benning park recreation center community meeting (march 2017)
TRANSCRIPT
BENNING PARK
COMMUNITY CENTER
CONCEPTUAL DESIGN COMMUNITY MEETING
WITH ALTERNATE OPTIONS
DATE: March 15, 2017
MEETING AGENDA DESIGN OVERVIEW
CONSTRUCTION PROCESS
SITE IMPACTS & CLOSURES
PROJECT TEAM:
Department of Parks and Recreation (DPR)
Project Managers: Peter Nohrden
Deputy Director of Recreation: Themba Masimini
Department of General Services (DGS)
Project Manager: Daniel Lauderbaugh
Moody Nolan ARCHITECTS
OPTION ONE
• Two Phase Construction
• Phase One
• New Roof
• New HVAC Unit
• Phase Two
• ADA Improvements
• Elevator Addition
• Life Safety Improvements
• Budget $5-10 Million
OPTION TWO
• Major Renovate of Existing
Recreation Center
• New Pool House
• New Pool
• LEED Project
• Budget Estimate $20-25
Million
OPTION THREE
• Demolish Existing Structure
• New Recreation Center
• New Pool House
• New Pool
• Enlarged Boxing Area
• Locker Rooms
• LEED Construction
• Green Options
• Budget $30-35 Million
BENNING PARK CONSTRUCTION OPTIONS
OPTION ONE OPTION TWO OPTION THREE
• Two Phase Construction • Building Renovation • Demolish Existing Structure
• Roof Replacement • New Pool House • New Recreation Center
• New HVAC Equipment • New Pool • New Pool
• Elevator Addition • LEED Building • Enlarged Boxing Area
• ADA Improvements • Locker Rooms
• Life Safety Improvements • LEED Building
• Green Options
OPTION ONE SCHEDULE OVERVIEW
ACTIVITY SCHEDULE MILESTONE
START CONSTRUCTION Early Fall 2017
CONSTRUCTION COMPLETION Early Fall 2018
QUESTIONS & ANSWERS
• Discussion of Recreation Center’s Benefit to the Community
• How can the Community Assist DPR?
DGS WEBSITE: HTTPS://WWW.DGS.DC.GOV
Jackie Stanley DGS Community Coordinator
DGS Government Affairs & Communications
(202) 431-1195
John Stokes DPR Deputy Director of Community
Engagement
(202) 288-7275