before the national green tribunalawsassets.wwfindia.org/downloads/pattancheru... · s/o late b....
TRANSCRIPT
1
BEFORE THE NATIONAL GREEN TRIBUNAL
SOUTHERN ZONE, CHENNAI
APPLICATION No. 92 of 2013 (SZ) (THC)
(W.P.No. 3510 of 2009 of the High court of Andhra Pradesh at
Hyderabad)
In the matter of:
M/s. Pattancheru Environ-Tech Ltd.,
Through its whole time Director
B.V. Ramana Murthy,
S/o Late B. Uma Maheswara Rao
Plot. No. 23-25, I.D.A., Phase-IV
Pattancheru, Andhra Pradesh .. Applicant/Petitioner in
the writ petition
AND
1. Andhra Pradesh Pollution Control Board
Through its Member Secretary
Paryavaran Bhawan,
2
A-3, Industrial Estate, Sanath Nagar
Hyderbad, Andhra Pradesh
2. Joint Chief Environmental Engineer
FAC, A P Pollution Control Board
Zonal Office
25-31/11, Tulasi Reddy Complex 2nd Floor
R.C. Puram, Medak District
3. The Branch Manager
ING Vysa Bank, Pattancheru
Medak District
4. The Branch Manager
HDFC Bank, Chandanagar
RR District
5. The Branch Manager
State Bank of India
Pattanchery Mandal
Medak District
6. The Branch Manager
Oriental Bank of Commerce
3
Ameerpet, Hyderabad .. Respondents/respondents
in the writ petition
(Respondent Nos. 3 to 6 were ordered to be not necessary
parties to the writ petitions by the Hon’ble High Court of Andhra
Pradesh at Hyderabad)
Counsel appearing:
Applicant .. M/s. Lakshmi Kumaran and Sridharan, Advocates
Respondents .. Shri T. Sai Krishnan, Advocate for respondent Nos. 1
and 2
ORDER
Present:
1. Hon’ble Shri Justice M. Chockalingam
Judicial Member
2. Hon’ble Prof. Dr. R. Nagendran
Expert Member
_____________________________________________________
4
Dated, 17th, December, 2014
_______________________________________________________
(Hon’ble Shri Justice M. Chockalingam)
This application has been taken on the file of the Tribunal
consequent to and order of transfer of the Writ Petition filed by the
applicant herein before the Hon’ble High Court of Andhra Pradesh,
Hyderabad in W.P.No. 3510 of 2009. The brief facts of the case as
could be made out from the averments in the writ petition are:
2. The applicant company was promoted jointly by the A.P.
Patancheru Industrial Belt in the year 1989. The applicant’s company
was incorporated for establishing and running a Common Effluent
Treatment Plant (CETP) for treating the industrial effluents generated
from industries in the area. The establishment of chemical,
pharmaceutical and bulk-drug industries in the Patancheru Industrial
Belt has reckoned the area on the industrial map in the years 1980-
1990. The entire area has seen remarkable economic growth and
generated employment to 2 lakh persons. The bulk-drug industries in
the area produce about 40% of the total production in the country and
5
earn substantial foreign exchange for the country apart from paying
about Rs.1000 crores to Government by way of taxes. The CETP
emerged as a necessity consequent to the industrial development in
the Patancheru area to overcome pollution problem and maintain the
ecological balance. With the industrial development in the area,
environmental pollution became an issue and a writ petition in W.P (C)
No. 1056/1990 was filed in the Hon’ble Supreme Court seeking
compensation and directions relating to environmental pollution
control. The applicant’s company was also impleaded as a party
respondent in the said writ petition. The applicant company started
CETP operations in year 1994. The said CETP was established with
a capacity of 7500 m3 per day and the total project cost was Rs. 5.70
crores. In 1996, the management of the plant was taken over by the
directors representing the industries and about Rs. 3.00 crores were
spent for upgrading the treatment facilities in the plant. Liquid Oxygen
Injection Technology was adopted for the first time in the country for
biological treatment in the CETP. On 12.05.1998, the Hon’ble
Supreme Court considered the Joint Action Plan (JAP) submitted by
the Central Pollution Control Board (CPCB) and directed that the
immediate measures as proposed in the said plan was to come into
6
force on 01.06.1998 subject to further order of the court. With respect
to medium term measures and long term measures proposed in the
said JAP, the Hon’ble Supreme Court directed that the State
Government as well as the industries would take adequate measures
to ensure that those are initiated. In course of proceedings of W.P (C)
No. 1056/1990 different options were discussed and vide order dated
10.10.2000, the Hon’ble Supreme Court directed the parties to
finalize one option pursuant to which the “pipe-line option” was
recommended. In November 2000, a revised JAP was submitted
before the Hon’ble Supreme Court outlining time frame for the pipe
line project which was finally approved for implementing the above-
mentioned option. The revised JAP proposed Environment Impact
Assessment (EIA) study, preparation of Environment Management
Plan (EMP) for the pipe line project and Environmental Clearance
from Andhra Pradesh Pollution Control Board (APPCB) etc., and only
thereafter any further activities such as financial agreements, tender,
award of work etc., were to be taken up. On 06.02.2001, the Hon’ble
Supreme Court approved the pipe line project and the time frame
proposed in the revised JAP was submitted before the court. As per
the Hon’ble Supreme Court order dated 06.02.2001 it is clear that the
7
parameters for outlet i.e., before the discharge, which was to be
conforming to the sewage standard parameters by the CETP as laid
down in the JAP. The status report indicating the measures taken by
APPCB in W.P. No. 19661 of 2002 WP (C) No. 1056/1990 was also
filed by the APPCB before Hon’ble Supreme Court of India.
3. Pursuant to the revised JAP, the applicant company was
asked to get an EIA report prepared and the applicant company
entrusted the same to Centre for Environment, Jawaharlal Nehru
Technological University, Hyderabad to prepare an EIA Report on two
aspects namely, (i) Laying pipe line from Patancheru Effluent
Treatment Ltd., (PETL) to K and S Main Balanagar, and (ii) Effect of
mixing of PETL (P) and PETL(B) effluent with sewage at Sewage
Treatment Plan (STP), Amberpet and release its outlet into Musi river
and downstream. The rapid EIA on commissioning of 18 km long pipe
line and discharge of the treated effluent from M/s PETL to STP at
Amberpet was submitted by Centre for Environment, Jawaharlal
Nehru Technological University, Hyderabad. The conclusion of the
EIA recorded is as under :
“By providing primary and secondary treatment of combined
(Sewage plus industrial wastes) wastes, there maybe a
8
reduction of more than 90% in BOD, up to 70% in COD. The
metallic ions also get reduced as fraction of these ions are
utilized as micro nutrients in the biological growth and wasted
as excess sludge. There may be an improvement in the outlet
water quality from present level after the provision of
treatment at Amberpet. Further, by this treatment facility, the
complex nature of the ions (BOD, COD, TDS and SS) will
reduce and with the quality of treated water at the outlet can
be utilized for irrigation/plan(t) growth/agriculture. The report
also contains information on evaluation of environmental
impacts and environmental management plans.”
4. The work of construction of pipe line commenced on
04.09.2002 was completed in two years. The finance for the said
project came from Andhra Pradesh Government and the Member-
Industries. The Writ Petition (C) No. 1056/1990 was transferred by to
A.P. High Court and a Fact Finding Committee was constituted by the
Order of the Hon’ble High Court. A report was submitted to the
Hon’ble High Court by the Fact Finding Committee wherein the
Committee also recommended for expediting the pipe line project. A
status report was filed by APPCB before the Hon’ble High Court
which clearly approved the measures taken. With regard to the
9
parameters fixed for pre-treated effluent from the member industries,
the Hon’ble Supreme Court vide order dated 12.05.98 fixed only 4
parameters with respect to pre-treated effluent (inlet). However, vide
order dated 05.08.2005, the 1st respondent fixed 20 parameters in
relation to effluent (inlet and outlet). The said order was challenged in
W.P. (C).No. 441/2005 and batch cases in the Hon’ble Supreme
Court and the Hon’ble Supreme Court disposed of the said writ
petition on 17.07.2007 with the following observation:
“It is not in dispute that the petitioner meets the
inlet standards prescribed by the action plan. It is
made clear, however, that the petitioner shall also
comply with the outlet standards prescribed and
mentioned in the action Plan. However, fulfilment of
outlet standards can happen only after the
connectivity is established with S.T.P. The
connectivity may be given as per the Action Plan.
Accordingly the writ petition stands disposed of”.
5. The respondents have not undertaken the connectivity of
the pipeline with STP at Amberpet. The bulk drug manufacturers
association made a representation to the Government to comply
with the directions of Hon’ble Supreme Court and to permit CETP,
Patancheru to discharge the effluent through a 18 km long
10
pipeline connected to STP, Amberpet. The Commissioner of
Industries, Government of Andhra Pradesh communicated in
letter No. 19-1-06-0638-06-0638, dated 21.02.2008 a copy of the
minutes of the meeting held on 10.01.2008 in the chambers of the
Chief Secretary to the Government on the issues raised by the
Bulk Drug Manufacturers Association. In the said minutes of the
meeting on the subject relating to connectivity of the pipeline it
has been observed as under.
“It was recognized that one of the important
elements of the JAP of the APPCB and CPCB is
that the standards of the effluents being delivered at
the inlet of the 18 km pipeline connected to the STP,
Amberpet need to be set having regard to the
ultimate discharge from Amberpet. This is because
the pipeline will be ultimately discharging the
effluents together with sewage effluent 18 km
downstream, and hence it would be more
appropriate to ensure that the standards at the
discharge point of the STP, Amberpet conform to
the prescribed specifications. It was agreed that the
APPCB, with due information to the CPCB, will in
consultation with Municipal Corporation,
Metropolitan Water Works etc., let in effluents of
different standards as received from the CETP and
thereafter measure the technical parameters of the
effluents being discharged at STP, Amberpet to
11
establish if they meet the prescribed standards. The
reports of the competent scientific and technical
tests should then be placed before the APPCB who
will examine whether the JAP should be revised and
if so, in what manner and submit the same to the
CPCB/Supreme Court for consideration”.
6. The 2nd respondent, contrary to the order of the Hon’ble
Supreme Court and the observations of the Chief Secretary
without issuing any notice to the petitioner, the applicant herein,
passed orders on different dates imposing a penalty of Rs.
2,32,62,000/- from November 2007 to October 2008 further
stating that if the penalty amount is not paid action will be initiated
for the non-compliance of the order of the Hon’ble Supreme Court
dated 17.07.2007. In no part of the order dated 17.07.2007 the
Hon’ble Supreme Court empowered the 2nd respondent to levy
and collect penalty from the applicant. The impugned action of
the 2nd respondent is highly discriminatory, unjust, improper and
illegal. The 2nd respondent by letter No. PTN-
25/PCB/ZO/RCP/2005, dated 06.02.2009 addressed to the
applicant’s bankers ING Vysya Bank, Patancheru and HDFC
12
Bank, Chandanagar Branch, invoked the bank guarantee and
encashed the bank guarantee amount of Rs. 50, 00, 000/-. The
2nd respondent addressed a letter dated 10.02.2009 to applicant’s
bankers ING Vysya Bank, Patancheru, HDFC Bank,
Chandanagar Branch, State Bank of India, Muthangi Branch and
Oriental Bank of Commerce, Ameerpet Branch to freeze the bank
accounts of the applicant and requested them to remit the funds
available in the applicant’s account to the 1st respondent to
implement the orders of the Hon’ble Supreme Court. The action
of the 2nd respondent is totally in violation of the orders of Hon’ble
Supreme Court in W.P. No.441 of 2005, dated 17.07.2007 and
the provision of Section 33A of the Water (Prevention and Control
of Pollution) Act, 1974 (Water Act, 1974) read with Rule 34 of
Water (Prevention and Control of Pollution) Rules, 1975 (Water
(P&CP) Rules, 1975. As per Rule 34 of the Water (P&CP) Rules.
1975, the 1st respondent is liable to issue a notice before passing
any direction under section 33A of the Water Act, 1974. The 2nd
respondent did not issue any notice either to the applicant or to
the respondents 3 to 6 before passing the directions to freeze
bank accounts of the Applicant which is arbitrary, discriminatory
13
and contrary to the principle of natural justice. The action of the
1st and 2nd respondents is also in violation of Articles 14 and 19 of
Constitution of India. In view of freezing of the bank accounts of
the applicant, the working of the CETP came to a standstill. It
would adversely affect the functioning of over 100 units where
over two lakhs of employees are depending on it for their
livelihood.
7. The 1st and 2nd respondent, namely, the APPCB, per contra,
filed the reply stating that the application is not at all maintainable and
deserves to be dismissed in limini. The appeal remedy has not been
exhausted and the application has been filed directly. The penalty has
been imposed on the applicant after giving due notice and opportunity
for violation of the standards as laid down by the JAP which was
approved by the Hon’ble Supreme Court of India. The applicant who
has neither denied nor disputed the violations cannot maintain the
challenge to the same by way of this application. The applicant wants
to take undue advantage of one particular sentence contained in the
order of the Hon’ble Supreme Court dated 17/07/2007 in W.P. (C) No:
441 of 2005 by reading it out of context. The very same order clearly
mandates that the applicant shall comply with the outlet standards
14
prescribed in the JAP. It directs that even after the connectivity is
established with the STP, the applicant shall continue to comply with
the outlet standards. The same cannot be taken advantage by the
applicant to say as though till such time the connectivity is given with
the STP, they need not comply with the outlet standards and that
penalty cannot be levied for such repeated violation in spite of issuing
notice and warnings.
8. During 1984, highly polluting industries like bulk drug and
other water polluting industries were established in Patancheru-
Bollaram area using grant of subsidies and due to proximity to
Hyderabad. The small scale industries could not set up full fledged
ETP and they discharged the partially treated effluents resulting in the
pollution of Patancheru area during 1984-1990. During 1990, the
Indian Council for Enviro Legal Action filed a Public Interest Litigation
in W.P. (C).No. 1056 of 1990 before the Hon’ble Supreme Court of
India regarding pollution problems in the area. From the year 1991
onward the Hon’ble Supreme Court has issued various directions for
supply of drinking water to the villages affected by pollution, payment
of compensation for crop damage and other remedial measures. The
applicant company promoted by a group of industries at the Industrial
15
Development Area (IDA), Patancheru with the active support of the
Andhra Pradesh Industrial Infrastructure Corporation Ltd.
(APIIC).came to be incorporated in the year 1989. The main
objective of the applicant company is to collect, treat and dispose of
industrial effluent. The applicant constructed the CETP at Patancheru
which was commissioned in September, 1994 with a design flow rate
of 7500 m3/d. The management of the applicant company was taken
from APIIC Ltd. during September, 1994. The CETP is having the
following units: Terminal pumping station with a capacity of 360 m3, 4
Equalization tanks with a capacity of 1400 m3 each with diffused air
grid, Primary Clariflocculator with a capacity of 100 m3/h, Dissolved
air flotation unit with a capacity of 120 m3/h, Decanter – I & II with a
capacity of 20 m3/h, 2 Buffer tanks (One is in use) with a capacity of
1575 m3, 13 Sludge drying beds each measuring 8m x 2m, Aeration
tank – I with a capacity of 4300 m3, Aeration tank – II with a capacity
of 4300 m3 with 4 x 50 HP fixed aerators and 13 x 30 HP floating
aerators, Two Secondary settling tanks having 150 m3/h capacity,
Oxygen mix flow system with a capacity of 60 HP. One of the
Digesters (which was earlier used) was converted for storage of
treated effluent. With 5 x 30 HP mortars the treated effluent is
16
pumped into 18 km pipeline which joins K & S main for further
treatment along with domestic effluents in Amberpet Sewage
Treatment Plant.
9. The Hon’ble Supreme Court of India in the said writ petition
W.P.(C) No. 1056 of 1990 directed the CPCB and the respondent to
jointly submit an action plan for containing industrial pollution in
Patancheru area. Accordingly, the CPCB and the respondent
submitted an Action Plan, including laying of a pipeline to carry the
treated industrial effluent of the applicant’s CETP. The JAP, 1998
was approved and endorsed by the Hon’ble Supreme Court of India
in its order on 12.05.1998. The CPCB submitted a comprehensive
report on effluents management in Nakkavagu basin during March,
1998 to the Hon’ble Supreme Court. The report indicated four
options. Option 1 contemplated that the industries will treat their
effluents to certain specified norms before discharging into the CETP.
The CETP must thereafter treat the effluents to sewer standards and
discharge the treated effluents to main sewer which leads to the STP.
Option 2 contemplated the same treatment as per Option 1, and
discharge the treated effluent on land for afforestation. Option-3
contemplated the same treatment as Option 1, and dispose the
17
treated effluent into Isakavaagu/Nakkavagu with connecting system
as suggested. Option – 4 contemplated the discharge of the treated
effluent of large industries into Isakaavagu/Nakkavagu with a
stringent limit of 30 mg/L of BOD, 250 mg/L of COD and 2100 mg/L
of TDS and provide connectivity to the drain. In case of small scale
industries (SSI), the effluent was to be treated at CETP and
discharged into Isakkavagu/Nakkavagu drain.
10. The CPCB further stated that the Option 1 provides
maximum certainty as compared to the other options. On
06.02.2001, the Hon’ ble Supreme Court accepted the revised JAP of
the project of providing 18 Km pipeline submitted in November, 2000
in the context of further treatment and dilution at Amberpet STP
which should be expanded and upgraded with secondary and tertiary
treatment facilities to treat and dispose mainly organic and nutrient
rich sewage into Musi river.
11. The Jawaharlal Nehru Technological University (JNTU),
Hyderabad, conducted the EIA studies for the 18 km long pipeline
project during March, 2001 and supplementary technical studies
during December, 2008 and concluded that there will not be any
negative impact on the environment due to discharge of treated
18
industrial effluents into river Musi river. The Hyderabad Metropolitan
Water Supply & Sewerage Board (HMWSSB) took up the work of
executing the 18 km long pipeline in the year 2001, the cost being
shared by the Government and the applicant. The work of laying the
pipelines was completed in the year 2006. The Hon’ble High Court of
Andhra Pradesh constituted a Five Member Fact Finding Committee
with former Justice A.Gopal Rao as the Chairman by its order dated
25.09.2003. The Fact Finding Committee was to submit a status
report on the Terms of Reference (TOR) based on which appropriate
orders could be passed by the Court. The Committee visited the
pollution affected villages and industries in Medak District during
December, 2003 and January, 2004. The Committee heard the
pollution problems from the villagers, visited the agricultural fields,
vagus, tanks and collected soil samples, surface water and ground
water samples. The Committee submitted its report to Hon’ble High
Court in March, 2004.
12. The Committee observed that the four parameters fixed by
the Hon’ble Supreme Court will give broad picture on the efficiency of
a treatment plant. However, they are not sufficient to evaluate the
treatment efficiency in clear terms. In furtherance of the orders of the
19
Hon’ble Supreme Court, in a matter that originated under the
Hazardous Waste Management, a Supreme Court Monitoring
Committee was constituted which made inspections all over the
country. In the month of October, 2004, the said Monitoring
Committee inspected the applicant’s CETP and other areas of
Hyderabad and came up with a finding that all the measures of the
CETPs are not environment friendly. Thereafter, the respondent
imposed stringent standards on industries and CETPs. The
respondent/APPCB issued certain directions vide order dated
05.08.2005 to the applicant based on the directions issued by the
Monitoring Committee, prescribing inlet standards [except dissolved
solids (inorganic)] and outlet standards to the applicant.
Subsequently, vide order dated 26.12.2005 the respondent/APPCB
issued further directions to the applicant prescribing TDS (inorganic)
standards at the inlet, in continuation of earlier directions issued by
order dated 05.08.2005. In the order dated 12.03.2007 passed in
W.P.(C). No. 476 of 2005 and 441 of 2005 and batch cases, the
Hon’ble Supreme Court suggested that the CPCB and the State
Pollution Control Board (SPCB) shall meet to sort out the problem,
and submit an action plan. Accordingly, the CPCB and the
20
respondent/APPCB convened a meeting on 02.07.2007 with CETPs
including the applicant herein. With due consideration to the
consultation had with the CETPs and the applicant, the CPCB and
the respondent/APPCB submitted a JAP to the Hon’ble Supreme
Court. The Hon’ble Supreme Court endorsed the action plan and
issued an order on 17.07.2007. The Hon’ble Supreme Court directed
the APPCB to implement the action plan at the earliest possible time
as per the schedule given in the action plan. The impugned orders in
the present application are orders issued by the APPCB in due
compliance of the orders issued by the Hon’ble Supreme Court. As
stated earlier, the actual context in which the Hon’ble Supreme Court
made the observations in respect of the applicant are to the effect
that even after connectivity is given to the STP the applicant should
continue to maintain the standards. The contention of the applicant
regarding the said order is not correct and the applicant cannot be
permitted to take advantage of the same when it is totally undisputed
that they had exceeded the standards as stated in the impugned
orders issued by the respondent/APPCB.
13. All possible steps were being continuously taken to lay and
connect the 18 km long pipeline with the STP at Amberpet. The
21
respondent/APPCB had suggested various measures to be
implemented by the applicant, as a consequence of which, there was
significant improvement in the outlet standards to the level of those
prescribed in the JAP, 2007 and there was consistency in the outlet
standards only during May, 2009. It was only thereafter that the
connectivity could be given to the STP, as otherwise it would have led
to serious consequences due to discharge of effluent still containing
high level of pollution potential factors into the STP. Accordingly, the
respondent/APPCB sent a communication on 09.06.2009 addressed
to the Managing Director, HMWSSB to give connectivity to the 18 km
pipeline to the outlet of the applicant’s effluent, through K & S main
sewer to the STP at Amberpet. Thereafter, the connectivity was
given on 07.07.2009 in a phased manner and at present all the
treated effluent of the applicant is connected to the STP at Amberpet
for further treatment and also the applicant and the STP at Amberpet
are meeting the prescribed discharge standards.
14. The respondent/APPCB vehemently denies that the
impugned orders were issued without any notice and in violation of
the principles of natural justice. Those averments are totally contrary
to the truth and hence not correct. In compliance with the directions of
22
the Hon’ble Supreme Court contained in the order dated 17.07.2007,
the respondent/APPCB issued directions to the applicant on
25.07.2007 and to the member industries on 31.07.2007 for effective
implementation of the JAP of CPCB and APPCB. The effective date
of implementation of the Joint Action Plan was from 01.08.2007 and
was completed in January, 2009. To implement the JAP, the
applicant furnished the bank guarantee for Rs. 50 lakhs on
23.10.2007. At no point of time the applicant objected to the said
directions issued on 25.07.2007. On the other hand, complied with
the same by furnishing the bank guarantee as required. The
applicant never questioned or challenged the correctness of the
directions issued on 25.07.2007. On having accepted the same at
that point of time, the applicant cannot now dispute the same by
making lame excuses after violations were noticed and penalties
imposed. Though the applicant addressed a communication dated
23.10.2007, it only contained a request for apportionment of the
penalty amount amongst the various parameters and to levy penalty
for violation of each of the parameters and it never objected to the
levy of penalty. It would be significant to note that in that letter the
applicant had not taken the stand that they are liable to meet the
23
outlet standards only after connectivity to the STP as falsely projected
now in this application. The respondent/APPCB has strictly
implemented the JAP and the defaulters were penalized as per the
said JAP. As the applicant was not complying with the standards
stipulated in the JAP, penalty was imposed for the period November,
2007 to January, 2009. The penalty imposed is as approved by the
Hon’ble Supreme Court of India at the rate of Rs. 300 KLD for
violating any parameter. The violations are neither denied nor
disputed and in such circumstances, the allegations of violation of
principle of natural justice are devoid of any merit. All through, the
applicant was part of the process of laying of the standards and the
formulation of the JAP, he is not a stranger to make such complaints.
The applicant who has the responsibility to check and control the
level of pollution, failed in doing the same during the relevant period
leading to the imposition of penalty as approved by the Hon’ble
Supreme Court of India.
15. The impugned orders came to be passed after collection of
samples of the effluent from the applicant’s CETP over a sufficiently
continuous period and each order specifies the values that have
exceeded the prescribed standards. No representation dated
24
18.04.2008 was received by the respondent/APPCB. The conduct of
the applicant shows that inspite of the orders passed by the
respondent/APPCB from March, 2008 onward in respect of the
exceeding the prescribed level of standards, the applicant paid no
regard to the same and on the other hand flagrantly continued the
violations resulting in the passing of the various orders. The applicant
was well aware of the standards to be adhered to and accepted the
same and had only requested for apportionment of penalty on the
basis of the number of parameters and did not question or challenge
the directions as contained in the order dated 25.07.2007. The
samples were collected in the presence of the officials of the
applicant over a sufficiently enough period of time and there is no
dispute regarding the analysis reports and the quantities arrived were
as per the records maintained by the applicant. The applicant who is
bound to maintain the standards and who had admittedly exceeded
the standards cannot raise frivolous contentions belatedly for the
purpose of avoiding and evading the payment of the penalty.
16. The impugned letter dated 06.02.2009 is only a reminder
and cannot be construed as the order by which the penalty was
imposed. If the applicant was actually aggrieved by the respective
25
orders imposing penalty, the applicant would have taken appropriate
recourse and the very fact that they did not question or challenge the
respective orders at the relevant points of time would only show that
they have accepted the orders. In such circumstances, the instant
application is also liable to be dismissed on the grounds of delay and
laches as there has been enormous and unexplained delay in
approaching the Court as the first order imposing penalty came to be
passed on 14.03.2008, whereas the writ petition was filed almost
after a year. The applicant cannot take advantage of the reminder
and challenge the same. This is clearly an afterthought to evade their
liability and responsibility somehow or the other. No representations
were submitted in respect of the orders levying penalty. Since the
applicant did not pay the penalty imposed and also not complied with
the standards, the respondent/APPCB vide letter dated 04.02.2009
invoked the Bank Guarantee for Rs.50 lakhs furnished by the
applicant. The respondent/APPCB requested the bank authorities to
freeze the bank accounts of the applicant and also requested the
bank to remit the funds available in its accounts to the
respondent/APPCB towards the realization of the total penalty
amount of Rs.2,32,62,000/-, for the period from November, 2007 to
26
October, 2008 vide order dated 10.02.2009. Pursuant to the interim
orders passed by the Hon’ble High Court of Andhra Pradesh, the
applicant deposited a sum of Rs. 50 lakhs on 31.03.2009.
17. The CPCB vide order dated 31.03.2009 directed the
respondent/APPCB to obtain Bank Guarantee from the applicant for
Rs.50 lakhs towards compliance of the directions issued therein.
Accordingly the respondent/APPCB issued orders dated 09.04.2009
to the applicant and pursuant thereto the applicant submitted a Bank
Guarantee for Rs. 50 lakhs vide letter dated 28.04.2009. The same
is not related to the above application.
18. The impugned orders are passed in accordance with the
JAP as approved and directed to be implemented by the Hon’ble
Supreme Court of India and which had been accepted by the
applicant and by following due and proper procedure. In these
circumstances, the present application is devoid of any merits or
substance and deserves to be dismissed. On the above grounds, the
respondent/APPCB seeks to dismiss the application.
19. In pursuance of an order of transfer made by the Hon’ble
High Court of Andhra Pradesh in Writ Petition No. 3510 of 2009, this
27
application was taken on file. The following questions were
formulated for decision.
(i) Whether the applicant is entitled for a declaration that the
action of the second respondent in Proceedings No. PTN-
25/PCB/ZO/RCP/2005 dated 06.02.2009 as arbitrary, illegal
and without jurisdiction and declare that the second
respondent has no authority to levy penalty against the
applicant.
(ii) Whether a direction has to be issued to the
respondent/Board to refund the amount collected against the
bank guarantee and release the bank accounts freezed.
(iii) To what reliefs the applicant is entitled to?
Points 1 to 3:
20. The Tribunal heard the arguments advanced on either side and
looked into all the materials made available and paid its consideration
on the same.
21. Admittedly, the applicant is a CETP incorporated in the year
1989 by a group of industries who were operating in the said areas
referred to in the application and commenced the operations in the
28
year 1994. The applicant receives partially treated waste/effluent
(inlet) from a number of industries which are operating in the area,
treat the effluent to meet the permitted standards and discharges the
treated effluent (outlet) to a STP at Amberpet for further treatment.
From the STP, the treated water is being discharged into the Musi
River since Amberpet is far away from the location of the applicant’s
CETP through an 18 km long pipeline. The work was taken up by the
Hyderabad Metropolitan Water Supply and Sewerage Board
(HMWSSB) in the year 2001 and completed in the year 2009.
22. In October 2004, a Monitoring Committee appointed by the
Hon’ble Apex Court of India inspected the applicant’s CETP and other
areas and reported that all the measures taken up by the CETP were
not upto the standards and issued certain directions. The said
Committee convened a meeting in which the officials and the
applicant/CETP participated for the purpose of discussing the
measures as a result of which directions were issued. Following the
same, the respondent/Board issued directions to all concerned
including the applicant/CETP under Section 33-A of the Water
(Prevention and Control of Pollution) Act, 1974 as could be seen from
the Annexure-R1 dated 05.08.2005. As a result of a review meeting
29
held in respect of status of compliance of the directions dated
05.08.2005 stated supra, fresh directions were issued to the applicant
as found in Annexure-R2. After making an inspection and having a
meeting with the applicant, a Joint Action Plan (JAP) was submitted
by the CPCB and APPCB before the Hon’ble Apex Court of India in
W.P.(C).Nos. 441 and 476 of 2005. The said JAP was approved by
the Hon’ble Apex Court of India and in so far as the applicant/CETP is
concerned orders were passed in W.P.(C). No. 441 of 2005. While the
matter stood so, a direction was issued to the applicant directing the
applicant to meet the standards prescribed by the JAP, 2007 as
approved by the Hon’ble Apex Court on 27.05.2007. Apart from
putting the applicant on notice that the effective date of approved plan
is from 01.08.2007, a penalty of Rs. 300/- per KLD was imposed for
violation as indicated in Annexure-R4. By the impugned proceedings,
the APPCB imposed a penalty of Rs. 2,32,62,000/- at Rs. 300/- per
KLD for non compliance of the standards both outlet and inlet from
November, 2007 to October,2008.which is sought to be quashed in
this application.
23. Advancing the arguments on behalf of the applicant, the
learned counsel would submit that the applicant should comply with
30
the standards strictly once the connectivity with STP is given. It is not
in dispute that there was no connectivity during the relevant period.
Hence, penalty was not imposable on the applicant for non-
conforming to the outlet standards. The Hon’ble Apex Court clearly
observed that the standards for outlet could happen only after
connectivity with the STP was established. Therefore, the outlet
norms must be complied with only after the connectivity with the STP
was given. Thus, the imposition of penalty for non-compliance of the
outlet standards when there was no connectivity with the STP was
contrary to the express direction of the Hon’ble Apex Court and thus it
is not sustainable. It is also submitted by the counsel that the
applicant cannot be made responsible for any alleged breach of the
inlet standards. In so far as the inlet standards are concerned, the
applicant absolutely has no control over the same. The inlet of the
applicant is partly treated wastewater/effluent received from the
member- industries. If such effluent does not confine to inlet norms, it
would mean that the respective industries have not treated the
wastewater/effluent properly for which the applicant/CETP could not
be held responsible. The responsibility of the applicant is only to
ensure compliance of CETP with outlet norms irrespective of the
31
quality of effluent received for treatment. The respondent authorities
are responsible to monitor the quality of inlet which was provided by
the member-industries. The said responsibility cannot be shifted to
the applicant/CETP. Thus, the imposition of penalty by the
respondents on the applicant was only on account of the failure of the
respondents to perform their functions effectively. For imposing
penalty, the 1st respondent relied on the JAP and stated that the JAP
provided for imposing the penalty for violation of the standards also.
The relevant part of the JAP imposing penalty must be interpreted in
such a way as to give a logical meaning. Imposition of penalty on the
applicant for non-compliance of the standards of inlet is thoroughly
illogical as the applicant/CETP has no control over the quality of the
inlet. It is pertinent to note that the monitoring of the compliance of
inlet norms is the duty and responsibility of the regulatory authorities,
namely, the respondents. Therefore, imposition of the penalty on the
applicant for non-compliance of inlet standards is not only arbitrary
but illegal. If there were any violation of the norms, the same has to
be attributed only to the industries who supplied effluent to the
applicant/CETP. The objective of the entire project is to ensure that
the effluent ultimately discharged into the river must comply with the
32
standards to reduce pollution. The applicant should not be punished
for the lapse on the part of the industries. If the interpretation of the
respondents for imposing the penalty on the applicant is to be
accepted, it would lead to a situation where even when the outlet
norms are satisfied, the applicant can still be punished with penalty
for the fault of the industries not conforming to the inlet standards.
Such an interpretation should not be accepted since it is contrary to
the objective of the project. Penalty for violation of the inlet standards
is applicable to member-industries and penalty for not conforming to
the outlet standards alone is imposable on the applicant. Having
imposed the penalty on the industries rightly, any imposition of
penalty on the applicant would amount to double jeopardy. Apart from
all the above, the quantum of penalty of Rs. 2,32,62,000/- on the
applicant is harsh. While the penalty of Rs. 30/- per KLD was
imposed on the industry for non-compliance, a penalty of Rs. 300/-
per KLD was imposed on the applicant for the same incident of non-
compliance which would be contrary to the principles of justice and
hence the proceedings have got to be quashed and the amount
already collected against the bank guarantee has to be refunded with
direction to release the bank accounts freezed.
33
24. Countering the above contentions, the learned counsel for
the respondents taking the Tribunal to different documents relied on
by the APPCB would submit that the imposition of penalty as found in
the order was perfectly correct and valid and the application was
without any substance whatsoever.
25. As seen above, the respondent/APPCB has imposed a
penalty of Rs. 2,32,62,000/- at Rs. 300/- per KLD on the
applicant/CETP for non-compliance of the standards both outlet and
inlet during the period from April, 2008 to October, 2008. Aggrieved
by the same, the applicant has brought forth this application.
26. At the outset, it would be more apt and appropriate to
reproduce the relevant part of the order of the Hon’ble Apex Court in
W.P. (C ).No. 441 of 2005 dated 17.07.2007:
“It is not in dispute that the petitioner meets the
inlet Standards prescribed by the Action. It is
made clear, however, that the petitioner shall
also comply with the outlet standards
prescribed and mentioned in the Action Plan.
However, fulfillment of outlet standards can
happen only after the connectivity is
established with STP. The requisite amount
34
has also been deposited by the petitioner. It is
made clear that the outlet standards will have
to be complied with by the petitioner after the
connectivity is given with the STP. The
connectivity may be given as per the Action
Plan”.
27. A reading of the above said order would make it abundantly
clear that the outlet standards were to be complied with by the
applicant after providing connectivity with the STP which is a part of
the Action Plan. The applicant who received partially treated
wastewater/effluent (inlet) from the industries after treating the same
has to discharge the treated wastewater/effluent (outlet) to the STP
at Amberpet for further treatment, which in turn should discharge the
same to Musi river. Since Amberpet is far away from the location of
the applicant’s CETP, a project of laying pipeline for a distance of 18
km was undertaken by the HWSSB in the year 2001 and the same
was completed in the year 2009. Thus, it is quite clear that during the
relevant period, i.e. 11/2007 to 10/2008 there was no connectivity.
Thus, imposition of penalty for non-compliance of the outlet
standards during the period, in the absence of any connectivity with
STP will be contrary to the order of the Hon’ble Apex Court. Hence,
35
the claim by the APPCB in that regard is liable to be set aside.
28. In so far as the imposing of penalty, the same is assailed
by the applicant on the ground that the applicant/CETP has no
control over the inlet, that it is the duty of the individual member-
industry to conform to the inlet standards and is the responsibility of
the regulatory authority, namely, the APPCB to monitor the standards
of inlet which is provided by the individual industries. If there is any
violation of the inlet standards, it is attributable only to the individual
industry and not to the applicant/CETP and thus the imposition of
penalty is illegal.
29. After careful consideration of the available materials, rules
thereon and the order of the Hon’ble Apex Court, the Tribunal has to
necessarily negative the contentions of the applicant’s side for the
following reasons:
30. A Monitoring Committee appointed by the Hon’ble Apex
Court of India placed a JAP pursuant to which the proposal for laying
a pipeline to carry the treated industrial effluent of the Applicant’s
CETP and then on to STP was undertaken. In the year 2004, the
said Monitoring Committee appointed by the Hon’ble Apex Court
36
inspected the applicant’s CETP along with others when it was
noticed that they were not meeting the standards. Following a
meeting of the members of the Committee with the officials and the
applicant to discuss the measures for directions to the
respondent/APPCB as found in Annexure- R, the APPCB issued
directions to the applicant under Section 33-A of the Water Act, 1974
which reads as follows:
“10. The Board after careful consideration of the
information `available on record and in exercise of the
powers conferred under Section 33-A of the
Water(Prevention and Control of Pollution) Amendment
Act, 1988 and its amendments thereof, hereby directs the
CETP to comply the following directions:
1. The CETP shall not discharge the treated effluent into
the proposed 18 km pipeline.
2. The CETP shall accept pretreated effluent from the
member industries with the following inlet standards for
further treatment and disposal:
Inlet standards of CETP
Sl.No. Parameter Concentration
in mg/l
(except pH,
temperature
37
& radioactive
materials)
1 pH 5.5-9.0
2 Temperature 45 degree C
3 Dissolved Solids (inorganic) Will be
prescribed
shortly
4 Oil and Grease 20
5 Phenoic Compounds as (C6H6OH) 5.0
6 Ammonical Nitrogen (as N) 50
7 Cynide (as CN) 2.0
8 Chromium Hexavalent as (Cr 6) 2.0
9 Chromium ( total ) as (Cr) 2.0
10 Copper (as Cu) 3.0
11 Lead (as Pb) 1.0
12 Nickel (as Nl) 3.0
13 Zinc (as Zn) 15
14 Arsenic (as As) 0.2
15 Mercury (as Hg) 0.01
16 Cadmium (as Cd) 1.0
17 Selenium (as Se) 0.05
18 Fluoride (as F) 15
38
19 Boron (as B) 2.0
20 Radioactive Materials:
(a)Alpha emitters, Hc/ml
(b)Beta emitters, Hc/ml
107
10 3
31. It was made clear that if the CETP fails to comply with the
above prescribed standards within the stipulated period of 30 days,
legal action would be initiated under Section 33-A of the Water
(Prevention and Prevention of Pollution) Amendment Act, 1988 for
closure of the facility in the interest of public health and environment.
In order to ascertain the above compliance, a review meeting was
convened on 14.12.2005 and further directions were issued on
26.12.2005 as found in Annexure-R2. Paragraph 5 of the said
communication addressed to the applicant reads as follows:
“5. In view of the above, the following directions are
issued to CETP under Section 33 (A) of Water
(Prevention and Control of Pollution) Amendment Act,
1988 in continuation of directions issued to your CETP
vide reference 1st cited in respect of inlet standards of
CETP.
39
M/s. PETL, Patancheru, in no case, shall accept effluents
for treatment from their member units having TDS more
than the standard mentioned above in para 4(l) stipulated
to the discharges from member units. (i.e. pre-treated
effluent).
1. M/s. PETL, Patancheru shall accept the quantity of
effluents from member units as permitted by the Board.
2. The other discharge standards stipulated in order dated
05.08.2005 issued to M/s. PETL shall remain same.”
32. The Hon’ble Apex Court made an order on 12.03.2007 in the
aforesaid writ petitions that both CPCB/SPCB should have a meeting
to solve the problem. Accordingly, a meeting was convened on
19.04.2007 wherein it was decided to carry out inspection of
JETL/PETL (applicant herein) and related industries jointly by
CPCB/SPCB to come out with specific recommendations. In a
meeting convened on 02.07.2008 the representative of the
applicant’s CETP also participated and expressed their views. The
Action Plan proposed in the Joint Inspection Report was finalized by
both the CPCB/APPCB with due consideration with consultations
with the applicant. Inter alia, it was decided as follows:
“6.2. Inlet standards to the CETP: The standards
applicable to CETPs are notified under the E P Act.
40
Further, Chemical Oxygen Demand (COD) and Total
Dissolved Solids (TDS) (inorganic) limits have been
additionally prescribed by APPCB as empowered
under Water Act, keeping in view the treatability in
the CETP, design features of CETP, final disposal
point and local conditions.
Para 7. The finalized Action Plan for joint submission
by CPCB/APPCB to Hon’ble Supreme Court in the
light of above discussion is as follows:
Sl.No. Description Action Plan Time Schedule
and other
parameters of
compliance
1. Inlet standards for the
CETPs (i.e. outlet of
member
industry/tankers
received at CETP)
All the
parameters as
stipulated in
Schedule-I
(S.No.55) of the
Environmental
(Protection)
Rules, 1986 and
its amendments
thereto
Within 3
months
33. It remains to be stated that the JAP submitted before the
41
Hon’ble Apex Court in the Writ Petition (C) Nos. 441, 446/2005 etc.,
was accepted.
34. All the above would clearly indicate that the applicant’s
CETP was a party to all the above meetings wherein it was decided
that the applicant CETP should accept the effluent from the member-
industries (inlet) not below the approved standards which are
applicable to CETP as notified in Serial No. 55 of Schedule I of the
Environmental (Protection) Rules, 1986. Having accepted the same
without any murmur and also to comply with the same within a period
of 3 months therefrom for meeting the said standards, it would be
futile on the part of the applicant to state that in so far as inlet is
concerned, neither the applicant CETP has control and it is the
responsibility of the individual units and it is the duty of the
respondent/APPCB to monitor the compliance and the applicant
cannot wriggle out by making such an unacceptable defence. In view
of the above, the contentions putforth by the counsel for the applicant
that imposing of penalty on the applicant/CETP after imposing penalty
on the industries would amount to double jeopardy cannot be
countenanced. Equally, the contention putforth by the applicant’s side
that the imposition of penalty at Rs. 300/- per KLD on the applicant is
42
not only harsh but also contrary to the principles of justice since the
respondent/APPCB has imposed penalty only at the rate of Rs. 30/-
per KLD for the industries for the non-compliance has to be rejected
for the simple reason that this rate was actually fixed by a Committee
which filed the JAP and was also approved by the Hon’ble Apex Court.
It is pertinent to point out that the applicant also participated in the
meetings convened and conducted by the Committee which resulted
in the JAP placed before the Hon’ble Apex Court. Not only being a
party to those proceedings, the applicant has not even raised its little
finger either during the fixation of rates or when the JAP was placed
and accepted by the Hon’ble Apex Court. Thus, the Tribunal is unable
to see any merit in those contentions.
35. It is an admitted position that the penalty of Rs. 2,32,62,000/-
was imposed on the applicant for non-compliance of standards for
both outlet as well as inlets during the period November, 2007 to
October, 2008. As could be seen from the available materials during
the said period there was no connectivity with the STP as held supra
and therefore the applicant is not liable to pay and the
respondent/APPCB cannot impose any penalty for the outlet for the
said period. In so far as the penalty imposed for inlet for the said
43
period, it is valid for the reasons discussed above.
36. Hence, it is declared that the impugned proceedings of the 2nd
respondent dated 06.02.2009 is set aside only to the extent of the
penalty for non-compliance of the standards for outlet during the
period from November, 2007 to October, 2008 and thus the applicant
is liable to pay the penalty in respect of non-compliance of the
standards for inlet during the period November, 2007 to October,
2008 to which extent the proceedings of the 2nd respondent dated
06.02.2009 is valid and executable. The 2nd respondent/APPCB is
directed to serve a fresh proceedings on the applicant in respect of
the penalty for non-compliance for inlet for the period from November,
2007 to October, 2008 within a week herefrom and the applicant shall
pay the said calculated amount within a period of 3 months from the
date of service of the proceedings.
Accordingly, with the above directions the application is
disposed of.
No cost.
(Justice M. Chockalingam) Judicial Member
44
(Prof. Dr.R. Nagendran)
Expert Member
Chennai,
Dated, 17th December, 2014
45