banglow2

12
roN OF SURVEYORS MALAYSIA rCHPLIJII"U COST INFORMATION CENTRE .. ....:...-. . COST ANALYSIS - Form 1 8-Residential Building , . A-2-863 JOB TITLE : Bungalow CLIENT: Private LOCATION: Shah Alam, Selangor TENDER DATE: 27th march 2003 INFORMATION TOTAL PROJECT Project and Contract Information Project Details and Site Condition: Contract : 2 Storey Bungalow and 1 service block annexed to it with associated works , PAM Standard Form of Contract 98 (With Quantities) The site is generally flat and easily accessible from the main road Market Conditions: COMPETITIVE Contract Particulars : Comgetitive Tender List Type of Contract : Cost Fluctuation : Yes 0 RM Int(Jv)/L No [JJ 4,867,874.30 L Basis of Tender Open/Selected Government [JJ Bills of Quantities OJ Competition OJ 4,254,712.10 L Private 0 Bills of Appr. Quant. D Negotiated D Provisional Sum RM 1,325,000.00 Sched. Of Rates/ Serials Spec. & Drawings D D Prime Cost Sum RM - Contract Period Stip. By Client: 52 weeks Preliminaries RM 205,500.00 Contract Period Offered by Builders: N/A Contingencies RM - Number of Tenders Issued: 3 Contract Sum RM 4,254,712.10 Number of Tenders Received: 2 ANALYSIS OF SINGLE BUILDING Design/Shape Information Accommodation and Design Features : The work containts a double storey bungalow house with an annexed block for services and a plunge pool. The buildings are generally irregular in shape Areas: Functional Unit: 400 Design m2 (usable area) Percentage of Gross Floor Area Below Ground Floor - m2 Ground Floor 623 m2 External Wall Area 561 m2 (a) Below Grd. Fir 0.00% Upper Floor 240 m2 Gross Floor Area 863 GROSS FLOOR AREA 863 m2 (b) Single Storey = 0.650 Construction 72.19% Usable Area 400 m2 Circulation Area 191 m2 (c) Two-storey AncillaIy Area 184 m2 Storey Heights : Construction 27.81% Internal Division 88 m2 GROSS FLOOR AREA 863 m2 Av. Below Grd Floor - m (d) 3-storey Construction 0.00% At Ground Floor 4.55 m Floor Space NOT Enclosed 375 m2 (e) 4-storey Above Ground Floor 3.00 m Construction 0.00% Roof Area (Structural and Plant Room) 717 m2 Brief Cost Information Contract Sums RM 4,254,712.10 Functional Unit Costs Provisional Sums RM 1,325,000.00 excluding external works : 9,828.92 perM2 Prime Cost Sums RM - Preliminaries RM 205,500.00 being 5.08% of remainder Contingencies RM - being 0.00% Contract Sum Contract Sums less Contingencies RM 4,254,712.10 Bungalow Shah Alam-ECA

Upload: rokiahhassan

Post on 13-Apr-2015

53 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: BANGLOW2

roN OF SURVEYORS MALAYSIA rCHPLIJII"U COST INFORMATION CENTRE

.. ....:...-. . • ~(:,lf-NTAt COST ANALYSIS - Form 1 8-Residential Building , . A-2-863

JOB TITLE : Bungalow CLIENT: Private

LOCATION: Shah Alam, Selangor TENDER DATE: 27th march 2003

INFORMATION TOTAL PROJECT

Project and Contract Information

Project Details and Site Condition: Contract : 2 Storey Bungalow and 1 service block annexed to it with associated works

, PAM Standard Form of Contract 98 (With Quantities)

The site is generally flat and easily accessible from the main road

Market Conditions: COMPETITIVE

Contract Particulars : Comgetitive Tender List

Type of Contract : Cost Fluctuation : Yes 0 RM Int(Jv)/L

No [JJ 4,867,874.30 L

Basis of Tender Open/Selected Government [JJ Bills of Quantities OJ Competition OJ 4,254,712.10 L

Private 0 Bills of Appr. Quant. D Negotiated D • Provisional Sum RM 1,325,000.00

Sched. Of Rates/ Serials

Spec. & Drawings D D Prime Cost Sum RM -

Contract Period Stip. By Client: 52 weeks Preliminaries RM 205,500.00

Contract Period Offered by Builders: N/A Contingencies RM -

Number of Tenders Issued: 3 Contract Sum RM 4,254,712.10

Number of Tenders Received: 2

ANALYSIS OF SINGLE BUILDING

Design/Shape Information

Accommodation and Design Features :

The work containts a double storey bungalow house with an annexed block for services and a plunge pool. The buildings are generally irregular in shape

• Areas: Functional Unit: 400 Design Sha~s m2 (usable area) Percentage of Gross Floor Area

Below Ground Floor - m2

Ground Floor 623 m2 External Wall Area 561 m2 (a) Below Grd. Fir 0.00%

Upper Floor 240 m2 Gross Floor Area 863

GROSS FLOOR AREA 863 m2 (b) Single Storey

= 0.650 Construction 72.19%

Usable Area 400 m2

Circulation Area 191 m2 (c) Two-storey

AncillaIy Area 184 m2 Storey Heights : Construction 27.81%

Internal Division 88 m2

GROSS FLOOR AREA 863 m2 Av. Below Grd Floor - m (d) 3-storey

Construction 0.00% At Ground Floor 4.55 m

Floor Space NOT Enclosed 375 m2 (e) 4-storey

Above Ground Floor 3.00 m Construction 0.00% Roof Area (Structural and Plant Room) 717 m2

Brief Cost Information Contract Sums RM 4,254,712.10 Functional Unit Costs Provisional Sums RM 1,325,000.00 excluding external works : 9,828.92 perM2 Prime Cost Sums RM -Preliminaries RM 205,500.00 being 5.08% of remainder Contingencies RM - being 0.00% Contract Sum Contract Sums less Contingencies RM 4,254,712.10

Bungalow Shah Alam-ECA

Page 2: BANGLOW2

f ~' I

INSTITUTION OF SURVEYORS MALAYSIA . \

BtllLplNGCOST INFORMATION CENTRE

I!LEMENTAL COST ANALYSIS - Form 2 8-Residential Building A·2·863

SUMMARY OF ELEMENT COSTS

GROSS FLOOR AREA: 863 M2 TENDER DATE 27th march 2003

Preliminaries Shown Separately

Total Cost Cost per m2 Element Element Unit Element Reinforced Reinforce- Formwork of Element GFA Unit Rate Ratio Concrete ment m2

RM RM Quantity RM perm2 GFA m3 kg

1 Substructure lA Piling 53,293.44 61.75 1,680 m 31.72 1.947 - - -lB Work Below Lowest Floor Finish 147156.58 170.52 623 m2 236.21 0.722 135 15,682 565

Group Element Total ?nn.d.<;nn? 232.27 135 15,682 565

2 Superstructure

2A Frame 77,879.97 90.24 863 m2 90.24 1.000 57 8,818 597

2B Upper Floors 20,002.40 23.18 240 m2 83.34 0.278 37 4,080 240

2C Roof 269,170.61 311.90 791 m2 340.29 0.917 - - -"0 Stairs 96,269.07 111.55 - - - 11 762 60

,- External Walls 81,225.37 94.12 416 m2 195.25 0.482 - - -2F Windows & External Doors 227,475.02 263.59 145 m2 1,568.79 0.168 - - -2G Internal Walls and Partitions 120,127.42 139.20 349 m2 344.20 0.404 - - -2H Internal Doors 176,873.66 204.95 219 m2 807.64 0.254 - - -Group Element Total 1 nE;~ n?<I <;? 1,238.73 105 13,660 897

3 Finishes

3A Internal Wall Finishes 51,513.68 59.69 992 m2 51.93 1.149

3B Internal Floor Finishes 172,416.37 199.79 506 m2 340.74 0.586

3C- Internal Ceiling Finishes 44,609.04 51.69 607 m2 73.49 0.703

30 External Finishes 280,101.11 324.57 - - -Group Element Total 548,640.20 635.74

4 Fittings and Furnishings 460,000.00 533.02 - -5 Services 5A Sanitary Appliances 65,152.00 75.49 33 No 1,974.30 0.038

5B Plumbing Installation 517,802.00 600.00 -5C Refuse Disposal - - -50 Air-conditioning & Ventilation System 80,000.00 92.70 3,245 TM3 24.65 3.760

5E Electrical Installation 770,000.00 892.24

5F Fire Protection Installation 5,000.00 5.79

Lift and Conveyor Installation - -Communication Installation 10,000.00 11.59

Special Installation - -5K Builder's Profit & Attendance

on Services - -5L Builder's Work in Connection -

with Services -Group Element Total 1,447,954.00 -1,677.81

Sub-total exc. External Works, Preliminaries and Contingencies 3,726,067.74 4,317.58

6 External Works 6A Site Work 60,585.09 70.20

6B. Drainage 21,115.66 24.47

6C External Services 9,012.15 10.44

60 Ancillary Buildings 232,431.46 269.33

6E Recreational Facilities - -Group Element Total 323,144.36 374.44 List of Provisional Sums

Preliminaries 205,500.00 238.12 Fittings and Furnishing RM 460,000.00

Electrical System RM 770,000.00

Telephone RM 10,000.00

Fire Protection RM 5,000.00

I TOT, (less Contingencies) 4,254,712.10 4,930.14 Air Conditioning and ventilations RM 80,000.00

Page 3: BANGLOW2

INSTITUTION OF S~RVEYORS MALAYSIA • ,BUILDING COST INFORMATION CENTRE

,

ELEMENTAL COST ANALYSIS - Form 3 8-Residential Building

A-2-863

BRIEF SPECIFICATION

GROSS FLOOR AREA: 863 m2 TENDER DATE: 27th march 2003

ELEMENT SPECIFICATION

1 Substructure

1A Piling Pre-cast concrete pile Grade 45, 150 mm x 150mm

1B Work Below Lowest Floor Finish Reinforced concrete pile cap, ground beam and slab

2 Su~erstructure

2A Frame Reinforced concrete column and beam

2B Upper Floors Reinforced concrete suspended slab

2C Roof Reinforced concrete roof slab and concrete roof tiles on steel truss

2D Stairs Reinforced concrete staircase with mild steel tubular h/railing, half briick balustrade and s/steel h/rail

2E External Walls Half brickwall of clay bricks

2F Windows & External Doors Timber casement and louvres windows

2G Internal Walls and Partitions Half brickwall of clay bricks

2H Internal Doors Plywood flush door, decorative door, composite glass door; all with timber frames

, 3 Finishes

<3A External Wall Finishes Shanghai plaster, timber wall board and timber strip panel

3B Internal Wall Finishes Cement and sand plaster and paint and ceramic tiles to wet area

3C External Floor Finishes Cement render, timber floor system, timber deck and granite tiles

3D Internal Floor Finishes Cement render, homogenoues tiles, granite, marble and timber floor system

3E External Ceiling Finishes Timber'T' and 'G' ceiling, skim coat, plaster and paint

3F Internal Ceiling Finishes Fibrous plaster ceiling and paint

4 Fittings and Furnishings IDworks

5 Services

5A Sanitary Appliances Imported product fittings; Gala; Vitra; Grohe etc.

5B Plumbing Installation GI pipe, FRP compartment suction tank for CWS and VCP pi pie for sanitary plumbing

5C Refuse Disposal N/A

5D Air-conditioning & Ventilation System Air cooled split unit, ventilation fan, starter panel exhaust duct, kitchen exhaust hood etc

5E Electrical Installation XLPE/PVC cu. Cable main cabling, PVC submain cabling, distribution bord etc, Lightning protection

5F Fire Protection Installation Portable fire extinguisher

5G Lift and Conveyor Installation N/A

5H Communication Installation Telephone & data

5J Special Installation N/A

5K Builder's Profit & Attendance on Services inclusive in the above cost , 5L Builder's Work in Connection with Services inclusive in the above cost

6 External Works

6A Site Work Road and car park, site preparation and retaining wall

6B Drainage Surface water drainage

6C External Services External water supply reticulation and sewerage

6D Ancillary Buildings Covered walkway, guard house, fencing and gates

6E Recreational Facilities N/A

Page 4: BANGLOW2

1" . ,

BUILDING COST INFORMATION CENTRE ,COST INDICES SUB-COMMITTEE DATA FORM 1 - TENDER PRICE INDEX

CONTRACT INFORMATION

A1. PROJECT DETAILS

Client

Project

Location Contract Period

Tender Date

Type of Contract

Fluctuations

No. of Tenders

Issued/Received

Site Conditions

Private

Bungalow

Shah Alam, Selangor

52 weeks Preliminaries Sum

27th March, 2003 Adjustments

PAM Standard Form of Contract (With Quantities) P.C Sums

No

3 2

SC/1I1/1 Rev 9/96

Project Ref: Date 27th March, 2003

• market Conditions

Easily accessible & on

sloping ground

COMPETITIVE

Profit & General

Attendance

Provisional Sum

SUB TOTAL

Contingency Sum

CONTRACT SUM 4,254,712.10

No of storey

Gross Floor Area

(GFA)

Functional Unit

specification

Bungalow with annexe block and plunge

pool.

2

863 M2

400 M2

Element

Superstructure

Substructure

Finishes

Fittings

Services

SUB-TOTAL

Ext. Works

Preliminaries Sum

TOTAL

(exc. Contingency Sum) 4,254,712.10 4,930.14 100.00%

The building is constructed of reinforced concrete foundations pile caps and precast reinforced concrete piles. Walls are generally of

clay brickwall. Windows are generally timber frame casement and louvres. Doors are timber flush doors, decorative timber and glass

doors all with timber frames. Wall finishes are generally cement render and paint with tiles at wet areas. Ceiling finishes are generally

fibrous plaster and paint. Services include plumbing, sanitary, electrical and air conditioning installation.

PROJECT Index as calculated

(From Data Form 3)

Base

: 77.97

: JKR Standard Schedules of Rates (SERIAL NO. JKR 20800-0117-2001)

Page 5: BANGLOW2

BUILDING COST INFORMATION CENTRE COST INDICES SUB-COMMITTEE

DATA FORM 3 - TENDER PRICE INDEX

SC 1/1/3 REV 3/86

o PROJECT INDEX CALCULATION SHEET

Project Ref Date 27th March, 2003

Measured Work

Provisional Sums Profit & General Attendance on P.C. Sum Adjustments SUB-TOTAL Add Preliminaries Sum Percentage * 2 ( 7.543% )

* 1

* 2

TOTAL

[ 3% xof

Preliminaries Sum Percentages

Base to Bills Factor

305,450.92

4,354,663.02

x 1.3794 x * 1

3%

[ P.C. Sum x Base To Bills Factor as Tendered ]

= 3% = 0.00

x

= Preliminaries Sum Contract Sum deduct

of adjusted P.C. Sum

(Preliminaries Sum, Contingency Sum, Dayworks)

= 205,500.00 x 100 2,724,212.10

= 7.543%

5,585,320.61

x 1.3794 ]

x 100%

.~----------~----------~ BASED ON

INDEX BY

JKR Standard Schedules of Rates (SERIAL NO. JKR 20800-0117-2001)

R.O

PROJECT INDEX:

Total Column (a) x 100 ~~~--~~----Total Column (c )

4,354,663.02 x 100 ~~~~--------5,585,320.61

= 77.97

Page 6: BANGLOW2

-

BUILDING COST INFORMATION CENTRE COST INDICES SUB-COMMITTEE

, '

--------------------------------~~--------------------------------------~>.-'~. SC 1/1/2 REV 9/96 Project Ref:

DATA FORM 2 - TENDER PRICE INDEX I CALCULATION SHEET FOR MEASURED WORK Date:

Base to Bills Factor H

387,841.44 281,174.95

1.3794

Page 7: BANGLOW2

-----------------

: I II

: I ----LIS:_-l

¥

• NEIGHB() U RING EMPTY LOT NO:l0

-- - -- - - - ++-IIHIt--

-----==~~ _ =~·=~--=~=-=-=_·-o).l._"_.~.!.J.:JJJ,)=!:=:=:_=§:i:~:~_~:~:~:~:~:~:~:~:~=~=~:~:~:~:~=~=~:~:~:~:~=~=~:~:~:::~::=:=::~~;~~l::9f;';;7:~~~-;:~~~~;'=N;~~::-~=:=;;'!~';;-~~:;:::::-:::.~",~",~:.:.;~""~~~ .. ~~

UM801(. nRNA~AN VoRl)

\.

1 ~~9~ND FLOOR PLAN )

230WIQEHAlfROUNDEO ~ PRECAST CONC. DRAIN A1202 lAID 10 FAll

~.,..,,,.,....::- ---- -----, l I I I I

l

vv(O-fl4 ... · /

tv11't

WF~"e)

NOTES:

02 .. D8 LOCAnON REVISED. Ale DUCT ADDED

\IA~\\\1<.OQ\-.\" A"IM\;t\tJW.

FOR CONSTRUCTION

KEY PLAN:

HTA KIN TAN ARCHITECT Arthit«tu~ and Oulgn

Blodt. B, Unit F~L08·3. Bayu Angkasa. "JalanMtdangKapas Bangsar, 59100 Kuahllumpur, WP,MALAYSIA

CUENT:

EN. MOHO. SIOIKbin SAAi~oSMX; lt9Jaian DltultSUI'iman,TamaI')TunDr.lsm.il·· .. 60000 Kuala lumpur, WP . j ..... v

, ''''' .. ,;1:: PROJECT :

CADANGAN MENOIRIKAN SEBUAH RUMAH.· f@!ANGLO OUA TINGKAT O~N BLOK SEIMS~lU'

nNGKAT BERSERTA ·PLUNGE POOl; 01 A'rA$ LOT NO. PI 54. NO.12JALAN PERt,fATA 7/1:.: SEKSYEN 7

BANDAR SHAH ALAM. SELANGORDARUL EHSAN 9s .. w

GENERAL ARRANGEMENT GROUND FLOOR PLAN

28/02/2003 A 1101

Page 8: BANGLOW2

"

1 ~~~r ~~?g~ P':AN' , -- ~ ,..." ....... ~ ~- ,'"

----------I I I I I ! I/;; d I iil

----LIS: --I ¥ -I-

" : I I I

I 1--+---'1.---- - - - -- - -,-

I -- --- - -- - --,-" I ~ I ~ I ~ I E I

.- - - - __ L -JIt--'\<--+lH1 I I I

--'i<----·-----r

I I I I

l

~

1!iOMM CONOlEtE WAll. ZONE

300 Mtd R0881! WAU ZONE

==================

-------------~-------~ / / ')

/ ~ / I'

~tl'l!!.."!!a.-----------~~~--j- ,i: ! ~ 1 2 --------L--_~-~~~

ROOF LINE AlIOI A2101 .' . ". . _/_ _ I ---, r ....

I I I I I ="'F'ifII'----+--+ l00e~~ - -:r~

_.,."",1=-' I I I

I I

I .wu.UWliJl.J!Jyt.W,UJ I

I I I I I

--

I I, ,J __ ----------~--I----I--------I--:.------

I I I _-.~ ---::}--t--l---~ J'

//J. ,. 'JI) , ,

/ /

~ i i

7000

./

.... -................................. - ..... -........ -.... .

) )

/

NOTES: , 02 + DB LOCATION REVISED. Ale DUCT ADDED

15A11\iZP~ ~""t>1'O

I

FOR CONSTRUCTION REV. DATE REASON fOR ISSUE CHECKED BY

01 05/05/03 FOR TENDER

01 19105/03 fOR CONSTRUCTION

02 30/05/00 FOR CONSTRUCTION --03 07/07/03 FOR CONSTRUCTION

-

KEY PIAN' -

~~ ~ -~ rLJl~l~ b-q

J U J ·,~c

~b r-

L 01 P , ! I ~ I

HTA H1N TAN ARCHITECf Architecture and Dtsign

Block B. Un;tF~lG6·3. BayuArtgkasa, TELEPHONE; 603·22892812 4 Jalan Medal'lg Kapas Ff&. 603-22892813 Bangsar, 59100 Kuala lumpur, WP, MALAYSIA

CLIENT:

EN, MOHO, SIDIK bin SHAIK OSMAN 119 Jalln Oatuk Sulaiman, Taman Tun Dr. Ismail 60000 Kuala lumpur, WP

PROJECT :

CADANGAN MENDIRIKAN SEBUAH RUMAH SANGLO DUA TlNGKAT DAN BLOK SERVIS SATU TlNGKAT BERSERTA "PWNGE POOL" 01 ATAS LOT NO, PT 54, NO.12)ALAN PERMATA 7/1 ,SEKSYEN 7 40000 BANDAR SHAH AIAM, SEIANGOR DARUL EHSAN

DRAWING TITlE :

GENERAL ARRANGEMENT FIRST FLOOR PLAN

JOB NO: ORIOlNATED: SCAlE: SHEET NO:

~ 02/005 HTA 1:100

DATE LOCATION: DRAWN BY:

28/02/2003 A1 102

Page 9: BANGLOW2

0

EXISTING

e.

4800

CD

INTERNAl nMBER SCREENING

BALAUnMBER BOARDING

CD 8 J:- 16600

4BOO 7000

1

t- 1

16600

J.--.-~--"",------_...2QQL_----.

i i

/

CD 0) I

.800

r--'--",re'NAl eURV"D CEIUN6 BALAU PLANKS

:~~ri---!.-.-.-- -.-.-.-.-.-.-.-

0) 0) 0) ... -------,L

I 4800 +-- 4800

i

; PAINTED PlASTER WAU

0)

__ ,~LqF~~V.!f~!:§y.!..!~...:!.~_._. __ ._._.~. _, __ -'\.-

01

:;$1 -I

-------11 ;,;1 Sil

-------11 /

illa 1URUKUR D • IlAflAN SDN laD!

!!AWING RECErveo ON, .... ) 4 JULlo03 FoR' ... ~.~.o.~.~~ ..... :::::~~.·.~:::.'::.'

L::.;:: ......................................................... .

NOTES,

,

FOR CONSTRUCTION 'EV. DATE REASON fOR ISSUE CHECKED BY

Ot 19/05/03 FOR CONSTRUCTION --02 30105/03 FOR CONSTRUCTION

.3 07107/03 FOR CONSTRUcrrON

--~-- !-----'----

.-, ------

---_.

KEY PLAN: -

~~ ~ ~

~~ -.~~: . I ~ I

.~~T-1f~\ ~ --~!~~ J i-~ ,=f=-'= ~ - ,.-i="1 ! if" \

.& §f --~'-~~- \ l H ~/~\\

/- iL...J:E - :~, \\ .--=-===-~~ , I

j I

HTA HIN TAN ARCHITECT , An::hitttture and Design

BloekB,Unitf-LG6-3,Bay .. Angka~, TELEPHONE: 603·22892812 4JalanMedangKapa~ fAX: 603-22892813 &angw, 59100 Kuala lump .. r, WP. MALAYSIA

CLIENT,

EN. MOHD. SIDIK bin SHAIK OSMAN 119 Jalan Datuk Sulaiman, Taman Tun Dt. Ismail 60000 Kuala Lump .. r, WP

PROJECT ,

CAOANGAN MENOIRIKAN SEBUAH RUMAH BANGLO OUA TlNGKAT DAN BLOK SERVIS SATU TINGKAT BERSERTA 'PLUNGE POOL' 01 ATAS LOT NO. PT 54. NO.12JALAN PERMATA 7/1 • SEKSYCN 7 40000 BANOAR SHAH ALAM. SELANGOR OARUL EHSAN

DRAWING TIm :

GENERAL ARRANGEMENT SECTION E-E SECTION F-F

J08NO: ORIGINATED: SCALE: SHEET NO:

~ 02/005 HTA 1:100

DAT! LOCATION: DRAWN BY;

28/02/2003 A2103

Page 10: BANGLOW2

.'

.-

1 ;",~~~T ELEVATION

4800

~ t----I I

4800

00 , !

Ppc ALUMINUM GUnER ~"-''--:;---,

o I

--.....J.o~---- 1000

4800 7000

,6200 00 I ,

12mm THIt TOUOHENED~L.ASS

Q) 1

..,.

-""':::L-+.--- PPC ALUMINUM GUTTER

q) 1 I

ROOfAlI7.S·PllCH INTERLOCKING ClAYT!LES.

-+-.- ._._.~.+--,!,~8.:.!.·?.st . ..!Q~.Q!'Y~~!"" AL~MINUM GUTTER

....... TOPOF8EAM ..2.. LEV + 101.'5 ___ ==t=::a®O~O~:.lZ.1!y+~6~:_

I , : I I . : I I

STONE C~RCWAU

~~~~~~~~~~~~~~~~~~~~-1~~ ______ ~~~·_·~R~~~~V~~~?L~_._ 12m~ F.RAMELEsS·TOUOHENEDGtASS

PAINTED CEMENT PLASTER WAll ." SA~U TIM~ER 8OX20

rOARDING

. ...!..~~.'L._

_ ._.~.l.D~liS . .2..~<!':.OFBEAM

ARH JURUKIJR BAHAN SPN BHD

DRAWING RECETVED ON. '. ~ 4 ~3

rOI{ : ... ~~.~~\~.~~.~~~~;'~:'::::::"""""""

NOTES:

FOR CONSTRUCTION REV. DATE REASON FOR ISSUE CHECKED BY

01 05105/03 FOR TENDER

01 19/05/03 FOR CONSTRUCTION

02 30105{O3 fOR CONSTRUCTION

03 07/07/03 FOR CONSTRUcnON

I

.. -

KEY PLAN:

~~. ~ .0. "~r~l~ ....J .,'

"'?r . Ti1.: \ ~:I 1"%'1.1 \ b 'r; , ~ 1:~ ,

I

~ \9 I

HTA HIN TAN ARCHITECT ArchitttturtandOtsign

B1ockB,UnitF-LG6-3,BayuAngka$3, TElEPHONE: 603·22892812 4 Jalan Mtdang Kapas fAX: 603·22892813

8.ngsar, 59100 Kuala lumpur, WP, MALAYSIA

CLIENT:

EN. MOHD. SIDIK bin SHAIK OSMAN 119 Jalan Oatuk Sulaiman, Taman Tun Or. Ismail 60000 Kuala Lumpur, WP

PROJECT : :

CADANGAN MENDIRIKAN SEBUAH RUMAH BANGLO DUA TINGKAT DAN BLOK SERVIS SATU TlNGKAT BERSERTA "PLUNGE POOL" 01 ATAS LOT NO. PI 54, NO.12)ALAN PERMATA 1/1 ,SEKSYEN 1 40000 BANDAR SHAH ALAM, SELANGOR OARUL EHSAN

DRAWING TITlE :

GENERAL ARRANGEMENT FRONT ELEVATION REAR ELEVATION

J08NO: ORIGINATED: SCALE; SHEET NO;

~ 02/005 HTA 1:100

DATE lOCATION: DRAWN BY:

28/02/2003 A3101 , :

Page 11: BANGLOW2

" . .,f ~

. NOTES: '.It

,'0 1

0) ! ~ 1

0) I

(£) I

I

FOR CONSTRUCTION 'EV. OATE REASON FOR ISSUE CHECKED BY 01 oslO5J03 fORTENOER

01 19/05/03 FOR CONSTRUCTION

02 30/05/03 FOR CONSTRUCTION

03 01(07/03 FOR CONSTRUCTION

...

RETAINING WALL

I----

KEY PLAN: ,

1 ~,~.~T SIDE ELEVATION

(9 1

® 1

I /

~~ ~ ~:.\ U!\ . n. '-.-~ ~\ .

_~i I~\

I rij-~" 0 w Li \ , Bbb- \ . :( \\

• , "

~ ,

HTA 6100

I~

•_u~ I .--+--------------t-

. ________ ....... ________ T~O~y~TSLl~+~81~5 r---t--- PAINTeo CEMENT !

'::::.:=:=~_.., / I PLASTER WAll •

STAI~lE5SSTEEl~ 1----1

, i

PPC ALUMINliM GunER

HIN TAN ARCHITECT Arehitttture and Oesigfl

Blocl: 8. Unit F-lG6-3, Bayu Angkasa. TELEPHONE: 603·22892812 4 Jalan M(dang K3pas FAX: 603·22892813 Bangsar. 59100 Kuala lumpur, WP, MALAYSIA

CLIENT.

EN. MOHO. SIOIK bin SHAIK OSMAN ,

119Jalan Oatuk Svlainlan, Taman Tun Dr.l!.mail 60000 Kuala Lumpur, WP

PROJECT •

ARB JlJRUK1JJt IAHAN SDN BHD

DRAWING RI!CI!lVED ON: .... !.], .. ~Y.~.J! P3 FOR: ... ~.~.~.~!f.!: ..................... ..

CADANGAN MENDIRIKAN SEBUAH RUMAH BANGLO DUA TlNGKAT DAN BlOK SERVIS SATU TINGKAT BERSERTA "PlUIQGE POOL' 01 ATAS lOT NO. PT 54. NO.12)ALAN PERMATA 7/1 ,SEKSYEN 7 40000 BAN DAR SHAH AlAM, SELANGOR DARUl EHSAN

......................................................... DRAWING TITlE :

GENERAL ARRANGEMENT RIGHT SIDE ELEVATION

RETAINING WAll LEFT SIDE ELEVATION

2 ~~,\TooSIDE ELEVATION JOaNO; ORIGINATED: SCALE; SHEET NO:

~ 02/005 HTA 1:100

DATI LOCATION; DRAWN 8Y;

28/02/2003 A3102

Page 12: BANGLOW2

!

,. '~ •

..

• 1 ~~,~!H ELEVATION

I

1-- 7200 , ...

(

2400

K '" .. j (0

!uor AT l]S PITCH IrflEltlPCKING t":i.,AYT11 f5

r-~~~- _JIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII~'il~~'~ ~I I~ SSt+l02~TOPOFBEAM ':-~: ~g~ (02.lQ..Jz. 8QlTOM OF 8}~M •

2 ~CA?~!H ELEVATION

'1<---

~I , ~!£lf.+))~~~l:':\~,t_ I ,-' -- - --

it ~i I , .~ ~-,:,99~60rN,~R~UND~~

LEV + 99.40 TURF LEVEL

ARH JURIlKUR BAHAN SDN lIHD

DRAWING RI!Ci!IVI!D ON: ... +.4-.. JUb .... 2 03 POR: ••• ~.~ ..................... .. ..................................................................

r---------------------------- -NOTES:

FOR CONSTRUCTION REV. OATE REASON FOR ISSUE ----~_LCHEC~

r00:-; -+O,.:;7JJO°':::IIO=O,'+-___ -=FO::'R=CO:::NST:::R:::UCTl==ON~ - __ _ FOR CONSTRUCTION __ _ __ _

,,-- r----

1---+--+--_ .. _---.--_ ... - --­-+--t---.---...... _,--_.- -_.­

.. _--_., --- .. _--1---+--+--_." -,,-- -,-- ~,,----_ .. - ,,---1---+--+--'--- .... "-_.-,,..,," ...

~r-"-!---- --"-----"--""-"" 1---+--+--- -.-----" .. ,,-

--+--- ._"----,,.,,"-- -,,-- ,,+-- ,,--+--

"'-1---+---+ --"-----,,----,, "'.-

" "

---, .... ---. 1--+--+----,,------- .. -- -,-

KEY PLAN:

HTA HIN TA;" ARCHITKT ArdllttdUrtlndDcsi~n

,,~~ \ ; p ,

8Iocl:B.UnitF.lGS·:l:,8a~-u/w;l." 04}~!1n Mtdang Kfpas

.. ~;t;P,10NE; 603-22M/2811 ,A)' 61::!.2189 ?~,~

? gSl'r,S9tOOrualalumpur.W'" 't,:"o,,<;:f.

J~Nl,

:I\j. MOHO. SIOIK bin SHAIK OSMA~ ,,;a!an D3tuk Sulaimgn, 7aman !,,;n 0 •. IYI'ail

0000 Kusla lumpur, WP

PROJECT :

CAOANGAN MENOIRIKAN SEBUAH RUMAH BANGLO OUA TlNGKAT OAN BLOK SERVIS SATU TINGKAT BERSERTA "PLUNGE POOL" 01 ATI>S LOT NO. PT 54, NO.12)ALAN PERMATA 7/1 • SEKSYEN 7 40000 BAND.'.- SHAH ALAM, SEL~NGOR CARUI EHSAN

DRAWING TIlLE:

SERVICE BLOCK ELEVATIONS AND CROSS SECTION

JOB NO IORIGINATED 'SCAlf !SHEET NO I 02/005! HTA 1 :100 : 02

, 'I I' i REV'~~ ::::212003 lOCATIO' I DRAWN BY I A 3 1 03