C742 Site Plan
Contract Interfaces
5
Key Dates and Times
Bid Opening May 6, 2015
Contract Award Date August 6, 2015
Expected Construction NTP Date
September 11, 2015
Time for Performance 459 Calendar Days
6
Scope of Work
• Site Work: demolition, clearing and grubbing, and grading
• Roadway Improvements and Construction • 350-space parking lot • Stormwater Treatment • Utility Construction
– Storm sewer, sanitary sewer, water lines
7
Scope of Work
• BART Police Zone Building Construction • Ancillary Building Construction • Transit Center Construction
– Bus shelters, signage
• Lighting and Traffic Signals Installation • Security and Communications Systems Installation
– CCTV, Emergency Call Boxes
• Station Plaza Construction
8
Scope of Work
• Shared Pedestrian/Bike Trail Construction • Native American Contemplation Garden
Construction • Preparation for Art Installation and
Coordination