australia – japan cable
DESCRIPTION
The Australia-Japan Cable company. The project is almost on completion & is successful.TRANSCRIPT
![Page 1: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/1.jpg)
Presented by:-Rohit Jain
Shally Rathi
![Page 2: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/2.jpg)
Overview
12,500km cable from Sydney
Australia to Japan via Guam at a cost of $520m
Key sponsors: Japan Telecom, Telstra and Teleglobe. Asset life of 15 years
Potential Sponsor: AT&T , NTT, MCI WorldCom
A Joint Feasibility study was carried out for the sponsors
![Page 3: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/3.jpg)
![Page 4: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/4.jpg)
Submarine Cable Industry
![Page 5: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/5.jpg)
Submarine Cable Technology
![Page 6: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/6.jpg)
![Page 7: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/7.jpg)
Demand for Submarine Cable Systems
From 1990 to 1999, the global telecommunications market grew at a compound annual rate of 10.2%
US$348 billion to US$835 billion In the late 1990’s the demand grew & faster
growth in capacity caused prices to fall at a rate of 20% to 40% per year
Ovum predicted that the cost of an STM had fallen from US$10 million in 1998 to US$5 million by the end of 1999, would be US$1 million by 2003
As a result, system owners faced front-loaded revenue & cash flow streams.
![Page 8: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/8.jpg)
Financing
![Page 9: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/9.jpg)
Reasons – Club Financing
Expensive
Slow & predictable growth in demand
Limit their exposure
![Page 10: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/10.jpg)
Private Carrier Deal Structure Larger blocks of capacity Quicker execution Competitive Market prices below their costs First Deal:-Cable & Wireless and WorldCom(1995)
Gemini – 20 Gbit/s (US & UK)
![Page 11: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/11.jpg)
Private Non-carrier Deal
Ownership of cable systems to non – carriers such as private investors
In 1996, the Pacific Group, a private investment firm completed the first private no carrier deal to raise equity to build Atlantic Crossing-1 (AC-1)
![Page 12: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/12.jpg)
Building Submarine Cable Systems First, system owners needed to
choose equipment suppliers and sign supply contracts
Second, system owners hired cable ships to install the cable and repeaters as the cable ship industry was highly concentrated
“Landing Party Agreements” – a contract to use preexisting stations
![Page 13: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/13.jpg)
Australian Submarine Cable Industry 1999 – 3 Australian Traffic Cables
1.SEA-ME-WE32.PacRim East & West3.Telecom Corporation of New
Zealand, Cable & Wireless of Australia, and MCI WorldCom of United States
![Page 14: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/14.jpg)
Southern Cross Cable Network US$1.2 billion cable network
29,600 km loop configuration system
Linking east coast of Australia, New Zealand & United States
Merrill Lynch analysts conducted an independent analysis of the project
![Page 15: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/15.jpg)
The Australia Japan Cable (AJC) Telstra - leading telecommunication
and information services company
International transmission infrastructure included both satellite and submarine cable transmission
Major submarine cable investment- SEA-ME-WE3, China-U.S. cable and Japan-U.S. cable
![Page 16: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/16.jpg)
PHILOSOPHY
“Sell shore to shore service on a wholesale basis and AJC should be producer of basic capacity services with wholesale and retail sellers between AJC and the end users”
![Page 17: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/17.jpg)
Execution Process of AJC Telstra commissioned $6 million feasibility
study in mid-1997 for AJC through Guam
Reasons to go through Guam:-1) More efficient to surface and repower the
signal than send it all the way to Japan2) It could connect with other cables running
through Guam
Use of Collapsed Ring Configuration
![Page 18: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/18.jpg)
Australia Japan Cable (AJC) System would use Telstra’s 2 landing stations near
Sydney
In Guam, the project could contract with AT&T to use landing stations
Telstra envisioned private carrier deal using project finance structure to fund construction
Telstra engaged ABN AMRO to advise on financing strategy
Brian Tellam, director of project finance at ABN AMRO, believed project could support highly leveraged capital structure
![Page 19: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/19.jpg)
Funding:-
![Page 20: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/20.jpg)
Risk’s - AJC
Market risk due to presence of number of competitors.
Completion delay due to environmental approvals and other permissions
Physical construction was not a big deal
![Page 21: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/21.jpg)
Debt Tranches
Telstra envisioned 2 debt tranches:-
1) Tranche A- secured and repaid (within 5 years) with pre sale commitment
2) Tranche B- repaid from future sales of capacity to other parties (within 5 years)
![Page 22: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/22.jpg)
Contd..
Findings of feasibility study :-1)There was more than sufficient
capacity demand2)Expected cash flow could support
highly leveraged capital structure
Japan telecom and Teleglobe agreed to sign MOU with Telstra
![Page 23: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/23.jpg)
Structuring The Project Company
![Page 24: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/24.jpg)
Project Governance
![Page 25: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/25.jpg)
Key Issues:-
Limited growth potential
Market risk from fast changing telecom market
Risk from project delay
Specialized use asset
![Page 26: Australia – Japan Cable](https://reader031.vdocuments.net/reader031/viewer/2022012308/5468da92af7959c23c8b5bfc/html5/thumbnails/26.jpg)
Current Updates