awips ii status update nws staff meeting november 30, 2010

17
AWIPS II Status Update NWS Staff Meeting November 30, 2010

Upload: skyler-kern

Post on 15-Dec-2015

221 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: AWIPS II Status Update NWS Staff Meeting November 30, 2010

AWIPS II Status Update

NWS Staff Meeting

November 30, 2010

Page 2: AWIPS II Status Update NWS Staff Meeting November 30, 2010

2

Events Since Last CB Brief

• Sep. 23 - CB Brief• Oct. 18 - DUS Brief

– Approved re-baselined schedule• Commitment to No-Later-Than Q1 FY12 deployment• NWS Target: Deployment Start Q4 FY11

• Oct. 18 –> 22 – Forecaster Initial Testing (FIT) #14– Localized to Salt Lake City

• Oct. 27 – Don Berchoff sponsored telco with RD’s on AWIPS II & local apps

• Oct. 29 – Commerce IT Review Board (CITRB) Brief– New schedule formally briefed and accepted

• Closely watching progress • Status update due in March ‘11

• DR’s down almost 500 – 932 Open impact 1-3’s as of 11/19 v.s. 1428 on Sep. 23

Page 3: AWIPS II Status Update NWS Staff Meeting November 30, 2010

3

Actions Status Update

# Action Source Status Notes

1 Enlist RD support to mobilize Local Applications team to identify and eliminate Local Application duplications; and develop a strategy to fence off critical field personnel

CB 9/23

In Progress

Results of scrub presented in this brief. Going well right now. Will keep watch on need to fence off resources

2 Schedule monthly AWIPS II telecon for OST/D with RDs; one week following each FIT

CB 9/23

Closed First one held Oct. 27

3 Arrange a meeting with Dave Caldwell to brief him on Field OT&E and early deployment strategy

CB 9/23

Closed Meeting held

4 Determine whether NCEP Centers can constitute an "official deployment" site

CB 9/23

Closed OBE due to re-baselined schedule there is no need

5 Determine if Honolulu WFO, due to ties with NAWIPS, could be considered an early deployment site (RD looking into prospect)

RD Telco

10/27

Closed OBE due to re-baselined schedule there is no need

6 Investigate and report on possible solutions to Pacific Region regarding feasibility of getting live data to their ADAM platforms

RD Telco

10/27

Closed Investigations have occurred, testing planned. Raytheon will report test results by Dec. 3

7 Investigate and report on possible solutions to Alaska Region regarding feasibility of getting live data to their ADAM platforms

RD Telco

10/27

Closed Same as #6

8 Provide answer to Pacific Region as to how and when they are going to get access to the MCIDAS/MTSAT data via satellite

RD Telco

10/27

Closed NCO has developed an AWIPS II plugin. Will turn over to Raytheon for inclusion in initial deployment. Earliest date for deployment to PR would be Field OT&E (June-Sep. ’11)

Page 4: AWIPS II Status Update NWS Staff Meeting November 30, 2010

4

Overview

• AWIPS II steadily improving• Raytheon DR fixing productivity increasing

– Avg. 110 fixes per week over last three weeks– 4 weeks of schedule margin

• Regions scrub of local apps reduced critical list by 324 (19%)– 5 critical remaining to complete for entry into Phase II of System OT&E– Currently, no blocking DR’s

• Training still a risk– Application Focal Point modules are the biggest challenge

• Acceptable drafts by April 15, for Field OT&E• New approach for FFMP expected to show success in December

– Small team of focused experts for each module» Focus on differences between AWIPS I and AWIPS II» Training Division staff to provide training development technique, mission

oriented focus and AWIPS I expertise» Raytheon to provide targeted AWIPS II expertise from individual developers

on an application by application basis– Use as model for remaining modules

• Next FIT (Dec 6 17) is critical for entrance into Phase II of System OT&E – Testing service backup– Testing fully localized RFC– Stability

• 12 day stability assessment• No more than 15 minutes total of system downtime

– WarnGen performance key

Page 5: AWIPS II Status Update NWS Staff Meeting November 30, 2010

5

DR Progress TrackingOpen Planned v.s. Actual (11/19/10)

5

Impact 1 --> 3 Open DR's

932

12011113

0

500

1000

1500

2000

2500

3000

11-M

ay

21-M

ay

4-Ju

n

18-J

un2-

Jul

16-J

ul

30-J

ul

13-A

ug

27-A

ug

10-S

ep

24-S

ep8-

Oct

22-O

ct

5-Nov

19-N

ov

3-Dec

17-D

ec

31-D

ec

14-J

an

28-J

an

11-F

eb

25-F

eb

11-M

ar

25-M

ar

8-Apr

22-A

pr

6-May

20-M

ay

3-Ju

n

17-J

un1-

Jul

15-J

ul

29-J

ul

Actual

Acceptable Upper Control Limit

Planned

# o

f O

pe

n D

R’s

• 104 net DR decrease, (v.s. 44 planned)

3 wk. rolling avg. = 104 (decrease) • 2.69 DR’s per person per week, for current wk.

– 2.46 wk. ending 11/12, 3.28 wk. ending 11/05• Raytheon staff: 39 (unchanged from wk. ending 6/28)• 105 DR’s fixed last week. Avg. 110/wk, last 3 wks.

– 96 wk. ending 11/12, 128 wk. ending 11/5

Actuals as of (11/19/10)

• 0% rework rate (0 failed DR’s out of 11 tested)– 9% wk. ending 11/12 28% wk. ending 11/5

• 22 DR’s Discovered last week Avg. 27/wk, last 3 wks

– 13 DRs wk ending 11/12, 47 DRs wk. ending 11/05

FIT TestsSystem OT&E Test Periods

Page 6: AWIPS II Status Update NWS Staff Meeting November 30, 2010

66

Local Applications Remaining to Migrate

24

3

5

0

5

10

15

20

25

30

5/1/10 6/1/10 7/1/10 8/1/10 9/1/10 10/1/10 11/1/10 12/1/10 1/1/11

Planned Migration Rate Per Month

# of

app

s Planned

Actual

Local ApplicationsBefore System OT&E Phase II

Start Phase IISystem OT&E

Page 7: AWIPS II Status Update NWS Staff Meeting November 30, 2010

77

Local Application Migration Status5 Remaining Critical Local Apps

Application Migration Lead

Migr. Tech. Expert

Office Status Issues and Concerns

ClimoPoP Dave Myrick John Olsen WRH In Progress Proposed Completion Date 12/17/2010

erhLAPS Joshua Watson

N/A ERH In Progress Should be only minor changes. Verify in Dec ReleaseProposed Completion Date 12/15/2010.

Meet-Me Notification John Lague Wufeng Zhou

KRF In Progress 75% complete. Outstanding Alert Vis DR. Proposed Completion Date 12/15/2010.

qpfHelper Ken Pomeroy Tom McGuire

WRH In Progress Proposed Completion Date 12/17/2010

CopyFromModelISC Tom Lefebrve Tom McGuire

GSD Testing Blocked

Need to populate the ISC database with grids. Will be addressed in Nov TIM.  Proposed Completion Date 12/30/2010.

Page 8: AWIPS II Status Update NWS Staff Meeting November 30, 2010

88

Local Applications Remaining to Migrate

396

577

66

579

514

0100

200300400500

600700

9/2/10 10/2/10 11/2/10 12/2/10 1/2/11 2/2/11 3/2/11 4/2/11 5/2/11 6/2/11

Planned Migration Rate Per Month

# of

app

s Planned

Actual

Start FieldOT&E

Local ApplicationsBefore Field OT&E

Start Phase IISystem OT&E

Regional Inventory Review

Page 9: AWIPS II Status Update NWS Staff Meeting November 30, 2010

99

Local Applications Remaining to Migrate

764

172417331748

1727

1423

0

500

1000

1500

2000

5/5/10 6/5/10 7/5/10 8/5/10 9/5/10 10/5/10 11/5/10 12/5/10 1/5/11 2/5/11 3/5/11 4/5/11 5/5/11 6/5/11 7/5/11 8/5/11 9/5/11 10/5/11

Planned Migration Rate Per Month

# of

app

s Planned

Actual

Start FieldOT&E

Start Deployment

Local ApplicationsBefore Deployment

Start Phase IISystem OT&E

Regional Inventory Review

Page 10: AWIPS II Status Update NWS Staff Meeting November 30, 2010

10

Training Progress

Percent Training Modules Complete as of 11/22/10

0

0

0

10

0

0

20

30

80

WFO Hydro Apps

RFC Apps

GFE

Decision Assistance Tools

General CAVE

AvnFPS

WarnGen

System Administration Residence Training

User Training

Actual

Ap

pli

cati

on

Fo

cal

Po

int

Tra

inin

g

Target: Acceptable Drafts of All Modules Complete by April 15, 2011

Page 11: AWIPS II Status Update NWS Staff Meeting November 30, 2010

11

AWIPS II Schedule

Phase Description Start Finish

1 System OT&E Phase I 5/10/2010 1/7/2011

2 System OT&E Phase II 1/10/2011 5/27/2011

Install at NWSHQ and NWS Training Center

January

Install at Central Region HQ and Southern Region HQ

February

Install at Western, Eastern and Pacific Region HQ

March - May

3 Field OT&E 5/31/2011

4 Deployment 9/30/2011

Page 12: AWIPS II Status Update NWS Staff Meeting November 30, 2010

12

ADAM Status

– AWIPS II Data & Application Migration (ADAM) platform: • a standalone, workstation platform (leveraging scalability of AWIPS II software) using

“baseline AWIPS II software” enables sites to migrate local data BEFORE AWIPS II installation, and migrate local applications prior to system deployment to mitigate technical and schedule risk.

– 45 sites have been identified as Beta sites – 19 sites installed so far – ingesting data successfully

• Delivered with November software release (R1G1-5) – Draft localization documents on track to be delivered Dec 1

• Sites can begin localizing– Once localized, sites can begin migration activities immediately with platform as is i.e. no

software upgrade needed• Existing DR’s in baseline functionality will not prevent local apps from being migrated

– New DR’s could be found that will prevent some local apps from being migrated» These will be prioritized appropriately by Test Review Group for resolution

by Raytheon• Local apps that can be immediately migrated will not have to be re-done later• Raytheon NCF will take trouble calls and support

– ADAM is non-operational so Trouble Tickets are will be lower priority than operational tickets and will be worked as resources are available

– AWIPS II DR’s can be written but must be filtered for duplicates and ADAM specific issues

• Raytheon will update software periodically– depending on local apps and site migration needs

Page 13: AWIPS II Status Update NWS Staff Meeting November 30, 2010

13

NCEP NAWIPS Migration Status

• Vendor missed key hardware delivery date of 11/4• On track to meet new delivery date of 11/24

– Vendor agreed to significant compensation for missed delivery• Impact to schedule

NCO Test Bed Tasks Original Scheduled Date

Schedule Slip Date

Delivery of Test Bed Hardware to WWB 11/05/2010 11/24/2010

Hardware Installation by RTS completed 11/19/2010 12/10/2010

Software Installation and Configuration by SIB completed

12/03/2010 12/23/2010

Dataflow established to Testbed by NCO 12/10/2010 1/07/2011

SIB Testing/Checkout Completed 12/17/2010 1/14/2011

Begin NCEP FIT’s w/National Center Participation

12/20/2010 01/18/2011

Impact #1: SIB will not have time to test software on Test Bed prior to software handoff to RTS scheduled for December 13

Impact #2: This will extend OTE for NCEP

Page 14: AWIPS II Status Update NWS Staff Meeting November 30, 2010

14

Summary

• Continue to support FIT’s and follow-on System OT&E Test Periods with field personnel

• Once ADAM is installed and localized, expect sites to begin local apps and site migration activities

• Support training development – Support new small-team expert approach to get training

materials in good enough shape for Field OT&E• April 15th target

Page 15: AWIPS II Status Update NWS Staff Meeting November 30, 2010

15

Backup

Page 16: AWIPS II Status Update NWS Staff Meeting November 30, 2010

1616

Preliminary Results of Regions Scrub of Local Apps (11/12/10)

Region FBSO Before

FBSO After

FBFO Before

FBFO After

Deploy. Before

DeployAfter

Total Before

TotalAfter

Diff/(%)

AR 3 3 21 31 20 28 44 62 +18 /(44)

CR 2 2 98 99 227 57 327 156 -171/(-48)

ER 2 2 214 214 240 230 456 446 -10/(-2)

PR 0 0 8 8 3 3 11 11 0/(0)

SR 2 2 56 37 216 237 274 267 7/(-3)

WR 13 2 193 236 414 261 620 466 -153/(-25)

Other 2 2 4 4 10 10 16 16 0/(0)

Total 24 13 594 629 1130 826 1748 1424 -324/(-19)

Page 17: AWIPS II Status Update NWS Staff Meeting November 30, 2010

17

AWIPS II System OT&E Phase 2 Entrance Criteria

StatusElement Status Color Code

All Impact 1-Critical, 2-critical, 2-high and 3-critical DRs in the first bin by 11/26/10

There are 36 DRs that are still open Cautiously Optimistic

FBSO critical local applications successfully migrated 8 applications complete, 5 incomplete Cautiously Optimistic

Radar Interface Certification Test successfully completed Test complete. Certification received for non-operational sites On Track

RRS interface test successfully completed Test complete. One issue identified. Retest planned once issue has been resolved.

On Track

Performance and Stability must be at acceptable levels for at least 12 consecutive days

Discussions are ongoing for determining specific criteria/metrics. Tentatively will use the December pre-FIT and FIT period as 12 day test

Concern

Operating System Upgrade beta test has started and is a prerequisite for installation at the 5 RHQ System Test sites

Beta has started on schedule with no major problems.On Track

NCF is ready to support transition from TTRs to TT. The NCF is currently training personnel on the aspects of the new software.

Cautiously Optimistic

Hardware: LAN Switch installation completed Installation complete at all System Test sites. On Track

Hardware: LX installation completed Installation complete at all System Test sites. On Track

Hardware: DX1/DX2/PV installation completed 11 sites complete, 2 incomplete (NTCA and NTCC). On Track

Hardware: DX3/DX4 installation completed 11 sites complete, 2 incomplete (NTCA and NTCC). On Track

Hardware: Rack Consolidation/Modem Nest installation 5 sites complete (NTCD, NHDA, NMTW, NHOR and NMTR), 8 incomplete.

Cautiously Optimistic

Updated draft of localization, SMM and variance training documentation

SMM: An interim update occurred October 2010. Forecaster Variance: latest version was released with the October FIT.

Cautiously Optimistic

Draft installation instructions that are suitable to begin mod note development

Redesign under evaluation Cautiously Optimistic

Support Task Order for Phase II must be approved and in place Current Task Order in place through February 1, 2011. On Track

ITSO provides Status update on Certification and Accreditation activities, including providing Authority to Operate at RHQ.

AWIPS Program Office to get required clearance by end of the year.

On Track

Configure and localize software for RFC operations are available

On schedule. Goal is to complete by December FIT Cautiously Optimistic