azharabdullahkpfka2006ttt

131
DEVELOPMENT OF COMMON WORK BREAKDOWN STRUCTURE (WBS) FOR SCHOOL PROJECT AZHAR BIN ABDULLAH University of Technology Malaysia

Upload: waqas979

Post on 27-Nov-2014

1.111 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: AzharAbdullahKPFKA2006TTT

DEVELOPMENT OF COMMON WORK BREAKDOWN STRUCTURE (WBS) FOR SCHOOL PROJECT

AZHAR BIN ABDULLAH

University of Technology Malaysia

Page 2: AzharAbdullahKPFKA2006TTT

DEVELOPMENT OF WORK BREAKDOWN STRUCTURE (WBS) FOR SCHOOL PROJECT

2006/2007

AZHAR BIN ABDULLAH

/

PM DR MOHAMAD IBRAHIM MOHAMAD

No.28 JALAN AU 1B/ 2C

TAMAN KERAMAT PERMAI

54200 KUALA LUMPUR

Page 3: AzharAbdullahKPFKA2006TTT

DEVELOPMENT OF COMMON WORK BREAKDOWN STRUCTURE (WBS) FOR SCHOOL PROJECT

AZHAR BIN ABDULLAH

A Project Report submitted as a Partial Fulfillment of The Requirement for The Award of

The Degree of Master of Science (Construction Management)

Faculty of Civil Engineering University of Technology Malaysia

November 2006

Page 4: AzharAbdullahKPFKA2006TTT

“I hereby declare that I have read this thesis and in my opinion this

thesis is sufficient in terms of scope and quality for the award of the

degree of Master of Science (Construction Management)”

Signature : ……………………….......................

Name of Supervisor I : PM Dr. Mohamad Ibrahim Mohamad

Date : . .

Page 5: AzharAbdullahKPFKA2006TTT

ii

DECLARATION

“I declare that this master’s report entitle “Development of Work Breakdown

Structure (WBS) for School Projects” is the result of my own effort and research

except as cited in references. This report has not been accepted for any degree and

is not concurrently submitted in candidature of any other degree.

Signature : ……………………………………… Name of writer : AZHAR BIN ABDULLAH Date : 8 Disember 2006

Page 6: AzharAbdullahKPFKA2006TTT

iii

To my wife

Naziah bt. Yusoff

Thank you for your everlasting trust

To my sons and daughter

Ahmad Wildan, Ahmad Addeen, Ahmad Khaldun, Ahmad Uwais, Ainna Falihin

Abah will keep on trying to be the best father in the world.

To my self

Syukur Alham dulillah

Page 7: AzharAbdullahKPFKA2006TTT

iv

ACKNOWLEDGEMENT

This project was never an individual effort, because in completing it, the author

was assist with many good and supportive people. The author was in contact with many

academicians from the University of Technology Malaysia and Mara University of

Technology , practitioners, consultants and people who are involve directly or indirectly

in the construction industry.

First and foremost, the author would like to extend his greatest thank you to the

project supervisor, Associate Professor Dr Mohamad Ibrahim Mohammad for his

enthusiastic effort and concern in guiding the author through this project. Without his

continuous advise and support, this thesis would never been the same as presented here.

The author would also like to extend his deepest gratitude to his family especially

his wife and children for their continuous understanding, patient, encouragement and

supports to the author through out the completion of this thesis.

May Allah blessed you all.

Page 8: AzharAbdullahKPFKA2006TTT

v

ABSTRACT

A lot have been said about delayed school projects. Among the main factors that

contribute to the problem are lacking of experience among the contractor, adopting non

suitable and non detailed scheduling method for project monitoring. Ministry of Works

and The Ministry of Education are two main bodies that offer school tender. They used

two different methods of tendering procedure which come out with two different methods

of project scheduling and monitoring.

Bear in mind that every scheduling technique has its own limitation. Proper

preparation of scheduling however will help in avoiding delay of completion. This

project explore the potential of Work Breakdown Structure (WBS) as a tool to enhance

the current scheduling method. Focus is given only on school projects. Among the

objectives of this project are to identified the normal steps in preparing WBS in the

project scheduling and to develop a common Work Breakdown Structure specifically for

school projects.

The methodology adopted involving literature search, interview with authorities,

consultants and contractors who have experienced in school projects. Analysis based on

the structured interview was used to identify the main reason for project delay. Result

from the survey has shown that reasons for school delayed are no proper scheduling tools

and lack of experience and bad site management. A newly developed common WBS for

school project is also proposed and used by contractors in assisting them during the

preparation of work scheduling on site.

Page 9: AzharAbdullahKPFKA2006TTT

vi

ABSTRAK

Banyak yang telah diperkatakan mengenai projek sekolah di Malayisa. Antara

factor utama yang di katakana menyumbang kepada masalah ini ialah kekurangan

pengalaman di pihak kontraktor dan penggunaan teknik penjadualan yang tidak betul di

tapak bina. Dua badan utaman yang menganugerahkan tender projek sekolah adalah

Kementerian Pendidikan dan Kementerian Kerja Raya. Mereka menggunakan kaedah

tender yang berbeza yang menghasilkan beberapa kaedah penjadualan tapak yang

berbeza beza di kalangan kontraktor.

Perlu di ingatkan bahawa setiap teknik penjadualan mempunyai had mereka

masing-masing. Penyediaan penjadualan yang betul dilihat boleh mengelakkan

kelewatan melaksanakan kerja. Kajian ini meneroka potensi Work Breakdown Structure

(WBS) sebagai satu alat untuk menambahbaikan kaedah penjagualan semasa. Tumpuan

hanya akan diberi keatas projek sekolah. Antara objektif kajian ini adalah untuk

mengenalpasti kaedah yang di gunakan untuk meyediakan Work Breakdown Structure

(WBS) dalam penjadualan projek dan membangunkan satu Work Breakdown Structure

(WBS) khusus untuk projek sekolah.

Metodologi kajian melibatkan kajian literatur dan temubual dengan pegawai

kerajaan, perunding, dan kontraktor yang mempunyai pengalaman dalam projek sekolah.

Analisa terhadap hasil temubual terancang dengan individu-individu berkenaan

digunakan untuk mengenal pasti punca kelewatan dan tertangguh projek sekolah. Dalam

kesimpulan kajian, masalah utama kontraktor dalam kelewatan untuk melaksanakan

projek sekolah telah di kenalpasti. Punca utama nya ‘Work Breakdown Structure’ yang

umum untuk projek sekolah telah berjaya di bangunkan. Ianya boleh diguna pakai oleh

kontraktor dalam penyediaan proses penjadualan kerja di tapak bina.

Page 10: AzharAbdullahKPFKA2006TTT

vii

CONTENTS CHAPTER TITLE PAGE DECLARATION ii

DEDICATION iii

ACKNOWLEDGEMENT iv

ABSTRACT v - vi

CONTENTS vii

LIST OF TABLES xii

LIST OF FIGURES xiv

LIST OF APPENDICES xiii

CHAPTER 1 INTRODUCTION 1

1.1 Background 1

1.2 Problem Statement 2

1.3 Objectives 4

1.4 Scope and Limitation of the Study 4

1.5 Brief and Methodology 5

Page 11: AzharAbdullahKPFKA2006TTT

viii

CHAPTER 2 LITERATURE REVIEW 7

2.1 Introduction 7

2.2 Malaysian School Projects 8

2.3 Method of Awarding Contract 9

2.3.1 Traditional Design, Tender and Construct

Contract 9

2.3.2 Design and Build Contract 10

2.3.3 Construction Management Contract 11

2.4 Main Contract Document 12

2.5 Project Planning and Scheduling for School

Construction 13

2.5.1 Project Scheduling 14

2.6 Types and choice of Scheduling Method 15

2.6.1 Computer Application on Project

Scheduling 15

2.6.2 Microsoft Project (MSP) Software 16

2.6.3 Primavera Project Planner (P3) Software 17

2.7 Basic Scheduling Technique 17

2.7.1 Gantt Chart 18

2.7.2 Arrow Diagram Method 21

2.7.3 Precedence Diagramming Method 22

2.7.4 Project Evaluation Review Technique

(PERT) 23

2.7.5 Line of Balance 24

2.8 Summary 25

Page 12: AzharAbdullahKPFKA2006TTT

ix

CHAPTER 3 ROLE OF WORK BREAKDOWN STRUCTURE IN PROJECT MANAGEMENT 26

3.1 Introduction 26

3.2 Work Breakdown Structure 27

3.3 Level of Works Breakdown Structure 28

3.4 Application of Work Breakdown Structure 30

3.5 Purposes and Benefits of WBS 32

3.5.1 WBS in Work Identification and

Assignment 36

3.5.2 WBS in Schedule Management 36

3.5.3 WBS in Plans 37

3.5.4 Status Reporting 37

3.5.5 Cost Management 38

3.5.6 Cost Estimating 38

3.5.7 Budgeting and Cost Control 39

3.6 WBS as a Performance Management 41

3.7 Failure of Works Breakdown Structure 41

3.8 Summary 43

CHAPTER 4 METHODOLOGY OF THE STUDY 45

4.1 Introduction 45

4.2 Determination of the Research Objective 46

4.3 Case Study on School Projects 47

4.3.1 Research Materials 47

4.3.2 Development of Questionnaire for the

Page 13: AzharAbdullahKPFKA2006TTT

x

Survey 48

4.4 Interview with Panel of Experts (Client) 49

4.4.1 Methodology of the Panel of Expert

Interview 50

4.4.2 Structured Questionnaire Discussion 50

4.5 Analyzing the WBS (Case Study) 51

4.6 Preliminary Guidelines for Preparing WBS for

Project Scheduling/ Construction Programme 52

4.7 Recommendation of a WBS for a Sample Project 54

CHAPTER 5 DATA ANALYSIS AND DISCUSSION 55

5.1 Introduction 55

5.2 Effect of Registration Grade and Type of

Documentation on the Completion of School

Projects 70

5.3 Lack of Experience Affecting School Projects

Delay 70

5.4 Effect of Work Programme on the Completion

Of School Project 70

CHAPTER 6 DEVELOPMENT OF WBS FORMAT AND GUIDELINES 72

6.1 Introduction 72

6.2 Preparation of WBS 73

6.3 Proposed Format of WBS Presentation 74

6.4 Guidelines for the Designing of WBS 78

6.5 Criteria in Developing the WBS 81

Page 14: AzharAbdullahKPFKA2006TTT

xi

6.6 Checklist for the Preparation of WBS 82

6.7 An Example of a WBS for a School Construction

Project 84

6.7.1 Project Brief 84

6.7.2 WBS on Construction of Sample Project

(School Building) 85

CHAPTER 7 CONCLUSION AND RECOMMENDATION 95

7.1 Introduction 95

7.2 Managing School Projects in the Future 96

7.3 Concept and Application of WBS in School

Project Scheduling 96

7.4 Application of WBS in Construction Schedules

for Selected School Projects 97

7.5 To Initiate/ Propose Format and Guidelines for

WBS 98

7.6 Example of WBS for a Building School Project 99

7.7 Conclusion 99

7.8 Recommendation 101

REFERENCES 102 APPENDIX I 104 APPENDIX II 105

Page 15: AzharAbdullahKPFKA2006TTT

xii

LIST OF TABLES

TABLE NO. TITLE PAGE

3.1 A typical of six-level project WBS 29

3.2 Work Breakdown Structure Outline 31

5.1 The summary of CIDB Registration grade and Type of

Contract documentation for delayed and non-delayed

school projects. 56

5.2 Summary of the expert panels and contractors involved

in the case study 58

5.3 Content Analysis – Summary of views from twenty

respondence towards the causes of school project delay 56

5.4 Comparison of construction activities generated from

Contract Document and Contract Sum Analysis 63

5.5 Comparison of construction activities based on WBS

element in project schedule generated from contract

document 66

6.1 Example of WBS for a school building project 85

Page 16: AzharAbdullahKPFKA2006TTT

xiii

LIST OF APPENDICES

APPENDIX TITLE PAGE I Detailed background of respondence 104 II Questionnaires for the expert panels and contractors 105

Page 17: AzharAbdullahKPFKA2006TTT

xiv

LIST OF FIGURES

FIGURE NO. TITLE PAGE 1.1 Brief Methodology 6

2.1 Contractual Relationship between every party involve

under the traditional design, tender and construct contract 10

2.2 Contractual Relationship of all party involved under the

Design and Build Type of contract 11

2.3 Contractual Relationship of all party involved under the

Construction Management contract 12

2.4 Example of Gantt Chart 20

2.5 Example of Arrow Diagramming Method 21

2.6 Example of Precedence Diagramming Method 22

3.1 A typical work breakdown structure 30

3.2 An example of WBS 35

Page 18: AzharAbdullahKPFKA2006TTT

CHAPTER 1

INTRODUCTION

1.1 Background

Construction industry is very unique and complex due to the

involvement of many parties and consumption of varieties of resources.

According to Ballard and Howell (1998) construction covers a spectrum ranging

from slow, certain, and simple project to quick, uncertain and complex project.

In addition, Koskela(1992) stated that construction is unique in the sense of it is

one-of a kind nature of projects, site production and temporary multi-

organization. However, failure of establishing a good management system in

construction project will lead to many problems that would cause cost of project

increases, late completion of project and low quality which finally reduce the

profit of the contractor.

According to Hendrickson (1989) good scheduling can eliminate

problems due to production bottlenecks, facilitate the timely procurement of

necessary materials, and otherwise insure the completion of a project as soon as

possible. In contrast, poor scheduling can result in considerable waste as

laborers and equipment wait for the availability of needed resources or the

completion of preceding tasks. Delays in the completion of an entire project due

Page 19: AzharAbdullahKPFKA2006TTT

2

to poor scheduling can also create havoc for owners who are eager to start using

the constructed facilities.

Currently, projects in Malaysia were monitored using several types of

project scheduling technique, where the most common approach is by using

Gantt Chart, Line of Balance or Networking technique such as Arrow Diagram

Method, Precedence Diagramming Method and Project Evaluation Review

Technique (PERT). However, Hendricson (1989) stated that there are several

limitations to these methods. These limitations has lead to a lot of problems as

mentioned by Koskela (1992). Therefore this research work focused on project

delay which is one of the contributing factor to project failure. However, only

school project has been chosen for the case study of this research work.

1.2 Problem Statement

Malaysia experiences a high growth in construction that lasted more than

one decade. In less than twenty years, Malaysia was crowned as having the most

developed infrastructure in East Asian countries, from what was once a

backward third world facility. Many success stories made it to the front page of

world press but very little of the major flop in construction sector ever make it to

the publics’ knowledge. Malaysian has it fair share of project cost overruns,

delays and uncompleted infrastructure development.

One only needs to pay more attention to realize that a large portion of the

development was not completed as planned, especially in the less “public-

aware” segment like government schools construction programs. In general,

among the prime factor that contributes prominently to project cost overrun and

delayed in project completion, is failure to continuously monitor the project

timely and diligently. Issues of abandoned uncompleted school construction

Page 20: AzharAbdullahKPFKA2006TTT

3

project or worse, completed but unfit for occupation should be given more

attention.

In Malaysia, the two relevant bodies that are responsible for handling out

schools construction works are The Ministry of Works or commonly known as

JKR and The Ministry of Education (MOE). While JKR utilizes the “Open

Tendering” method, MOE uses the Design and Build (Turnkey) system.

Although in this context the method of awarding the schools construction

projects can not be argued as a predetermined outcome of the particular project,

it is nevertheless undeniable that each of this mentioned method of awarding

projects has their benefits and their weakness.

Delayed or sometimes, abandoned school projects were always related to

poor site management, inexperienced contractors, poor mobilization of resources

such as man power and machineries, poor communication among parties

involved and most important of all is lack of knowledge in using the appropriate

scheduling technique. Although there are several scheduling technique practiced

by contractors, it seems that delays still occurs. Issues related to the limitation of

current practice in scheduling, lack of having good and relevant Work

Breakdown Structures in project schedule, consistency and coordination

between the process in preparation of Bill of Quantities and project schedule

must be given priority in order to minimized such cause. Often, these forgotten

element is remembered only when the project is underway and required the

missing element. In most cases, forgotten works has serious influence on the

development schedule and delivery, and may impact the project cost severely.

The WBS is one tool that if used correctly, helps everyone involved avoid such

occurrence by ensuring that nothing significant has been forgotten.

Page 21: AzharAbdullahKPFKA2006TTT

4

1.3 Objectives

The aim of this study is to develop a common work breakdown structure

(WBS) for school construction projects. This study will look into the current

approach in preparing of WBS elements in school construction project. It will

also investigate and analyzes the limitation of current scheduling method

commonly used in school construction project.

The objectives of this study are as follows:

i. To analyse the work breakdown system in current school

construction contract.

ii. To investigate the actual requirement in project breakdown and

to facilitate the work process at site.

iii. To develop a common Work Breakdown Structure system for

school construction project.

1.4 Scope and Limitation of the Study

The scopes and limitation of this study are as follows:

i. The focus of this study confine within the school construction

projects only.

ii. Observation done on contract documents produced by the

Ministry of Works and Ministry of Education, all related to

school construction projects.

iii. Observation was also done on work program used by contractors

for these school construction projects. Attention was focused on

how the work is being divided on site and on how these normal

Page 22: AzharAbdullahKPFKA2006TTT

5

methods are used by contractors on guiding them in terms of

project scheduling reports, managing resources and controlling

budget.

iv. Structured interview with professionals, panels of expert,

consultant and contractors within the industries. Findings from

these interviews will be utilized to develop a common WBS that

can be used to better guide, control and manage sub-contractors,

contractors and the clients specifically for school construction

projects.

1.5 Brief Methodology The flow chart of research methodology for this study is shown in Figure 1.1

Page 23: AzharAbdullahKPFKA2006TTT

6

Literature Search

Comparison on contract documents, work programs and WBS elements on selected school projects. Interview and discussion with Panels of

Experts in the industry and contractors.

Problem Statement, Objectives & Scope of Study.

Identification of current procedures, their advantages and limitations. Studies on scheduling techniques used to monitor project performance.

Factor that contribute to unperformed or delay in schools project scheduling method and site management.

Validat

Study onEach element will be break

reach the level of work pa

DiscR

Analysis of the proposed Coand recomm

Common Workfor sch

Analysis and ion of a common WBS

elements in current WBS down into further levels of detail until theyckages, which are portions of the project.

ussion, Conclusion & ecommendation.

mmon Work breakdown Structure, conclusion endations. Proposed of a new

Breakdown Structure specifically ool construction projects.

Figure 1.1 Brief Methodology

Page 24: AzharAbdullahKPFKA2006TTT

CHAPTER 2

LITERATURE REVIEW 2.1 Introduction

The project schedule is one of the most important components of a

school project development plan. This plan is often the first formal document

generated within the school project, and includes not only the scheduling of

development activities but also the scheduling of project resources. The project

development plan describes in detail how the project manager plans to develop

the project, what resources will be required, and how these resources will be

applied (Martin 1996).

A schedule is a list of activities and their anticipated time of

implementation. There are many ways of representing a schedule: lists of

activities, diagrams, graphs, etc. The most common methods of schedule

representation are precedence network diagrams, Gantt charts, and lists of

milestones. The schedule, as part of the overall project development plan, must

be periodically updated. In order to enable the project manager to maintain an

updated schedule, current update-to-date information must flow regularly from

the development team. This is achieved through periodic reports, reviews, and

other monitoring activities (Martin 1996).

Page 25: AzharAbdullahKPFKA2006TTT

8

2.2 Malaysian School Projects.

Malaysian Government has always put a lot of emphasis on the nation�s

education development. Educational spending thus has always been substantial

in comparison to other government spending. Under the recently approved

annual budget, The Ministry of Education has identified 54 new schools

construction projects for year 2007. On a grander scale, more development was

proposed under the new Ninth Malaysia Plan (9MP).

Besides new school construction projects planned for year 2007, the

Ministry has further ascertained another 220 schools for upgrading development.

With the advent of these projects and the fact that, historical records on school

construction projects show poor completions, the Ministry has no other choice

but to adopt a tougher stance on irresponsible contractors.

Under this year school construction project master plan, the Ministry will

construct 9 new primary schools in various part of Malaysia at a cost of around

RM82million. The Ministry also set their sight on building additional 10 full

boarding schools costing an estimated RM400million. The major part of the

master plan goes to constructing 35 secondary schools on a budget of

RM353million. As for the 220 school upgrading programs, it is estimated to

cost RM195million. All in all, government spending on school constructions and

school upgrading programs will be in excess of RM980million. With so much

money and responsibility at stake, the government has always been in the look

out for a better monitoring and administration tool.

Page 26: AzharAbdullahKPFKA2006TTT

9

2.3 Method of Awarding Contract

There is no single project organization chart that will represent the entire

organizational structure for all the players in the construction industry,

regardless of type of contract. The current practice allows different agencies in

Malaysia to practice different ways of contract award procedure. The three most

common types of construction contracts are;

a) Traditional (design � bid � built) contract

b) Design & Build contract

c) Construction Management contract.

2.3.1 Traditional design, tender and construct contract

The Ministry of Works has been adopting this type of contract awarding

technique for years. Under this traditional contract the Ministry usually engages

the services of a professional architect or qualified engineer to execute the

planning and design work, which includes the preparation of the tender

documents. Upon completion of the tender documents, contractors are normally

invited to tender for the project. Successful contractor will be awarded the

contract. Upon awarding of the project, the successful contractor will carry out

the construction works. During the construction stage, the role of architect or

engineer whose previous task was to prepare the tender documents switch their

role to function as the client representative to oversee the construction works

done by the contractor and at the same time, to ensure that the works are

completed to the specified contract terms and conditions.

Page 27: AzharAbdullahKPFKA2006TTT

10

Figure 2.1 is a diagrammatic illustration of the contractual relationship

between every party involved operating under the traditional design, tender and

construct contract.

Client

Project Consultant

Architect/Engineer

Contractual Relationship

Supervision/Contract Administration

Main (Prime) Contractor

Nominated Subcontractor

Domestic Sub-contractors

Nominated Suppliers

Direct labour

Figure 2.1 Contractual Relationship between every party involved under the

traditional design, tender and construct contract

2.3.2 Design and Build Contract

Ministry of Education has their own authorization over awarding school

construction project to contractors. The sole holder of this authority was

Ministry of Works before the authorization of school construction project

awarding was co-shared. Since taking over some of the task in awarding

contracts to contractors, the Ministry of Education has preferred the Design and

Built Contract concept. Under the Design the Build, the client enters into an

agreement with one single construction company to execute the whole process

of planning, design and construct. Although sometimes, this single company

Page 28: AzharAbdullahKPFKA2006TTT

11

will need to arrange for financing of the project under a turnkey package, but for

this case, financing will be from the ministry itself.

Figure 2.2 shows a diagrammatic illustration of the contractual

relationship of all party involved under the Design & Build type of contract.

CLIENT

Contractual Relationship

Contractual Relationship

Project Manager from Project Management

Consultant

Design and Build Contractor

Design Team Architect/Enginee

Construction Team (Main Contractor)

Direct Labour Sub-contractorsSuppliers

Figure 2.2 : Contractual Relationship of all party involved under the Design

and Build Type of Contract

2.3.3 Construction Management Contract

Under the Construction Management type of contract, the client engages

a construction management company to manage the direct contractors appointed

by him, while retaining the appointment of the architect and engineer. In the

Malaysian context, this type of contract is sometimes also known as Project

Page 29: AzharAbdullahKPFKA2006TTT

12

Management Consultant (PMC) Contract. In this scenario, the construction

management company is responsible for reviewing the design outputs and

coordinating and supervising the works of the direct contractors appointed by

the client. The construction management company is also responsible for the

project meeting the dateline, costs and quality parameters.

Figure 2.3 shows a diagrammatic illustration of the contractual relationship of

all party involved under the Project Management Consultancy.

CLIENT

Working Relationship

Contractual R l ti hi

ConstructionManagement

Company

Contractual Relationship

Working Relationship

Architect /Engineer

Direct contractors Suppliers Direct contractors

Figure 2.3 Contractual relationships of all party involved under the

Construction Management contract

2.4 Main Contract Document

Upon awarding contract to the specific contractor, the Ministries will

then furnished the contractors, list of document known as the Main Contract

Document. It will explained the overall aspect of the project in terms of time

frame given, cost, responsibilities, laws and project specifications.

Page 30: AzharAbdullahKPFKA2006TTT

13

Main Contract Document shall consist of : • PWD Form of Contract (Form PWD 203A Rev. 10/83); • Form of Tender (Form PWD 203B Rev. 3/2003); • Letter of Acceptance of Tender (Form PWD 203D Rev. 5/2003); • Special Provisions to the Condition of Contract as listed in the

PWD Form of Contract; • Contract Drawings; • Specification; • Summary of Tender; • Bill of Quantities; • Treasury Instructions as set in the Appendix to the Contract.

Every item in the Main Contract Document is essential when preparing a

work program and choosing the best scheduling method. In this regards, failure

to complete and implements the school construction projects on time will create

havocs and chaos to the public and community indirectly. In order to properly

implement of a project, proper management and using the best method in

planning is required. One of the important tools in planning is by using the

project schedule for the school construction project. Each scope of works and

activities in a particular construction will be break-down into smaller scope for

monitoring, control, costing and reporting purposes.

2.5 Project Planning and Scheduling for School Construction

Planning has a purpose, that is, to prepare for an enabling process that

can lead to a desired result (Young, 1993). Project planning and scheduling is

part of the project management processes. Project Management processes can

be organized into five groups of one or more processes each (PMI, 2000):

(i) Initiating Process � authorizing the project or phase.

Page 31: AzharAbdullahKPFKA2006TTT

14

(ii) Planning processes � defining and refining objectives and

selecting the best of the alternative courses of action to attain the

objectives that the project was undertaken to address.

(iii) Executing processes � coordinating people and other resources to

carry out the plan

(iv) Controlling processes � ensuring project objectives are met by

monitoring and measuring progress regularly to identify

variances from plan so that corrective action can be taken when

necessary.

(v) Closing processes � formalizing acceptance of the project or

phase and bringing it to an orderly end.

2.5.1 Project Scheduling

Scheduling school project work is an essential element of project

management. A project schedule makes clear to all participants when work is

expected to be completed. It also shows the time-related dependencies between

different project tasks. In a school project, several schedules may be necessary,

covering different levels of detail or different parts of the project.

Setting overall completion dates must be done by the government, which

in this case is the Ministry of Works and the Ministry of Education. The project

manager assists in this by digesting information about scope, deliverables, and

resources, and estimating times for completion of project tasks. Once an overall

schedule is set, the project manager is responsible for monitoring the progress of

the project and revising the schedule if needed. This must be done in

consultation with project team members who are doing the work. Working with

team members to produce accurate time estimates is one of the high mysteries of

the art of project management. The project manager must balance the needs for

honesty and realism with appropriate motivation to keep the project on track

despite inevitable surprises.

Page 32: AzharAbdullahKPFKA2006TTT

15

There will typically be give-and-take as a project proceeds among budget,

features, and schedule. It is essential for the project manager to keep all

participants informed as to current schedule status.

2.6 Types and choice of Scheduling Method

Since the invention of scheduling technique, various method had been

develop from time to time, Some scheduling method are very simple to use but

have limitation in their application. On the other hand there are technique which

requires some training before the contractors can be familiarized with the system.

Some of the factors that governed the choice of the technique are familiarity on

the technique to be used, type and size of the school projects and purpose of

scheduling.

2.6.1 Computer Application of Project Schedule

In Malaysia, it is the practice of the government agency requesting the

contractor to submit the project schedule using Microsoft Project (MSP) for

school project cost les than Rm10million. Project scheduling using Primavera is

requested for school project worth more than Rm10million. At present, most

computer softwares are using the Precedence Diagram Method and Critical Path

Method. The most popular softwares are the Microsoft Project for project

valued less then RM10 million and the Primavera Project Planner for more than

Rm10million. Among the other software available in the market for project

scheduling and planning are Suretrak, Artimis, Milestone and Proplan.

Generally, every scheduling program software package run on micro-

computer. Most of the software today like Microsoft Project, Time Line and

Primavera are currently available on Window�s version and user friendly. One

of the most important contribution of the computer base scheduling technique is

Page 33: AzharAbdullahKPFKA2006TTT

16

in term of the report that can be generated. Another important advantage of

using computer base scheduling technique is the capabilities to instantly

reschedule and updating project progress. Obviously these cannot be practically

accomplished manually.

However it must be realized that it is very important for the planners and

contractors to understand basic scheduling principle such as computation of

project duration, critical path method resource leveling and many others prior to

the use of computer base scheduling software for their school projects.

2.6.2 Microsoft Project (MSP) Software

Using MSP for scheduling is very common in small projects since the

WBS items is not many. Microsoft Project is the world�s most popular project

management software developed and sold by Microsoft. The application is

designed to assist project managers in developing plans, assigning resources to

tasks, tracking progress, managing budgets and analysing workloads. Microsoft

Project creates critical path schedules, although a critical chain third-party add-

ons is available from ProChain and Spherical Angle. Schedules can be resource

leveled. The chain is visualised in a Gantt chart.

Resource definitions (people, equipment and materials) can be shared

between projects using a shared resource pool. Each resource can have its own

calendar which defines what days and shifts a resource is available. Resource

rates are used to calculate resource assignment costs which are rolled up and

summarized the resource level. Each resource can be assigned to multiple tasks

in multiple plans and each task can be assigned multiple resources. Microsoft

Project schedules task work based on the resource availability as defined in the

resource calendars. All resources can be defined in an enterprise resource pool.

Microsoft Project creates budgets based on assignment work and resource rates.

Page 34: AzharAbdullahKPFKA2006TTT

17

As resources are assigned to tasks and assignment work estimated, Microsoft

Project calculates the cost equals the work times the rate. This rolls up to the

task level, then to any summary tasks and finally to the project level. It is an

user-friendly software and designed to interface with other Microsoft

programmes such as Excell and Words

2.6.3 Primavera Project Planner (P3) Software

It is the most popular computer scheduling software practiced in the

construction industry. Many contracts for goverment projects require the

contractors to submit project schedules using this programme. With a maximum

capacity of 100,000 activities on a single project plus the ability to group

projects together, Primavera is so powerful and applicable on virtually any

projects (Hinze, 1998).

Data input is done through various assistants, called Wizards. Project

performance can be measured according to earned value, BCWS and costs.

Cash flow diagram can be displayed showing costs, revenues, and the nett

amount as a function of time. Primavera programme offer 200 different reports

and related graphic representation of the schedule.

Primavera offers sample projects as reference and guidance. Schedules

can be run through more than one baselines. Each activity of the WBS can be

related to more than one type of logical relationship. It is compatible to other

softwares such as �Suretrak� and can be updated from the construction site

through internet. Module attachments to P3 provide additional project

management tools for reports, cost control, resource management and estimating.

Due to its many functions and features that makes it the most powerful

management software ever, the programme price tag of several thousand dollars

and it is a costly investment

Page 35: AzharAbdullahKPFKA2006TTT

18

2.7 Basic Scheduling Technique

There are a few method of project scheduling technique practices in

managing the projects. Some of the techniques are;

i. Gantt Chart (Bar Chart)

ii. Linked Bar Chart

iii. Networking Technique

(a) Activities on Arrow (AOA)

- Critical Path Method (CPM)

- Project Evaluation Review Technique (PERT)

(b) Activities on Node (AON)

- Precedence Diagram Method (PDM)

(c) Line of Balance

2.7.1 Gantt Chart

A Gantt chart is a matrix which lists on the vertical axis all the tasks to

be performed. Each row contains a single task identification which usually

consists of a number and name(Fig. 6). The horizontal axis is headed by

columns indicating estimated task duration, skill level needed to perform the

task, and the name of the person assigned to the task, followed by one column

for each period in the project's duration. Each period may be expressed in hours,

days, weeks, months, and other time units. In some cases it may be necessary to

label the period columns as period 1, period 2, and so on.

The graphics portion of the Gantt chart consists of a horizontal bar for

each task connecting the period start and period ending columns. A set of

markers is usually used to indicate estimated and actual start and end. Each bar

Page 36: AzharAbdullahKPFKA2006TTT

19

on a separate line, and the name of each person assigned to the task is on a

separate line. In many cases when this type of project plan is used, a blank row

is left between tasks. When the project is under way, this row is used to indicate

progress, indicated by a second bar which starts in the period column when the

task is actually started and continues until the task is actually completed.

Comparison between �estimated start and end� and �actual start and end�

should indicate project status on a task-by-task basics. Variants of this method

include a lower chart which shows personnel allocations on a person-by-person

basis. For this section the vertical axis contains the number of people assigned to

the project, and the columns indicating task duration are left blank, as is the

column indicating person assigned. The graphics consists of the same bar

notation as in the upper chart indicates that the person is working on a task. The

value of this lower chart is evident when it shows slack time for the project

personnel, that is, times when they are not actually working on any project.

Page 37: AzharAbdullahKPFKA2006TTT

20

ID Task Name Duration BaselineDuration

TF % Complete

1 OVERALL WORK 129 days 0 days 0 days 0%2 Start 0 days 0 days? 0 days 0%3 Prelim. Works 30 days 0 days 0 days 0%4 Site Clearing 2 days 0 days? 0 days 0%7 Hoarding 14 days 0 days 11 days 0%8 excavate Footing 3 days 0 days? 11 days 0%9 Inst. Column 3 days 0 days? 11 days 0%10 Boards 6 days 0 days? 11 days 0%11 Painting 2 days 0 days? 11 days 0%12 Temporary works 28 days 0 days 0 days 0%16 Temporary Road 6 days 0 days? 0 days 0%15 Site Offices 3 days 0 days? 0 days 0%14 Kongsi House 7 days 0 days? 0 days 0%13 Canteen 5 days 0 days? 0 days 0%17 Temporary water supply 2 days 0 days? 0 days 0%18 Temporary Power supply 2 days 0 days? 0 days 0%19 Excavate to Working Platform 12 days 0 days 8 days 0%5 Mobilisation 2 days 0 days 123 days 0%6 Portable Offices 2 days 0 days? 123 days 0%20 Piling 73 days 0 days 0 days 0%21 Piling Mobilisation 3 days 0 days? 8 days 0%22 Test Pile 22 days 0 days? 0 days 0%23 Fabrication of steel bar 1 day 0 days 0 days 0%24 Boring Works (Test Pile) 1 day 0 days 0 days 0%25 Rebar Works (Test Pile) 1 day 0 days 0 days 0%

8/1

8/1 8/2

8/3 8/5

8/6 8/9

8/10 8/16

8/17 8/18

8/3 8/9

8/10 8/12

8/16 8/23

8/25 8/30

8/31 9/1

9/2 9/3

8/3 8/16

8/5 8/6

8/23 8/25

9/5 9/

9/6 9

9/6 9

29 5 12 19 26 3 10 17 24 31 7 14 21 28 4Jun '05 Jul '05 Aug '05 Sep '0

Figure 2.4 Example of Gantt Chart

Page 38: AzharAbdullahKPFKA2006TTT

2.7.2 Arrow Diagram Method

Arrow Diagramming Method (ADM) (Fig. 2.5) is once-popular but

disappearing method of representing project activities with arrows, with a node

shown as a circle, representing events at the ends of the arrows. In arrow

diagram, project task or activities are represented by the arrow and connected by

the node to express their logical relationship. The tail of the arrow is the

beginning and the head represents the completion. While it is less flexible than

PDM, it has the advantage of defining the logical relationships between

activities entirely by the activity numbers.

Figure 2.5: Example of Arrow Diagramming Method

Page 39: AzharAbdullahKPFKA2006TTT

22

2.7.3 Precedence Diagram Method

Precedence Diagramming Method (PDM) (Fig. 2.6). Developed in the

early 1960s into current form by H.B. Zachry in cooperation with IBM, this

popular and flexible technique avoids using the dummy activities to maintain

logic relationships needed in Arrow Diagram Method. Unlike the Arrow

Diagram Method, in Precedence Diagram, activity is place on the node instead

of on arrow. The arrow or linked is then used to connect between project task in

orderly manner to show their logical relationship. It represents activities as

boxes that are assigned properties of the activities they represent. Includes the

four types of lag relationships: finish-to-start, finish-to-finish, start-to-start and

start-to-finish.

Figure 2.6 : Example of Precedence Diagramming

Method

Page 40: AzharAbdullahKPFKA2006TTT

23

2.7.4 Program Evaluation Review Technique (PERT)

PERT of Program Evaluation Review Technique is basically similar to

Arrow Diagram method. However PERT employs three time estimate instead of

one deterministic time as in other technique.

• Optimistic Time - generally the shortest time in which the

activity can be completed. It is common practice to specify

optimistic times to be three standard deviations from the mean so

that there is approximately a one percent chance that the activity

will be completed within the optimistic time.

• Most likely time � the completion time having the highest

probability. Note that this time is different from the expected

time.

• Pessimistic time � the longest time that an activity might require.

Three standard deviations from the mean is commonly used for

the pessimistic time.

In order to combined the three estimates time the expected mean duration for the

activity or task, a formula was derived, base on principles of statistics. The

estimate of average expected time to perform an activity is given by the

following expression:

te = a + m + b

te = expected

a = optimisti

m = most like

b = pessimis

46

time

c time estimate

ly time

tic time

Page 41: AzharAbdullahKPFKA2006TTT

24

A suitable estimator of activity standard deviation is given by :

s = b - a

where s is the standa

Once the critical path

deviation for the tota

the sum of the varian

deviation is given by

S cp =

Critical Path Method

duration. Saad Al-Jib

the availability of the

on schedules.

2.7.5 Line of Balan

Line of balan

repetitive activities. T

plant to assure that e

orderly way, comple

waiting the preceding

concept of keeping a

productivity. The ma

use of all resources. T

of progress of the act

interference. This is d

that this approximate

6

rd deviation of the expected time, te.

had been determined for the network, the standard

l critical path can be calculated by taking the square root of

ces of the activities on the critical path. The standard

: 2 2 2

√S 1 + S 2 + S 3

(CPM) and PERT are concerned with minimizing project

ori et al, (2001) state that, both method assume no limit on

resources to be employed to complete all project activities

ce

ce chart is used to plan for construction of a number of

he technique analyze the use of resources such labor and

ach resource can progress from one item to the next in an

ting its own work on all items without being delayed in

work to be completed. Thus the technique is base upon the

ll of resources in balance, each following the other

in objective of using line of balance is to make optimum

he purpose of line of balance analysis is to balance the rate

ivities, and to schedule the activities to eliminate

one by adjusting the rate of production of each activity so

s to a common rate of production for all activities and by

Page 42: AzharAbdullahKPFKA2006TTT

25

delaying the start of those activities that proceed faster than the activity

immediately preceding it, to maintain at least the minimum buffer specified at

all times.

2.8 Summary

This chapter explained extensively the present scenario on Malaysian

school projects. It touched on the government�s emphasis on the nation�s

education development. Nevertheless that it is sad to learn that the nation�s

school project faced a lot of problems due to improper management among

contractors.

This chapter also touched and explained clearly the typical method

adopted by two main relevant bodies that are responsible for handling out

schools construction works and all the documentation involve in it. The

Ministry of Works utilizes the �Open Tendering� method while the Ministry of

Education uses the �Design and Built� system. We cannot say which method is

better as both method, if were being conducted in the proper ways, can produce

excellent output.

Types of scheduling techniques that are helpful for contractor to

supervise, control and manage their projects were also mentioned at the end of

the chapter. Those are beneficiaries if its being positively manipulate for the

sake of completing the projects within the time frame and budget.

Page 43: AzharAbdullahKPFKA2006TTT

CHAPTER 3

THE ROLE OF WBS IN SCHOOL PROJECT MANAGEMENT

3.1 Introduction

When any contractors contracts for an acquisition, they have to refer to

the Master Schedule in order for the final product to be delivered within the

allotted time, budget and with both the physical and functional characteristics

required.

In Chapter 2, we have discussed the various scheduling technique used

by school contractors to guide them on how they are going to complete their

project successfully. The ability to calculate and forecast dates effectively and

accurately is essential to successfully completing the project. Although the

master Schedule is the highest level summary schedule for a project, depicting

overall project phasing and all major interfaces, contractual milestones, and

project elements, contractors, especially with less experience faced difficulty in

anticipating problems with regards to the work program. They sometimes

overlook since they do not take time to plan a project thoroughly, or do so in

haphazard manner. The result is unnecessary delays, poor quality workmanship

and cost overruns. This chapter will focus on the importance of a tool called a

Work Breakdown Structure, or WBS that can help and guide contractors to

Page 44: AzharAbdullahKPFKA2006TTT

27

complete their work more efficiently, diligently, minimizing delays and

avoiding lost in their project.

3.2 Work Breakdown Structure

Martin, 1996 derives a work breakdown structure (WBS) as a hierarchic

decomposition or breakdown of a project or major activity into successive levels,

in which each level is a finer breakdown of the preceding one. In final form a

WBS is very similar in structure and layout to a document outline

A Work Breakdown Structure (WBS) is a hierarchical chart used to

organize the activities required in a project into related areas. It often takes the

form of a tree diagram or an outline. The completed WBS can be used for

budgeting and personnel-selection purposes as well as scheduling and network

diagramming. In a WBS, a project is broken down into the following levels:

• The total project

• Sub-projects if the project is a complicated one Milestones that

summarize the completion of an important set of work packages or the

completion of an important event in a project such as sub-project (which

is just a smaller portion of the overall project)

• Major activities – also called summary tasks

• Work packages (also sometimes called tasks, activities, or work elements)

Roman (1986) defines WBS as a basic management technique which

presents systematically subdivided blocks of work down to the point which

represent the lowest level of control effort. It is a product-oriented family tree

composed of hardware, software, services and other work tasks. A WBS

Page 45: AzharAbdullahKPFKA2006TTT

28

displays and defines the product to be developed and relates the tests to be

accomplished to each other and to the end product.

Kliem (1998) defines WBS as a detailed listing of the project

deliverables and tasks for building the product or delivering the services. It is a

top-down, broad-to-specific hierarchical outcome of the work to perform.

Project Management Institute (PMI, 2000) defines WBS as a deliverable-

oriented grouping of project elements that organizes and defines the total work

scope of the project. Each descending level represents an increasingly detailed

definition of the project work.

Almost all planning tools and programmes for scheduling such as

Primavera Project Planner, Suretrack and Microsoft Project need to have a

proper breakdown structure to be more efficient in the planning process.

We can have as many sub-projects, milestones, and major activities, and

work packages in your WBS as long as they benefit your needs. As a project

manager, the levels in your WBS will help us control work at each level. An

appropriately organized WBS can help identify the right time to ask and answer

resource and staffing questions.

3.3 Level of Works Breakdown Structure (WBS)

As a planning technique, the WBS allows the customer-driven project

lead team to organize the project works into level of activity. Each level of

activity is defined further and in even greater detail by process owners (Barkley

and Saylor, 2001). The purpose is to structure each project as a hierarchy of

Page 46: AzharAbdullahKPFKA2006TTT

29

work leading up to the project deliverable and down to each more detailed

breakout of the work to be done.

The WBS structure can be arranged in a variety of formats. The format

defines the project tasks and their relationship to the total project. A WBS can

have as many levels as appropriate but normally up to the sixth level. Some

organization refer the different level of tasks, sub-tasks and work package but

others could prefer to use the term as phases, entries and activities.

Table 3.1 shows the function of each level inclusive their coding. Tasks

at the first four levels of the WBS provide the summary information necessary

for the customer-driven project to perform project planning, scheduling,

monitoring and management activities. Level 5 and 6 normally used performing

the work.

Table 3.1: A typical of six-level project WBS.

LEVEL ITEM NUMBER

1 Project 1 2 Process 1.X 3 Task 1.X.X 4 Subtask 1.X.X.X 5 Work Package 1.X.X.X.X 6 Level of Effort 1.X.X.X.X.X

Page 47: AzharAbdullahKPFKA2006TTT

30

3.4 Application of Work Break Down Structure

The function of management is to plan and direct activities to achieve the

program goals. A complex project is made manageable by first breaking it

down into individual components in a hierarchical structure, known as the Work

Breakdown Structure (WBS). Such a structure defines tasks that can be

completed independently of other tasks, facilitating resource allocation,

assignment of responsibilities, measurement & control of the project. Figure 3.1

below shows a typical WBS.

Project

Task 1 Task 2

F

Sub-task 1.1

igure 3.1 A ty

Sub-task1.2

Sub-task 1.1.1

Sub-task1.1.2

pical work break

Sub-task1.1.3

down structure

Page 48: AzharAbdullahKPFKA2006TTT

31

The purpose of a WBS is to divide the program/project into manageable

pieces of work to facilitate planning & control of cost, schedule & technical

content. A WBS is written early in program/projects development. It identifies

the total work to be performed & divides the work into manageable elements,

with increasing levels of detail.

The WBS is project management tool. It provides a framework for

specifying the technical aspects of the project by defining the project in terms of

hierarchically related, product-oriented elements & the work processes required

for each element’s completion. Each element of the WBS provides logical

summary points for assessing technical accomplishments, for measuring cost

and schedule performance. Because the WBS is a hierarchical structure, it may

be conveyed in outline form as shown in Table 3.2.

Table 3.2: Work Breakdown Structure Outline

Level 1 Level 2 Level 3

Task 1

Sub-task 1.1

Work Package 1.1.1

Work Package 1.1.2

Work Package 1.1.3

Sub-task 1.2

Work Package 1.2.1

Work Package 1.2.2

Work Package 1.2.3

Task 2

Sub-task 2.1

Work Package 2.1.1

Page 49: AzharAbdullahKPFKA2006TTT

32

Work Package 2.1.2

Work Package 2.1.3

In short, WBS is used for technical management, work identification and

assignment, schedule management, status report, cost management and

performance measurement.

3.5 Purposes and Benefits of WBS.

WBS has many uses during a project’s life. It go through many iterations

as the work becomes more defined, it may changed continually from the time

specifications are agreed on with the client until the project complete. Listed

below are among the seven of the distinct purposes of WBS (Barkley and

Saylor, 2001):

(i) The WBS defines project team responsibility. WBS helps to

assign task-level work in project teams and gives the project lead

team a means of developing task description, work outputs and

objectives for each task.

(ii) The WBS set out organization structure. Each project team or

team member is identified with one or more tasks or sub-task

work element and reporting to the project lead team

(Superintending Officer); the WBS serves as the basis for setting-

up project team. This can be represented by the Organizational

Breakdown Structure (OBS).

Page 50: AzharAbdullahKPFKA2006TTT

33

(iii) WBS allows co-ordination of activities. The project objectives are

supported by the WBS because the interfaces between elements

are made clear in WBS.

(iv) WBS allows control. WBS facilitates control by providing a clear

basis for monitoring project progress using the structure of the

project; thus each team is accountable for the tasks assign to

them. The real value of WBS is that it provides a graphic

representation of the entire programme with an orderly

identification scheme for each level of the project. It provides

continuity and a frame of reference throughout the project for

interconnections, interfaces between team members and the

critical path planning process.

(v) WBS facilitates project scheduling. The WBS enable to resemble

the start of a system diagram relates tasks and other elements in

term of sequence. With WBS, developing a task list and project

schedule consisting of critical path analysis network that

identifies all milestones and task activities has become very much

easier and practical.

(vi) The WBS facilitates costing. The cost of each element of the

WBS can be estimated and control. In this way, the WBS

becomes the mean by which costs are “rolled-up” and captured.

Unit costs are derived from this structure in order to document

the project cost history.

Page 51: AzharAbdullahKPFKA2006TTT

34

(vii) The WBS facilitates risks analysis. Each element in the WBS can

be assessed in term of the inherent risk involved in completion of

that element. It is important in critical path as well as in the

process of protecting against unforeseen failures.

From the seven purposes mentioned above, we can summarize the

benefits of the WBS as follows (Kliem and Ludin, 1998):

(i) WBS forces the project manager, the team members and client to

delineate the steps required for a project completion. It encourage

dialogue and discussion that could help to eliminate red-tape,

clarify ambiguities, bring out assumptions, narrow down the

project scope of work and early detection of critical

issues/complications.

(ii) WBS lays the ground work for developing an effective schedule

and almost accurate budget plan. A well define WBS enables

resources to be allocated to specific tasks, generating a

meaningful schedule and easy budget costing.

(iii) A well defined task can be allocated to specific individual and

easier to hold the person accountable for completing their tasks.

(iv) The process of developing and completing WBS breed

excitement and commitment. This participation will spark

involvement in the project.

Page 52: AzharAbdullahKPFKA2006TTT

35

Of course, developing a WBS is not easy. It could take several weeks to

prepare for a large WBS for a few thousand activities. It requires knowledge

transfer and brain power thus experience from the similar past projects could

help a lot in the developing it. An example of WBS for a project is shown in

Figure 3.2.

Figure. 3.2 An example of WBS

A specification tree developed by system engineering structures the

performance parameters for the system or systems being developed. It

subdivides the system(s) into its functional constituent elements and identifies

the performance objectives of the system(s) and its elements. The performance

characteristics are explicitly identified and quantified.

The completed specification tree represents a hierarchy of performance

requirements for each element of the system for which design responsibility is

Page 53: AzharAbdullahKPFKA2006TTT

36

assigned. Because specifications may not be written for each WBS elements,

the specification tree may not map the WBS completely. Administrative tasks

associated with system engineering & development of the specification tree is

normally treated as a support services WBS element.

3.5.1 WBS in Work Identification and Assignment

People performing work are organized to facilitate effective management,

whether the organization is designed along projectized, functional, or matrix

structure. To assign specific work responsibility to a specific organization, the

WBS and organizational structure should be integrated with each other (i.e.,

functional responsibility is established for managing specified work to produce

defined products). This integration can occur at any level of the WBS, but

certainly occurs at the top project level and whichever level responsibility that

has been assigned to manage the work. Other natural points of integration may

occur as a result of how the scheduling, budgeting, work authorization,

estimating and cost management systems interface with each other, with the

WBS and with the organization.

3.5.2 WBS in Schedule Management

WBS will be used to help plan, revise and update status schedules.

Schedule management typically involves the management team performing the

following steps in an incremental, iterative, parallel, time boxed, and ongoing

manner:

• collect schedule estimates from members of the development team.

• Develop, document, communicate, and maintain the schedules and

associated work breakdown structure.

Page 54: AzharAbdullahKPFKA2006TTT

37

• Maintain and control changes to the schedules and work breakdown

structure.

3.5.3 WBS in Plans

The WBS provides a framework for detailed work schedule information

based on technically verifiable product completion. A network of events (e.g.

start, complete) and activities (e.g. design, develop, operate) must take place.

There is logic to the relationship of the activities needed to produce and

complete the WBS products. Resources (e.g., labour, finance, plants, materials)

and responsible organizations (e.g., mechanical and electrical engineering

departments, fabrication department, sub-contractor) can then be identified for

each of the activities.

The scope and complexity of the work and the needs of management for

schedule visibility dictate the number and type of schedules. Schedule levels and

management levels need not coincide with WBS levels. There is no requirement

for separate schedules for each WBS levels.

Although scheduling methodologies may vary, it is important that

schedule events require completion of a tangible product in accordance with

predefined specifications and that completion is verified by test or inspection by

persons other than those responsible for performance of the activities leading to

completion of the product.

3.5.4 Status Reporting

Product-oriented schedules allow owners, consultants and builders to

monitor the schedule baseline for the project’s outputs to ensure that the project

objectives are completed on time. Owners or consultants may require builders

Page 55: AzharAbdullahKPFKA2006TTT

38

to file the following reports to monitor schedule progress and to manage the

project such as;

a) Periodic Milestone Schedule Status Report – to provide schedule

status information in terms of duration

b) Cost Performance Report – to assess schedule performance in

terms of earned value

c) Status Report – to provide a narrative description of the schedule

3.5.5 Cost Management

The WBS assists management in measuring cost. By breaking the total

product into successively smaller entities, management can verify that all work

identified to the WBS, hence charged to the effort that contributed to the project

objectives. Using WBS elements to plan the work serves as the basis for

estimating and scheduling resource requirements.

3.5.6 Cost Estimating

Using the WBS to help with cost estimating facilitates project and

contract management. The WBS provides a systematic approach to cost

estimating that helps ensure that relevant costs are not omitted. An estimate

based on WBS elements helps owners and builders to plan, coordinate and

control the various project activities that clients and builders are undertaking.

The WBS also provides a common framework for tracking the evolution of

estimates (e.g., conceptual estimates, preliminary design estimates and detailed

design estimates). The WBS can also provide a framework for life cycle cost

analysis.

Page 56: AzharAbdullahKPFKA2006TTT

39

As periodic project cost estimates are developed, each succeeding estimate is

made in an attempt to forecast more accurately the project’s total cost. Basically,

the estimates may be organized in two ways, i.e., by WBS element or by code of

accounts. Both support owners’ on-going efforts in preparing budgets and

evaluating contractor’s performance.

3.5.7 Budgeting and Cost Control

In general, funds management involves periodic comparison of actual

costs with time-phased budgets, analysis of variances and follow-up corrective

actions (as required). When WBS elements and the supporting work are

scheduled, a solid base for time-phased budgets is ready-made. This is

important for less experience contractors that have minimal knowledge in

controlling budgets. Assignment of planned resource cost estimates to scheduled

activities and summarization of each WBS element by time period results in a

time-phased project/contract budget, which becomes the performance

measurement baseline.

The Following is a brief discussion of analysis and control as well as

historical database development in relation to accounting.

a) Analysis & Control

If budgets are based on WBS elements and time phased with

scheduled accomplishment, the accounting process must similarly be

able to cost WBS elements over time (i.e., costed transactions must be

coded in such a way that they can be identified to the WBS element

which incurred the transaction cost and to the time period when the

transaction occurred).

Page 57: AzharAbdullahKPFKA2006TTT

40

An accounting process or system that can accommodate the WBS

has some advantages. The accounting system can be programmed to

accept or reject charges to relatively small increments of work with the

planned time schedule for the work and this helps to minimize

unauthorized charges. Also, the accounting and financial organizations

can better ensure that they have achieved what they paid for since a

product is accepted as complete only when a third party (e.g., work

inspector, quality controller, project manager) agrees that it meets the

specified objectives. As a result, periodic accounting and financial

variance analyses become more meaningful. Also, project performance

measurement, with its dependence on cost and schedule variance

analysis is then possible.

b) Historical Database Development

When cost information is accounted by WBS element, it can be

used in cost estimations for pricing and negotiating contract changes and

for follow-on procurements. Over time, owners and consultants will be

able to accumulate a growing cost database of similar WBS elements

from different projects. Such historical cost data can be used in

conjunction with learning curves, regression and other techniques to

estimate the cost requirements for similar elements of new projects.

Subsequent cost data collected can be compared to the original estimates

to establish their validity, identify trends and re-estimate future project

needs.

Contractors will similarly benefit from use of such databases.

Contractors are expected to periodically provide a current estimate of

future costs and the total estimated cost for each reporting element.

They are also expected to complete a detailed bottoms-up estimate

Page 58: AzharAbdullahKPFKA2006TTT

41

periodically. The WBS provides the framework for summarizing

detailed costs. Since contractors tend to provide similar products on

similar projects, the cost history that is accumulated can assist them in

bidding future contracts and in budgeting new work.

3.6 WBS as a Performance Measurement

Proper use of the WBS for technical, schedule and cost management

accomplishes the performance measurement objectives of defining work and

related resources, ensuring that all work is included and ensuring there is no

duplication of effort. In addition, the WBS is used to accumulate performance

data and associated variances. This permits the contractors to evaluate progress

in terms of contract performance. There is no need for separate contract

performance assessments to be made at levels above the cost account because

the WBS facilitates the summarization of data for successively higher levels of

management. Significant variances will usually appear at summary WBS levels.

Using the WBS, variances can then be traced to their sources.

3.7 Failure of Works Breakdown Structure (WBS)

It happens, sometimes, however, a WBS can do more harm than good.

The failure of WBS to improve performance of project

construction/implementation could be as follows:

(i) WBS does not reach to the detail level. It is kept to too high level

where responsibility of a team for specific activities cannot be

captured. Estimating, tracking the schedule and cost performance

has become “guestimation” (Kliem and Ludin, 1998). This is

Page 59: AzharAbdullahKPFKA2006TTT

42

because the lower levels are missing thus making the WBS too

general to be reliable.

(ii) The WBS is prepared by one individual and not by a collective

effort. Preparing WBS needs input from respective team who will

work on the tasks. As a result, few teams could be responsible for

certain activities.

(iii) WBS does not cover the whole project implementation. It may

cover only for the construction activities but ignored the other

related activities such as administration, procurement, testing,

training and process of submission to authorities. Due to it, the

delivery to customer could take longer time thus overall cost

could be higher and the end product is unsatisfactory.

(iv) WBS is not used in the project implementation. The project

manager takes an elective view of the WBS thus using only

selected activities in execution of the project. As the result, due to

lacking of experience and comprehensive view, the delivery is

not perfect. The defects are a lot and some of it may be quite

serious.

(v) WBS is flexible and subject to changes. Once everyone agreed to

it, WBS should not become “frozen”. Changes due to new

materials or method of construction or omission/addition of some

activities/tasks should be captured in the revised WBS/schedule.

Failure to manage changes to the WBS can result in unanticipated

impacts on the scope, schedule or cost.

Page 60: AzharAbdullahKPFKA2006TTT

43

In order to have the almost perfect WBS, an example of WBS from

similar past projects or a standard of WBS references should be established. By

this way, the one who prepared the WBS for the scheduling has a basic idea of

the activities/tasks involved. A basic standard and guidelines for preparing the

WBS released by a reliable body/organization could need to suit the current site

condition and any special project requirements imposed by the client or

authorities if a planner is required to prepare the WBS for the project scheduling

purpose.

3.8 Summary

The WBS is the foundation of project planning. It is developed before

dependencies are identified and activity durations are estimated. The WBS can

be used to identify the tasks in the CPM & PERT project planning models. In

this chapter, the advantages of using WBS in project scheduling shows that

WBS can helps contractors in many ways especially in helping them knows

what steps to be taken when certain phase of the construction takes place.

Contractors can avoid delays and wastage during the construction progress by

knowing clearly the do’s and don’ts when referring to WBS. The WBS is a tool

that helps contractors and project managers measure technical and schedule

performance as well as cost. By dividing the total product into successively

smaller entities, contractors and project managers can ensure that all required

products are identified in terms of technical performance goals. They can also

verify that all work identified to the WBS and then charged to the project,

actually contributes to the project objectives.

The planning of work based on WBS elements serves as the basis for

estimating and scheduling resource requirements. Subsequently, the assignment

of performance budgets to scheduled segments of contract work produces a

Page 61: AzharAbdullahKPFKA2006TTT

44

time-phased plan against which actual performance can be compared. When

performance deviates from the plan, appropriate corrective actions can be

undertaken. Identification of potential cost and schedule impacts of proposed

technical changes is simplified when this integrated approach to work planning

is used.

Page 62: AzharAbdullahKPFKA2006TTT

CHAPTER 4

METHODOLOGY OF THE STUDY

4.1 Introduction

The methods used in carrying out this study are explained in this chapter.

Based from Chapter 2 and Chapter 3, it is shown that WBS is very important in

school project planning. Although normal scheduling technique helps

contractors through the process of completing the project, its undeniable that

without preparing a proper WBS in the scheduling, some major items could be

missing or overlooked thus the preparation taken in implementing the items was

unintentionally and unfortunately ignored. More ever if the contractor engaged

in the school building projects have very little experience in managing school

projects. By the time the contractor realized the missing item was excluded in

the work program, damaged have been done

The methodology of this study has been carefully planned,

systematically organized and properly sequenced so as to ensure that a well

structured WBS for school project is develop. The result of this effort is a

seamless study program, from literature review, interviews, questionnaire survey

data collection, to the discussion of the results and finally the suggestion and

conclusion.

Page 63: AzharAbdullahKPFKA2006TTT

46

4.2 Determination of the Research Objectives.

The primary topic of research was mooted out of the consideration for

the difficulties and problems faced by government school construction projects.

However, the research objectives and scope of the dissertation was determined

after some preliminary studies which include facts-finding discussions with

relevant government officers, expert panels and on-site observation. Also, in the

process, some information of the contract documents especially those documents

related to project implementation has been investigated and some feasible

methods to carry out the study has also been considered. Later, more targeted

interviews have been conducted to reestablish the importance of the study.

The structured interviews has been carried out to the respondents from

senior officers in the Ministry Of Works in Johore, Ministry of Works for the

District of Petaling, officers from the Ministry of Education, professional

engineers from Jurutera Arena Consulting Engineers, experienced quantity

surveyors from Cawangan Ukur Bahan, Ministry Of Works and officers from

Wawasan Utama PMC, an appointed and established Project Management

Consultant company by the Ministry of Education. The highlight come from The

Director for The Cawangan Ukur Bahan, Ministry of Works, who commented

positively on the WBS topic and its importance for the supervision of school

construction.

Interviews were also conducted with a few contractors that have in depth

experiences in building schools. After the preliminary review, some specific

scopes of the study were determined based on the various consideration

elements such as achievability of the study, the time constraints and availability

of the research materials. The specific scopes of study have been discussed

previously in the first chapter.

Page 64: AzharAbdullahKPFKA2006TTT

47

4.3 Case Study on School Projects

Substantiating the ability to conduct this study more comprehensively,

numerous literatures have been reviewed to establish as much knowledge as

possible and equally important, to collect historical and current information,

trend and development pertaining to the study area. The material for the

literature review has been obtained from a wide variety of sources such as

published books, textbooks, information, discussion and blog from the internet

and articles in journals.

There are also published guidance papers from practitioners in the

industry and previous construction records both from the private sector and the

government construction departments. The purpose of literature review is to

gather important information related to the study topic and deepen the

understanding on how school project scheduling method was historically

practiced in the construction of government schools and how scheduling is

applied to present projects.

4.3.1 Research Materials

Few numbers of Work Programs, Progress reports, Bill of Quantities and

Contract Sum Analysis has been analyzed and studied. The main construction

program for each of the project report has been studied and made comparison in

order to identify the WBS elements. By comparing this documentations, the

lacking and imperfectness of the WBS prepared in the reports were analysed.

As for other data collection, interviews of two different stages were

conducted with each stage targeting different group of people. These interviews

are structured to include face to face interview in session one and requesting the

Page 65: AzharAbdullahKPFKA2006TTT

48

respondents to answer the structured questionnaires later. The first set of

interviews was focused to the project initiator, officers from the two ministry.

These face to face discussions reveal trends and policies of relevant authorities.

The second set of interviews was conducted with contractors, Civil

Engineering and Quantity Surveyors consultants and officers from the Project

Management Consultant for information related to factors influencing the

success or failure of a school construction project and also their opinions and

suggestions on improving how things are done.

This study does not include a general public sampling questionnaire

method of the industry. The explanation behind this was because, firstly, there

are only two government agencies responsible for school construction projects.

And secondly, public sampling might not be feasible as percentage of contractor

with realistic school construction project is relative low. Instead of Public

Sampling, this study used “target” group interview for more accurate and better

representation results.

4.3.2 Development of Questionnaire for the Survey

Questionnaires developed for the interviews are not aimed at mass

respondents as this study does not adopt the “Public Sampling” approach.

Instead, the study adopts “targeted group” interview approach for reasons

specified above. To get the most information out of the interview, questions

included for these surveys needs to be very specific and very objective

orientated. Questionnaires are thus constructed based on a subjective answering

model as Average Index Analysis on Likert’s Scale are not suitable in this

context.

Page 66: AzharAbdullahKPFKA2006TTT

49

Subjective answers obtained from these interviews are interpreted as best

as possible based on researcher’s understanding and further reassure by

confirming the answers with interviewee during the face to face discussion.

4.4 Interview with Panel of Experts (Clients)

These are sessions of interviews conducted between researcher and

officers who are involved in the preparation of tender / contract documents from

the Ministry of Work and Ministry of Education. These interviews also include

sessions with officers in both Ministries that are involved in technical evaluation

of the tender documents returned and submitted by tender participants.

These interviews with Panel of Experts are to establish how and what

documents are handed out to tender participants, and understanding the tender

documents to identify what are the required return-tender submission.

Interviews enable actual facts finding. The objectives of these discussions and

face to face sessions are to authenticate and further strengthen the research

findings in accordance to the main objective of this study. The objectives of our

interviews in this study are as follows:

• To single out what are the documents holders’ requirements

from tender participants or successful contractors.

• To examine these documents and analyze how these

documents influence tender participants / successful

contractors’ planning for scheduling of project.

• To identify the main weakness and causes of delays in

school construction project.

• To get their points of view on how WBS can help in

guiding contractors completing their job on time.

Page 67: AzharAbdullahKPFKA2006TTT

50

4.4.1 Methodology of the Panel of Experts Interview

Interviews with the panel of experts are conducted in two stages. During

the first stage, interviewees were asked to explain in details all tender

documents. Interviewees were also asked about relevant returned tender

submissions and how these documents are technically evaluated. During stage

two of the interview, interviewees were asked questions in accordance to the

questionnaire prepared to collect their opinions of current practice and on their

suggestive improvement measures.

Face to face interviews were conducted with officers in the Panel of

Experts category. These senior officers represent some of the most experienced

individuals from Ministry of Work and Ministry of Education whose work

functions directly related preparing, hand out, accept return tender submissions

and technical evaluation of contract / tender documents. Their explanation of

each documents were evaluated to determine benefits and weakness of the

current procedure. Their clarification of the returned tender submissions, which

directly reflect how contractors prepare their work scheduling planning, reveal

what are the conventional practice by contractors.

4.4.2 Structured Questionnaire Discussion

Structured questionnaire was conducted with officers from the Ministry

of Work and Ministry of Education. It is designed to be subjective answers

model where interviewer ask a question and interviewee reply. Their response

was recorded, analyzed and interpreted to as best as the researcher’s

understanding and the findings been tabulated for further discussion and studies.

Structured questionnaire and interviews were also conducted between the

researcher and panel of professionals who are involved in project administration

Page 68: AzharAbdullahKPFKA2006TTT

51

and monitoring, quantity surveyors and contractors who actually involved in

construction of schools. The interviews were carried out to review their opinion

on how the current methods of work scheduling planning is helping the

monitoring and administering of a school construction project.

The objectives of these interviews are to strengthen the research findings

based on the main objectives of this research:

• To discover the influential factors that determines the

successful / failure implementation of the school construction

project

• To pinpoint what actually goes wrong in the project

implementation.

• To gather suggestions and opinions on improving future

implementation on scheduling of project using WBS.

4.5 Analyzing the WBS (Case Study)

Based on each case study, the WBS for the main programme will be

studied. How well the WBS prepared will be commented. Matters to be

identified during the checking of WBS element are:

i) Highest level of the WBS

ii) Procurement of materials and machine

iii) Detail of breakdown structure

iv) Assignment of responsibility for each task in the WBS

v) Any milestone imposed by client/owner.

vi) Any items left out in the WBS.

vii) Any testing to be done and site visit to be organized.

Page 69: AzharAbdullahKPFKA2006TTT

52

After checking the above mentioned factors including many more, the

summary of the project’s WBS was tabulated and comparison was done to the

nine similar school building projects. From the table, the weakness of the WBS

were identified and commented. By identifying the weakness and the missing

items, suggestion for the proposed preliminary guidelines was proposed. The

format of the WBS presentation was also being introduced by dividing it into 3

main phases that are:

Phase 1 : Pre-construction phase

Phase 2 : Construction phase

Phase 3 : Post construction phase

4.6 Preliminary Guidelines for Preparing WBS for Project Scheduling /

Construction Programme

There is no simple formula to define how much detail should be included

in a work breakdown. Here are some helpful guidelines for completion:

• Break down the work until accurate estimates of cost and

resources needed to perform the task are provided.

• Ensure that clear starting and ending events are defined for the task.

• Verify that the lowest level tasks can be performed within a

“reasonable” time schedule. If the time to complete a task is too

long, an accurate project status in the implementation phase may

not be possible.

• Each task must have one clearly identified what type of tread of job

to be done.

Based on the above mentioned project examples, through experience and

referring to books/journals, a preliminary guidelines of WBS preparation was

Page 70: AzharAbdullahKPFKA2006TTT

53

prepared. From the suggested guidelines, it is hoped that the WBS preparation

by the contractors to be more precise and practical for construction planning.

The guidelines have been broken up into 4 parts mainly the characteristics,

preparation before and during the design of WBS and also the checklist. The

proposed guidelines can be used to help all parties that involved in construction

industry to prepare the WBS for scheduling that could achieve to their target and

expectation during construction period thus the chance of getting maximum

profit margin should be greater.

Part A of the guidelines was discussing the requirements and things to be

considered before designing the WBS. The number of subcontractors and budget

allocation are among the items to be considered in this section. Part B of the

guidelines was stressing the matters to be included when designing the WBS.

Among the matters are the ability for revision, tracking and controlling can be

performed and responsibility assignment can be done.

Part C of the guidelines mainly discussing the good characteristics of a

well prepared WBS while Part D presents the checklist to double check and

ensure the WBS designed is acceptable and capable to perform its actual

functions.

The guidelines had been revised by three senior personals that involved

in the construction industry mainly the planning works. From their feedback, the

guidelines were revised to be more perfect and comprehensive. Appendix G

shows the results of the interview. Anyway, the guidelines required to be

certified by the relevant parties such as JKR, CIDB, IEM, BEM, PAM and

others for it to be used as standard guidelines on WBS for our construction

industry.

Page 71: AzharAbdullahKPFKA2006TTT

54

4.7 Recommendation of a WBS for a Sample Project.

Through the abovementioned cases studied and from other examples, a

set of WBS for typical school building project was presented thus could be a

good example for building project of conventional type of contract. All

tasks/activities in the WBS of course will be slightly differs for every projects

depending on the site condition, location, materials and contract requirements.

The proposed WBS has not been tested for its effectiveness and weakness.

Of course, it is better to have at least something rather than nothing. By the

example given, it is much easier for a contractor to start designing their own

construction programme by picking-up the relevant items that could suite to

their project. By applying the WBS in a computer programme, the contractor

could fit in the dates for the schedules and adjust it whenever necessary during

monitoring or revising it due to the latest information and requirements.

Furthermore, delay can be avoided.

Page 72: AzharAbdullahKPFKA2006TTT

CHAPTER 5

DATA ANALYSIS AND DISCUSSION 5.1 Introduction

This chapter deal with the analysis and discussion of data collected from

interviews from the expert panels and contractors involved in the construction of

delayed and non-delayed school projects. The identification of non-delayed and

delayed school projects were obtained from the Ministry of Education and

Ministry of Works. Total of nine school projects were selected which comprises

of five delayed school projects and four non-delayed school projects.

The summary of delayed and non-delayed school projects were tabulated

in Table 5.1 as shown below. Contract document and contract sum analysis for

delayed and non-delayed were identified, extracted, tabulated and analyzed.

Table 5.2 summarizes the expert panels and contractors that were involved with

the school projects identified for the case studies. In addition, Table 5.3 gives

the views from twenty respondence towards the causes of school project delay.

On the other hand, Table 5.4 shows the comparison on element in contract

document for breakdown structure for delayed and non-delayed school projects

which were obtained from Ministry of Works and Ministry of Education and

Table 5.5 shows the comparison of construction activities based on WBS

element in project schedule from contract documents for the delayed and non-

delayed school projects. .

Page 73: AzharAbdullahKPFKA2006TTT

Table 5.1: The summary of CIDB registration grade and type of contract documentation for delayed and non-

delayed school projects (Ministry of Education and Ministry of Works, 2005)

Non delayed School construction projects

No Project Title Main Contractor CIDB Registration

Type of Contract and documentation

Reference Code

1. The Construction and Completion of Sekolah Kebangsaan Kampong Lindungan, Daerah Petaling, Selangor.

Federal Malay Enterprise Sdn. Bhd.

Grade G7 Open Tender, Contract Document and BQ

ND1

2. The Construction and Completion of Sekolah Menengah Kebangsaan Rasau, Kemaman, Terengganu.

Pembinaan M.A.N sdn. Bhd. Grade G7 Design and Built, Contract Sum Analysis

ND2

3. The Construction and Completion of Sekolah Menengah Kebangsaan Muazam Jaya, Rompin Pahang.

Pembinaan TLN Sdn. Bhd. Grade G7 Design and Built Contract Sum Analysis

ND3

4. The Construction and Completion of Sekolah Menengah Kebangsaan Teluk Gunung, Kuala Lipis. Pahang.

Manap Maju Sdn. Bhd. Grade G7 Open Tender, Contract Document and BQ

ND4

* ND – Non delayed D - Delayed 56

Page 74: AzharAbdullahKPFKA2006TTT

Table 5.1: continued.. Delayed School construction project

5. The Construction and Completion of Sekolah Chedung Jaya, Maran, Pahang.

GPP Sendirian Bhd. Grade G7 Design and Built, Contract Sum Analysis

D1

6. The Construction and Completion of Sekolah Kebangsaan Tanjung Batu, Temerloh, Pahang.

Asasteraju Construction Sdn. Bhd.

Grade G7 Design and Built, Contract Sum Analysis

D2

7. The Construction and Completion of Sekolah Menengah Kebangsaan Seri Serating, Terengganu.

PALAS Berhad. Grade G7 Design and Built, Contract Sum Analysis

D3

8. The Construction and Completion of Sekolah Menengah Kebangsaan Nyiur Paka, Terengganu.

Chulan Construction Sdn. Bhd.

Grade G7 Design and Built, Contract Sum Analysis

D4

9. The Construction and Completion of Sekolah Menengah Seri Bandi, Kemaman, Terengganu.

Ensidesa Sdn. Bhd. Grade G7 Design and Built, Contract Sum Analysis

D5

* ND – Non delayed D - Delayed

57

Page 75: AzharAbdullahKPFKA2006TTT

Table 5.2: Summary of the expert panels and contractors involved in the case study

(Ministry of Education and Ministry of Works, 2005).

School Project

Panel of Expert

Contractors, PMC and Consultant

Sekolah Kebangsaan Kampong Lindungan Daerah Petaling, Selangor.

Ministry of Works Federal Malay Enterprise Sdn. Bhd. Jururunding Pakatan Arena Sdn. Bhd.

Sekolah Menengah Kebangsaan Rasau Kemaman Terengganu

Ministry of Education Pembinaan M.A.N Sdn. Bhd Wawasan Utama PMC

Sekolah Menengah Kebangsaan Muazam Jaya, Rompin, Pahang.

Ministry of Education Pembinaan TLN Sdn. Bhd Wawasan Utama PMC

Non Delayed School Projects

Sekolah Rendah Kebangsaan Teluk Gunung Kuala Lipis, Pahang

Ministry of Works Manap Maju Sd. Bhd. Jururunding Pakatan Arena Sdn. Bhd.

Sekolah Menengah Kebangsaan Chedung Jaya Maran, Pahang

Ministry of Education GPP Sendirian Berhad Wawasan Utama PMC

Sekolah Kebangsaan Tanjung Batu Temerloh, Pahang

Ministry of Education Asasteraju Contruction Sdn. Bhd Wawasan Utama PMC

Sekolah Menengah Kebangsaan Seri Serating Terengganu

Ministry of Education PALAS Berhad Wawasan Utama PMC

Sekolah Menengah Kebangsaan Nyiur Paka , Terengganu

Ministry of Education Chulan Construction Sdn. Bhd Wawasan Utama PMC

Delayed School Projects

Sekolah Menengah Kebangsaan Seri Bandi Kemaman, Terengganu

Ministry of Education Ensidesa Sdn. Bhd.

58

Page 76: AzharAbdullahKPFKA2006TTT

Table 5.3: Content Analysis - Summary of views from twenty respondence towards the causes of school project

delay.

Question Resp. 1 Resp. 2 Resp. 3 Resp. 4 Resp. 5 Resp. 6 Resp. 7 Resp. 8 Resp. 9 Resp. 10 1. Do you have

previous experience in handling school projects?

Yes in Preparation of Tender Document

Yes In tendering.

Yes In tendering

Yes In monitoring school projects

Yes as a Superintending Officer on behalf of the government

Yes. But not specific on school projects. Others too.

Yes. On behalf of the contractor.

Not directly but as a management team.

Yes for monitoring

Yes for monitoring

2. What

constitute to the school project delay or failure?

Lack of experience. Claims done badly.

Poor working strategies.

Poor monitoring, mobilization of resources

Lack of experience.

Contractor didn’t follow the work program properly.

Bad site management

No proper scheduling tools.

New contractor. No experience.

Project not well managed.

Understanding of scheduling technique not taken care of.

3. What was the

monitoring and administering strategy adopted?

Project Manager or a Clerk of Work at site. Based on work program.

Project Manager or a Clerk of Work at site. Based on work program.

Project Manager or a Clerk of Work at site. Based on work program.

Representative from the MOE to monitor project.

Reporting on weekly basis to the project initiator.

Site meeting held from time to time. Progress of work were monitored.

Client have their representative doing the monitoring.

Representative from the MOE to monitor project

PMC will monitor the project based from the work program.

PMC will monitor the project based from the work program

4. What is your

perception of work program? Is this method of project planning detail enough?

A good work program is essential but must be with good experience

It helps contractor to monitor their project.

A work program must include WBS. It really helps.

Contractor must understand the needs to have good work program.

Delay happens when some task or activity was not clearly shown on work program. Must include WBS.

A work program must come with detailed task. WBS must be included.

Understanding work program is important at the early stage of the project.

It is important.

Work program must be understood by all parties involved.

Work program must be understood by all parties involved

59

Page 77: AzharAbdullahKPFKA2006TTT

Table 5.3: continued.. Question Resp. 1 Resp. 2 Resp. 3 Resp. 4 Resp. 5 Resp. 6 Resp. 7 Resp. 8 Resp. 9 Resp. 10 5. Does any

Project Management Consultant has any guideline or ISO to monitor project?

No idea. No idea. They should have the guidelines at least.

Yes. But it differs from others PMC.

No idea. Never engage any deal with any PMC before. No idea.

No. They haveguidelines, since it will be put in their monitoring site report.

Yes and it applied as a standard monitoring document. No ISO.

Yes and it applied as a standard monitoring document. No ISO.

6. How is the

project payment being facilitated? Paid on time?

Depend on the claiming process and procedure.

Yes if they did the job.

Yes. Genuine claims will be attended fairly.

Depend on the total cost of work done.

Normally no. Have to wait for new allocate budget.

No. Contractor must be financially strong.

Good payment scheme can avoid delay.

Payment made based on work progress.

Delay can be due to lack of experience when making claims.

No record on good payment.

7. Based on your

experience, what are the most common type of project scheduling technique used?

Bar chart with a few of them using WBS

Bar chart, Gantt Chart and PDM

Gantt Chart. A few used PDM and WBS.

Bar chart and Gantt Chart

Bar chart is widely used. A few with WBS and PDM

Bar Chart and Gantt Chart

Gantt Chart set by the consultant

Bar chart and a few using Gantt Chart

Bar Chart from the Contract Sum Analysis

Bar chart and Gantt Chart

8. In terms of work packages on site, do you think WBS can help to guide contractor better?

Yes. Strongly agreed and should be supported.

Yes. Contractor must know the advantages of WBS.

WBS can be handy for new contractors with little experience.

Yes. Exposed it to contractors.

WBS can help to reduce delays.

Nothing will be left unseen if WBS exists.

Yes. Contractors can develop WBS with the aid of consultant engineers.

May be. Extra effort must be done by the contractors.

Yes. They will know what and when to do the task.

Yes. For sub contracting purposes.

9. Your overall

view on WBS?

Good but may be new to some.

Must be fully adopted

Make it as a contract document.

Can help contractors a lot.

Good approach to avoid delay.

Good. Should have guidelines.

They must be a standard check list on it.

Good. Can assist contractor.

Good. A new approach.

Get every construction personnel involved.

60

Page 78: AzharAbdullahKPFKA2006TTT

Table 5.3: continued..

Question Resp. 11 Resp.12 Resp. 13 Resp. 14 Resp. 15 Resp. 16 Resp. 17 Resp. 18 Resp. 19 Resp. 20 1.Do you have

previous experience in handling school projects?

No but have some similarity.

Yes, as a sub contractor.

Yes.

Sub contractor for mechanical and electrical works.

Yes. Main contractor for school projects.

Yes, from the Ministry of Works.

Yes

Yes

Yes

Yes, portion of it. As a Sub contractor

2. What

constitute to the school project delay or failure?

Poor communication among parties involved.

Poor management by the main contractor.

Experience, knowledge to do work.

Main contractor lack or experience.

Poor connection with suppliers.

Poor coordination, late payment.

No experience.

Poor financial management.

Poor management, no experience.

Poor coordination, poor monitoring.

3. What was the

monitoring and administering strategy adopted?

Client representative refer to work program.

Refer to work program.

Clerk of work to follow work program.

Work done based on time frame.

Site engineer with vast experience. Follow work program.

Project Manager to attend site meeting with client.

Day to day monitoring by clerk of work.

Project monitoring and site meeting.

Monitoring by PMC

Client representative and site meeting held from time to time.

4. What is your

perception of work program? Is this method of project planning detail enough?

Must be prepare by contractor, although not detail but use full.

No. sometimes work program doesn’t show the actual work.

If properly prepared, can help contractor to avoid delay.

Must be understood by others. Should be detail enough.

Make it simple but detail. Add on with WBS is much better.

Very important document, a guide to finish the job. Must be detail.

Prepared by contractor. Must make detail.

Work program must be detail. Must show work packages or WBS.

Important document to assist contractor to complete the job. Yes, detail enough.

Main work program must be detail, can coordinate sub contractors and suppliers.

61

Page 79: AzharAbdullahKPFKA2006TTT

Table 5.3: continued..

Question Resp. 11 Resp. 12 Resp. 13 Resp. 14 Resp. 15 Resp. 16 Resp. 17 Resp. 18 Resp. 19 Resp. 20 5. Does any

Project Management Consultant has any guideline or ISO to monitor project?

No idea. No idea. Yes. They should have.

No idea. Yes, they do have guide lines. For the ISO, no idea.

Yes, for the purpose of reporting.

No idea. Doesn’t have any experience with them.

Yes. Their monitoring based on guidelines.

Yes. They have guidelines

Although the PMC are lack of experience, they have guidelines

6. How is the

project payment being facilitated? Paid on time?

Late payment is common.

If we prepare good paper works, it wont be a problem.

Project depends on payment. Late payment is common.

Can coup with late payment. Have good financial background.

Contractors needs good pay master

Payment will help contractor to pay sub contractors

Need to control cash flow. Always late payment.

Contractor relies on claims to continue the work.

Late payment can cause delay.

Contribute to delay of work

7. Based on your

experience, what are the most common type of project scheduling technique used?

Gantt Chart and Bar chart.

Bar chart and Gantt chart. Few use the PDM.

Gantt chart. Easy to understand.

Gantt chart for overall project. Bar chart for sub contractors.

Main contractors used Gantt chart.

Gantt chart, easy to update.

Gantt chart and Bar chart.

Bar chart and Gantt chart

Most common, Gantt chart

Bar chart applicable for small projects

8. In terms of work packages on site, do you think WBS can help to guide contractor better?

Yes, strongly agreed.

WBS can help contractors with less experience.

Yes. WBS shows detail work that should be done.

WBS can guide main contractors. Sub contractors know their work well.

Yes. Its advisable to have detailed works shown.

WBS is new. Can try to adapt it.

Yes. It helps contractor to avoid delay.

Yes. Must be included in the Gantt chart.

Yes Subcontractors are well verse with their routine job.

9. Your overall

view on WBS?

Help full to avoid delay

Use full for new contractors

Very detailed.

Can adapt JIT concept

Guidance for contractors.

Give it a try

Will know what to do and when.

Very use full

Can avoid delay and wastage.

It will help main contractors.

Note: Refer to Appendix 1 for the detail background of respondent (Resp 1,2,3,4,5,6,7,8,9,10,11,12, 13,14,15,16,17,18,19,20)

62

Page 80: AzharAbdullahKPFKA2006TTT

63

Table 5.4: Comparison of construction activities generated from Contract Document and Contract Sum analysis

No DESCRIPTION ND1

ND2

ND3

ND4

D1

D2

D3

D4

D5

1 PART 1 - INITIAL COST 2 Contract 3 Performance Bond X X X X X X X X X 4 Insurance X X X X 5 SOCSO X X X 6 Site Office for the SO X X X X X X X X 7 Equipment and Facilities X X X X 8 SO Telephone X X 9 Survey Instrument and Personnel X X 10 Site Items for SO X X 11 Office Equipment X X 12 General Facilities and Obligation 13 General Obligations 14 Site Survey X X X X X X X X X 15 Project Signboard X X 16 Statutory Obligation 17 CIDB Act X X X X X X X X X 18 Safety and protection 19 Safety Precaution X X X X X X X X 20 Hoarding X X X X X X X X 21 First Aid Kit X X 22 Environmental Protection 23 Environmental Protection X X X X 24 Control of Noise & Disturbance X X 25 Drainage and Erosion Control X X 26 Project Monitoring 27 Programmed of Work X X X X X X X X 28 Construction Quality Plan X X 28 Contractors Plant, Equipment, Facilities X X 30 Contractors Storage and Office X X X X X X 31 Contractors Temporary Accommodation X X X X 32 Contractors Plant and Equipment X X X X X X X X 33 Sanitation X X X X 34 Foremen and Assistant X X 35 Temporary Facilities and services 36 Temporary Water, Lighting and Power X X X X X X X X 37 Water for the works X 38 Lighting and Power X 39 Access and Temporary Road X X X X X X 40 Temporary Diversion / Services Relocation X X X X X X X

Page 81: AzharAbdullahKPFKA2006TTT

64

Table 5.4: continued..

41 PART II - PROGRESSIVE COST 42 Contract 43 Site Office for the SO X X X X X X X X X 44 Equipment and Facilities X X X X X X X X 45 SO Telephone X X 46 Survey Instrument and Personnel X X 47 Site Items for SO X X 48 Office Equipment X X X X X X 49 General Facilities and Obligation 50 General Obligations 51 Clearing, Cleaning and Making Good X X X 52 Statutory Obligation 53 Safety and protection X X X X X X X X X 54 Safety Precaution X 55 Hoarding X X X X X X X X X 56 First Aid Kit X X 57 Adjoining Property 58 Watching 59 Care and Protection X X X X X X 60 Environmental Protection 61 Environmental Protection X X X X X X X 62 Control of Noise & Disturbance X X 63 Drainage and Erosion Control X X 64 Project Monitoring 65 Programmed of Work X X X X X X X X X 66 Construction Quality Plan X X 67 Progress Photograph X X 68 Video Filming X X 69 Contractors Plant, Equipment, Facilities 70 Contractors Storage and Office X X X X 71 Contractors Temporary Accommodation X X X X X X X X X 72 Contractors Plant and Equipment X 73 Sanitation X X X X X X X X X 74 Foremen and Assistant X X X X X 75 Temporary Facilities and services X X X 76 Temporary Water, Lighting and Power X X X X X X 77 Water for the works X X 78 Lighting and Power X X 79 Access and Temporary Road X X X X X X X X X 80 Temporary Diversion / Services Relocation X 81 PART III – COMPLETION COST 82 Contract 83 Site Office for the SO X X X X X X X X X 84 Equipment and Facilities X X X 85 SO Telephone X X

Page 82: AzharAbdullahKPFKA2006TTT

65

Table 5.4: continued..

86 General Facilities and Obligation 87 General Obligations X X 88 Project Signboard X X X X X X X X X 89 Clearing, Cleaning and Making Good X X X X X X X X X 90 Statutory Obligation 91 Safety and protection X X X X X 92 Safety Precaution X 93 Hoarding X X X X 94 Adjoining Property X X 95 Watching X X 96 Care and Protection X X 97 Contractors Plant, Equipment, facilities

and Site Agent

98 Contractor Storage and Office X X X X 99 Contractor Temporary Accommodation X X X X X X X 100 Contractor Plant and Equipment X 101 Sanitation X X X 102 Temporary Facilities and Services 103 Access and temporary Road X X X X 104 Temporary Diversion, Relocation Existing

Services X

105 Submittals 106 As-Built Drawing X X X X 107 Piling Records X X

Page 83: AzharAbdullahKPFKA2006TTT

66

Table 5.5: Comparison of construction activities based on WBS element in project

schedule generated from contract documents.

No WBS ELEMENT ND 1

ND 2

ND 3

ND 4

D1 D2 D3 D4 D5

1 Pre Construction Phase 2 Soil investigation X X X X X X X 3 Submission for approval X X X 4 Accommodation X X 5 Milestone activities X X 6 Construction Phase 7 Prelim X X X X X X X X 8 Part I – Initial cost X X 9 Part II - Progressive cost X X 10 Part III - Completion Cost X X 11 Mobilization X X X 12 Deliverables X X X 13 Setting out X X X X X 14 Temporary water / power supply X X X 15 Temporary access X X X 16 Site clearing X X X X X 17 Hoarding X X 18 Piling Works X X X X X X 19 External Works 20 Site Preparation and Earthworks X X X X X X X 21 Site clearance X X X X X X 22 Excavation and remove surplus X X X 23 Filling X X 24 Water Reticulation and Related works X X X 25 Sewer Reticulation and related works X X 26 Telecommunication works X X X X X X X X X 27 Permanent power supply X X X X 28 Fencing/gate X X X X 29 Landscape (softscape/hardscape) X X X X 30 Street/compound lighting X X X X 31 Road//hardstanding/parking X X 32 Substations, rubbish bin area, workshops X X 33 Field/ playground X X X X

Page 84: AzharAbdullahKPFKA2006TTT

67

Table 5.5: continued..

34 Building Works Block A X X X X X 35 Pile cap X X X 36 Ground beams X X 37 Columns X X 38 Ground Floors slab X X 39 Ground floor column X X 40 1st floor beam X X 41 1st floor column X 42 2nd floor beam X 43 2nd floor column X 44 3rd floor beam X 45 3rd floor column X 46 Roof beam X X 47 Roof trusses X 48 Roofing X X 49 Ceiling finishes X X 50 Ground floor 51 Staircase X X 52 Brick works X X 53 Doors, windows and frame X X 54 Wall finishes x X 55 Cement Plaster (internal) X 56 Cement Plaster (external) X 57 Floor finishes X X 58 Tiling X X 59 Furniture X X 60 1st Floor 61 Staircase X X 62 Brick works X X 63 Doors, windows and frame X X 64 Wall finishes X X 65 Cement Plaster (internal) X 66 Cement Plaster (external) X 67 Floor finishes X 68 Tiling X X 69 Gypsum board partition X 70 Furniture X X 71 2nd Floor 72 Staircase X X 73 Brick works X X 74 Doors, windows and frame X X 75 Wall finishes X X 76 Cement Plaster (internal) X

Page 85: AzharAbdullahKPFKA2006TTT

68

Table 5.5: continued..

77 Cement Plaster (external) X 78 Floor finishes X X 79 Tiling X X 80 Gypsum board partition X 81 Furniture X X 82 3rd Floor 83 Brick works X X 84 Doors, windows and frame X X 85 Wall finishes X X 86 Cement Plaster (internal) X 87 Cement Plaster (external) X 88 Floor finishes X X 89 Tiling X X 90 Gypsum board partition X 91 Furniture X 92 REPETATION FOR BLOCK B AND C X X X X X X 93 M&E works X X X X X 94 Plumbing and sanitary Appliances X X X X X 95 Cold water system X X X X X 96 Rain water down Pipe and Gutter X X X X 97 Painting Works X X X X 98 Apron and perimeter drain X X X X 99 Deadline X X 100 Deliver X 101 Anjung X X X X X 102 Piling Works X X 103 Construction work X X 104 Linking bridge 105 Piling Works X X Construction Works X X 106 Guard House 107 Construction works X X X X X X X X X 108 TNB Substation X X X X X X X 109 Piling work X X 110 Construction work X X 111 External works X X X X X X 112 Refuse bin X X X 113 Wakaf X X X X X X X 114 Netball X X X

Page 86: AzharAbdullahKPFKA2006TTT

69

Table 5.5: continued..

115 Takraw X X X X X 116 Badminton X X X 117 Covered Walkway X X X X 118 Fencing, gates and footpath X X X X 119 Courtyard stage and flag post X X 120 Roads and car park X X X X 121 Surface water drainage X 122 Water reticulation X X 123 Sewerage system X X X 124 Piling X X 125 Sewer pipe and manhole X X X 126 Provisional Sum and Turfing X X X 127 Deadline X 128 Handing over

Page 87: AzharAbdullahKPFKA2006TTT

70

5.2 Effect of registration grade and type of documentation on the

completion of school projects

Table 5.1 shows that all contractors involved in the construction of

school projects in this case study was from CIDB registered as Grade 7. From

Table 5.1 and 5.2 it was seen that non-delayed school project adopted 50% Open

Tender Contract Document which were provided by Ministry of Works and 50%

Design and Built Contract Sum Analysis which were provided by the Ministry

of Education. However, for the delayed school projects, all contractors adopted

Design and Built Contract Sum Analysis. Therefore it can be said that adopting

Open Tender Contract Document provided by the Ministry of Works can avoid

delay in school projects.

5.3 Lack of experience affecting school projects delay

Content analysis as shown in Table 5.3 summarizes the factors that

contribute to the success and failures of school projects. 30% views from

respondents of various construction backgrounds responsibilities states lack of

experience contribute to school project failure. However, 20% of poor

understanding in project scheduling, 15% poor management, 20% poor

coordination between the contractor and the supplier and 15% due to late

payment.

5.4 Effect of work program on the completion of school project

From Table 5.3, 100% of respondent‘s view states that work program

will contribute to a successful construction projects. However, 20% of them

agreed that by introducing WBS in any scheduling technique could improve the

Page 88: AzharAbdullahKPFKA2006TTT

71

site management in terms of coordination between the contractors and the

laborers and hence avoiding delay in school construction projects.

In addition, Table 5.4 shows that all non-delayed construction project

detailed out their work program into work activities. However, the delayed

construction school projects ignored the importance of detailing out the work

activities in their work program.

From the above analysis and discussions it can be concluded that role of

WBS in school construction work program is critical to ensure non-delayed

construction of school projects. Therefore the development of WBS for school

construction projects will be elaborated in chapter 6.

Page 89: AzharAbdullahKPFKA2006TTT

CHAPTER 6

DEVELOPMENT OF WBS FORMAT AND GUIDELINES

6.1 Introduction

From Chapter 1 to Chapter 4, the study has discussed in length on issues

related to the development of school construction project in Malaysia. More

specifically, the chapter has also discussed the process practiced by The

Ministry of Works and The Ministry of Education. With these insights, we are

able to see the overall picture of the undertakings that a tender participating

contractor will have to go through and how the normal construction works will

be implemented.

Chapter 3 was dedicated to discussion on the importance of Work

Breakdown Scheduling (WBS) in the context of construction industry in general

and school construction project in specific. From this discussion, the study

managed to establish the contribution of a well planned and implemented WBS

in assisting the contractors to manage and supervise their project. WBS also

displayed its usefulness in the entire construction project from the work program

planning stage to completion, adhering to timeframe set and conforming to

quality expected.

Page 90: AzharAbdullahKPFKA2006TTT

73

6.2 Preparation of WBS

From the nine cases studied earlier, we can conclude that almost all

items in the work program calendar that does not carried any significant

(dummy activities) were normally ignored. Dummy activities although do not

indicate the progress of work, it is nevertheless very important for the project

completion and hand-over. Activities such as submission of samples and factory

visit do not contribute directly to the works progress but without the approval of

materials, it will be hard to imagine how the work on site can be started.

Many contractors refer only to the BQ when during their preparation of

WBS for the works programme. This sometimes proves to be a serious flaw and

render the whole purpose of WBS significantly useless. Instead, they should also

refer to all other contract documents like the specifications documents and other

contract requirements. A well prepared WBS will ensure that no interruption in

the work progress due to minor missed-out like non-compliance to specifications

or method statements.

The non-uniformity of reference adopted by different contractors has

created confusion among not only themselves, but other working partners like

the client, the sub-contractor and the PMCs. Some contractors refer to the BQ to

generate their WBS while some others refer to the specifications documents and

plan drawings, worse there are even those who just ignored any reference to the

contract documents and creating their own baseless WBS. Amidst this confusion

most of these contractors resorted to simplify the WBS elements to the level that

it is only to satisfies the documentation requirement by the client, resulting in

the principal purpose of WBS such as costing, monitoring, controlling and

reporting cannot be utilized effectively.

Page 91: AzharAbdullahKPFKA2006TTT

74

It is also disheartening to discover that, contractor has treated WBS

preparation as just another documentation requirement in process of winning

tender. Some of them even employ outsider who has no knowledge of that

specific tender / project to produce the WBS on their behalf. In the actual

implementation, they ignore and do not reap the full potential of WBS

deployment on site. In cases like this, we discovered that, contractor was no

doubt, not following the schedule since they had asked others to prepare the

WBS / scheduling for them.

Because of the lack of knowledge in the WBS they have submitted for

approval (they employ third party to do it for them), these contractors sometimes

do not realize or recognize the items / tasks that were indicated in the work

programme. To employ a permanent professional planner does not appear to be

a important thing to do. Therefore, it is normal to them that the progress of work

on site being delayed for checking, while supervision were not conducted

closely and diligently. Just another point on mind: One can never hear a project

that is running smoothly and on time in school construction project. If you walk

into a site meeting, everybody seems to always be struggling to catch-up to the

delayed delivery.

6.3 Proposed Format of WBS Presentation

After reviewing the nine case studies, analyzing inputs from experts’

panel and extracting resource from professional progress reports and literature

references, this study formulated and recommend the following format of WBS

presentation. The WBS items for school building works are proposed to be done

as below:

Page 92: AzharAbdullahKPFKA2006TTT

75

A) Stage 1 : Pre-construction Phase

i.) Soil investigation ii) Submission for approval iii) Accommodation iv) Milestone activities

B) Stage 2 : Construction Phase i) Preliminaries Part I – Initial cost Part II - Progressive cost Part III - Completion Cost ii) Mobilization iii) Deliverables iv) Setting out v) Temporary water / power supply vi) Temporary access vii) Site clearing viii) Hoarding ix) Piling Works

x) Building Works Block A

Pile cap Ground beams Columns Ground Floors slab Ground floor column 1st floor beam 1st floor column 2nd floor beam 2nd floor column 3rd floor beam 3rd floor column Roof beam Roof trusses Roofing Ceiling finishes

Ground floor

Staircase Brick works Doors, windows and frame Wall finishes Cement Plaster (int)

Page 93: AzharAbdullahKPFKA2006TTT

76

Cement Plaster (ext) Floor finishes Tiling Furniture

1st Floor

Staircase Brick works Doors, windows and frame Wall finishes Cement Plaster (int) Cement Plaster (ext) Floor finishes Tiling Gypsum board partition Furniture

2nd Floor Staircase Brick works Doors, windows and frame Wall finishes Cement Plaster (int) Cement Plaster (ext) Floor finishes Tiling Gypsum board partition Furniture

3rd Floor

Brick works Doors, windows and frame Wall finishes Cement Plaster (int) Cement Plaster (ext) Floor finishes Tiling Gypsum board partition Furniture

M&E works Plumbing and sanitary Appliances Cold water system Rain water down Pipe and Gutter Painting Works

Page 94: AzharAbdullahKPFKA2006TTT

77

Apron and perimeter drain Deadline

REPETATION FOR BLOCK B AND C

Anjung Piling Works Construction work Linking bridge Piling Works Construction Works Guard House Construction works TNB Substation Piling work Construction work

External works Refuse bin Wakaf Netball Takraw Badminton Covered Walkway Fencing, gates and footpath Courtyard stage and flag post Roads and carpark Surface water drainage Water reticulation Sewerage system Piling Sewer pipe and manhole Provisional Sum and Turfing Deadline

C) Stage 3 : Post Construction Phase i) Demobilization

ii) Clearing of debris

iii) Submission of as-built drawing

iv) Submission of test reports

v) Submission of O&M manual

Page 95: AzharAbdullahKPFKA2006TTT

78

vi) Submission of defects list

vii) Testing and commissioning

viii) Submission of warranty and certificates

ix) Submission of approval from authorities

xi) Inspection for CPC

xii) Final measurement/account

Please note that, the recommended formulation might deviate slightly

from a project to another. This is mainly due to differing circumstances like site

location, climate, availability of material and machines. In view of the non-

standardization of project awarding processes practiced within the school

construction project sector, the recommended format might also differ slightly to

adapt to contract conditions and requirements.

6.4 Guidelines for the Designing of WBS

There is no simple formula to define how much detail should be included

in a work breakdown. Here are some helpful guidelines for completion:

• Break down [decompose] the work until accurate estimates of cost

and resources needed to perform the task are provided.

• Ensure that clear starting and ending events are defined for the task.

• If necessary, verify that the lowest level tasks can be performed

within a “reasonable” time schedule. If the time to complete a task

is too long, an accurate project status in the implementation phase

may not be possible.

• Each task must have one clearly identified what type of tread of job

to be done.

Page 96: AzharAbdullahKPFKA2006TTT

79

Harbans (2004) noted in the “Buletin Ingenieur” that :

“As for the form, there are currently no guideline available locally

spelling out the expected contents of the work programme. Much is left to the

contractor to decide based on his experience, bearing in mind the purpose of the

programme in the context of the particular circumstances of the contract works

being undertaken.”

Referring to Construction Industry Development Board (CIDB) contract

form Clause 5.1 (a) reads:

“ … the contractor shall, not later than Date of Commencement submit

for the approval of the Superintending Officer.”

a) a works programme related in the Time for completion, clearly

identifying the sequence, logic and critical path in which he proposes to carry

out the works, including the various work activities and milestone to be

achieved ….”

Harbans, (2004) again quoted that :-

“In approaching this subject, one should be mindful of the fact that the

actual content of a particular works programme is also influenced by the

method of contract procurement adopted. Hence, it is therefore inevitable that

the content of a ‘Package Deal’ type of work programme will materially differ

from that under the traditional contracting route”.

For a contractor preparing his own Contractor’s Work Breakdown

Structure (CWBS), the guidelines (Part A) below can be utilized as the basis and

framework to draw up their CWBS:

Page 97: AzharAbdullahKPFKA2006TTT

80

Part A

1. Technical requirement and complexity of work

2. Resource requirements

3. Cost of works programme

4. Time span in preparing the programme

5. Contractor – client internal structure in term of management control

and reporting.

6. Numbers of subcontractor to implement the project

Based on the findings and referring to the existing recommendation from

the experts, listed below (Part B) are some of the characteristics to be taken into

consideration and practiced by the planner / planning engineer in preparing the

WBS for project scheduling.

Part B

1. Manageable, in that specific authority and responsibility can be

assigned.

2. Independent or at least with minimum interfacing with other WBS

elements.

3. Measurable for each element to monitor the progress.

4. Integratable so that the total package can be seen.

5. The summation of elements to be represented by the next upper level

elements.

6. Cost and budget can be established.

7. Planning can be performed.

8. Tracking work in term of time, cost and performance can be

implemented.

9. Responsibility assignment for each element can be done.

Page 98: AzharAbdullahKPFKA2006TTT

81

10. Reporting of progress scheduled can be established.

11. Objectives and company resources can be linked in logical manner.

To identify the complexity of the WBS, all the above mentioned

guidelines have to be considered. All sections and departments are required to

produce relevant data to the planner for the input in preparing the WBS. Co-

ordination and co-operation of every party is required so that the WBS produced

will reflect the ability and strength of the company at the same time, reflecting

sub-contractors’ ability to perform the project implementation. This also served

to satisfy all parties involved in the project construction.

6.5 Criteria in Developing the WBS

The criteria to be considered and practiced to ensure the minimum risk of

failure are listed below. By having the required and relevant data from all parties

(as mentioned in Para 6.4 above), the planners and implementers must be in

agreement as to what is expected from the WBS. There is a needs for a common

understanding between the planners and the implementers of the achievable

later when the project is being implemented because they are the only ones who

know the strength and usefulness of the criteria (Part C) applied to develop the

WBS. The criteria mentioned are :-

Part C

1. Tasks should be clearly defined the start/end date

2. WBS and work description to be easy to understand.

3. Tasks should be usable as a communication tools in which result can

be used to be compared with expectation.

4. Tasks/WBS elements to be structured in such a way that minimum

project office control and documentation is required.

Page 99: AzharAbdullahKPFKA2006TTT

82

5. All schedules to follow the WBS in order to ease the management

and co-ordination work.

6. The lowest WBS level should not be subdivided in order to have a

realistic cost compared to other tasks.

7. WBS should be flexible in order to accept any change scope of effort

during construction.

8. WBS also acts as tangible milestone for the subcontractors since their

delay can affect other trades completion date.

9. The level of WBS prepared can reflect the organization and line of

communication for the subcontractor’s involved in the project

construction.

10. WBS elements also should be able to segregate the recurring from

nonrecurring costs.

11. Normally, the lowest WBS elements should have 0.5 – 2.5 percent of

the total project budget.

Many companies across various industries have successes in managing

programmes / project without the using WBS technique. This is especially true

when the programmes / projects are repetitive in nature. However more and

more companies are entering diversified project areas where some

fundamentally common basis is needed for organizational synergy (Kerzner,

1984)

6.6 Checklist for the Preparation of WBS

After analyzing the characteristics of a proper and ideal WBS, and

comparing the criterion for the development of WBS with the newly

recommended WBS, it is advisable to counter check the WBS with the checklist

Page 100: AzharAbdullahKPFKA2006TTT

83

(Part D) below to ensure the generated WBS is functional and practical.

Amongst the checklists are :-

Part D

1. There can be one and only one (1) WBS for the contract

2. Once created, the WBS will exist for the life of the contract

3. Only formal contract change will effect the change in the WBS

4. Ensure that the WBS elements had been divided to the lowest

manageable level and to include more than one subcontractor if this

reflects the actual situation.

5. Check the proposed WBS and the contemplated efforts for

completeness, compatibility and continuity.

6. Ensure that the WBS satisfied both functional and programme /

project requirements including recurring and nonrecurring costs.

7. Check if the WBS provides to logical subdivision of all project work.

8. Ensure that all proposed WBS could fulfill the reporting

requirements of the organisation.

9. Check of assignment of responsibility for each element specific to

only one organisation.

10. Ensure the proposed WBS compatable to the contractor’s

organisation, arrangement and management system.

11. Review the WBS elements to ensure correlation with :-

! Construct specification and requirements

! End items of the contract

! Data items required

! Works statement tasks

! Management requirements

Page 101: AzharAbdullahKPFKA2006TTT

84

12. Ensure WBS covers measurable effort, level of effort, apportion

effort and subcontracts, if applicable.

13. Ensure the total costs of a particular level is the sum of all elements

cost of its next lower level.

Should a WBS passes the above mentioned processes of Characteristic

Check, Conforming to Criteria of WBS Development and Passes the Checklist,

it will deliver the full functional expectation of a ideal WBS. From the study, all

the WBS prepared for the school construction projects does not measure up to

the proposed guidelines and checklist, proving again that a hastily prepared

WBS not only bring no value to the project, but in extreme cases, contributed

negatively to the overall implementation.

6.7 An Example of a WBS for a School Construction Project

After introducing the appropriate format, characteristic requirement,

WBS development criteria, guidelines and checklists of WBS (Part A to Part D),

this paper present a sample of WBS for a School Construction Project, which

also can be used as guidance for the beginners in preparing the WBS for their

own project.

6.7.1 Project Brief

A typical Secondary school normally consist of three building

blocks for the classrooms and administrative . It will also have one canteen

block, a surau, an Anjung (a small shade for leisure), linking bridge, guard

house and a sub-station. Piling works are required for the Administrative ,

Classroom block), linking bridge, guard house and a sub-station

Page 102: AzharAbdullahKPFKA2006TTT

85

External works inclusive of the fencing, gates, guard house, approach

road, parking area, street / compound lighting, turfing / landscaping, external

drain, sewer system, a badminton court and rubbish chamber.

For internal works, the scope of works involved are the electrical supply,

air-condition installation, plumbing and sanitary work, electrical and telephone

services, installation of fire fighting system, lighting arrestors and PA/MATV

installation. Covered walkway joining to ‘surau’ and canteen is also required.

6.7.2 WBS on Construction of Sample Project (School Building)

Base on the project brief mentioned above, the sample WBS has been

designed as guidance for the beginners. Details of WBS are as per Table 6.1

Table 6.1 : Example of WBS for a school building project.

Construction and Completion of School Building and Ancillary Works

Activity ID WBS Elements

1.0 Pre Construction Phase 1.1 Soil investigation 1.2 Submission for approval 1.3 Accommodation 1.4 Milestone activities 2.0 Construction Phase 2.1 Preliminaries 2.1.1 Part I-Initial cost 2.1.2 Part II-Progressive cost 2.1.3 Part III-Completion Cost 2.2 Mobilization 2.3 Deliverables 2.4 Setting out

Page 103: AzharAbdullahKPFKA2006TTT

86

Table 6.1- Continue 2.5 Temporary water/power supply 2.6 Temporary access 2.7 Site clearing 2.8 Hoarding 2.9 Piling Works 3.0 External Works 3.1 Site Preparation and earthworks 3.1.1 Site clearance 3.1.2 Excavation and remove surplus 3.1.3 Filling 3.2 Water reticulation and related works 3.3 Sewer Reticulation and related works 3.4 Telecommunication works 3.5 Permanent power supply 3.6 Fencing/gate 3.7 Landscape(softscape/hardscape) 3.8 Street/compound lighting 3.9 Road/hardstanding/parking 3.10 Substations ,rubbish bin area, workshops 3.11 Field/playground

4.0 Building Works Block A 4.1 Pile cap 4.2 Ground beams 4.3 Column 4.4 Ground Floors slab 4.5 Ground floor column 4.6 1st floor beam 4.7 1st floor column 4.8 2nd floor beam 4.9 2nd floor column 4.10 3rd floor beam 4.11 3rd floor column 4.12 Roof beam and trusses 4.13 Ground floor 4.13.1 Staircase 4.13.2 Brick works 4.13.3 Doors, windows and frame 4.13.4 Wall finishes

Page 104: AzharAbdullahKPFKA2006TTT

87

Table 6.1- Continue 4.13.4.1 Cement Plaster(int) 4.13.4.2 Cement Plaster(ext) 4.13.5 Floor finishes 4.13.6 Tiling 4.13.7 Gypsum board partition 4.13.8 Furniture 4.14 1st Floor 4.14.1 Staircase 4.14.2 Brick works 4.14.3 Doors, windows and frame 4.14.4 Wall finishes 4.14.4.1 Cement Plaster(int) 4.14.4.2 Cement Plaster(ext) 4.14.4.3 Balustrade wall at corridor 4.14.5 Floor finishes 4.14.6 Tiling

4.14.7 Gypsum board partition 4.14.8 Furniture 4.15 2nd floor 4.15.1 Staircase 4.15.2 Brick works 4.15.3 Doors, windows and frame 4.15.4 Wall finishes 4.15.4.1 Cement Plaster(int) 4.15.4.2 Cement Plaster(ext) 4.15.4.3 Balustrade wall at corridor 4.15.5 Floor finishes 4.15.6 Tiling

4.15.7 Gypsum board partition 4.15.8 Furniture

4.16 3rd Floor 4.16.1 Staircase 4.16.2 Brick works 4.16.3 Doors, windows and frame

4.16.4 Wall finishes 4.16.4.1 Cement Plaster(int) 4.16.4.2 Cement Plaster(ext) 4.16.4.3 Balustrade wall at corridor

Page 105: AzharAbdullahKPFKA2006TTT

88

Table 6.1- Continue

4.16.5 Floor finishes 4.16.6 Tiling

4.16.7 Gypsum board partition 4.16.8 Furniture 4.17 M&E works 4.18 Plumbing and sanitary appliances

4.18.1 Cold water system 4.18.2 Water Tank 4.18.3 Soil, Waste and Vent Pipe 4.18.4 Testing 4.19 Roof 4.19.1 Roof Beam 4.19.2 Roof Slab

4.19.3 Roof Stiffener 4.19.4 Roof Trusses

4.19.5 Roof Covering and Finishes 4.20 Rain water down Pipe and Gutter 4.21 Painting works 4.22 Apron and perimeter drain 4.23 Deadline 5.0 Building Works Block B 5.1 Pile cap 5.2 Ground beams 5.3 Column 5.4 Ground Floors slab 5.5 Ground floor column 5.6 1st floor beam 5.7 1st floor column 5.8 2nd floor beam 5.9 2nd floor column 5.10 3rd floor beam 5.11 3rd floor column 5.12 Roof beam and trusses 5.13 Ground floor 5.13.1 Staircase 5.13.2 Brick works 5.13.3 Doors, windows and frame 5.13.4 Wall finishes

Page 106: AzharAbdullahKPFKA2006TTT

89

Table 6.1- Continue 5.13.4.1 Cement Plaster(int) 5.13.4.2 Cement Plaster(ext) 5.13.5 Floor finishes 5.13.6 Tiling 5.13.7 Gypsum board partition 5.13.8 Furniture 5.14 1st Floor 5.14.1 Staircase 5.14.2 Brick works 5.14.3 Doors, windows and frame 5.14.4 Wall finishes 5.14.4.1 Cement Plaster(int) 5.14.4.2 Cement Plaster(ext) 5.14.4.3 Balustrade wall at corridor 5.14.5 Floor finishes 5.14.6 Tiling

5.14.7 Gypsum board partition 5.14.8 Furniture 5.15 2nd floor 5.15.1 Staircase 5.15.2 Brick works 5.15.3 Doors, windows and frame 5.15.4 Wall finishes 5.15.4.1 Cement Plaster(int) 5.15.4.2 Cement Plaster(ext) 5.15.4.3 Balustrade wall at corridor 5.15.5 Floor finishes 5.15.6 Tiling

5.15.7 Gypsum board partition 5.15.8 Furniture

5.16 3rd Floor 5.16.1 Staircase 5.16.2 Brick works 5.16.3 Doors, windows and frame

5.16.4 Wall finishes 5.16.4.1 Cement Plaster(int) 5.16.4.2 Cement Plaster(ext)

Page 107: AzharAbdullahKPFKA2006TTT

90

Table 6.1- Continue

5.16.4.3 Balustrade wall at corridor 5.16.5 Floor finishes 5.16.6 Tiling

5.16.7 Gypsum board partition 5.16.8 Furniture 5.17 M&E works 5.18 Plumbing and sanitary appliances

5.18.1 Cold water system 5.18.2 Water Tank 5.18.3 Soil, Waste and Vent Pipe 5.18.4 Testing 5.19 Roof 5.19.1 Roof Beam 5.19.2 Roof Slab

5.19.3 Roof Stiffener 5.19.4 Roof Trusses

5.19.5 Roof Covering and Finishes 5.20 Rain water down Pipe and Gutter 5.21 Painting works 5.22 Apron and perimeter drain 5.23 Deadline 6.0 Building Works Block C 6.1 Pile cap 6.2 Ground beams 6.3 Column 6.4 Ground Floors slab 6.5 Ground floor column 6.6 1st floor beam 6.7 1st floor column 6.8 2nd floor beam 6.9 2nd floor column 6.10 3rd floor beam 6.11 3rd floor column 6.12 Roof beam and trusses 6.13 Ground floor 6.13.1 Staircase 6.13.2 Brick works 6.13.3 Doors, windows and frame

Page 108: AzharAbdullahKPFKA2006TTT

91

Table 6.1- Continue

6.13.4 Wall finishes 6.13.4.1 Cement Plaster(int) 6.13.4.2 Cement Plaster(ext) 6.13.5 Floor finishes 6.13.6 Tiling 6.13.7 Gypsum board partition 6.13.8 Furniture 6.14 1st Floor 6.14.1 Staircase 6.14.2 Brick works 6.14.3 Doors, windows and frame 6.14.4 Wall finishes 6.14.4.1 Cement Plaster(int) 6.14.4.2 Cement Plaster(ext) 6.14.4.3 Balustrade wall at corridor 6.14.5 Floor finishes 6.14.6 Tiling

6.14.7 Gypsum board partition 6.14.8 Furniture 6.15 2nd floor 6.15.1 Staircase 6.15.2 Brick works 6.15.3 Doors, windows and frame 6.15.4 Wall finishes 6.15.4.1 Cement Plaster(int) 6.15.4.2 Cement Plaster(ext) 6.15.4.3 Balustrade wall at corridor 6.15.5 Floor finishes 6.15.6 Tiling

6.15.7 Gypsum board partition 6.15.8 Furniture

6.16 3rd Floor 6.16.1 Staircase 6.16.2 Brick works 6.16.3 Doors, windows and frame

6.16.4 Wall finishes 6.16.4.1 Cement Plaster(int) 6.16.4.2 Cement Plaster(ext) 6.16.4.3 Balustrade wall at corridor

Page 109: AzharAbdullahKPFKA2006TTT

92

Table 6.1- Continue

6.16.5 Floor finishes 6.16.6 Tiling

6.16.7 Gypsum board partition 6.16.8 Furniture 6.17 M&E works 6.18 Plumbing and sanitary appliances

6.18.1 Cold water system 6.18.2 Water Tank 6.18.3 Soil, Waste and Vent Pipe 6.18.4 Testing 6.19 Roof 6.19.1 Roof Beam 6.19.2 Roof Slab

6.19.3 Roof Stiffener 6.19.4 Roof Trusses

6.19.5 Roof Covering and Finishes 6.20 Rain water down Pipe and Gutter 6.21 Painting works 6.22 Apron and perimeter drain 6.23 Deadline 6.24 Delivery 7.0 Anjung (Resting Area) 7.1 Piling works 7.2 Column 7.3 Roof Beams 7.4 Roof trusses 7.5 Roof Covering 7.6 Flooring 7.7 Plumbing 7.8 Electrical Wiring 8.0 Linking bridge 8.1 Piling works 8.2 Column 8.3 Staircase 8.4 Roof Beams 8.5 Roof trusses 8.6 Roof Covering

Page 110: AzharAbdullahKPFKA2006TTT

93

Table 6.1- Continue

9.0 Guard House 9.1 Piling works 9.2 Column 9.3 Roof Beams 9.4 Roof trusses 9.5 Roof Covering 9.6 Flooring 9.7 Plumbing 9.8 Electrical Wiring 10.0 TNB Substation 10.1 Piling work 10.2 Column 10.3 Roof Beams 10.4 Roof trusses 10.5 Roof Covering 10.6 Flooring 10.8 Electrical Wiring 11.0 External works 11.1 Refuse bin 11.2 Wakaf 11.3 Netball 11.4 Takraw 11.5 Badminton 11.6 Covered walkway 11.7 Fencing 11.8 Entrance Gate 11.9 Courtyard stage and flag post 11.10 Roads and car park 11.10.1 Concrete Edge 11.10.2 Car park 11.10.3 Footpath 11.11 Surface water drainage 11.12 Water reticulation 11.13 Sewerage system 11.13.1 Piling 11.13.2 Sewer pipe and manhole 11.14 Provisional Sum and Turfing 11.15 Deadline 11.16 Delivery

Page 111: AzharAbdullahKPFKA2006TTT

94

Table 6.1- Continue

12.0 Post Construction Phase 12.1 Demobilization 12.2 Clearing of debris 12.3 Submission of as-built drawing 12.4 Submission of test reports 12.5 Submission of O & M manual 12.6 Submission of defects list 12.7 Testing and commissioning 12.8 Submission of warranty and certificates 12.9 Submission of approval from authorities 12.10 Inspection for CPC 12.11 Final measurement / account

Page 112: AzharAbdullahKPFKA2006TTT

CHAPTER 7

CONCLUSION AND RECOMMENDATION

7.1 Introduction

Any school construction project is a complex operation, requiring

coordination of multiple people, tasks and organization. Construction of a

school can be particularly challenging, both in terms of meeting the needs of the

clients and gaining the outmost profit from it. There is no doubt of the

importance of the WBS in the project planning and scheduling. It has been

explained clearly in Chapter 1, 2 and 3 and also being verified by conducting a

structured interview as explained in Chapter 4 .

The success of a school project starts at inception with getting the right

people for the job. Effective management must take into account adequate

planning and communication and selecting the contractors. . Without a proper

WBS, the planning/scheduling could not achieve its purposes and could also

disrupt the site management. So, it is essential to provide enough time and

attention for planning and designing WBS, since mistakes made in the planning

and early stages will carry through the entire life of the project.

Page 113: AzharAbdullahKPFKA2006TTT

96

7.2 Managing School Projects in The Future

With 54 new school construction projects and 220 school for upgrading

development in the pipeline for the new Ninth Malaysia Plan (9MP) , the

industry must admit that they should gear up their capabilities of producing first

class construction works in terms of quality and value for money. Bear in mind

that all in all, government spending on school construction and school upgrading

programs will be in excess of Rm980 million. Now days, the construction

industry, specifically covering schools building and laboratories have been

lacking behind. Although there was a tendency for some contractors to be

protective of their long-standing practice, but as school projects getting more

complex and together with the increase expectations from the government, it is

strongly belief that the acceptance of WBS in project management culture is

inevitable.

7.3 Concept and Application of WBS in School Project Scheduling.

The concept and application of WBS in the preparation of work program

and scheduling has been elaborated in Chapter 2, Chapter 3 and Chapter 4. Few

examples have been given including the different kind of numbering the WBS

elements to ease the using of identification of each activity and its level

(hierarchy). From the numbering itself, the position and its grouping can be

identified. Although WBS is part of the project scheduling, it is very important

to be properly prepared since its reflect the type and activities to be executed and

assignment of responsibility can be implemented. Its also help the management

to identify the subcontractors required and quotation for the works can also be

distributed.

Page 114: AzharAbdullahKPFKA2006TTT

97

A well developed WBS can assist and guide contractors, PMCs and

Construction Managers in terms of providing insight, direction and supervision

through the entire construction process. Good WBS makes construction

managers will have a comprehensive understanding of the full scope of work,

and will be able to oversee and coordinate sub-contractors and special trade-

contractors to ensure that the new facility meets the expectations. WBS can

also help the planners to identify their resources. Manpower, materials

resourcing , machines required and costing are among the activities that can be

planned with the help of the WBS.

7.4 Application of WBS in Construction Schedules for Selected School

Projects.

Out of the nine school projects that were selected and identified for the

cases to be studied in this dissertation, two were known to have a good WBS

done based from experience and referring from the building drawings. Both

school projects were completed within the stipulated time frame, although, as

mentioned earlier, both were granted EOT by the government due to unforeseen

circumstance. The advantages of having clear WBS is as it can coordinate

activities to minimize impact to the school projects, such as

• Coordinate purchase and delivery of materials that may have long

lead times to obtain.

• Schedule work to mesh smoothly with school schedules and to

minimize disruptions to school activities in the case of renovation

and alteration.

Page 115: AzharAbdullahKPFKA2006TTT

98

• Review contract and bid packages to minimize gaps and ambiguity in

contract requirements

• To work with suppliers to obtain better prices, while assuring

sufficient quality.

Other then that it was also found that there are negative trend among

contractors who prefer not to prepare the construction schedules as details as

possible. Some of the activities/tasks were failed to assign responsibility to only

one party/gang. Problems may arise when the activities are delayed as the

responsible party can deny their fault. Of course, some of them were not capable

of practicing the right way of doing the WBS for construction schedules due to

lack of knowledge and resources.

For the post construction items such as testing & commissioning,

demobilization, submission as-built drawings including the O&M manual were

also excluded from the list. This is due to the reason that mostly all activities in

the pre and post construction phase are not carrying any weight age to the works

progress either physically or financially.

7.5 To Initiate/Propose Format and Guidelines for WBS.

The format and proposed guidelines have been elaborated in Chapter 5

and Chapter 6 and the format and guidelines are just the first step towards

preparing the standard and well prepared format and guidelines. To certify the

guidelines, feedback from five professionals in the construction industry has

been obtained. Their relevant comments have been incorporated in the

guidelines.

Page 116: AzharAbdullahKPFKA2006TTT

99

The propose format and guidelines are hopefully to ease the planners

when designing the WBS. As for checking, a check list has been proposed to

confirm the designed WBS in term of application and usage. The format,

guidelines and check list have been elaborate in details in Chapter 5 and

Chapter 6.

7.6 Example of WBS for a Building School Project.

Studied done shows that a basic school projects consists of three

building blocks for classroom and administrative, a canteen block, a guard house,

a surau or a wakaf, TNB sub-station and playing field for badminton or sepak

takraw. Proactively, a lingking bridge is added during the development of the

proposd WBS.

An example of WBS which is suitable for a normal school project is

introduced hoping that it will act as a guidance for contractors and project

managers when managing school projects. By having an example, the beginners

can refer to the items and suite it to their projects. Although all projects are not

the same , they are quite similar in certain ways. Therefore, some merging were

done to obtain the most practical WBS for school projects.

7.7 Conclusion

Initially WBS was misunderstood as a scheduling tools. WBS is not an

instrument. It is one of the approach as process in preparing project schedule. It

is not a technique by itself rather it is part of the scheduling process. Some

Page 117: AzharAbdullahKPFKA2006TTT

100

contractors thought that WBS is a ‘polished’ version of a present scheduling

technique. They misunderstood that WBS function is never quite different from

CPM method or a Gantt Chart. A WBS does not show the sequence in which

work is performed. A WBS shows what should be done in order to complete

certain task. Only after further explanation, only they realized the importance of

WBS which act as a guiding tools that can help them manage their project.

Further study on WBS has explained all aspects of WBS including its

importance, usage, current perception and proposed format and guidelines of

preparing it.

It was found that many contractors are ignoring the importance of

project planning and scheduling mainly in preparing the WBS. This may lead to

delay and failure to the project. Although there are factors that contribute to the

project failure, at least by planning, the risk can be minimized and the potential

problems can also be identified during initial stage.

This study also shows that the Open Tender Method practiced by The

Ministry of Works in awarding school projects to contractors proved to produce

better and healthier competitive way in awarding the right and credible

contractors to do the jobs. On the other hands, it was sad to learn that, due to

weak supervision and improper tendering process and documentation, the

Design and Built method adopted by The Ministry of Education produced a lot

of failures. In this context, WBS can play a big roll in assisting new contractors

There is no formal guidelines in preparing the WBS in our country.

Among contractors uses building drawings, experience and informal guidelines

based from books, journals and technical papers. This proposed guidelines

presented could at least help the contractors to prepare the functional WBS for

their school projects.

Page 118: AzharAbdullahKPFKA2006TTT

101

7.8 Recommendation.

There a studies done on WBS before and lots of things have be said

about it. Though some quarters will look at it as a surviving tools for the

construction industry players , others might take it negatively as another pain

staking paper work that must be done without knowing the main objective.

The guidelines, format, checklist and project example have not been

certified by relevant agencies such as CIDB and JKR although CIDB, through

their “Certified Construction Project Manager”s, program, stressed the needs of

knowing and developing WBS for all Project Managers in the program’s module.

For the proposed guidelines to be standardized and applied to the government

and private projects, their certification is required. For the first step, there should

be a working committee which include all relevant ministry that are responsible

either directly or indirectly, responsible for handling out schools construction

projects. Since the certification is time consuming, further effort to be done in

highlighting this problems to the higher level/authorities for the benefits of our

construction industry.

In the Malaysian construction sector, there are lots of type of

construction, such as housing, highways, bridges, factories, hill side

development and many more include school projects. WBS can be develop for

all type of construction. We can start it first by concentrating on school projects

since there’s a lot of problems in this field.

Without a good and proper construction management plus lack of

knowledge, our contractors could not go further to compete in the global market.

Their mind have to be changed and perception on planning have to be corrected

in order to have effective planning capability thus contribute to the advancement

in construction industry generally.

Page 119: AzharAbdullahKPFKA2006TTT

102

REFERENCES

Baker, B. (1997). Cost/Time Trade-Off Analysis for the Critical Path Method: A Derivation of the Network Flow Approach, Journal of the Operational Research Society, Stockton, UK, vol. 48, no. 12, pp241-4.

Ballard and Howell,G (1999). What is Kind Of Production Is

Construction? Proceeding Sixth Annual Conference Of International Group Of Lean Construction, IGLC-7, Guaruja, Brazil

Chris Hendrickson (1989). Department of Civil Engineering, Carnegie Mellon

University, Pittsburgh. Clough, Richard H (1991). Construction Project Management 3rd ed. Fisk, R., Edward (1992). Construction Project Administration 4th ed.,

Prentice Hall. Feigenbaum, (1998). Construction Scheduling with Primavera Project Planner,

Prentice Hall, Howell,G. (1999) What is Lean Construction? Proceeding Seventh Annual

Conference Of International Group Of Lean Construction, IGLC-7, University Of California, Berkeley, CA, USA

Halpin, Daniel W. (1980). Construction Management . John Wiley. Horsely, William F. (1991). Means Scheduling Manual 3rd. ed. RS Means J. Hill, L.C. Thomas and Allen D. (2000). Experts’ estimate of task duration in

software development projects. International Journal of Project Management

James P.L. (2000), Project Planning Scheduling and Control: A Hands-On

Guide to Bringing Projects In On Time and On Budget, McGraw-Hill Third Edition.,

Page 120: AzharAbdullahKPFKA2006TTT

103

Koskela, L (1992) Application Of The New Production Philosophy

Of Construction, Technical Report, No.72, CIFE Stanford University, Stanford,CA

Kerzner, (1998). Project Management: A Systems Approach to Planning,

Scheduling and Controlling, Wiley, Moder, J.J. (1970). Project Management with CPM, PERT and Precedence

Diagramming Van Nostrand 2nd ed., Martin E. M. (1996). A Professional's Guide to Systems Analysis, 2nd. Ed.

McGraw Hill. McGovern and Gene. (1999). Easing the pain.Managing school construction

projects American School and University Moder and Phillips (1983), Project Management with CPM, PERT and

Precedence Programming 2nd ed., Saad Al-Jibori (2002) , Effect of resource management regimes on project

schedule. International Journal of Project Management 20 The Hartford’s Guide to Emergency Preparedness Planning, Hartford, Conn:

The Hartford, c1998. Waldron, (1968). Applied Principles of Project Planning and Control, A.

James Waldron,

Page 121: AzharAbdullahKPFKA2006TTT

104

APPENDIX I Detailed background of respondents. R1 - Director of Cawangan Ukur Bahan, Ministry of Works. R2 - Assistant Director of Cawangan Ukur Bahan, Ministry of Works. R3 - Assistant Director of Cawangan Ukur Bahan, Ministry of Works. R4 - Project Engineer, Department of Education, Johore. R5 - Senior Quantity Surveyor. R6 - Civil Engineer, JKR Pahang. R7 - Professional Civil Engineer, Consultant. R8 - Administrative and Diplomatic Officer (PTD), Ministry Of Education. R9 - Quantity Surveyor, Project Management Consultant. R9 - Quantity Surveyor, Project Management Consultant. R10 - Quantity Surveyor, Project Management Consultant. R11 – R20 Contractors.

Page 122: AzharAbdullahKPFKA2006TTT

105

APPENDIX II

QUESTIONNAIRES FOR THE EXPERTS’ PANELS AND CONTRACTORS

Page 123: AzharAbdullahKPFKA2006TTT

106

Gratitude Note:

Thank you for sparing your precious time to participate in this research study. You are

participating in a Master Degree Research entitled: “Development of Common Work

Breakdown Structure (WBS) for School Construction Project”. You are assured that your

input will be put to great use to develop a better Work Scheduling Management for

school construction project in Malaysia. Thank you again.

General Information of Participant: 1). Title: ………………………………………. (Mr., Ms., Dr., Ir., Dato’, etc) 2). Name of Ministry / Organization: ……………………………………………….. 3). Department attached to: ……………………………………………….. 4). Designation: ……………………….………… 5). Brief description of job function: ……………………………………….………. ……………………………………………….. ……………………………………………….. ……………………………………………….. ……………………………………………….. ………………………………………………..

6). Duration in current position: …….. years and …………months 7). Position before current designation: ……………….…………………………….

Professional Qualification of Participant

Mark “X”

Civil Engineering Mechanical Engineering Electrical/Electronics Engineering

Legal Personnel Economic Major Quantity Surveyor Others (please specify) …………………………………..

Page 124: AzharAbdullahKPFKA2006TTT

107

Face to Face Session This section aims to establish the influential factors that govern a school construction project success/failure, pinpoint the cause of unsuccessful project and to gather opinions and suggestions on improving future project implementation. Structured Questionnaire:

Date : ………………………..

Time : …………………………

Remark : …………………………………………………..…………………………………………………..…………………………………………………..

Question 1. What is the percentage of project failure in the category of “School Construction Project” awarded by Ministry of Work / Ministry of Education working with Project Management Consultancy company. Result to the above question:

………………………………………………………………………………………………………………………………………………………………………………………………………………

What is the cause of the problem:

………………………………………………………………………………………………………………………………………………………………………………………………………………

At what stage is the problem discovered?

………………………………………………………………………………………………………………………………………………………………………………………………………………

Who are responsible for the mistake:

………………………………………………………………………………………………………………………………………………………………………………………………………………

If it is not the direct fault of the party assigned to the

Page 125: AzharAbdullahKPFKA2006TTT

108

job, stage who and explain: ………………………………………………………………………………………………………………………………………………………………………………………………………………

Remedy and Improvement suggestions:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Other Remark: ………………………………………………………………………………………………………………………………………………………………………………………………………………

Question 2. What constitute to the school construction project failure? Result to the above question:

………………………………………………………………………………………………………………………………………………………………………………………………………………

What is the cause of the problem:

………………………………………………………………………………………………………………………………………………………………………………………………………………

At what stage is the problem discovered?

………………………………………………………………………………………………………………………………………………………………………………………………………………

Who are responsible for the mistake:

………………………………………………………………………………………………………………………………………………………………………………………………………………

If it is not the direct fault of the party assigned to the job, stage who and explain:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Remedy and Improvement suggestions:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Other Remark: ………………………………………………………………………………………………………………………………………………………………………………………………………………

Page 126: AzharAbdullahKPFKA2006TTT

109

Question 3. What is the project financing structure? What was the monitoring and administering strategy adopted? Result to the above question:

………………………………………………………………………………………………………………………………………………………………………………………………………………

What is the cause of the problem:

………………………………………………………………………………………………………………………………………………………………………………………………………………

At what stage is the problem discovered?

………………………………………………………………………………………………………………………………………………………………………………………………………………

Who are responsible for the mistake:

………………………………………………………………………………………………………………………………………………………………………………………………………………

If it is not the direct fault of the party assigned to the job, stage who and explain:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Remedy and Improvement suggestions:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Other Remark: ………………………………………………………………………………………………………………………………………………………………………………………………………………

Page 127: AzharAbdullahKPFKA2006TTT

110

Question 4. What is the type of project monitoring system adopted by Ministry of Work/Ministry of Education or Project Management Consultancy Company. Work Breakdown Scheduling or other system? What is the outcome? Result to the above question:

………………………………………………………………………………………………………………………………………………………………………………………………………………

What is the cause of the problem:

………………………………………………………………………………………………………………………………………………………………………………………………………………

At what stage is the problem discovered?

………………………………………………………………………………………………………………………………………………………………………………………………………………

Who are responsible for the mistake:

………………………………………………………………………………………………………………………………………………………………………………………………………………

If it is not the direct fault of the party assigned to the job, stage who and explain:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Remedy and Improvement suggestions:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Other Remark: ………………………………………………………………………………………………………………………………………………………………………………………………………………

Page 128: AzharAbdullahKPFKA2006TTT

111

Question 5. What is your perception on “Program of Work”? Is this method of project planning detail enough? Result to the above question:

………………………………………………………………………………………………………………………………………………………………………………………………………………

What is the cause of the problem:

………………………………………………………………………………………………………………………………………………………………………………………………………………

At what stage is the problem discovered?

………………………………………………………………………………………………………………………………………………………………………………………………………………

Who are responsible for the mistake:

………………………………………………………………………………………………………………………………………………………………………………………………………………

If it is not the direct fault of the party assigned to the job, stage who and explain:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Remedy and Improvement suggestions:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Other Remark: ………………………………………………………………………………………………………………………………………………………………………………………………………………

Page 129: AzharAbdullahKPFKA2006TTT

112

Question 6. Does Project Management Consultancy Company of the Ministry has any guideline or ISO to monitor project based on any type of program? Result to the above question:

………………………………………………………………………………………………………………………………………………………………………………………………………………

What is the cause of the problem:

………………………………………………………………………………………………………………………………………………………………………………………………………………

At what stage is the problem discovered?

………………………………………………………………………………………………………………………………………………………………………………………………………………

Who are responsible for the mistake:

………………………………………………………………………………………………………………………………………………………………………………………………………………

If it is not the direct fault of the party assigned to the job, stage who and explain:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Remedy and Improvement suggestions:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Other Remark: ………………………………………………………………………………………………………………………………………………………………………………………………………………

Page 130: AzharAbdullahKPFKA2006TTT

113

Question 7. How is the project payment being facilitated? If schedule payment, did payment paid on time? If not, please list problems. Result to the above question:

………………………………………………………………………………………………………………………………………………………………………………………………………………

What is the cause of the problem:

………………………………………………………………………………………………………………………………………………………………………………………………………………

At what stage is the problem discovered?

………………………………………………………………………………………………………………………………………………………………………………………………………………

Who are responsible for the mistake:

………………………………………………………………………………………………………………………………………………………………………………………………………………

If it is not the direct fault of the party assigned to the job, stage who and explain:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Remedy and Improvement suggestions:

………………………………………………………………………………………………………………………………………………………………………………………………………………

Other Remark: ………………………………………………………………………………………………………………………………………………………………………………………………………………

Page 131: AzharAbdullahKPFKA2006TTT

114

Question 8. Please list at least one (1) school construction project which in your opinion failure miserably: Name of Project: Location:

…………………………………………………….…………………………………………………….

Date of Commencement: …………………………………………………….

Reasons why it fail: …………………………………………………….…………………………………………………….

Additional Remarks: …………………………………………………….…………………………………………………….

Question 9. Please list at least one (1) school construction project which in your opinion is highly successful: Name of Project: Location:

…………………………………………………….…………………………………………………….

Date of Commencement: …………………………………………………….

Reasons why it fail: …………………………………………………….…………………………………………………….

Additional Remarks: …………………………………………………….…………………………………………………….

End of Question

Thanks you for your corporation.