software industry more successful, the Lean Toyota

principles are then applied to software development and Information Technology

to come up with a new Lean way of software development and Information

Technology.

With some organizations becoming Lean, an examination is made of what

opportunities arise for Information Technology, as organizations adopt Lean.

A literature search is conducted to see what organizations have done

using Lean in software development and Information Technology as an indicator

of the current state of adopting Lean in the software industry, and whether the

proposal given in this Master’s Essay would be successful.

Assumptions of the Master’s Essay

It is assumed the reader knows about the problems within software

development and Information Technology, and they will not be discussed here

focusing instead on how Lean, the Toyota Way, can improve upon software

development and Information Technology.

Page 13: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

3

Significance

The significance of this topic is many organizations have been adopting

Lean in order to survive in the competitive world. Organizations adopting Lean

has improved immensely in reducing waste, becoming more profitable, gaining

market shares, and be a leader within their own industry (Womack & Jones,

2003). The organization which pioneered the concepts of Lean even before it

became known as Lean is Toyota, and it is important the software industry learn

from Toyota’s Lean principles, and use it as a way to become Lean and

successful. This becomes even more important when organizations adopting

Lean expects software development and Information Technology to also adopt

Lean. When this happens opportunities for Information Technology arises as well

(Bell, 2006).

Finally it is important to find the current state of adopting Lean in the

software industry as an indicator of success in applying Lean to software

development and Information Technology.

Limitations

Although Toyota has been around for many years, and the concept of

Lean has been introduced into North America, its impact upon software

development and Information Technology is pretty much an unexplored area with

very little literature or research done in this area with the exception of Mary

Poppendieck (Poppendieck & Poppendieck, 2003, 2007). Lean Software

Development is categorized as part of Agile Software Development. While Lean

is Agile, Agile is not Lean, but Agility may evolve to be Lean.

Page 14: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

4

Definition of Terms

Lean is a term coined by John Krafcik, a researcher for the International

Motor Vehicle Program. Lean because in comparison to companies doing mass

production, it uses less of everything, including less human effort, less

manufacturing space, less inventory, less investments on tools, and less

engineering hours with less time to develop a product. In addition, there are

fewer defects with a greater variety of quality products. The company which best

epitomize Lean is the Toyota Motor Corporation (Womak, James, & Roos, 1990).

In this paper, Lean and the principles of the Toyota Way are considered to

be one and the same.

Kaizen is the Japanese word for continuous improvement. It is derived

from two Japanese roots, kai meaning to take apart, and zen meaning to make

good. It is the art of reducing a system to its components, understanding how the

components work and interact with one another, and put it back together in a

better way (Bell, 2006). The philosophy of kaizen believes people’s life deserves

to be improved. Kaizen recognizes nothing is prefect, and there is always room

for improvement. As a result, one must always strive for perfection by improving

continuously (Imai, 1986).

This also implies once an improvement is thought of, one must do and not

merely talk about it, as these improvements will realize a benefit right away and

into the future (Ohno, 1988).

Page 15: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

5

Delimitations

The concept of Lean easily covers several books, and it would be

unrealistic to fully talk about Lean here. For the purpose of this Master’s Essay

only the relevant points of Lean are highlighted, and for those who want to

pursue Lean further can refer to the References.

Organization of Master’s Essay

The Master’s Essay is organized into several sections categorized by the

various chapters. The separate sections are as follows:

Chapter I – Introduction, introduces the topic of Lean, and why it is

important to software development and Information Technology.

Chapter II – Toyota and Lean, gives a background of Toyota and Lean.

Chapter III – The Toyota Way, gives a description of the principles of the

Toyota Way.

Chapter IV – Application of Lean to Software Development and

Information Technology, describes how the principles of the Toyota Way can be

applied to software development and Information Technology to make it Lean.

Chapter V – Lean Opportunities for Information Technology, talks about

opportunities for Information Technology when an organization decides to

become Lean. This is an exploration of what these new opportunities would be.

Chapter VI – Literature Search on Applying Lean to Software

Development and Information Technology, is research on who may have used

Lean in Software Development, and what the outcome is, as a gage to the

Page 16: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

6

success of the approach proposed in this Master’s Essay. This will be a literature

search on the World Wide Web.

Chapter VII – Conclusion, concludes the Master’s essay, with

recommendations on what should be done, and what further future research can

be done in this topic area.

References, contains a list of references used to write this Master’s Essay.

Appendix ~ Glossary, contains many of the non-English terminology used

in Lean. Many of these terminology has its root in Japanese, and it would be

easier for the reader to refer to the glossary if they come across a Lean

Japanese terminology they did not understand rather than flipping back through

the Master’s Essay to find the definition.

Disclaimer

I do not, and have not ever worked for Toyota. I do not even own a Toyota

motor vehicle. My eyes opened up to Toyota when one day I noticed most of the

cars I see driving around are Toyotas, and that relatives, friends, and neighbors

of mine all own Toyotas! As someone who is a career software developer, I am

always on the lookout on how to do software development better, and decided to

pursue the Toyota Way as a way to kaizen software development and

Information Technology.

Page 17: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

7

CHAPTER II

TOYOTA AND LEAN

Toyota, The Birth of Lean

In the early days of automobile production, automobiles were made by

craft production. The workforce consists of highly trained skilled workers who

have to undergo an apprenticeship program to become a craftsman. The tools

used were general purpose machines, with no standard gauges, and thus each

part has to be custom fitted. Each automobile was custom made one at time with

a very low production volume, and high production cost. There could be many

companies competing against each other to make automobiles, each taking an

order from a customer, and custom building it. What this means is each

automobile is actually a working prototype where there is no consistency, and

reliability, due to lack of systemic testing. Since these companies also work

independently, there was no money to develop new technologies (Womak,

James, & Roos, 1990).

Henry Ford came up with an innovative way to reduce cost, and increase

product quality which he called mass production. The key to mass production is

the interchangeability of parts, and the simplicity of attaching parts which gave

him a huge advantage over craft production. Next Ford, created the moving

continuous assembly line which made the assembly of automobiles much easier.

In addition, the worker was interchangeable, as the worker does not need much

skill to assemble a vehicle. Each worker was only required to do a simple task in

Page 18: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

8

their part of the assembly. Someone has to think of how to put the parts together,

and what the assembler should so, and this created the new profession of an

industrial engineer. A production engineer was required to figure out how to

move the product along as it is assembled. There are other people for cleanup,

maintaining the machines, and finally quality professional which acted like the

craftsmen who would fix defects in the vehicles after they were manufactured.

Mass production soon became the dominant way of manufacturing (Womak,

James, & Roos, 1990).

The story of Toyota begins with Sakichi Toyoda during the 1800s. To

prevent any confusion of the reader thinking there is a spelling mistake, Toyoda

is Toyota’s founding family name meaning “abundant rice field” in Japanese. For

marketing considerations, the company name was later changed to Toyota which

has no meaning in Japanese (Womak, James, & Roos, 1990).

Sakichi Toyoda was a tinker, and inventor. A lot of what he learnt, he

learnt himself by observing things first hand. This is the start of Genchi

Genbutsu, go and see. He grew up during a time when the then Japanese

government wanted to encourage cottage industries throughout Japan, and one

of those industries was textile. Sakichi Toyoda having learnt carpentry from his

father designed, and built a manual loom cheaper than anyone else, but the

looming industry was still very hard work, so he designed, and built an automatic

loom. What was so unique about the automated loom he created was that it has

a special device which can detect when a thread is broken, and automatically

stops the machine. This invention will eventually become one of the two pillars of

Page 19: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

9

the Toyota Production System called jidoka which is automation with a human

touch (Womak, James, & Roos, 1990).

Sakichi Toyoda knew the world was changing and thought the power loom

was yesterday’s technology while the automobile will be tomorrow’s technology.

He instructed his son Kiichiro Toyoda to sell the patent for the automatic loom,

and start an automobile company; he wanted his son to have his own opportunity

in the world (Womak, James, & Roos, 1990).

Kiichiro Toyoda is the founder of Toyota Motor Company. He inherited his

father’s learning and creative ability, and added the second pillar of the Toyota

Production System, Just-In-Time (Womak, James, & Roos, 1990).

In 1945, when Japan lost the war, it was a new beginning for Toyota.

Kiichiro Toyoda wanted to catch up to the Americans in “three” years. He brought

in Taiichi Ohno as Chief Production Engineer to help build Toyota. Ohno had

heard the Germans were three times more productive than the Japanese, and

the Americans were three times more productive than the Germans, concluding

the Americans were nine times more productive than the Japanese. Ohno felt the

Japanese has too much waste in their productivity, and thus the start of the idea

for the Toyota Production System. Ultimately Ohno created the now famous

Toyota Production System (Ohno, 1988).

Lean production combines the advantages of both craft production and

mass production, while avoiding the high cost of craft production and avoiding

the rigidity of mass production. In order to achieve this, Lean production employs

multi skilled workers at all levels of the organization, and using highly flexible

Page 20: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

10

machines to produce a greater number of products with greater variety for

consumers (Womak, James, & Roos, 1990).

In the 1973 oil crisis, when many companies suffered, Toyota did not

suffer as much, and recovered faster. This put Toyota in the spotlight (Ohno,

1988). Toyota continued to rise, and later in 1990, Womak, Jones, and Roos

wrote about Toyota in their book “The Machine that Changed the World”,

introducing the idea of Lean, and Toyota’s Leanness to North America. In their

revised edition in 2004, much of their predictions of Toyota’s greatness have

become true (Liker, 2004).

According to Ohno, “All we are doing is looking at the time line from the

moment the customer give us an order to the point we collect the cash. And we

are reducing that time line by removing the non-value-added waste.” (Ohno,

1988, p ix).

This is why we have to borrow from Toyota and Lean to improve the

software industry!

Page 21: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

11

CHAPTER III

THE TOYOTA WAY

The Toyota Way is Toyota being a true learning company. Toyota

challenges its people to experiment, and learn by using initiative and creativity.

They challenge their workers to grow by constantly solving problems. The key to

the Toyota Production System is Toyota’s commitment to continuously invest in

its people, and foster a culture of kaizen. Their workers are given directives to

improve a process, and satisfy customers. At Toyota, it is not simply about

finding the best people which makes the company good. It is about finding

ordinary hard working people with a passion for automobile, which Toyota then

takes, and trains these people to make them a part of the Toyota culture (Liker,

2004).

Although the Toyota Production System is what Toyota is most famous

for, it is really the Toyota Way which makes Toyota what it is. The Toyota

Production System is only a manifestation of the Toyota Way, representing how

Toyota implemented the Toyota Way. The Toyota Way can be explained through

Toyota’s Principles (Liker, 2004). It is important to understand these principles in

order to apply it to software development and Information Technology. The

principals of the Toyota Way are as follows:

Long Term Philosophy

Toyota bases its management decisions on a long term philosophy, and

not on short term financial gains. Everyone at Toyota is instilled with the notion of

Page 22: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

12

doing what is right for the company, employee, customer, and society (Liker,

2004).

Doing right for the company means using the money earned by the

company to reinvest back in the company. In addition, the company learned hard

to be self-reliant, doing things themselves instead of relying on outsiders (Liker,

2004).

When Toyota formed a joint venture with General Motors, they took over a

light truck factory in Fremont, California called NUMMI. Against General Motor’s

advice, Toyota hired back most of the workers including the union leaders, and

made the company a success surpassing all of General Motor’s plants in North

America in terms of productivity, quality, space, and inventory turnovers. When

times were bad, Toyota gained their trust by not laying off anyone, and placed

extra people on kaizen projects. This is because the short-sighted move of

layoffs will cause ill will, and encourage workers not to participate in kaizen

efforts. When extra workers arise due to productivity improvements, they too are

not laid off, with the best worker chosen to be leaders for other productivity

improvement projects (Liker, 2004).

Establish Customer Defined Value

In a Lean organization, the customer is the starting point. By establishing

customer defined values, value added activity can be separated from waste. The

customer defined values must be communicated, and used throughout the

product development process to align objectives, focusing on the customer, and

eliminate waste from the system. Those activities which does not add value from

Page 23: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

13

the customer’s perspective is a waste. In product development, there are two

kinds of waste. The first waste is poor engineering, and the second is waste in

the product development process itself (Morgan & Liker, 2006).

To understand the customer better, Toyota creates a top program

leadership called the Chief Engineer. This Chief engineer has the background,

and experience to establish an emotional connection with the targeted customer

(Morgan & Liker, 2006). For example, the Chief Engineer responsible for the

RAV moved in with a young targeted family in Southern California. The Chief

Engineer for the Sienna drove a mini-van, usually a Sienna mini-van, through all

the states in the US, through all the provinces and territories of Canada, and

through Mexico (Morgan & Liker, 2006).

The Chief Engineer is responsible for delivering value to the customer,

creating the customer defined values, then communicating the customer-defined

values along with the objectives and goals of vehicle level performance to the

product team. The Chief Engineer creates the Chief Engineer’s Concept Paper

which is a twenty five page document of the vehicle product. It has input from

many people taking many months to complete, containing quantitative and

qualitative objectives for quality, cost, performance, and characteristics. Once

passed, the concept paper becomes the law, or direct order, and the Chief

Engineer develops the objectives for each functional program team with the

vehicle performance goals translated to specific measurable objectives for each

specialty area of the product team. A value hierarchy is created where high level

vehicle performance targets are decomposed, and assigned to tasks. The

Page 24: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

14

module development team meets to define the measurable goals for the

subsystems, and communicates this to the Chief Engineer team. Value targets

and specific strategies are developed to deliver the value driven commitments of

the teams (Morgan & Liker, 2006).

Another way to establish customer value is to have Quality Function

Deployment (QFD). It is a method of designing with the aim of satisfying the

customer by translating customer needs through design targets and quality

assurance points which is used throughout each stage of the product

development (Akao, 1990). QFD is a set of techniques which focuses all efforts

and design traits on a set of customer values into product features. It is a

powerful tool to map customer values with design characteristics and design

tradeoffs (Middleton & Sutton, 2005).

Create Continuous Process Flow

In manufacturing, and services, it is important to have continuous flow, as

it is through flow, one would find inefficiencies, and waste. An often Lean

expression used is to lower the water level, as high water levels would hide

wastes such as excess inventory, and when the water level is lowered, one can

see waste easier such as the excess inventory. Flow is triggered when a

customer places an order which will cause a chain reaction of processes to fulfill

the order in a short period of time (Liker, 2004).

In Toyota, there are eight wastes identified as follows:

Overproduction. Producing items where there are no orders (Liker, 2004).

Page 25: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

15

Waiting. Workers observing automated machines, or workers waiting for

the next step (Liker, 2004).

Unnecessary Transport or Conveyance. Transporting work over long

distances, or moving work in and out of storage (Liker, 2004).

Over Processing. Unneeded steps are taken in a process. This could be

due to improper design which results in rework on a product (Liker, 2004).

Excess Inventory. Excess inventory takes up extra space, can be

damaged, become obsolete, creates longer lead time, but more importantly hides

problems such a production imbalance, late deliveries, defects, equipment

downtime, and long setup time (Liker, 2004).

Unnecessary Movement. Wasted motion in the process, such as looking

for things, reaching, stacking, and walking (Liker, 2004).

Defects. Production of defect results in wasted resources. Defect requires

repair, rework, and replacement resulting in wasteful time and effort (Liker,

2004).

Unused Employee Creativity. Not engaging, or listening to employees,

resulting in lost learning opportunities, time, ideas, skills, and improvements

(Womak, James, & Roos, 1990).

Often one thinks an increase in speed for production would mean

sacrificing on quality. This is the exact opposite for flow. If one were to do things

in batches, and a defect occurs, the error would not be detected until much later,

and by that time, many more such errors would have occurred, and it would be

Page 26: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

16

hard to trace back to the source of the error. As these defects occur, bureaucracy

will be created to handle problems, building in a lot of non-value added

processes such as waiting on others to make decisions. It would be better to take

the people who does the value added work, line them up, and let the project flow

through these people, thus gaining speed, productivity, and quality (Liker, 2004).

One way of seeing if there is continuous flow is to have one piece flow

where only one piece is allowed to flow making it easier to see problems (Liker,

2004).

Use Pull Systems

A push system is when products are pushed onto the next step whether it

is required or not. For example, an automobile manufacturer can push vehicles to

automobile dealers to sell whether they need to or not, and the automobile

dealers try to sell it to customers whether they want to buy it or not (Liker, 2004).

A better strategy is to use a pull system. In a pull system, it is very much

like a supermarket, where the customer picks up a product to buy which in term

will trigger a process to replenish the product. The customer only picks up the

products they demand, and the retailers only reorder the product which was sold.

To avoid excess inventory, you may even be willing to pay more for the on

demand service (Liker, 2004).

Heijunka

Heijunka means leveling out the workload. Earlier we talked about pull

where nothing gets made until there is a customer order. Unfortunately customer

Page 27: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

17

orders can, be erratic where at times there are great demands, and at other

times, there are none. Strictly building to order would mean at times, there are

excessive work where there could be excess inventory along with a lot of

overtime, and then at other times there are no work. What needs to be done here

is to level the work. If customer orders are accumulated a little, to allow for

leveling of production, then the production line can be leaner (Liker, 2004).

The Japanese word for waste is muda. Focusing strictly on the eight

wastes above can be harmful, as there are two other wastes to consider in a

system, and they both start with an ‘m’. Therefore there is the elimination of the

three wastes as follows:

Muda – No Value Added Waste. These are the eight wastes discussed

earlier. They are wastes which lengthens lead time, extra movement, excess

inventory, which results in waiting (Liker, 2004).

Muri – Overburden Waste. This is the pushing of resources such as

people, and machineries beyond there natural limits. It some ways, it is the

opposite of muda. Pushing people too fast can cause safety concerns, and

decrease in quality. Overusing machineries can cause machines to breakdown,

and cause defects (Liker, 2004).

Mura – Unevenness Waste. This can be thought of as the balancing of

muda and muri. Unevenness occurs when at times there are more work than can

be handle, and then at other times there are not enough work. They can be due

to irregular scheduling or fluctuating production volumes. If mura is not resolved,

then muda will be the result (Liker, 2004).

Page 28: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

18

To eliminate the waste of unevenness it is important to have enough extra

inventories, and people on hand to handle the highest level of production, even if

the average required is much lower. For example, focusing too much on muda or

the eight wastes will cause erratic one piece flow where there are stops and

starts, and thus creating underutilization, and over-utilization which in turn will

cause other problems such as lower quality. As a result it is more important to

work like the slow and steady tortoise, rather than like the jerky hare (Liker,

2004).

Value Stream Mapping

Mapping will enable you to see the ideal state or the better state to go to.

Figure 1 Value Stream Mapping

Page 29: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

19

Toyota uses Material and Information Flow Mapping to depict current state

and future ideal state in the process of developing implementation plans for

installing Lean systems. Attention is given to eliminating waste, adding value,

and establishing flow. Toyota focuses on three flows, flow of material, flow of

information, and flow of people and processes. In Lean, Material and Information

Flow Mapping is called Value Stream Mapping (Rother & Shook, 2003).

A value stream is all the value added, and non value added actions

required to bring a product from raw materials to a finished good in the hands of

the customer. It consists of two flows, orders traveling upstream from the

customers, and products traveling downstream from raw materials to finished

goods to the customer (Jones & Womak, 2003). Using paper kaizen, one can

record all the work elements, and the time to take to do each work element. After

doing this, stack all the work elements, and remove the wasteful work elements.

The improved stack of work element is shorter than the original stack. Since the

value adding work is the same, by removing waste, future operators can devote a

greater percentage of work on the value added activity and thus do more without

working harder (Rother & Harris, 2001)! Value Stream Mapping is an essential

tool for Lean. It helps one visualize the flows and see the sources of waste, tying

together the Lean concepts and techniques, and avoid cherry picking practices.

Value Stream Mapping is the basis for implementing Lean, showing linkages

between information flow and material flow, and describes exactly what you are

going to do for process improvement (Rother & Shook, 2003). In Mapping Value

Page 30: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

20

Streams, it is important to keep in focus the customer values, and one way to do

this is to integrate QFD with Value Stream Mapping (Middleton & Sutton, 2005).

Jones and Womak (2003) also talked of an Extended Value Stream

Mapping which is the same as Value Stream Mapping, but extended beyond a

single plant into multiple plants, and across companies. The same analysis in

Value Stream Mapping applies, but can analyze the added complexity of multiple

plants, and external companies. In this paper, the two concepts will be treated as

the same.

Culture of Quality

Create a culture which stops to fix problems, and have quality the first

time. This idea came for Sakichi Toyoda where one of his inventions is the

automatic loom, which automatically stops when a defect is found (Liker, 2004).

At Toyota, when a defect is found, the production line worker is trained to

pull an andon cord or stop cord when a defect is discovered. When the cord is

pulled, the supervisor comes over to see if the problem can be remedied, and

within a certain time limit, if the problem cannot be resolved, the whole assembly

line stops. Problem solving is done to find the problem, and how to fix the

problem so that it will not occur again, then the assembly line is started again

(Liker, 2004).

Poka-yoke is used to prevent errors before they happen. It is a way to

error proof a process. Ways to prevent errors are to be simple, and often comes

from the people doing the work. Often there is a tendency to introduce

bureaucracy and complicated steps for quality, thinking as long as these steps

Page 31: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

21

are taken, quality would be there. The problem is that the people who think of

these steps do not work with the process, and often comes up with arcane steps

which hinder the process. It is better to have the people doing the work to come

up with ways for quality improvement, and creates the steps themselves. The

steps created have to be easy steps. In order to do this, the worker has to be

trained in problem solving, trained to go and see, analyze the situation, use one

piece flow to surface the problem, and ask why five times (Liker, 2004).

Toyota also uses check list to make sure steps are not missed to reduce

defects. Standard components from one vehicle can be used on other vehicles

as a way of doing incremental development, and ‘time out’ is used if people are

thinking too narrowly. It is not so much the tools to use for quality, but to have a

principle of quality (Liker, 2004).

Thoroughly Explore Alternative Solutions

At Toyota, product development is talent driven, committing the most

capable resources at the beginning. The best opportunity to explore alternative

solutions is at the beginning. Toyota front loads its product development process

with integrated cross-functional engineering to resolve major engineering

challenges early when the maximum possible options are available. This will

allow for exploring alternatives (Morgan & Liker, 2006).

Toyota uses what is called Set Based Concurrent Engineering (SBCE). In

SBCE, for every subsystem of both product and manufacturing system, multiple

solutions are explored simultaneously, as learning increases geometrically by

considering design alternatives at every level of the system. If this process is

Page 32: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

22

managed carefully, a highly robust, reliable, and predictable product life cycle

can be created. For each solution, aggressively attack it with rapid low cost

analysis and tests to eliminate weak solutions. To avoid using excessive

resources in determining alternatives, a system is devised to eliminate weak

alternatives, and this is done through the use of knowledge base trade off curves.

Systematically synthesize learning such as the results of analysis and tests are

placed on design space maps where knowledge can be reused in subsequent

projects, which can then increase speed and quality of design. This runs counter

to iterative development. Basically in product development, it is important for

participants to reason and communicate in sets of ideas, and gradually narrow

the sets of ideas until there is a convergence to a final design. The convergence

to a solution is possible only after it has been proven (Ward, 2007).

Toyota uses SBCE to examine a broad range of alternatives, before

making a final decision. By using the “set-based” approach of examining multiple

alternatives simultaneously as opposed to point to point, Toyota increases its

chances of coming to an optimal solution which will minimize expensive changes

later on. An example of this use is the development of the first commercial

hybrid, the Toyota Prius. The Prius Chief Engineer Mr. Uchiyamada, despite tight

deadlines, asked four design studios to come up with competing styling designs,

of which two were chosen for clay models, before a final decision was made. In

using SBCE, Toyota engineers have a sense of how the vehicle work as a

system, and spends a lot of energy on interfaces, not only between components,

but how they will be manufactured later on. There is a focus on system

Page 33: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

23

compatibility before the individual design is considered complete, rather than a

focus on individual design completion (Morgan & Liker, 2006).

Standardized Task

There is the misconception that standardization is about finding the best

way to do something. In fact kaizen cannot be done, until there is a stabilized

standard process. Standardized work is necessary for quality. When a defect is

discovered, the first step to discovering the problem is to see if standardized

work is followed. If it is, then standardized work must be changed to get rid of the

defect. The people who write the standardized work must be the ones actually

doing the work. This is because they are closest to the problem, and also most

likely to follow the standardized work if they created them themselves. To do

otherwise would create top down rigid bureaucracy, hierarchical structures with

slow communications, resistance to change, and standards not followed. What

Toyota does is to have an enabling bureaucracy which is organic where the

worker is the most valuable resource. The worker is an analyst and problem

solver and sets standards for themselves, and knows how to change the

standards for improvement. For example, engineers are taught the standards of

product development so that everyone knows what to do, and use a common

terminology. Check lists has evolved to show what practices are good, and what

practices are bad, but more importantly, the engineers know how to use

standards, and when to change the standards they use to make the standard

processes better (Liker, 2004). If the standards have not been updated for a

Page 34: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

24

while, it means kaizen has stopped, so supervisors are encouraged to be

embarrassed when standards have not changed (Shingo, 1989).

Use Visual Controls to Make Problems Visible

To make sure no problems are hidden, use visual controls. One important

aspect of this is to keep the work area clean, because in a clean work area, one

can easily spot problems. One way for doing this is to use the Five S Program.

The Five S Program is as follows:

Sort (Seiri). – Sort items separating those which are needed from those

which should be disposed of.

Straighten (Seiton). – Orderliness, everything must be placed in the proper

place.

Shine (Seiso). – Cleanliness, where the act of cleaning serves as

inspection to expose abnormalities, and find pre-conditions for failure.

Standardize (Seiketsu). – Creating rules, developing systems and

procedures to monitor and maintain the first three S.

Sustain (Shitsuke). – Self discipline to stabilize and maintain the work

place for kaizen.

(Liker, 2004).

Use Reliable Technology

Toyota uses new technology only after it is proven to be useful by a broad

spectrum of people through some experimentation. When using new technology,

Toyota looks to see if it adds value. If the new technology has an adverse effect

Page 35: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

25

on existing Toyota principles, the new technology is rejected, or delayed until the

problem the new technology introduces can be removed. The new technology

must help Toyota in its flow, and it must have visibility. Information Technology

does not drive Toyota, and it must not get in the way of Toyota’s principles.

Information Technology is still critical to Toyota, but technology is simply a tool

for Toyota, which must be evaluated like any other tools (Liker, 2004).

For example, instead of using complicated supply chain software, Toyota’s

preference is to use a manual system of kanban to control the supply chain

process. Instead of having Information Technology diagram of information

systems, Toyota prefers diagrams of how Toyota does business, and how the

Information Technology will support the business at Toyota. This is because

Toyota is an automobile manufacturer, and not a software manufacturer (Liker,

2004).

Grow Leaders

One of the biggest differences between Toyota, and other organization, is

Toyota grows their own leaders. All of Toyota’s CEO comes from within the

company while most of North America’s companies have their leader coming in

from the outside. For example, Fujio Cho, a former president of Toyota grew

through the ranks of Toyota. He was one of the original Sensei taught by Taiichi

Ohno himself. He was also the leader of the Toyota plant in Georgetown,

Kentucky. Throughout time, Toyota has always found the right person within the

company to lead the company in the right direction (Liker, 2004).

Page 36: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

26

Since the leaders are all home grown, they all support the culture at

Toyota, unlike in North American companies, where leaders goes through a

revolving door going form one company to the next (Liker, 2004).

Another leader is the Chief Engineer. The Chief Engineer at Toyota is the

person responsible for the development of an automobile model. This person

goes through the typical training that all engineers does at Toyota. Only the top

engineer becomes a Chief Engineer, and this person must not only be a good

engineer but must have other expertise as well to be the champion of the

automobile model he is responsible for. The Chief Engineer is the one who “runs

the program”. Chief Engineer acts as the program manager, project manager,

leader, technical systems integrator, makes the difficult decision for problem

resolution, chief technical architect, champion of the product, delivering value to

the customer, holds the whole product development system together, and the

one person accountable for the success of the team. The range of responsibility

for the Chief Engineer includes being the voice of the customer, defining

customer value, concept of the product, objectives of the program, vision of the

program, and product planning. The Chief Engineer is also responsible for the

vehicle level architecture, performance, characteristics, and objectives. The skills

of a Chief Engineer includes exceptional engineering skills, exceptional

communicator, feel for what customer wants, intuitive, grounded in fact,

innovative, skeptical of unproven technology, visionary, practical, teach,

motivator, disciplinarian, patient listener, attitude of achieving targets, and ready

to get hands dirty (Morgan & Liker, 2006).

Page 37: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

27

There is no such thing as someone walking out of university and be a

manager right away. In order to be a manager or team lead, one must be able to

teach, and train more junior workers. This is one of the ways management add

value to a product, as management activities are consider to be non-valued

added activities. If a worker has not learnt what they were suppose to learn for a

job, it is considered to be the fault of the manager! The managers themselves

learnt the same way from having their superiors teach them, and they can easily

substitute for the worker doing the work (Liker & Meier, 2007). For example,

when Fujio Cho was President of Toyota in the Kentucky branch, he is often

found on the shop floor teaching! If management cannot teach to their

subordinates and pass on skills acquired, the person cannot be a manager

(Liker, 2004).

Develop Exceptional People and Teams

Toyota develops exceptional people, and teams to follow the philosophy of

the Toyota way. While it is the individual which does the actual work, adding

value, it is the team which provides support for the individual, and also provides a

point of socialization to exchange ideas, and help one another. Toyota

establishes a balance between individual work and team work, and spends

consider effort to train an individual to develop depth of technical knowledge

along with a wide range of skills, and to have the Toyota philosophy second

nature to everyone. At the same time, team work is the foundation for the

individual to work hard for the company. The Toyota Production System originally

was also known as the “respect for humanity system” (Liker, 2004).

Page 38: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

28

Technical excellence is fundamental to Lean product development, and is

revered at Toyota. Engineers at Toyota spend much of their time doing core

engineering. After a rigorous hiring process, engineers first learn to sell cars at

the dealership and door to door, learning to understand the customer better, then

are placed on a career path with a deep technical skill acquisition, and mentored

critical tactical skills. There is a push for engineers to get their hands dirty, and

use Genchi Genbutsu to go see directly for them self. It is important engineers

are connected to the product they design. Much of the engineers training come

through on the job training, and mentoring through a Sensei. Toyota managers

are also teachers, and they are responsible for the development of his

subordinates (Morgan & Liker, 2006).

Freshmen are also placed on a freshmen project lasting four to nine

months to hone their skills of using engineering tools and accomplishing the task

the Toyota Way. This means coming out with more than one solution, and

presenting the ideas in an A3 form. This is quite different than what they have

learned at university, and quite emotional as senior Toyota managers still

remembers there freshmen projects vividly. Following this, they are placed into a

two tier on the job training. In the first tier, CAD work is one of the things they

have to learn to do, and they spend time doing this for two years. In the second

tier, they spend three to six years working on designing related parts. Only when

they could do this are they considered an engineer. During this eight years, the

manager mentor interviews the engineer four times a year not only on

performance and peer review, but also on technical progress, adherence to

Page 39: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

29

company process, and standard methodology based on Toyota’s standard skill

set. From this the manager outlines areas of improvement and develops an

action plan for the engineer to work on for the next interview (Morgan & Liker,

2006).

Most companies do not want to train their engineers to great depth,

because of the high turn over. What most companies does not realize is the fact

this education is necessary for Lean Product Development. Standardization of

skill sets is important, and all engineers have to strive to learn the standard skill

set. At the same time, the organization must be a learning organization where

managers and leaders are expected to be able teach and mentor others (Morgan

& Liker, 2006).

The commitment for a deep education of engineers evolved out of

Toyota’s history where they have to do almost everything from the ground up

when they first manufactured vehicles (Morgan & Liker, 2006).

Toyota invests in its people, and in return gets a commitment from its

people to do their best at Toyota (Liker, 2004).

Respect and Challenge Partners and Suppliers

Toyota not only uses the Toyota Way internally, they also move upstream,

and teaches the Toyota Way to its suppliers (Liker, 2004).

Toyota does not deal with its suppliers in an adversarial way, they go out

of their way to work with a supplier, and even have suppliers design part of a

system of an automobile such as the radiator. If Toyota wants its suppliers to cut

cost, it will also send people to the supplier to help them cut costs. When

Page 40: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

30

suppliers have problem which causes Toyota to shut its assembly line, Toyota

will send people to the suppliers to help them diagnose the problem, and correct

the problem. Toyota focuses on fixing the problem, and not blame. Only as a last

resort, will Toyota terminate a supplier. If a supplier does very well, then in the

next automobile model, the supplier may have a bigger contract, as they have

proven themselves (Liker, 2004).

When a company becomes a supplier to Toyota, the company is

essentially adopted into the Toyota family and is treated as part of the Toyota

family. Often partnerships are formed between Toyota and suppliers, where

Toyota may take part ownership of the supplier (Liker, 2004).

Often engineers from suppliers can be found, at Toyota, and Toyota

engineers are found at supplies as a way to cross train. This does not mean

Toyota is totally dependent on its suppliers, and Toyota keeps some core

technologies in house, and as a rule, have two suppliers for the same part (Liker,

2004).

The respect, and challenges Toyota gives its employee, they do the same

to their suppliers. Suppliers are given respect, and they are also challenged to do

better, undergoing kaizen to reduce cost, and increase quality. In asking for a

part, Toyota may only give a general description, and it is expected, the supplier

will design the rest since the supplier will have the most knowledge in its own

field (Liker, 2004).

Page 41: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

31

Genchi Genbutsu

To understand the situation or any part of a business problem, you must

go see for yourself first hand. Do not rely on reports from others, and do not take

anything for granted. This is the first part of any problem-solving. Accompanied

with this, one must have the skill to analyze, and understand the situation (Liker,

2004).

Teruyuki Minoura, a former president of Toyota Motor Manufacturing in

North America was taught by Ohno. Mr. Ohno made him stand in a circle for

eight hours on the shop floor to teach the power of observation, to think for

oneself what one sees, question, analyze, and evaluate. Data is important, but

fact is more important, as data is one step removed (Liker, 2004).

Toyota is a learning company, and it expects its employees, including the

president to go and see problems for themselves, and learn from it. For example,

when Chief Engineer Yuji Yokoya was assigned to develop the next version of

the Toyota Sienna, he traveled to North America, rented a van in most cases a

Toyota Sienna, and drove through all fifty states in the United States, all

provinces and territories in Canada, and all parts of Mexico. He did this to

personally see for himself what North Americans would like to have in a van. As

a result of this, the next version was a much improved version, and it became a

very popular mini-van in North America (Liker, 2004).

President and executives all practice Genchi Genbutsu, and spend a

considerable amount of time on the shop floor going and seeing for them self

(Liker, 2004).

Page 42: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

32

Decisions by Consensus

At Toyota decisions are made by consensus after considering all options,

and then implementing the decision very rapidly. How one arrives to making a

decision is just as important as making the decision itself. Toyota management

will forget a wrong decision, if the process used to make the decision is the right

one, but will give a reprimand if the decision was the correct one, but the process

for arriving to the decision was based on chance (Liker, 2004).

Nemawashi is a process used to gain consensus. Young engineers are

taught to seek the input of others as a way to generate consensus, and by the

time the decision has to be made, it only becomes a formality because, a

decision has already been made before hand by consensus (Liker, 2004).

Such efforts are expended because it serves three purposes. The first is

all facts are uncovered to avoid painful backtracking. The second is gets

everyone on board for the decision, and the third is there is a great deal of

learning at the beginning even before a project is started (Liker, 2004).

Become a Learning Organization

Toyota is a learning organization. The Toyota Way is about how Toyota

learns as an organization. It involves the company to learn from its mistakes,

determine the root cause, provide effective counter measures, empower the

people to implement measures, and a process to transfer new knowledge to the

right people (Liker, 2004).

Toyota has a seven step method for practical problem solving as follows:

Page 43: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

33

Initial problem perception is when a problem is first recognized. It could be

a defect discovered in the production line.

Clarify the problem is to “grasp the situation”, clarifying the problem to

understand the real problem. It starts with observing the situation with a

clear mind using Genchi Genbutsu, and comparing it to the standard.

Pareto Diagram can be used to sort the problems.

Locate area and/or point of cause trying to identify where the problem is,

where the cause is most likely, leading a person to the general vicinity of

the problem.

Investigation of root cause is conducted to identify the root cause. Toyota

uses a very simple and effective way of finding the root cause, and that is

to use the “5 Why” analysis. In the “5 Why” analysis, the problem solver

will ask why five times in order to determine the root cause. It does not

necessary have to be five times, it can be more, the point being often the

problem is not where you first see it, you must look at it deeper, and one

way of looking at it deeper is to ask why many times.

Countermeasure is developed to fix the problem, and prevent it from

happening again once the root cause is discovered.

Evaluate the countermeasure to see if it does what it is suppose to do.

Standardize the new process after the evaluation has shown the

countermeasure is effective in correcting the problem.

(Liker, 2004).

Page 44: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

34

From these principles of the Toyota Way, the Toyota Product

Development System, and the Toyota Production System is created. In the next

chapter we will use these principles to apply on software development and

Information Technology to come up with Lean Software Development and Lean

Information Technology.

Page 45: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

35

CHAPTER IV

APPLICATION OF LEAN TO SOFTWARE DEVELOPMENT AND

INFORMATION TECHNOLOGY

When Lantech, Inc. and Wiremold Company switch to Lean, they found

out their accounting department has to change also. Accounting departments

often produce information which is too late to be useful, and in fact some of the

financial statements run counter to what Lean is trying to do. For example, in

Lean, one of the goals is to reduce inventory, and if traditional cost accounting is

used, the lower inventory will result in confusing financial statements. This is

because of the use of standard cost and variance style income statement, where

the cost of the old inventory must be included in the expense column. When

inventories are lowered, the result of the Lean initiative will make the profit look

lower initially, and the results of the financial statements will look like it is worse

when doing the right thing of using Lean. It is important to remember the real

expense of carrying inventory is hidden in the old system, but brought out visibly

with Lean. Adding this with the pressure to show monthly or quarterly results for

public traded companies, it is important to work with investors of the meaning of

the confusing financial statements when adopting Lean (Cunningham & Fiume,

2003).

At the same time accounting departments must switch to cost

management, and not cost accounting, as the real goal here is to reduce cost. In

other words, the accounting department must work as a partner in the Lean

Page 46: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

36

initiative, and not hinder it. As well the Lean initiative also applies to the

accounting department in making it Lean thus making the accounting department

more efficient with lower costs (Cunningham & Fiume, 2003).

Also when companies switch to Lean, their project management practice

has to change as well, especially if it is used in product development. Having

Lean product development also means to use Lean project management. Special

consideration must be given to heavy loading of resources at the beginning of the

project. As well the PMBOK guidelines must be modified to work with Lean,

especially the Toyota Way of doing Lean. Without this adaptation, project

management will hinder or kill the Lean initiative (Leach, 2005).

Information Technology must adjust accordingly like the accounting

departments in Lean organizations, and Lean project management. What this

means is Information Technology must act as a partner to the Lean initiative,

making it useful to the Lean process while at the same time find ways to be Lean

itself.

With this in mind, we will apply the Lean Toyota Way principles to software

development and Information Technology as follows:

Long Term Philosophy

Management should make Information Technology management

decisions based upon a long term philosophy.

Information Technology should do what is right for the company. This

means developing software which truly represent the needs of the company, and

Page 47: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

37

keeping the software relevant to the company, reinvesting back to Information

Technology whenever possible.

What this means for Information Technology is as follow:

Instead of lay offs for Information Technology workers when times are

bad, and outsourcing jobs to lower wage countries such as India,

organizations should guarantee Information Technology workers job

security, putting excess Information Technology workers on kaizen

initiatives. This would gain trust to the worker. We want to be Lean, but not

mean. Nothing kills off kaizen, trust, initiative, and loyalty quicker than

having layoffs.

The customer is important. When releasing software to the customer, the

software should be free of defect, and if it is not, it should be fixed for free

rather then charging a customer for an upgrade release later on.

To be a benefit to society, organizations should allow its Information

Technology workers to donate their time for creating software for charity.

Establish Customer Defined Value

A modification to Agile Software Development would be to have a Chief

Engineer who is the product champion. If the software is developed for the

consumer market, then someone like the Chief Engineer would be the driver for

the product. For an in-house developed application, or custom built application,

the Chief Engineer must interact with the customer in their own environment to

understand what is required. Having the customer as part of the Team as in

Scrum and Extreme Programming is not enough. The Chief Engineer must

Page 48: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

38

understand how the customer does their work, and how the new software will

support them in their work.

Instead of a model in Extreme Programming, a concept paper should be

created with input from everyone to describe what the new software is to do.

Each area of specialty will do the work to create a value hierarchy, and what

each area of specialty within the product development team should do. QFD can

be used to map customer values into software design, and software design

tradeoffs.

Create Continuous Process Flow

It is important to have continuous flow in software development. Instead of

a batch of analysis, then a batch of design, followed by a batch of coding, and

finally testing, it would be better to structure the work such that it flows. For

example instead of batching a horizontal slice, do a vertical slice for each feature

or function point of the software where each vertical slice gets its own analysis,

design, coding, and testing. This would make it easier to create any one feature.

For each cycle done, experience gained can be used in the next cycle.

In software development, there are eight wastes identified as follows:

Overproduction. Extra features are overproduction. Every code written has

to be tracked, compiled, integrated, and tested. Each new code written adds

complexity, and increases the point of failure. Since extra features are not

required in the first place, it may well not be needed, and become obsolete,

getting in the way. If there is not a clear economic need for a new feature, it

should not be done (Poppendieck & Poppendieck, 2007). One way to alleviate

Page 49: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

39

this problem is to have an architecture which will allow features to be easily

added later, thus removing the need to add the features now (Poppendieck &

Poppendieck, 2003).

Waiting. Any delays keep the customer from realizing value as soon as

possible. This includes waiting for the necessary resources to be available for a

project, developers waiting to find the right people to understand a requirement to

be implemented, the project team waiting for top management to give approval

for the project, waiting for the change approval process, and waiting for code to

pass tests (Poppendieck & Poppendieck, 2007).

Unnecessary Transport or Conveyance. Handoff is unnecessary transport

or conveyance. When work is handed off from one to another, tacit knowledge is

loss. Tacit knowledge are knowledge which a worker possess about the work,

which is not written down, and often when the work is handed off to another

worker, much of the tacit knowledge is loss. To reduce this waste, there has to

be a reduction in handoff, and if that is not possible, have workers work in teams

where they can use face to face communication to pass the tacit knowledge

along better. Also release work for feed back earlier would reduce this defect

(Poppendieck & Poppendieck, 2007).

Over Processing. Unnecessary work which is not required such as paper

work which does not add value, especially when no one is going to read it! The

paper work consumes resource, slows response time, hides quality problems,

gets lost, degrades, and becomes obsolete. If the wasted paper work does not

add any value, do not require software developers to do it. This includes

Page 50: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

40

requiring software developers to write various reports such as status reports. A

good test to see if the reports add value is to see if anyone uses the work

afterwards (Poppendieck & Poppendieck, 2007).

In addition, relearning is an example of rework in software development.

Sometimes software developers may have to relearn something they have learnt

once before, and then forgot about it. This can be alleviated by engaging

software developers more in the project (Poppendieck & Poppendieck, 2007).

Excess Inventory. Partially done work is excess inventory. Partially done

work ties up resources in investments which do not yield results, and there is no

guarantee the partially done work will work. They get in the way of other software

development, and if they never go into production, then they will truly be a waste

(Poppendieck & Poppendieck, 2007). Some examples of partially done work are

as follows:

Not coded requirements documentation. This is as a result of

requirements written too soon. The longer design and requirements

sit not coded, the more likely they need to be changed before

coding (Poppendieck & Poppendieck, 2003).

Unsynchronized code – Code checked out or in different branches

of version control which needs to be merged. The longer they are

unsynchronized as work progress on the different branches, the

harder it is to merge the code, and increases the need to put the

same or similar code in two different branches (Poppendieck &

Poppendieck, 2003).

Page 51: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

41

Untested Code – Code has to be integrated, tested, and accepted

or it does not count. If testing is not done right away, there is no

immediate feed back to the developer who created the code, and if

the developer has moved on, then there would be no feedback at

all resulting in some other developing relearning the work to fix the

defect (Poppendieck & Poppendieck, 2003).

Undocumented Code – If documentation is needed, they should be

done as the code is written such as the user guide. The code itself

should be as self documenting as possible (Poppendieck &

Poppendieck, 2003).

Code Not Deployed – There should be a bias for deploying as

quickly as possible. Users can handle small increments better

(Poppendieck & Poppendieck, 2003).

Unnecessary Movement. The fastest way to do two things which have to

be done is to do it one at a time. When switching tasks, there is a significant

overhead incurred. One has to remember what they were doing, and what they

were thinking about before they can get back to the high level of concentration

necessary to complete the task when a task is switched from one to the other

(Poppendieck & Poppendieck, 2007).

Defects. Defect becomes a huge waste, if it goes on undetected. To avoid

this, test immediately, integrate often, and release to production as quickly as

possible (Poppendieck & Poppendieck, 2007). To get rid of defects, make use of

base classes, and frameworks, employ automated unit testing and integration

Page 52: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

42

testing. Use exploratory testing to find defects, and put processes in place to

prevent defects from happening again. Defects should be detected as early as

possible. The primary purpose is to mistake proof the code, and to detect defects

as early as possible to prevent them from happening again. Inspection to prevent

defects is important, inspection to find defect is too late. Prevent errors from

happening. Never build good code on top of bad (Poppendieck & Poppendieck,

2003).

Unused Employee Creativity. Software developers and Information

Technology workers are expensive resources, and if they are not allowed to do

what they do best, then that is a waste.

Often one thinks an increase in speed for software development means

sacrificing quality. If one were to have continuous flow, where wastes are

eliminated, and allowing people who add value to kaizen their own processes,

the software development process will go much faster without sacrificing quality.

Use Pull Systems

In the Water Fall software development lifecycle where there is a batch of

analysis, followed by a batch of design, programming, then testing, the results of

each phase is pushed to the next phase.

Examples of having a pull system in software development is to not code

a feature until quality assurance can test it so that the code is tested as soon as it

is written. In turn, design is not done until a developer is ready to code it. Finally

analysis is not to be done until the feature is ready to be designed. In this way,

Page 53: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

43

there is no batching of each step of the software development cycle such as the

water fall software development lifecycle. Ideally, we want flow, and if it is hard to

have flow, create flow by using pull, not push.

Heijunka

In software development, the problem of unevenness occurs quite often,

and they should be leveled to correct the problems of muda, mura, and muri.

Often an organization have a new budget at the beginning of the fiscal year, and

want to start all the software projects all at once, and then toward the end of the

fiscal year, they may find there is not enough funds, so there are not much work

to do. In this situation it is better to have the projects released throughout the

year as projects are created, and new projects are started.

Within a software project, there is also unevenness. Developers at times

could be waiting on getting approvals, waiting to get feed back, waiting for the

design, whereas at other times they have to work extra hours to code up a

feature. Quality assurance may not have much to do while code is being created,

but rush to test everything as all of a sudden they have a lot of code to test, and

may find out they have less time to do so due to developers taking up some of

the time of quality assurance in the overall schedule.

It is important to add slack time to a software project. Once pass 80%

utilization, cycle time increases especially with greater batches. To reduce cycle

time, it is important to have smaller chunks of work to even out the arrival of

work. In other words the waterfall software development life cycle creates huge

batches from one phase to the next. It is better to break this down into small sets

Page 54: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

44

of work, say one feature at a time. Have budgeting processes such that not all

projects are released at the same time (Poppendieck & Poppendieck, 2003).

Value Stream Mapping

It is very important for Information Technology to learn Value Stream

Mapping. The concept of Value Stream Mapping is very similar to Process

Modeling, a skill a Systems Analysis should have. Part of a Systems Analysis’s

job is to look for improvement, especially in terms of using Information

Technology. Systems Analysis are accustomed to solve a problem for the user

through analyzing the practice of what the user are doing now, versus what

improvements to the process could be had if the user were doing what they are

doing with a new computer system. As a result, it would be easy for Information

Technology to adopt value stream mapping. When organizations adopt Lean,

Information Technology armed with Value Stream Mapping capability can be a

partner in helping other parts of the organization become Lean. In doing so,

rather than having information systems being in the way of being Lean, new

systems can be thought up to help Lean. Of course Information Technology can

also use Lean to improve its own department, and thus give it more credibility

when they help other parts of the organization become Lean.

Paper kaizen is also used along with mapping the future value stream of

the software development process to figure how long it takes to do each work

element and removing those processes which does not add value.

Page 55: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

45

Culture of Quality

A culture of stopping to fix problems, and have quality the first time is

important to software development.

Poka-yoke for software development is writing the test cases first. These

test cases are to be automated so they can be easily run again, and again. As

code changes are made, the automated test cases can be run as a regression

test to prevent introducing an error to existing code. These automated testing can

be for unit testing and integration testing, using tools such as JUnit for Java, and

NUnit for C#. For web development, Watir can be used for quality assurance

testing, or acceptance testing which can be easily run each time code is

deployed to quality assurance. These automated tests can be hooked up with a

continuous build tool such as Cruise Control which will automatically check out

code, compile, and then run the automated tests. When an error is detected an

email is sent out to all that has made code changes since the last successful

build (Clark, 2004). Most developers do not know how to write the test case first,

and it is important to teach developers how to do this. As with Toyota, software

developers must be taught to go and see, analyze the situation, and ask why five

times to figure out the problem and how to fix it.

Another way to build quality is to create a well tested base class for

subclasses to inherit from. These base classes could be as a result of getting rid

of repeated code. Instead of having many repeated code, or variation of the

same code which does the same thing, get rid of the different versions, and

inherit from a common base class which encapsulates the same functionality. A

Page 56: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

46

good example of this would be the desire to have a consistent look and feel on all

the screens of an application where the buttons and other functionalities have the

same behavior throughout the application. To implement a new screen, all a

developer has to due is to subclass the base class with the appropriate behavior,

and the specific screen behavior, and the screen is done. Automated testing is

only needed for the specific behavior, as the base class behavior already has its

own automated tests.

Standardized components can also be used in software. Within a

company certain software written has the same functionalities. If they are written

in the same language, then they can be reused in other projects. Many software

developers have a tendency to write their own code no matter what, in a sort of

‘not invented here’ syndrome, even when there are standardized software

component available to use. A good example is the wealth of open source

software out there which software developers can use. While not all open source

software has high quality, there are many which have high quality, especially

those in www.apache.org. For example, many Java software developers want to

write their own database connection pooling, their own object relational

database, and even their own application server. There is no need to write

software for these in a Java project, as the open source software will do,

especially when many of the open source software are well tested in the

community, and comes with their own set of regression tests.

Page 57: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

47

In addition, analysis patterns, design patterns, implementation patterns,

and testing patterns can be used in software development. Patterns represent

time tested solutions for a given problem.

Software also benefits from having check list. For example, a method of

procedure can be created for deploying a new application to production. A check

list can be used on how to put a screen together, or how to map objects to a

relational database for object relational mapping. If developers are stuck on a

problem, then ‘time out’ is required to allow the developer to approach the

problem from another angle.

Thoroughly Explore Alternative Solutions

Encourage developers to take the time and explore alternative solutions,

front loading the project at the beginning to allow for this. Use Set Based

Concurrent Engineering (SBCE) for software development. In Extreme

Programming, there is an aversion to a Big Up Front Design, as a reaction to the

Waterfall Software Development Lifecycle, but Extreme Programming goes too

far the other way. Extreme Programming uses an emergent design, where the

design of the software will evolve through iterations. As the design emerges,

refactoring is necessary to achieve the emergent design. Perhaps the Extreme

Programmers should plan more and use set based concurrent engineering to

explore all options. By doing this, the amount of refactoring necessary for an

emergent design will be reduced. Also the iterations used in Agile Software

Development is point based which implies picking only one design, then you

have to move from one point to another to change the design. This is not to say

Page 58: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

48

the Water Fall Software Development Lifecycle should be used, but to use

SBCE.

SBCE must be used in software development to find the optimal solution.

This would also make the design much better than upon relying on an emergent

design, as it is based upon exploring a broad range of options. Also, this will take

away a weakness of Scrum where the Scrum Master arbitrarily makes a decision

based upon the gut feeling of the Scrum Master just to get going. What is

important to note, with SBCE, the team pretty well knows where the direction is

going anyways, and not on the whim of a Scrum Master. This means front

loading the software development project with experts from each domain to iron

out problems at the beginning!

Standardized Task

Standardized work is necessary for software development quality.

Although there are parts of software development which requires creativity, there

are many parts of software development which is very procedural and can

probably be standardized. For example, the basic create, insert, update, delete

functionalities to the database, where the steps or repeated over and over again.

One can write standards to do this, and how to write unit tests for them to make

sure they work. Also developers can experiment with the best way to put a

screen together, and come up with a standard to do so. If there is a better way to

do it, then the standard will be updated by the developers themselves. Also

developers can all be trained the same way as the Toyota engineers are trained

on product development, so all the software developers within the same

Page 59: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

49

company can work together with the same standards using the same

terminology.

Use Visual Controls to Make Problems Visible

The 5 S Program is also an important part of visual controls to keep the

work place clean in software development and Information Technology.

The 5 S Program can apply to Java coding as follows:

Sort (Seiri). - Reduce size of code based by removing unneeded items.

Examples of items to remove include commented out code, unused imports,

unused variables, unused methods, and unused classes. Refactor code to

remove redundant code.

Straighten (Seiton). - Organize projects, and packages, removing package

dependencies, and minimize dependencies. Classes should be loosely coupled

between them, and code should be very cohesive within the class.

Shine (Seiso). - Clean up so problems can be more visible. This means

resolving failed unit tests, improving the coverage of unit tests, and improving the

performance of the unit tests. Resolve warnings upon compiling including not

using deprecated methods, have proper JavaDocs in the code, and TODOs are

completed and then removed.

Standardize (Seiketsu). - Create standardize procedures, and follow them.

This includes such things as properly naming classes, methods, and variables.

Adopt a code format standard agreed to by the development team. If the project

uses a third party product such as Hibernate, create a set of procedures on how

to use the third party product, such as how to assemble the code, and

Page 60: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

50

configuration files to use the third party product. If the project uses many

screens, then create a standard on how the screens can be assembled.

Sustain (Shitsuke). - Keep up with the discipline. Do this continuously.

(Poppendieck & Poppendieck, 2003).

Similarly, the 5 S Program can apply to Information Technology as follows:

Sort (Seiri). - Sort through workstations, and servers separating what is

not important from what is important. Not important files such as old versions of

software, old files, and old reports are backed up, and then deleted.

Straighten (Seiton). - For workstations which are commonly used, they

should conform to a common team layout, and logically organized to make things

easy to find. This will make it easy for team members to use wherever they log

in.

Shine (Seiso). - Clean up. This means the work place has to be clean

such as throwing away garbage, cleaning the monitor, clean the whiteboard after

taking pictures of the important design.

Standardize (Seiketsu). - Have automation and standards, such as each

work station has the latest version of tools, is backed up regularly, and do not

allow junk to accumulate.

Sustain (Shitsuke). - Keep up with the discipline.

(Poppendieck & Poppendieck, 2003).

The Five S Program is to be conducted every day, unlike most North

American companies where it is either not conducted, or if conducted, is only

Page 61: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

51

once a month, or only once a week at the most, or only when an important visitor

comes. The idea is not simply to superficially do it, but to become a part of the

worker’s daily habit to properly organize the work area continuously to make the

work area a much better place to work.

For Information Technology, a dash board could be used to communicate

status. In software develop project management, user stories can be pinned on

the wall, and as they are completed, are moved from the not completed side of

the wall to the completed side of the wall, as a way for visually identifying the

status of a project. For continuous integration, and automated testing, lava lamps

could be use to indicate the status of a build along with automated testing where

the green lamp lighting means a successful build which passes all the automated

tests, and a red lamp lighting means otherwise (Clark, 2004).

Use Reliable Technology

This has huge implications for Information Technology. Information

Technology must support the business. Adding new technology does not

necessary mean the business will work better. Before new technology are used,

they must be shown to fit with the business needs of the company, and only if

there is a clear benefit would they be introduced.

Also technology is not flexible when changes are required. Often when the

environment changes, a request to make changes in technology may take time,

but with a manual system, people can adjust to the change very quickly. In other

words it is easy to have kaizen with people, but with automation, they cannot be

improved, as they only do what they are programmed to do.

Page 62: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

52

In order for Information Technology to be more useful, the automation

must be able to be kaizen as well, where necessary process improvements on

the automation are quickly added by Information Technology. What this means is

that in addition to having efficient processes before automating, the automation

has to be easily adjusted through kaizen, since a fixed automated process will

show no process improvements (Liker, 2004).

Toyota prefers to use simple software applications which can work

collaboratively with the Toyota Way (Liker, 2004).

In doing software development, the same applies. It is often better to use

proven technology for developing a software application, and it must support the

software developers in what they were doing. For example, some companies

have a policy of adopting Microsoft applications such as C# and .Net for software

development without regards to whether it is appropriate or not. Developers then

struggle to create a web application using Visual Studio even when much of the

web development can easily be done with a simple text editor.

Grow Leaders

What companies should strive to do is to develop their own people,

including developing their own people to become leaders. In software

development, there have been studies done, where one of the most effective

software projects is to have the concept of a Chief Surgeon. The problem with

this is not everyone can be a Chief Surgeon, because no one has all the required

skills to be one (Schach, 2005). The implication to this is that Information

Technology, as well as other parts of the company must train their people well,

Page 63: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

53

especially training people to become leaders within their own company. The

resource to do this is the leader, and the leader must be able to teach!

In software development within a company there may be a product

manager, program manager, project manager, technical architect, and team lead

which borders on being obscure because in small projects, there can be more

non-value added people than there are people who does the actual value added

work. A chief engineer can replace these five people with one person thus

reducing cost, and at the same time have a role similar to the Chief Surgeon. In

Extreme Programming, there is no concept of a leader of the project, with the

coach being the closest thing. Similarly in Scrum, there is the Scrum Leader who

leads the project, but is in no way anywhere near the responsibility,

accountability, and skill of the Chief Engineer. Often time, they mire themselves

in the methodology, rather than getting the real work done.

The concept of Chief Engineer would greatly enhance the software

development process, and software companies should take the time to develop a

Chief Engineer.

Develop Exceptional People and Teams

Most companies, after hiring their best, simply placed these people into

positions to fend for themselves. They are given no further education other than

company education programs which amounts to lip services, and their boss were

trained similarly with no ability, or desire to teach subordinates. This is true in

software development. In Extreme Programming, workers can learn from the

coach or from one another in pair programming, and in Scrum workers have to

Page 64: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

54

try and learn from themselves or help each other learn. Even before thinking of

methodologies, organizations and Information Technology must invest in their

employees, and train them further. It is not enough from what employees learn at

a technical school or university, or someone taking a continuing education

program. At Toyota, engineers are trained for twelve years before they are

considered engineers. In Information Technology the same thing should be done

for Information Technology workers. If not, they will find a situation where

workers do not know what to do, and as a short term solution, hires outside

consultant to do the work, giving them the work experience, and then leaves the

organization taking the knowledge with them (Morgan & Liker, 2006).

Information Technology should borrow from the way Toyota train there

engineers. This starts with recruitment where in addition to hiring at the top of the

class the potential Information Technology worker must have an aptitude for

computers, technical competence, creativity, problem solving, ability to work in

teams, see the situation, communications, discipline, motivation, and dedication

to work. There should be a broad training of the Information Technology worker

including orientation, working on the company’s core business in the front line,

and doing a freshman project with a focus on finding alternative solutions and

presenting ideas in an A3 form. In addition they must learn modeling with Unified

Modeling Language (UML) and Entity Relationship diagrams, and be a part of a

project where they learn various technologies including open source software,

and learn how to write the test cases first before writing code. The freshmen

should be mentored by senior people as they progress, and does not become a

Page 65: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

55

Senior Information Technologist until they gain all the necessary skills. This will

build an Information Technology worker who would have a standard set of in

depth technological competence.

For any organization, especially Information Technology, one person

cannot do a project, and project work requires workers to work in teams. Based

on the effort Toyota spends on developing the team, Information Technology,

should similarly expend the same kind of effort so that each member of the team

can contribute individually as well as contributing to the team. Team members

are to be taught to work together, and there must be no hands off leader. For

example, the software architect, must know how to code, and does so readily,

the project manager might chip in by helping quality assurance to test to help

meet deadlines. Testers can help write testing code to reproduce a defect to

make it easier for developers to correct a defect. Allow developers to talk to the

user to help the business analyst gather the necessary requirements he needs

to. Managers chip in with the project whenever they can without demanding

useless reports.

When starting a project, the first iterations should be slow, to allow for the

team to interact with one another in a social way to help one another. A leader is

there to help guide the project team. As the project proceeds, the leader steps

back, and let the team take over, but the leader can step in at any time to help,

as the leader cannot be hands off.

Page 66: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

56

Since it is so important to see value from the customer’s point of view,

Information Technology workers should also be trained in the customer areas

where the software they are creating or maintaining is being used.

Respect and Challenge Partners and Suppliers

In Information Technology, sometimes there is a need to hire outside

consultants. Outside consultants have to be trained like regular employees to

understand how to work with the company and contribute as well. This means

the outside consultant will have to be trained just like the internal employee with

the same support system. In addition, internal developers do work in the

consulting company as a way to cross train, and gain more experience.

Genchi Genbutsu

For Information Technology one must go out and see how the customers

use the software created by Information Technology. This will give them a better

idea of how to make the software better, and more useful. In explaining the

failure of the Chrysler Three Corporation, Kent Beck, the founder of Extreme

Programming, blamed the new customer representative for failure of the project

as a single point of failure (Stephens & Rosenberg, 2003). In connecting with the

customer, it is more than simply having the customer as part of the team. For

example, Kent Beck should have used Genchi Genbutsu to see for himself,

analyze, and evaluate to make his software development better. Information

Technology professionals should use Genchi Genbutsu to understand their

customers better in order to create better software. Information Technology

Page 67: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

57

managers, as well as company executive should take the time to talk to people

on the front line, and see things for themselves to help them better understand

how the business is doing (Middleton & Sutton, 2005).

Decisions by Consensus

In software development, it is important to get everyone on the same page

so the project team can all move at the same direction to get the software

developed without damaging conflict. Information technology should be taught to

seek the input of others as a way to generate consensus. This will allow for

uncovering all the facts, gets everyone on board for the decision, and be a

learning experience. By using consensus, the silos in software development of

business analyst, software architect, data administration, database

administration, developer, quality assurance will be removed.

An improvement made to Scrum would be instead of the Scrum Master

making a quick decision when a decision has to be made, the Chief Engineer

Scrum Master should allow the team to make the decision through consensus.

Alternative the Chief Engineer Scrum Master makes the decision by seeking

broad input from everyone including administration to thoroughly explore the

problem, and again gain consensus to make a well informed decision.

Become a Learning Organization

Often time in a software project there is not enough time to do things. In

the mad push to get things done, processes and code are written haphazardly on

the grounds that there is no time to do it the right way. Unfortunately what this

Page 68: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

58

also means is there is always time to do things the wrong way despite the fact

the project will result in a product full of defects with missed deadlines.

What this means is hansei is required to reflect on what is not done right

and what should be done to improve, as a learning experience. If a developer

does self reflection and realized the over all consequences of having time to do

things the wrong way, then they will realize what needs to be done and have

time to do things the right way to achieve a high quality product while meeting

deadlines, and learning to do things the correct way.

In software development, one should do more than a post mortem to

determine what went well, and what can be improved. Instead of waiting for an

iteration, or end of project to determine problems, this should be done throughout

the project. This is because each improvement will make the process better, and

speed up software development.

Most developers look at defects as inevitable, quality assurance will

always find defect. Developers should do as much as possible to eliminate

defects first before releasing to quality assurance such as writing the test case

first. When defects are found through quality assurance, the seven steps for

practical problem solving should be used to discover the root of the defect, and

fix it, fixing it in such a way that these kinds of defects will not be repeated in the

future.

Lean Scrum

When Takeuchi and Hirotaka (1986) wrote about Scrum for product

development in “The New Product Development Game”, of which Scrum for

Page 69: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

59

software development is based upon, they did not include Toyota in their study

amongst companies which they thought were successful in product development

(Schwaber & Beetle, 2002). Had they did that, Scrum for software development

may have included some of the principles of the applying the Toyota Way to

software development and Information Technology as stated in this Master’s

Essay to come up with a Lean Scrum.

Page 70: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

60

CHAPTER V

LEAN OPPORTUNITIES FOR INFORMATION TECHNOLOGY

In this chapter, we will take a glimpse of establishing customer defined

value of a Lean organization from the point of view of Information Technology.

This is what a Chief Engineer of Information Technology intending to create

software for Lean organizations must at least know as a minimum to look for

opportunities which arises when organizations decides to become Lean. This is

limited to the scope of the principles of the Toyota Way as defined in this

Master’s Essay.

For manufacturers, there are two camps, Lean, and information systems.

These two camps are opposite one of another, and they clash. In the Lean camp,

there is a disdain for information systems, seeing them as introducing

complications, and extraneous tasks; if the production process was good to begin

with, there would be no need for an information system. Instead, kanban can be

used as the information system. Having automations and computer systems

would drain resources from the organization’s core business, as a huge amount

of time can be spent fixing misbehaving robots, and information systems instead

of building the product. Computer based planning and control would overly

centralize manufacturing which is especially true for Material Resource Planning

systems, and Enterprise Resource Planning systems which would lead to a huge

disconnect from the reality of the plant floor with the computer generated

schedules and inventories (Piszczalski, n.d.). Practitioner of Lean values kaizen,

adaptability, fluid organic systems, and rejects a system which is designed,

Page 71: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

61

implemented, and then left alone. Lean requires each individual to search for

new ideas making improvements continuously and incrementally each minute of

each day. Information Technology, especially traditional Information Technology

is noted for rigidity, and does not bode well for Lean. Once Information

Technology is added, it is hard to take out, and becomes a technological

monument as far a Lean is concerned (Bell, 2006).

Even with the faults of Information Technology, most organizations,

especially a manufacturing plant, is a complex organization. Value streams are

becoming faster with more variables, global supply chains are more complex,

and capable, and customers are becoming more demanding (Bell, 2006). It is

only through computer systems could the organization manage itself. As a result,

Information Technology, and information systems will have to be integrated with

Lean, to create eLean or Lean Information Technology. If an organization is

unwilling to leverage Information Technology, it can find itself at a competitive

disadvantage (Piszczalski, n.d.) (Bell, 2006). From a manufacturing standpoint,

the two are trying to achieve the same end goal. Lean should be made the

foundation, with which computer systems layered on top to optimize Lean

(Piszczalski, n.d.). Information Technology can be used to add value and remove

waste, but if used improperly can institutionalize waste. If Information Technology

helps a Lean organization, then it is a useful tool, but the second it impedes,

becomes a crutch or a distraction, then it should be removed as waste (Bell,

2006)!

Page 72: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

62

Organizations choosing to become Lean usually hire Lean consultants to

make them become Lean. Lean consultants advocates getting rid of the

expensive inflexible legacy computer systems, favoring pencil and paper, and

spreadsheets for doing streamlined value added chains. For large complex

organizations, the solution does not scale, and as a result, there is a need for

Information Technology solutions to help organizations scale the Lean solutions.

One area where Information Technology may help is to have software which will

help manufacturing organizations load level production especially setting the

pacemaker process. Also in streamlining the value chain, Information Technology

solutions will be required for integrating manufacturing, and logistics. With

complex operations possibly separated by geographical distances, software is

required to integrate all the different processes to enable the pull of the different

parts of the product being manufactured so there is no waiting for parts,

especially when inventory is not to be kept. As software vendors recognize the

unique characteristics of a Lean organization, they become better at supplying

software which will aid the Lean organizations, thus allowing for the maturing of

Lean Information Technology software. There is a movement away from

Materials Requirements Planning business models to Lean oriented business

models, especially solutions which enables Lean value chains. Information

Technology solutions should be customer focused, help eliminate waste such as

excess inventory, and simplify the value streams and operations. In this way

Information Technology can gain acceptance in Lean organizations by being an

enabler of Lean (Aberdeen Group, 2004).

Page 73: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

63

Without automation, as Lean moves to the supply chain, it becomes more

difficult to orchestrate activities. Businesses are evolving to have integrated

companies which will serve the end customer, and not the intermediate

customer, creating a sort of virtual Enterprise. This makes supply chain very

important where the supply chain must not only integrate internally, but with

external organizations as well. Supply chain has to become more than point to

point interaction between organizations, but also being an information exchange

on the entire supply chain. From the context of Lean, supply chain management

entails the processes of product movement where value is gained and lost

(Aberdeen Group, 2006).

With Lean, supply chain has to pull, rather than push. In the execution of

the supply chain, the logistics are different such as there are more frequent

deliveries rather than one huge batch delivery. The elimination of large

warehouses means there is no need to retrieve, inspect, put away, store, and

retrieve process cycles. Supply chain event management requires business

processes for monitoring, notifying, simulating, controlling, and measurement.

These can be implemented independently of Enterprise Resource Planning

software applications, in a cost effective manner to allow enterprises examine

and measure Lean activities through the entire supply chain. This leads to

integration tools which will allow for the exchange of information in one usable

format (Aberdeen Group, 2006).

For supply chain intelligence, metrics must be tied to strategies,

objectives, and goals. All productivity measures which do not have a link to the

Page 74: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

64

extended enterprise should be removed. Within the Lean philosophy, metrics

needs to be based on value stream activities with the goal of customer

satisfaction (Aberdeen Group, 2006).

For best of breed manufacturing organizations adopting Lean, there is

heavy use of systems integrator professionals to enable technologies, and

extend Lean across the entire supply chain. Over time, Lean manufacturing

organizations should make these Lean experts internal, rather than rely on

external expertise (Aberdeen Group, 2006).

When Lean experts advise against the use of a particular systems such as

Materials Requirements Planning, they are not saying to stop using technology

but to stop using technology as a substitute for thinking! Only when the manual

process is perfected with no room for improvement should the process be

automated, but the automation has to prove itself to be better than the manual

process, and even then, the manual process is still in place in case the

information system goes down (Liker & Meier, 2006).

Software could also be created to aid in schedules and activities. Flow of

product and materials flow can be easily collected on the shop floor with the aid

of bar code, wireless technology, and electronic kanban. Software can help with

scheduling, inventory management, logistics, quality, and maintenance.

Dashboard review can compare performance between two different sites. More

important, enabling technology can support manufacture’s needs to adjust to

market demands, facilitating root cause analysis, corrective action, and a

Page 75: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

65

formalized processes for problem resolutions extending back to the supplier base

(Aberdeen Group, 2006).

Toyota has three information systems which will be of increasing

importance as follows:

1. Product Data Management – This is used to retrieve product information,

bring together functional components, and construct manufacturing

sequence tables.

2. Supply Chain Management – Used to arrange upstream and downstream

organizations in a chain and globally optimizes cost, quality, quantities,

and timing for all processes from sales outlet to suppliers, and does this

by leveling out flows.

3. Company Wide Information System – Toyota is very conservative on this,

preferring to see how other organizations uses it first. Toyota realizes it is

a competitive strength to do this and is currently rebuilding, and integrating

information systems throughout its company.

(Hino, 2006).

Kanban – Information Flow

Integration of Material Resource Planning systems with Just-In-Time

systems can improve manufacturing system efficiency. Information Technology

integration can facilitate the use of a pull system, both internal and external to the

organization, as it can transmit the order information through the entire supply

chain in a timely manner. Information Technology systems can reduce lot sizes.

Between firms Information Technology systems can improve lead time by having

Page 76: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

66

the customer information transmitted from customer service or help desk to the

production system in a timely manner (Ward & Honggeng, 2006).

Information Technology integration by itself is not as effective as using

Information Technology integration with Lean/Just-In-Time. In order for

Information Technology integration to be effective, the organization must have a

sound Lean/Just-In-Time system first. Lean/Just-In-Time can first provide the

standardization, and then Information Technology can then reduce the

uncertainty. For example, Toyota has spent many years perfecting its Lean/Just-

In-Time system, but it also recognizes the importance of Information Technology

to improve its performance, and as a result, implemented SAP (Ward &

Honggeng, 2006).

Global Production Centre

In July 2003, Toyota established the Global Production Center to train

shop floor experts. Part of this effort was to convert implicit knowledge into

explicit “standardized knowledge” using digital technology. As Toyota grows,

Toyota’s “mother plan” system of support for its overseas affiliates are stretched

to the limit supporting over fifty manufacturing sites in twenty six countries. The

Global Production Centre, located in Toyota City, Aichi Prefecture, Japan, is

used to train approximately eight hundred people per year drawing from two

hundred and thirty personnel from Toyota Plants. In addition to teaching skills,

the facility has V-comm which is an engineering technology allowing engineers in

Japan to work with engineers overseas (Toyota Motor Manufacturing Kentucky,

Inc., 2004).

Page 77: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

67

This came as a result of applying kaizen to the “mother plant” concept,

and found rooms for improvement, especially for overseas plants. This means

finding best practices from individual practices which were handed down person

to person. Digital technologies were used to compile these best practices into

visual manuals, keeping text to a minimum. Photos, animation, and video clips

were used to facilitate comprehension. Slow motion videos were used to

demonstrate to the student skills which a seasoned expert may do too fast. The

training is to provide a common base training which includes digital training along

with other hands on training, especially in concepts of Lean such as takt (Toyota

Motor Manufacturing Kentucky, Inc., 2004).

This center cuts training time in half (Toyota Motor Manufacturing

Kentucky, Inc., 2004).

Information Technology departs should similarly create a center to train

Information Technology workers for an organization. As part of this training,

implicit knowledge, and best practices should be digitized with photos, animation,

and video clips which can then be used to train the Information Technology

worker.

Andon

Andon is a sign used to indicate when something goes wrong (Liker

2004).

Andon can also used in Information Technology. For example, in doing

continuous build, when the application does not compile, or a test fails, then one

can use software such as Cruise Control to send emails to notify developers. In

Page 78: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

68

addition, lamps can be hooked up to show green for a successful build and test,

with a red lamp to show an unsuccessful build to show something is wrong

(Clark, 2004).

Check List

The check list which Toyota engineer uses, along with the book of what

went wrong computerized at Toyota, and maintained by the people who uses

them (Liker 2004).

Information Technology should also use check lists and record what went

wrong, and these too should be computerized with the owners of these items

updating them.

Lean and Simulation

Lean can be hard to learn. Ncube (2007) came up with the idea of using

games and simulations for experiential learning. The Experiential Learning Cycle

(ELC) consists of four parts as follows:

Experience – activity phase of activity and doing;

Process – What, sharing reactions and observations, patterns and

dynamics;

Generalize – So what, develop real world principles;

Application – Now what, planning effectively using what has been learned.

She went on to create the Lemonade Tycoon simulation game for the

developmental learning of Principles of the Lean Enterprise. The outcome of

using Lemonade to learn Lean concepts included problem solving, team

Page 79: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

69

development, and concept development, and has enhanced the learning of the

concepts of Lean. Good games allow students to make mistakes and learn from

their mistakes in a realistic environment, without suffering from the

consequences of real life.

Manufacturing Agent-Based Emulation System

Changing from traditional manufacturing approach to a Lean

manufacturing approach is a complex enterprise wide task. To ease the

transition, Ivezic, Potok, & Pouchard.(1999), came up with Manufacturing Agent-

Based Emulation System (MABES)., a distributed autonomous agent framework

is to emulate manufacturing allowing people to see the effects of the changes

before making the changes. It is an open framework to allow for the analysis and

design of manufacturing systems, enabling one to see the effects of

manufacturing approaches from traditional push to the Lean customer driven task

of pull systems with takt, minimizing inventory, and minimizing work-in-progress.

MABES have a collaborative interface to the design and analysis tool, and

can animate message passing among agents and display manufacturing-process

statistics for several metrics. This allows for the analysis of alternative scheduling

strategies such as push, pull, and takt, and the effects of special events such as

bottlenecks, and disruptions in production. From this, one can determine the

proper scheduling when converting to a Lean manufacturing approach (Ivezic et

al., 1999).

Clearly there are unique customer defined values for a Lean organization,

opportunities for Information Technology to provide services to.

Page 80: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

70

CHAPTER VI

LITERATURE SEARCH ON APPLYING LEAN TO SOFTWARE

DEVELOPMENT AND INFORMATION TECHNOLOGY

In this chapter we will be taking a look at the results of a literature search

conducted on where Lean has been applied to software development and

Information Technology to give an indication of the state of Lean in the software

industry. The literature search was conducted on IEEE journals online using the

key word of “Lean”, as well as on search engine “Google” with keywords

“Toyota”, “Lean Software Development”, and “Lean Information Technology”. The

definition of a successful Lean implementation is that it must cut cost, use fewer

resources or be more productive with the same resource, and have a higher

quality of service or software product. The result of the search is as follows:

Innovation in Software Development Process By Introducing Toyota Production

System

Fujitsu Software Technologies sought to improve their software

development processes following the Information Technology bubble burst of

2000 to stem profit decline. They tried some things like using Unified Modeling

Language, but these efforts did not improve productivity as much as they wanted,

so they decided to introduce the Toyota Production System along with Agile

Software Development into their software development process. Their reasoning

for this was because the Toyota Production System has proven itself in hardware

manufacturing. As a result, they decided to introduce Toyota Production System

Page 81: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

71

concepts of visual management, jidoka (automatic detection of defect), heijunka

(leveling), and the elimination of muda (waste) with Agile Software Development.

This was introduced experimentally to some divisions in 2003, and all divisions in

2004. By September of 2004, they have found their profits have stopped

declining, and began a slow process of recovery (Furugaki, Takagi, Sakata, &

Okayama, 2006).

Fujitsu Software Technologies used their own customized Agile Software

Development noting some aspects of Agile have the same concept as their

interpretation of the Toyota Production System. Acceptance tests were used to

create pull, customer prioritization was used to achieve Just-In-Time, use of

visual management, multi-skill development, and heijunka. Productivity was 24%

lower than company standard during the first iteration, and then improved to

26.6% in the last iteration (Furugaki et el., 2006).

For software maintenance, Fujitsu Software Technologies implemented

the following heijunka process using a store pull system for work execution,

workload management with a single queue, and control through visual

management. By using heijunka, they have found the overtime hours were

reduced with no one having to work during holidays like before, and productivity

improved by eighty percent in four months (Furugaki et el., 2006).

This is an indication of success as there is reduced cost of overtime, and

increased productivity along with an improvement of profits.

Page 82: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

72

Learning to Love Lean IT

In 2004, Acuity Brands got a new CEO with a mandate of making the

company Lean. Pat Quinn came on board as CIO responsible for providing

systems to enable changes in manufacturing. As he learned about the Lean tools

of removing waste, and kaizen, he realized Information Technology can benefit

from Lean as well. The people in Information Technology was at first skeptical,

seeing itself as creative, but Quinn sees a lot of waste in software development,

and sees a process framework which can reduce waste, and at the same time

does not stifle creativity (Overby, 2007).

The people in Information Technology began conducting kaizen events,

and saw potential efficiency and process improvement in software development,

and network management. This resulted in weaning the company of mainframes,

and transitioning the company to use VoIP, as well as improving application

development (Overby, 2007).

Acuity Brand is well on its way to being Lean along with the Information

Technology. The kaizen requires a lot of training, and heavy involvement by the

CIO. Quinn points out they are not their yet saying Toyota has been at it for forty

years, and still not there yet, as it is an ever evolving kaizen (Overby, 2007).

The reduction in cost of not using mainframes along with improved

application development means this company is successful in transitioning

Information Technology to Lean.

Page 83: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

73

Lean Software For The Lean Aircraft

Through the Lean Aircraft Initiative (LAI)., the U.S. Air force attempted to

spread the Lean paradigm to the aerospace industry by collecting lessons

learned from Lean production into a model called the Lean Enterprise Model

(LEM). The LEM consists of principles such as responsiveness to change;

minimization of waste; right thing at right place time, and quality; value streams,

kaizen, and quality (Sutton, 1996).

Lockheed Martin Aeronautical Systems (LMAS) has been evolving its

software practices for the last ten years to achieve high quality at a low cost.

Lean was applied to a specific Lean software project for the Lockheed

Martin Aeronautical Systems (LMAS) C-130J air lifter (Sutton, 1996).

For responsiveness to change, domain engineering is used to identify stable

repetitive structure of the problem and solution domain with the requirements,

and architecture structured along stable domain lines. Problems are divided into

sub-domains, to facilitate requirements engineering. The solution domain is

modeled such that repetitive elements are identified, generalized, and captured

with a Domain Specific Language Design (DSDL) with strict rules on how they

interact. This allowed for a “Lego” block approach to be used for component

construction and integration, and limits the scope of errors (Sutton, 1996).

Waste minimization is achieved through reuse, obtaining the maximum

benefit from all the work done in the program. Domain driven designed is

achieved through DSDL. A “Narrow-slice development” is used to develop a

narrow complete example of the next development phase’s product during the

Page 84: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

74

current phase which is then used to refine the current phase’s product and next

phase’s process (Sutton, 1996).

Quality Function Deployment is used to prioritize customer desires and

project needs to enable doing the right thing at the right place, time, and quality

(Sutton, 1996).

Quality is achieved through correctness by construction with formal

requirements. For each stage of development, formal methods are used to make

the product inherently correct as it is produced, or use formal verification after a

product is produced. All release integrations are tested in the target environment

(Sutton, 1996).

Through Lean practices, they have been able to repeatedly do a new

software build from requirements to completed qualification testing in forty-eight

hours, with the software changes working correctly most of the time the first time.

As a result, few errors were discovered during FAA rigors testing, with the

software metric below industry metrics for schedule and budget. The Lean

paradigm enabled them to produce a superior and safe product at low risk, and

cost (Sutton, 1996).

The high quality of the product along with the lower cost definitely makes

this a success story.

Introducing Lean Principles with Agile Practices at a Fortune 500 Company

Capital One is a Fortune 500 financial services company faced with the

challenges of decreasing operating costs, and to be the first in delivering

innovative product offerings to customers with a goal of doing so with a reduced

Page 85: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

75

timeframe to market. They did this by making a deliberate decision of applying

Lean Principles with Agile techniques (Parnell-Klabo, 2006).

Lean provided a framework to focus on delivering value to the customer.

Before they changed their process, they spent twelve weeks to define their

current processes, finding a wealth of quantitative and qualitative insights into

root causes of duration. A future value stream was created to show them where

to go to reduce this duration. Employing Lean principles, they found insights on

eliminating wastes, and used the “Five Whys” technique to do root cause

analysis, identifying processes for waste removal opportunities. These processes

were prioritized as to which one should be worked on first, moving quickly to

remove non value added tasks, and reducing handoffs (Parnell-Klabo, 2006).

At the same time, they explored Agile noting the fact average Information

Technology projects spend only 10% of the actually doing software development.

More importantly, they discovered their current processes do not support agile

development. They had attempted Extreme Programming before, but have to

abandon it. On the second time around, they have discovered Scrum

methodology to use as a guide (Parnell-Klabo, 2006).

To introduce Lean and Scrum, they selected a pilot project which is

representative of their current projects. The pilot became a learning experience

for both performers and stake holders. Success measures were defined including

decrease duration, no cost increase, decrease effort, no degradation in quality.

The outcome of this pilot shows a 40% decrease in duration compared with the

waterfall method, and coming 10% under the allocated budget with no

Page 86: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

76

degradation in the quality of code. Furthermore, a targeted survey show an

increase morale by the performers, with other water fall projects wanting to be

next project to use Lean and Scrum, as well as positive endorsements from the

customer (Parnell-Klabo, 2006).

After the switch to using Lean and Scrum approach, projects were

delivered 40% to 50% faster than the waterfall approach with 10% to 17% under

budget. The ruling hypothesis is to start with the Lean tools first, applying Lean

principles, and then apply the agile techniques (Parnell-Klabo, 2006).

The decrease in duration with no increase in cost, decrease effort with no

degradation in quality means Capital One successfully achieved its Lean

Information Technology objectives.

Scrum and CMMI Level 5 : The Magic Potion for Code Warriors

Systematic is a company which has already a CMMI Level 5 practice, but

still wanted to do better, and decided to adopt Lean for future improvements

(Sutherland, Carsten, & Johnson, Kent, 2007).

Lean competencies were established through training and process were

identified and prioritized for using Lean. Pilot projects were created to use. The

results of the pilots confirmed the Lean mindset is a good way to identify

improvements, and that Scrum with story-based early testing can be adopted

while still maintaining CMMI Level 5. The pilot projects showed significant gains

in productivity and quality over traditional methods. Every category of work was

found to be reduced by almost 50% (Sutherland et al., 2007).

Page 87: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

77

Systematic concluded CMMI and Scrum can result in significant

improvements while maintaining CMMI compliance. Lean Software Development

can be used as an operational tool to identify opportunities for improvement

within a CMMI 5 company (Sutherland et al., 2007).

The significant gain in productivity along with reduced work without

affecting CMMI compliance clearly shows Lean in Information Technology is

successful here.

Summary of Literature Search on Applying Lean to Software Development and

Information Technology

The literature search on applying Lean to Software Development and

Information Technology did not turn up a huge number of hits. This is not

surprising considering the fact Lean is still a very new concept in many

organizations outside of Japan, let alone be used in software development and

Information Technology. Of the small sample set of results returned, they all

implemented some aspects of the Toyota Way, but not all of it. More importantly,

they all indicated positive feed back on the use of Lean in either software

development, or Information Technology based on the criteria of cutting cost,

using fewer resources or be more productive with the same resource, and having

a higher quality of service or software product. This is not a definitive affirmation

of applying the Lean Toyota Way to software development and Information

Technology, but it does say this is the right direction to go.

Page 88: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

78

CHAPTER VII

CONCLUSIONS AND RECOMMENDATIONS

Conclusions

A background of Toyota and Lean is given to show why we should borrow

from Toyota to improve the software industry.

The Lean principles of the Toyota Way are given, as they are basically the

cornerstone to Toyota’s success and what it truly means to be Lean. These

principles are then applied to software development and Information Technology

to come up with a new Lean way of doing software development and Information

Technology in an effort to solve the problems encountered in the software

industry.

Also with organizations becoming Lean there are Lean customer defined

values for Information Technology to be aware of. The Lean customer defined

values represent new opportunities which Information Technology must be aware

of to provide services for the Lean organization.

Through a literature search, there is really not much material found on

using Lean within the software industry making the sample size too small to

make any definitive conclusion. Of those which were found and illustrated in this

Master’s Essay, they achieved successes in applying some aspects of Lean to

software development and Information Technology. Success is defined as cutting

cost, using fewer resources or be more productive with the same resource, and

having a higher quality of service or software product, This is not enough to

Page 89: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

79

indicate if the proposal given in this Master’s Essay would be successful, but it

does give an indication this is the right direction to go.

Recommendations

With the success of Toyota through its use of Lean, and the formula given

in this Master’s Essay for applying Toyota’s Lean principles to software

development and Information Technology, as well as some successes of Lean in

the software industry as found through a literature search, organizations should

adopt Lean in their software development and Information Technology.

As well, Information Technology should also take advantage of the

opportunities which exists when organizations decides to become Lean.

Suggestions for Further Research

Find a software development or Information Technology organizations

which has adopted Lean, and to see how they compare with those software

development or Information Technology organizations which has not adopted

Lean. Do Lean in software development and Information Technology

organizations have the same kind of success as Toyota? One such company to

investigate is Google.

If one cannot find a Lean Information Technology organization, perhaps

an experiment can be done where one creates such an organization, operating

on the Lean Toyota Way principles. This would ultimately show if Lean has the

same kind of successes when applied to software development and Information

Technology.

Page 90: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

80

REFERENCES

Aberdeen Group (2004, June). The Lean Strategies Benchmark Report.

Manufacturing Excellence Moves to the Value Chain.

Retrieved January 8, 2008 from

http://www.lean.org/Community/Registered/ArticleDocuments/LeanStrateg

iesReport.pdf

Aberdeen Group (2006, September). The Lean Supply Chain Report

Lean Concepts Transcend Manufacturing through the Supply Chain.

Retrieved January 8, 2008 from

http://www.lean.org/Community/Registered/ArticleDocuments/Aberdeen_L

eanSC_MB_3450.pdf

Akao, Yoji (Eds.). (1990). Quality Function Deployment.

Integrating Customer Requirements into Product Design.

(Mazur, Glenn H., Trans.).

New York: Productivity Press (Original work published 1988).

Bell, Steve (2006). Lean Enterprise Systems

Using IT for Continuous Improvement

Hoboken, NJ: John Wiley & Sons.

CBC. News (2008, January 23). No. 1 automaker? Too close to call

Retrieved January 23 from

http://www.cbc.ca/money/story/2008/01/23/gm-toyota.html

Clark, Mike (2004). Pragmatic Project Automation

How to Build, Deploy, and Monitor Java Applications

Page 91: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

81

Raleigh, North Carolina: The Pragmatic Programmers, LLC.

Cunningham, Jean E., Fiume, Orest J (2003). Real Numbers

Management Account in a Lean Organization.

Durham, NC: Managing Times Press.

Furugaki, Koichi., Takagi, Tooru., Sakata, Akinori., & Okayama, Daisuke (2006).

Innovation in Software Development Process

by Introducing Toyota Production System.

FUJITSU Sci. Tech J. January 2007, 139-150.

Retrieved January 8, 2008 from

http://www.fujitsu.com/downloads/MAG/vol43-1/paper16.pdf

Hino, Satoshi (2006). Inside the Mind of Toyota

Management Principles for Enduring Growth (Dillon, Andrew P. Trans.).

New York: Productivity Press (Original work published 2002).

Imai, Masaaki (1986). KAIZEN The Key to Japan’s Competitive Success.

New York: McGraw-Hill.

Ivezic, Nenad., Potok, Thomas E., & Pouchard, Line (1999).

Multiagent Framework for Lean Manufacturing

IEEE Internet Computing, September October 1999, 58-59

Retrieve January 17, 2008 from

http://0-

ieeexplore.ieee.org.aupac.lib.athabascau.ca/iel5/4236/17230/00793459.p

df?tp=&arnumber=793459&isnumber=17230

Jones, Dan., & Womack, Jim (2003). Seeing the Whole

Page 92: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

82

mapping the extended value stream.

Cambridge MA: Lean Enterprise Institute.

Kennedy, Michael N (2003). Product Development for the Lean Enterprise.

Richmond, Virginia: The Oaklea Press.

Leach, Lawrence P (2005). Lean Project Management:

Eight Principles for Success.

Boise, Idaho: Advanced Projects Inc.

Liker, Jeffrey K (2004). The Toyota Way.

New York: McGraw-Hill.

Liker, Jeffrey K., & Meier, David P (2007). The Toyota Talent

Developing Your People The Toyota Way.

New York: McGraw-Hill.

Liker, Jeffrey K., & Meier, David P (2004). The Toyota Way Fieldbook

A Practical Guide For Implementing Toyota’s 4Ps.

New York: McGraw-Hill.

Marchwinski, Chet., Shook, John (Eds.). (2006). Lean Lexicon

A graphical glossary for Lean Thinkers (3rd ed).

Cambridge, MA: Lean Enterprise Institute.

Middleton, Peter. & Sutton, James (2005). Lean Software Strategies

– Proven Techniques for Managers and Developers

New York: Productivity Press

Morgan, James M., & Liker, Jeffrey K (2006).

The Toyota Product Development System

Page 93: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

83

Integrating People, Process, and Technology.

New York: Productivity Press.

Ncube, Lisa B (2007). Exploring the application of experiential learning in

developing technology and engineering concepts:

The Lean Lemonade Tycoon

37th ASEE/IEEE Frontiers in Education Conference.

2007 IEEE, F1J-5 – F1J-10.

Retrieved January 17, 2008 from

http://0-

ieeexplore.ieee.org.aupac.lib.athabascau.ca/iel5/4417794/4417795/04418

021.pdf?tp=&arnumber=4418021&isnumber=4417795

Ohno, Taiichi (1988). Toyota Production System (Dillon, Andrew P. Trans.).

New York: Productivity Press (Original work published 1978).

Overby, Stephanie (2007). Learning to Love Lean IT.

Retrieved January 8, 2008 from

http://www.cio.com/article/106900/Learning_to_Love_Lean_IT

Parnell-Klabo, Emmal (2006). Introducing Lean Principles with Agile Practices at

a Fortune 500 Company.

Proceedings of AGILE 2006 Conference (AGILE’06).

IEEE COMPUTER SOCIETY

Retrieved January 17, 2008 from

Page 94: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

84

http://0-

ieeexplore.ieee.org.aupac.lib.athabascau.ca/iel5/11054/34909/01667584.

pdf?tp=&arnumber=1667584&isnumber=34909

Piszczalski, Martin (n.d.). Lean vs. Information Systems.

Sextant Research

Retrieved January 8, 2008 from

http://www.autofieldguide.com/columns/0800it.html

Poppendieck, Mary., & Poppendieck, Tom (2007).

Implementing Lean Software Development From Concept to Cash.

Upper Saddle River, NJ: Addison Wesley.

Poppendieck, Mary., & Poppendieck, Tom (2003).

Lean Software Development An Agile Toolkit.

Upper Saddle River NJ: Addison Wesley.

Rother, Mike., & Shook, John (2003). Learning to See

Value-Stream Mapping to Create Value and Eliminate Muda.

Cambridge MA: Lean Enterprise Institute.

Rother, Mike., & Harris, Rick (2001). Creating Continuous Flow

an action guide for manager, engineers & production associates.

Cambridge MA: Lean Enterprise Institute.

Schach, Stephen R., (2005). Object-Oriented & Classical Software Engineering

(6th ed).

New York: McGraw-Hill

Schwaber, Ken., & Beedle, Mike (2002).

Page 95: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

85

Agile Software Development with Scrum.

Upper Saddle River NJ: Prentice Hall.

Shingo, Shigeo (1989). A Study of the Toyota Production System.

(Dillion, Andrew P. Trans.). New York: Productivity Press.

(Original work published 1981).

Stephens, Matt., & Rosenberg, Doug (2003). Extreme Programming Refactored:

The Case Against XP.

New York: Apress.

Sutherland, Jeff., Jakobsen, Carsten Ruseng., & Johnson, Kent (2007).

Scrum and CMMI Level 5: The Magic Potion for Code Warriors

Agile 2007.

IEEE COMPUTER SOCIETY

Retrieved January 17, 2008 from

http://0-

ieeexplore.ieee.org.aupac.lib.athabascau.ca/iel5/4293562/4293563/04293

608.pdf?tp=&arnumber=4293608&isnumber=4293563

Sutton, James M. Sutton (1996).

Lean Software Development For The Lean Aircraft

IEEE 1996, 49-54.

Retrieved January 17, 2008 from

http://0-

ieeexplore.ieee.org.aupac.lib.athabascau.ca/iel3/4139/12182/00559134.p

df?tp=&arnumber=559134&isnumber=12182

Page 96: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

86

Takeuchi, Hirotaka., & Nonaka, Ikujiro (1986).

The New Product Development Game

Harvard Business Review, January – February 1986, 1-12.

Retrieved November 18, 2007 from

http://apln-richmond.pbwiki.com/f/New+New+Prod+Devel+Game.pdf

The Standish Group (1995). The Standish Group Report Chaos

Chaos Report, 1-8.

Retrieved November 2, 2007 from

http://www.projectsmart.co.uk/docs/chaos-report.pdf

Toyota Motor Manufacturing Kentucky, Inc (2004).

New Facility Efficiently Trains Experts to Support Toyota’s Expanding

Scale of Global Manufacturing

Retrieved January 6, 2008 from

http://www.toyotageorgetown.com/gpc.asp

Toyota Production System (n.d.). Toyota Production System

Retrieved December 8, 2007 from

http://www.toyota.co.jp/en/vision/production_system/index.html

Ward, Allen C (2007). Lean Product and Process Development.

Cambridge MA: Lean Enterprise Institute.

Ward, Peter., Honggeng, Zhou (2006). Impact of Information Technology

Integration and Lean/Just-In-Time Practices on Lead-Time Performances

Decision Sciences 37(2)., 177-203.

Retrieved December 8, 2007 from

Page 97: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

87

http://www.google.com/search?as_q=Impact+of+Information+Technology

+Integration+and+Lean%2FJust-In-Time+Practices+on+Lead-

Time+Performances&hl=en&num=100&btnG=Google+Search&as_epq=&

as_oq=&as_eq=&lr=&cr=&as_ft=i&as_filetype=&as_qdr=all&as_nlo=&as_

nhi=&as_occt=any&as_dt=i&as_sitesearch=&as_rights=&safe=images

Womak, James P., & Jones, Daniel T., Roos, Daniel (2003). Lean Thinking.

New York: Free Press.

Womak, James P., & Jones, Daniel T., Roos, Daniel (1990).

The Machine That Changed the World.

New York: Free Press.

Page 98: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

88

APPENDIX A ~ GLOSSARY

andon – A Japanese term for lamp. It is a visual management tool for highlighting

the status of operations in an area in a single glance. It signals red whenever an

abnormality occurs, but can also indicate production status in terms of units

planned versus actual units processed. Problems can be tripped by an

automated error detection device or a worker pulling a cord or pushes a button,

signaling a quick response is required by the team leader (Marchwinski & Shook,

2006).

autonomation - Automation with a human touch, not to be confused with

automation. It means an automated machine can shut itself off autonomously

when it detects an error (Ohno, 1988).

Genchi Genbutsu – A Japanese term for go and see, but translated as actual

place and actual thing. It is the Toyota practice of personal observation at the

source of the condition to confirm information or data. For example, a decision

maker including executives, and managers, will go to the shop floor personally to

investigate a problem instead of relying solely on information from others or

computer data (Marchwinski & Shook, 2006).

hansei – A Japanese term for reflection. It is the practice of looking back at

oneself to determine shortcomings which can be improved, and the same applies

for processes. Hansei meetings is typically conducted at Toyota during

Page 99: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

89

milestones and end of project to identify problems along with countermeasures to

the problems, and these are communicated to the rest of the organization as

improvements so the same mistakes are not made over and over again. It is also

the check, of the Plan, Do, Check, and Action cycle (Marchwinski & Shook,

2006).

heijunka – A Japanese term for leveling. Over a fixed period of time, it is

important to level the type, and quantity of production. It is important to efficiently

meet customer demands while at the same time avoid batching to minimize

inventories, costs, manpower, and lead time through the whole value stream.

One way of doing this is to level the production (Marchwinski & Shook, 2006).

hetakuso-sekke – A small book used at Toyota containing failures in the pass as

a reminder of what to avoid (Morgan & Liker, 2006).

hoshin kanri – A Japanese term for shining metal, pointing directions, policy

deployment, and policy planning (Middleton & Sutton, 2005). A management

process to align both vertical and horizontal functions and activities with strategic

objectives. It is a specific plan to develop measures, responsibilities, timelines,

actions and goals (Marchwinski & Shook, 2006).

ijiwaru – Testing to the point of failure (Morgan & Liker, 2006).

Page 100: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

90

jidoka - Provide operators and machines the ability to stop work immediately

when an abnormal condition has occurred to allow for fixing the problem, and

thus build in quality. It is one of the two pillars of the Toyota Production System

along with just-in-time (Marchwinski & Shook, 2006).

kaizen – Continuous improvement (Marchwinski & Shook, 2006).

kanban – A Japanese term for sign or signboard. It is a signaling device which

gives instruction and authorization for the withdrawal or production of items in a

pull system (Marchwinski & Shook, 2006).

kentou - The idea proposal stage of a designing a new vehicle at Toyota (Morgan

& Liker, 2006).

kozokeikaku – Phase of designing a new vehicle at Toyota where all the pieces

are pulled together which is basically the requirement of the vehicle, and the

body execution plan (Morgan & Liker, 2006).

muda – An activity which does not create value to the customer, but consumers

resources. There are two kinds of muda. Type one muda are non-value activities

which cannot be removed immediately, and type two muda which can be easily

be removed through kaizen (Marchwinski & Shook, 2006).

Page 101: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

91

mura– Unevenness, an operation which is uneven. It can be eliminated by having

a level schedule, and a good paste of work (Marchwinski & Shook, 2006).

muri - Overburdening of operators and equipment, running them harder or higher

pace with more force and effort for a longer time than what workforce

management will allow or what the equipment is designed for (Marchwinski &

Shook, 2006).

nemawashi – A Japanese term for preparing the ground for planting. It is the

process of gaining pre-approval, acceptance, and consensus on a proposal. This

is done by first evaluating the idea, and secondly by planning with stakeholders

and management getting their input, anticipating resistance, and aligning

proposal with the organization’s perspective and priorities. The formal approval

comes in a formal meeting, but by that time, it is a mere formality (Marchwinski &

Shook, 2006).

ninjutsu - the art of invisibility (Ohno, 1988).

obeya – A Japanese term for big room. It is a major project management tool at

Toyota to coordinate effective timely communication used especially in product

development to ensure product success. The room contains highly visual graphs

and charts indicating the progress to date, timing, and milestones, with

Page 102: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

92

countermeasures for technical problems and timing. It is a shorten version of the

Plan, Do, Check, Act Cycle (Marchwinski & Shook, 2006).

Ohno, Taiichi – Toyota executive widely credited for the Toyota Production

System (Marchwinski & Shook, 2006).

poka-yoke – error proofing, mistake proofing and baka-yoke for fool proofing. It is

a way to avoid mistakes in a process. For example, in a production line, parts

may have a certain shape to prevent installing parts with the wrong orientation,

photo cells above parts container preventing the movement to next stage if

operator’s hand did not break the light in obtaining the necessary parts

(Marchwinski & Shook, 2006).

seiketsu – standardization; standardize the maintaining of cleanliness

(Marchwinski & Shook, 2006).

seiso – cleanliness; wash and clean, everyone must clean the workplace

(Marchwinski & Shook, 2006).

seiton orderliness; after seiri, properly place everything in its proper order for

quick retrieval and storage. There is a place for everything, and everything has

its place (Marchwinski & Shook, 2006).

Page 103: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

93

sensei – Japanese term for teacher. In Lean thinking, it is someone who has a

master level of Lean knowledge with many years of experience in Lean and

knows how to transform the work place to Lean. The role is very similar to the

sensei in martial arts such as in karate (Marchwinski & Shook, 2006).

senzu – Stamping of engineering drawings where each stamped component

have a three view drawing with all special information placed in the relevant

places (Liker, 2004).

seiri – tidiness; separate needed items from unneeded, and discard the

unneeded (Marchwinski & Shook, 2006).

Shingo, Shigeo – Consultant to Toyota who made key contributions to the Toyota

Production System such as the Single Minute Exchange of Die (SMED) for quick

change over of manufacturing different products on a production line

(Marchwinski & Shook, 2006).

shitsuke – commitment; discipline to practice the Five S’s daily as a way of life

(Marchwinski & Shook, 2006).

shusha – chief engineer (Liker, 2004).

Page 104: ATHABASCA UNIVERSITY LEAN SOFTWARE DEVELOPMENT …dtpr.lib.athabascau.ca/action/download.php?filename=scis... · 2020-07-22 · ii ABSTRACT The software industry is plagued with many

94

takt – German word for a precise interval of time such as a musical meter on a

metronome. It is the rate of customer demand, the rate at which customers are

buying products. It is the interval to move a product ahead to the next production

station (Liker, 2004) (Marchwinski & Shook, 2006).

technik – German for superior technology as a means for market success