batson cssi.pptx (1)

Upload: ryan-a-battick

Post on 17-Feb-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/23/2019 Batson Cssi.pptx (1)

    1/41

    GENERATION SYSTEM

    Electricity generationis the process of generating electric

    power from other sources of primary energy. The fundamental

    principles of electricity generation were discovered during the 1820s

    and early 1830s by the British scientist Michael Faraday. The basic

    principle is the electricity movement of a loop of wire, or disc copper

    between the poles of a magnet. For electric utilities. it is the first

    process in the delivery of electricity to consumers. Electricity is most

    often generated at a power station by electromechanical generators,

    primarily driven by heat engines fuelled by chemical combustion or

    nuclear fission but also by other means such as the kinetic energy of

    flowing water and wind. Other energy sources include

    solar photovoltaic and geothermal power and electrochemical

    batteries.

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    2/41

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    3/41

    The layout shows the components of a

    standard electrical supply for a city whereelectricity is produced by a source, the

    primary supply and then transmitted tosubstations by high voltage wires which

    uses transformersto amplify the voltagethen transmit it to secondary substation

    and onto secondary lines throughtransformers into the premises of the end

    users

    In Jamaica electricity is transmitted using138000volts step-down to 24000volts for

    domestic and industrial use.

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    4/41

    1. Step-down Transformer

    2. Step-up Transformer

    Step-down transformers are employed at the point of transmitting load into the facilities to the users. They are usually P

    Mounted or Pad mounted

    POLE MOUNTED TYPE 1 PAD MOUNTED TYPE

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    5/41

    Transformers

    Transformers that are generally employed in the built environment are Step-down Transformers. The step-are used mostly by the power supply company in the transmission of power.

    Step-down Transformer

    The step down transformer is used to reduce the voltage from the high voltage used for transmission to thevoltage that is employed in the built environment

    130000 volts 24000 volts 440/240/220/110 etc

    Construction Services Structure Integration (CSSI)

    CROSS SECTION OF

    TRANSFORMER

  • 7/23/2019 Batson Cssi.pptx (1)

    6/41

    FROM SERVICE PROVIDER TO INTERNAL

    DISTRIBUTION

  • 7/23/2019 Batson Cssi.pptx (1)

    7/41

    ONE LINE DIAGRAM OF ELECTRICAL SYSTEM

    Panel Box

    Construction Services Structure Integration (CSSI)

    TP 1

    TP 2

    TP 3

    TP 4

    TP 4

    TP 5

  • 7/23/2019 Batson Cssi.pptx (1)

    8/41

    Panels, Breakers, Sub-Panels and distribution Panels Conduits i

    Construction Services Structure Integration (CSSI)

    1 2 3

    4

    `

    5 6

    1: Distri

    2: Main

    3: Cond

    concret

    4: Main 5: Main

    6: Break

  • 7/23/2019 Batson Cssi.pptx (1)

    9/41

    METERING

    Metering is done through a single meter or through a meter centre

    In single metering the main comes from a pothead directly to the individual meter

    In the meter centre the mains comes to a control switch and then each meter feeds from that point

    Meter centres are mostly used for buildings or structures where the clients needs individual electrical billing, while single meterin

    need only one billing

    The rules regulating meter centres is found in JS-21 , but some of the most common BUT regulation are:

    The base of the meter centre must have a minimum thickness of eighteen inches (18) First metre socket must be one foot {1-0) from the finish floor level Load on the rooms cannot be more than 400 AMPS with special permits need to go above

    The room can be open front The room must be ventilated

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    10/41

    Circuits

    Each circuit is govern by a breaker that is located in a panel box mounted on a wall of the structure Circuits are rated by the resistance of the control breaker. The amperage is usually marked on the breakers in the panels and

    load rating of the circuit

    The typical plug circuits are either 110 or 220 volts

    Five plugs are allowed 120 volts/20amps circuits. In the kitchen it is reduced to three per circuits

    Light circuits are 15 amps with a maximum 12 lights permitted per circuits

    Switches and Plugs

    Switches are placed 4-6 from the finish floor level (FFL)

    Plugs are Placed 0-18 from the finish floor level

    110 plugs are vertical while 220 are tandem

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    11/41

    GEI

    The GEI is the government electrical inspectors that gives certification on

    behalf of the government for the purpose of the utility company toconduct any form of termination.

    No electrical connection can be made by the utility company without thecertification of the GEI.

    Application for electrical supply

    Application is made by a licensed electrician to the GEI office forinspection

    If approval is given it is taken to the utility company along with thetitle of the property and the approved drawings from the parish

    council. The drawings are usually stamped by PE ( professionalengineer)

    The supply from point is determined by the utility company

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    12/41

    Solar & Photovoltaic

    8+

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    13/41

    Solar Photovoltaic (PV) power generation has recently emerged from its long hibernation; a technologyonly used in satellites and special remote applications is now available to everyman

    This is due to a convergence of:

    Governments looking for alternative energy forms to replace the unsustainable ones wedepend on today

    Modern manufacturing capability

    The energy needs of modern society

    World-wide abundance of free solar energy

    Introduction

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    14/41

    High dependency on imported fossil fuels

    Dependency on traditional biomass fuels, e.g. wood, charcoal, plant/animal waste

    Exposure to negative impact of climate change and environmental damages,

    e.g. sea level rising, hurricanes, flooding

    Substantial sources of renewable energy, e.g. solar resources

    Inadequate local human capacity for installation, operation, and maintenance

    of sustainable energy systems

    Caribbean Background

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    15/41

    Shortly after the silicon PV cell was invented the first commercial applicationsof PV were in rural telephone systems and radio transmitters

    Today rural off-grid applications of PV improves life in very important ways;pumping water for drinking and irrigation, providing energy for lights inschools, refrigeration of medicines, and much more

    This is especially true in developing nations where the utility grid isunavailable or unreliable

    Rural health clinic ZambiaRural telephone power USA 1955

    Myanmar water pumping

    images courtesy ofDOE/NREL: (M. & W. RhodeByron Stafford), LORENTZ

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    16/41

    A utility-connected Photovoltaic (PV) system is becomingthe most common system configuration

    Solar power-plant components can be arranged in manyways to design PV systems for different situations, but themost common configuration is a utility-connected system,a.k.a grid-tied

    In most cases energy is not stored at the home (batteries) instead the power is fed to the loads and the excess issold to the grid it is a power generator

    Systems and Configurations

    A utility-connected Photovoltaic (PV) system

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    17/41

    Distributed Generation (DG) systems produce electricity close to whereit is used avoiding losses from long transmission lines

    Small scale Distributed Generation systems can include PV systems,wind turbines, water turbines

    If consumers are connected to the utility grid, excess power not used atthe moment can be sold to the grid

    DG system may also be the only power source, a.k.a. Off-Grid

    Distributed Generation (DG) systems

    Construction Services Structure Integration (CSSI)

    COMBINATIO

  • 7/23/2019 Batson Cssi.pptx (1)

    18/41

    Construction Services Structure Integration (CSSI)

    Portable PV systems focus on mobility, examples of thesesystems are boats, temporary traffic signs, and powersources for portable electronics.

    A number of applications require power when the sun is notavailable, requiring a form of storage as part of the PVsystem

    Portable PV systems

    1

    3

    IMAGE:1 PV USE FOR REMOTE CELL SITE

    2 BOAT USING PV SYSTEM3 REMOTE TENT IN THE HIGH MOUNTAINS

  • 7/23/2019 Batson Cssi.pptx (1)

    19/41

    The simplest device to harvest solar radiation is theflat-plate collector

    solar energy is absorbed on a flat surface without anyform of concentration

    Not as sensitive to the incidence angle to the sun;direct as well as diffuse radiation is converted topower

    Flat-plate collectors may be installed in a fixedorientation or on a sun-tracking mount

    Nearly all residential and commercial hot water andPV solar energy collectors are flat-plate

    Types of solar collection

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    20/41

    Residential PV has two unique advantages over all forms of energy; solar modules fit on rooftops,close to the load

    By bringing energy production and consumption together - something fossil fuel power plants andother renewable energy can't do suburban PV is distributed generation (DG) without the

    transmission losses incurred with grid power Being distributed, PV actually competes with retail power delivered by the utility not wholesale

    (enforced by law: net metering)

    Imagine a world with solar on every possible rooftop - and electric vehicles in every garage

    Every person becomes an energy entrepreneur

    The sun never sends a bil l

    No wars over energy, no man-made environmental disasters

    Domestic Application

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    21/41

    The cost to bring power from a utility may in some cases be prohibitive

    Remote or Off-Grid PV systems are a great option for architecturalapplications that are too distant to be economically connected to theutility grid

    In these cases PV is often an ideal choice due to its simplicity; no fuelto transport and very low maintenance

    Water pumping Navigation beacon

    Traffic signs LightingNavaho homesteadRemote cabin Communications

    Consideration

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    22/41

    The rate of change in energy consumption isunsustainable economically and environmentally

    The worlds population has grown by a factor of 3in the last 60 years and the USAs energy demandby a factor of 6 per capita 1)

    China and India joining industrialized life furtherresult in explosive growth

    Each year energy demand grows by ~2% - and isexpected to grow by 30-50% by 2020, almostdoubling by 2050 from today 2)

    There are large amounts of coal and natural gas,however the pollution from these fuels will destroyour current habitat

    Energy demand is unsustainablewith currentmeans

    Considerations

    1) World Energy Council2) Graph and data source: Novatlantis http://www.novat

    ch/fileadmin/downloads/2000watt/leichterleben_eng.

    The unsustainable rate of energy use must be reve

    Who is going to solve this problem and how

    Construction Services Structure Integration (CSSI)

    C id i

    http://www.novatlantis.ch/fileadmin/downloads/2000watt/leichterleben_eng.pdfhttp://www.novatlantis.ch/fileadmin/downloads/2000watt/leichterleben_eng.pdf
  • 7/23/2019 Batson Cssi.pptx (1)

    23/41

    The long term trends are all very alarming

    Peak-oil production has occurred twice now (USA ~1976, global ~2010)

    Replacing oil and coal will be monumental undertakings and will take decades ofconcertedeffort

    The longer we wait the more difficult, risky, and expensive it will become

    The USA has 2% of the worlds reserves and requires 25% of the oil produced -no amount of drilling will fix this

    Fossil Fuels

    Considerations

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    24/41

    Not all countries are developing PV at the same rate; Germany has been the steady and strong growth center thanks to a solidPV policy and a strong desire to replace nuclear energy with renewables

    Spains attempt to develop PV was rapid and sporadic (2008) due to poorly developed incentives and commitments

    USA and China are just awakening to PVs potential to provide a significant part of the energy demands, with enormouspotential growth due to the large energy needs

    PV Growth

    Graph courtesy of European Photovoltaic Industry Association (EPIA)

    Construction Services Structure Integration (CSSI)

  • 7/23/2019 Batson Cssi.pptx (1)

    25/41

    Construction Services Structure Integration (CSSI)

    Most material used in the production of PV are imported into thecountry, The same is done for fossil fuel energy production thereforeit is the cost benefit analysis that will be the deciding factor if acountry promote the use of this natural form of energy consumption.

    Architectural consideration is one of the positive factor in theapplication of PV due in large part to the passive nature of totalproduct.

    The sourcing and the manufacturing of cheap technology tomaximize on the delivery of PV energy to the point of use willcontinue to under changes and improvement, but it still will be a ofthe a cheaper and sustainable type of energy.

    Incentive driven by govern contribution will have to be the driving

    factor for PV in the Caribbean.

    Considerations

    Image: creative commons Ed Uthman

    Industry overall requires a few elements

    Cost-effective and reliable technol

    Political will, support, and incentive Educated consumers

    Safe and reliable installations

    Solar consideration for building

  • 7/23/2019 Batson Cssi.pptx (1)

    26/41

    PHOTOVOLTAIC AND ELECTRICAL SY

  • 7/23/2019 Batson Cssi.pptx (1)

    27/41

    BUILDING ELECTRICAL SYSTEM

    The layout shows the components of a standard electrical supply for a city where

    electricity is produced by a source, the primary supply and then transmitted to

    substations by high voltage wires which uses transformersto amplify the

    voltage then transmit it to secondary substation and onto secondary lines

    throughtransformers into the premises of the end users

    In Jamaica electricity is transmitted using 138000volts step-down to 24000volts

    for domestic and industrial use.

    Area of Design

    ELECTRICAL LINE DIAGRAM

  • 7/23/2019 Batson Cssi.pptx (1)

    28/41

    ELECTRICAL LINE DIAGRAM

    distribution

    Panel

    transformer

  • 7/23/2019 Batson Cssi.pptx (1)

    29/41

    ELECTRICAL

    Lot Service Main: JPS Supply

    No 2 or 2/0

    Estimated distance from supply main =50 feet

    Electrical cable runs underground From electrical poles to utilities room

    Underground cable area

    BUILDING ELECTRICAL SYSTE

  • 7/23/2019 Batson Cssi.pptx (1)

    30/41

    BUILDING ELECTRICAL SYSTEJPS 250KVA

    Equipment

    ITEMS DESCRIPTION LOCATION VOLTS EQUIPTMENT AMPS QUANTITY TYPE HP PHASE

    safety factor 1.5

    General electrics Outlets 110/120-volts Offices 110v 15 20 Double Pole 1

    220/450-volts offices 220v 20 10 Double Pole 2

    Elevator 415v Elevator 60 1 Triple Pole 3

    Main Panels 3phase Air-condition 415v AHU 60 2 Triple Pole 3

    15 tonne ROOF 415 Chiller 150 1 Triple Pole 3

    EQUIPTMENT 220v 40 Triple Pole

    FIRE PROTECTION PUMPS 40 2 Triple Pole 25 3

    fire detection 2Audio 2

    SERVERS 110v 70 3

    SPRINKLER

    HEATERS 220v 40 Triple Pole 3

    domestic Water 110v PUMPS 20 1 5 1

    IRRIGATION PUMPS 220v PUMPS 20 1 5 3

    SERVERS

    535

    LIGHTING

    Items Description type Location lux Lumens Area sq,ft Room Height mf Uf # of lamps spacing

    Safety Factor 1.5

    Lighting LED Light Fixtures 2'x2 Troffers Offices 1 500 10000 8.520526723 15' 0.4 0.75 1.420087787 10'

    " " office 2 500 10000 25.31696037 15' 0.4 0.75 4.219493395 10'

    " " Services 500 10000 14.91092177 15' 0.4 0.75 2.485153628 10'

    " " Vault 500 10000 10.26336174 15' 0.4 0.75 1.710560289 10'

    " " Passage 500 10000 53.135378 15' 0.4 0.75 8.855896334 10'

    " " lobby 500 10000 165.2744677 15' 0.4 0.75 27.54574461 10'

    " " Conference 500 10000 25.464756 15' 0.4 0.75 4.244126001 10'

    " " upper lobby 500 10000 31.46785438 15' 0.4 0.75 5.244642396 10'

    " " bathroom 300 10000 45.70100697 15' 0.4 0.75 4.570100697 10'

    External

    Generators stand by main generators Kva output 60.29580514

    CIRCUITS

    Items Description type Location volts Breakers(AMPS) QUANTITY TYPE

    Safety Factor 1.5 1.5

    General electrics Outlets 110/220v Offices 110 20 20 Single pole

    " 110/220v offices 220 15 10 Double Pole

    lighting 110/220v Ceiling 220 15 7 Double Pole

    Generators

    100kva 3*100 amps

    Ele ct ri ca l Sys te m 2 50 kv a

    Floors 220/110

  • 7/23/2019 Batson Cssi.pptx (1)

    31/41

  • 7/23/2019 Batson Cssi.pptx (1)

    32/41

    Lighting for the internal of the building will consist of :

    2 x 2 LED Ceiling Mounted Direct truffers 9w 220v DIRECT recess Lamp 90 LPW standard efficacy, and designed to 50,000 or 75,000 hours. Or 8 years Step able Dimmable Input voltage 220volts 22 watts 2000 LUMENS CRI 93

  • 7/23/2019 Batson Cssi.pptx (1)

    33/41

    PHOTOVOLTAIC

    A utility-connected Photovoltaic (PV) system is becoming the most common systemconfiguration

    Solar power-plant components can be arranged in many ways to design PVsystems for different situations, but the most common configuration is a utility-connected system, a.k.a grid-tiedIn most cases energy is not stored at the home (batteries) instead the power is fed

    to the loads and the excess is sold to the grid it is a power generator

    El t i l O tl t l t

  • 7/23/2019 Batson Cssi.pptx (1)

    34/41

    Electrical Outlet layout

    Section A-A

    A

    ELECTRICAL ROOM

    ELECTRICAL WIRING

    Attached to roof

    ELECTRICAL WIRING

    In walls

    ELECTRICAL WIRING

    from panels

    Ground Floor

    PV PANELS

    ELECTRICAL PV

    http://www.photovoltaic-software.com/
  • 7/23/2019 Batson Cssi.pptx (1)

    35/41

    Calculation of the solar PV energy output of a photovoltaic system

    Yellow cell = enter your own data

    Green cell = result (do not change the value)

    White cell = calculated value (do not change the value)

    Global formula : E = A * r * H * PR

    E = Energy (kWh) 75329kWh/an A = Total solar panel Area (m) 335m

    r = solar panel yield (%) 15%

    H = Annual average irradiation on tilted panels (shadings not included)* 2000kWh/m.an

    PR = Performance ratio, coeff ic ient for losses (range between 0.9 and 0.5, default value = 0 .75) 0.75

    Total powerof thesystem 50.3kWp

    Losses details (depend of site, technology, and sizing of the system)

    - Inverter losses (6% to 15 %) 8%

    - Temprature losses (5% to 15%) 8%

    - DC cables losses (1 to 3 %) 2%

    - AC cables losses (1 to 3 %) 2%

    - Shadings 0 % to 40% (depends of site) 3% - Losses weak irradiation 3% yo 7% 3%

    - Losses due to dust, snow... (2%) 2%

    - Other Losses 0%

    *You can find this value on the map below or here : solar radiation data

    You have to find the global annual irradiation incident on your PV panels with your specific inclination (slope, tilt)

    and orientation (azimuth).

    More info

    Source : www.photovoltaic-software.com

    ORIEN

    : 1 8 D

    DUE

    http://www.photovoltaic-software.com/http://www.photovoltaic-software.com/http://www.photovoltaic-software.com/http://www.photovoltaic-software.com/http://www.photovoltaic-software.com/http://www.photovoltaic-software.com/http://www.photovoltaic-software.com/solar-radiation-database.php
  • 7/23/2019 Batson Cssi.pptx (1)

    36/41

    PV PANELS SIZE 3FEET X 5FEET

    WEIGHT

    MANUFACTURER: GENCO

    LOCATION ON STRUCTION ROOF

    18 DEGREES SOUTH SUPPLIED BY ENERSAVE SOLUTION

    PANELS

    INVERTER

    MAIN ELEC, PANELTYPICAL FLAT PV PANEL SAME PROPOSED FORBUILDING SYSTEM (3FEET X 5FEET)

  • 7/23/2019 Batson Cssi.pptx (1)

    37/41

    BATTERIES

    BATTERIESNo Batteries

    ITEMS ROOF AREA UNITS % USE PANEL SIZE # PANELS PANEL WATTAGE (W) KW STORAGE STORAGE No Batteries

    1 479MSQ

    70 1.953697372 172 250 42905.82625 40% 17162.3305

    2

    3 PEAK SUN HOURS

    KWH/DAY

    (Consumption) AH/DAY

    WH/day

    (Consumption) SYSTEM VOLTAGE

    TOTAL AH REQUIRED FOR 60%

    DEPLETION

    Battery Ah

    Capacity BATTERY VOLTAGE BATTERIES IN PARALLEL BATTERIES IN SERIES

    Total Batteries

    Required

    4 6257.43

    5363.125 257430 48 8581 420 6 20.43095238 8 163.45

    Batteries : Alignment : Series

    6 volts Type Solar

    # of 168

    TYPICAL BATTERIE

    PV APPLICATION

    BATTERIES SPECIFICATION SHEET

  • 7/23/2019 Batson Cssi.pptx (1)

    38/41

    BATTERIES SPECIFICATION SHEET

    TYPICAL BATTERIES IN

    SERIES

  • 7/23/2019 Batson Cssi.pptx (1)

    39/41

    PLAN VIEW OF PHOTOVOLTAIC APPLIC

    The placement of the panels on the roof provided

    for the best advantage for the direct feeding of

    sunlight. The panels also provided shading for the

    roof. The roof of the building is the part of thebuilding envelope that is responsible for the

    largest amount of radiant heat flow into the

    building. The application of the PV panel on theroof provides also a radiant barrier for the building.

    PANORAMIC VIEW OF BUILD WITH PV APP

  • 7/23/2019 Batson Cssi.pptx (1)

    40/41

    PANORAMIC VIEW OF BUILD WITH PV APPThe panel arrangement occupy 60 percent

    of the roof area with the remainder of spaceused for the purpose of mechanical and

    maintenance.

    The amount of panel placed on the roof is110 with ease of access for maintenance

    BUILDING CONSUMPTION AND PV SYST

  • 7/23/2019 Batson Cssi.pptx (1)

    41/41

    Total load ( building power consumption)

    413 amps (90.860 kw}

    Total production of pv system ( peak output}

    50.3 kw

    The peak output power of the system is 50.3kw which provides 251.3keh per day over the 5

    peak sun hours.

    The facility consumes 95.260kw peak power which amounts to 762.08 kwh hours per 8 hour day

    The system therefore offsets 33% of the overall consumption of the facility

    BUILDING CONSUMPTION AND PV SYST

    OUTPUT