Page 1: Basic Steps to Create Dymanic Modification Rule _ SCN

7/18/2019 Basic Steps to Create Dymanic Modification Rule _ SCN

http://slidepdf.com/reader/full/basic-steps-to-create-dymanic-modification-rule-scn 1/6

6/3/2014 Basic Steps to Create Dymanic Modification Rule | SCN

http://scn.sap.com/docs/DOC-46551

Process: 

Quality Management --> Inspection Planning--> Basic data--> Sample --> Dynamic modification Rule (QDR1)

● DMR is basically used to vary the inspection scope.● DMR can define in 1. Task list at header level

  2. Task list at characteristic level

  3. Inspection setup of the material master at  inspection type level

E.g:  Normal inspect(5 lots(A*)) --> skip(10lots(A*))--> Reduced inspect(1 lot(A*))--> skip(10lots(A*))

  skip(10lots(R *))--> Tighten inspect(5 lot(A*))--> Normal inspect(5 lots(A*))

  A- Lot Accept

  R - Any one Lot Reject

Select option Dynamic modification rule is created for usage decision /At lot creation.

Page 2: Basic Steps to Create Dymanic Modification Rule _ SCN

7/18/2019 Basic Steps to Create Dymanic Modification Rule _ SCN

http://slidepdf.com/reader/full/basic-steps-to-create-dymanic-modification-rule-scn 2/6

6/3/2014 Basic Steps to Create Dymanic Modification Rule | SCN

http://scn.sap.com/docs/DOC-46551

Assign stage, required inspection severity, enter short text and tick on Initial Inspection

Stage(ISt) )/Skip stage. 

Normal inspection:

Page 3: Basic Steps to Create Dymanic Modification Rule _ SCN

7/18/2019 Basic Steps to Create Dymanic Modification Rule _ SCN

http://slidepdf.com/reader/full/basic-steps-to-create-dymanic-modification-rule-scn 3/6

6/3/2014 Basic Steps to Create Dymanic Modification Rule | SCN

http://scn.sap.com/docs/DOC-46551

Skip Stage:

Max.skip duration is in days :

 This field is used in the following ways: 

To determine the current inspection stage at sample determination

When the quality level is updated

The system first checks the number of skips and then the skip duration.

 Inspection lot creation

 At sample determination for a lot, if the number of allowed skips has not yet been reached, but themaximum skip duration has been reached or exceeded, the next stage in the sequence for accepted lots is taken as the current stage for the inspection lot. If this stage is another skip, then

the next stage in the sequence for a rejected lot is taken as the current inspection stage. Thismeans that the current inspection lot is due for inspection as a result of the maximum skip durationalthough the quality level contains a skip as the next inspection stage.

Update of the quality level

The quality level is updated either at lot creation or when the usage decision is made. The updateoccurs independently of sample determination for an inspection lot (even if dynamic modificationtakes place at lot creation) and always occurs after the current inspection stage has beendetermined for the inspection lot. If the maximum skip duration has been reached or exceeded,when the quality level is updated, the system calculates the next inspection stage for the quality

level of an accepted lot based on the same algorithm. This means that the following stage in thesequence for accepted lots is used as the next inspection stage. If this stage is a skip, thefollowing stage in the sequence for a rejected lot is taken as the inspection stage for the qualitylevel. Since this stage usually specifies an inspection, the next inspection lot is to be inspected.

Page 4: Basic Steps to Create Dymanic Modification Rule _ SCN

7/18/2019 Basic Steps to Create Dymanic Modification Rule _ SCN

http://slidepdf.com/reader/full/basic-steps-to-create-dymanic-modification-rule-scn 4/6

6/3/2014 Basic Steps to Create Dymanic Modification Rule | SCN

http://scn.sap.com/docs/DOC-46551

Tighten inspection:

Reduced inspection:

Page 5: Basic Steps to Create Dymanic Modification Rule _ SCN

7/18/2019 Basic Steps to Create Dymanic Modification Rule _ SCN

http://slidepdf.com/reader/full/basic-steps-to-create-dymanic-modification-rule-scn 5/6

6/3/2014 Basic Steps to Create Dymanic Modification Rule | SCN

http://scn.sap.com/docs/DOC-46551

 

Page 6: Basic Steps to Create Dymanic Modification Rule _ SCN

7/18/2019 Basic Steps to Create Dymanic Modification Rule _ SCN

http://slidepdf.com/reader/full/basic-steps-to-create-dymanic-modification-rule-scn 6/6