BENSCL / STATUS OF WORKS 19.10.2020
Status of Road Works taken up by Bengaluru Smart City – 19.10.2020
1. Bengaluru Smart City Limited under the Smart Cities Mission has taken up 13
projects (with 36 specific roads) for Revitalization of the historic heart of the city and
is currently constructing the roads in the CBD area of the city. These roads have been
taken up as part of the Original Action Plan proposed by the BBMP in 2017.
2. The total length of these road works is 30 kilometers and the SMART roads are being
built on the lines of TenderSURE roads of BBMP.
3. Shifting of utilities, provision of ducts, improvement of Junctions, development of
Footpaths and Cycling lanes, household-level service connections, etc. are the major
features.
4. Along with the above, the implementation is also focussing on the improvement of
seamless connectivity between different modes of transport, development of
residual spaces, provision of green buffers, and place-making themes for enhanced
accessibility and sustainable mobility in the ABD of Bengaluru Smart City.
5. The major stakeholders are BBMP, Bengaluru Traffic Police, BESCOM, BWSSB, BSNL,
BMTC along with the local associations and our citizens. In view of ease of
implementation, Bengaluru Smart City is working in close coordination with all the
stakeholders and executing the works on site. The Consultants from WRI have been
on-site to handhold and guide concerning drawings and design issues.
6. It may be noted that the work orders for these 36 road works have been issued in
2019. There was an inordinate delay by the PMC to issue the Good-for-Construction
drawings. After continuous persuasion and several deadlines, the GFC drawings
were issued for a few roads works in the first week of November 2019.
7. Following this, the Hon’ble Chief Minister of Karnataka laid the ground-breaking
ceremony for the 13 road projects (Phase A – 7 Packages and Phase B – 6 Packages)
on 09.11.2019.
8. The works commenced on the ground after due permission from the police
department as all the roads are in the high-density traffic zones and after the
necessary coordination with the stakeholder departments phase by phase.
9. The works were started with a target to complete by end of May 2020 (the one side
of the road works that were started by January 2020).
BENSCL / STATUS OF WORKS 19.10.2020
10. By March 2020, for 15 road works all machinery and manpower were mobilized and
work was in full swing as per the PERT chart identified by the CE and PMC.
11. However, owing to the COVID-19 pandemic and the national lockdown, migration of
labor, it has become extremely difficult to mobilize labor and carry out the work at
the desired speed. Issues of COVID-19 spread for labor/contractor/engineer and
their families have led to delay in the progress of work as it affected the pace of
different skilled labor teams who work on-site in close coordination and tandem
(sequential nature of activities).
12. The projects have gathered momentum in the Unlock scenario and work is being
monitored day and night. It may be noted that major utility shifting tasks and
junction improvement or connectivity are being handled during the night only after
the complete mobilization of men and materials at the site as per the PERT chart.
13. Instructions have been given to follow all the guidelines about the safety of
pedestrians and motorists, and adherence to the safety measures – barricading, use
of reflective material, precautions to be taken while carrying out critical tasks during
the night is being monitored by the CE and EEs day and night and the same is
constantly being reviewed and updated to the Senior Officers.
0
2
4
6
8
10
12
14
Jan
-20
Feb
-20
Mar
-20
Ap
r-2
0
May
-20
Jun
-20
Jul-
20
Au
g-2
0
Sep
-20
Oct
-20
No
v-2
0
De
c-2
0
Jan
-21
Feb
-21
Mar
-21
Ap
r-2
1
12
21
2
6
21
2
7
12
8
5
3
7
2
5 5 5 54 4
5
3
5
14
5
32
3
Jan-20
Feb-20
Mar-20
Apr-20
May-20
Jun-20
Jul-20
Aug-20
Sep-20
Oct-20
Nov-20
Dec-20
Jan-21
Feb-21
Mar-21
Apr-21
Excavation 12 2 1 2 6 2 1 2 7
Utility Shifting 12 8 5 3 7
Footpath 2 5 5 5 5 4 4 5
Target date for Completion 3 5 14 5 3 2 3
Status of Roads - 19.10.2020
Excavation Utility Shifting Footpath Target date for Completion
BENSCL / STATUS OF WORKS 19.10.2020
14. The Contractors have been given clear directions to ensure the tree pits are provided
to guard the plantation on the existing site and watering/spraying of water is carried
out on the roads to avoid dust and remove all the debris from the site regularly.
15. Site inspections and regular inspections are being carried out both by the engineers
and the Consultants.
16. The following information regarding the current status, progress of the road works,
and the timelines may be noted:
SN Name of the Road Length
(Kms) Side
Actual
Date of
Excavation
Current Stage as on
10.10.2020
Target
Date for
Completion
1
Commercial Street - From
Kamraj Road to Jumma Masjid
Road (Near Bowring Hospital)
0.46 RHS 10.06.2020 Utility Shifting 30.11.2020
2
Kamaraj Road from M G Road
up to Commercial Street and up
to St. Johns Church Road
1.83 RHS 10.12.2020 1. Chamber work
2. Utility Shifting 31.12.2020
3 Ulsoor Road from Dickenson
Road to Kensington Road 0.59 LHS 09.06.2020 Utility Shifting 31.12.2020
4 Dickenson Road from M G
Road to Kamraj Road. 1.2
LHS 25.12.2020 Utility Shifting 31.12.2020
RHS 24.12.2020 SWD & sewer
chamber work 31.12.2020
5
Infantry Road from Ali Askar
Road to Safina Plaza complex
(Main Guard Cross Road).
1.65
RHS 10.12.2020
1. Excavation
2. Utility Shifting
3. Junction Crossover
31.12.2020
LHS 10.12.2020
1. Excavation
2. Utility Shifting
3. Junction Crossover
31.12.2020
6
Bowring Hospital Road from
Main Guard Cross Road to HSIS
Gosha Hospital.
0.84 RHS 05.09.2020 Chamber work 31.12.2020
LHS 30.12.2020 Chamber work 31.12.2020
7
Central Street from M G Road to
Shivajinagar Bus Stand (TTMC)
and up to Indian Express
(Balekundri) Junction.
0.84 RHS 25.12.2020 Chamber work 31.12.2020
8
Millers Road from Chalukya
Circle to Cantonment via Queens
Road
1.31 RHS 20.07.2020 Excavation 31.03.2021
9 Raj Bhavan Road from Minsk
Square to Basaveshwara Circle. 0.92 RHS 07.01.2020
1. Junction cross over:
a) Near Thimmaiah
circle complete
b) Near Minsk Square
pending
2.. Footpath formation
(PCC Laying)
3. Road Formation to
start
31.10.2020
BENSCL / STATUS OF WORKS 19.10.2020
10 Mcgrath Road from Brigade
Road up to Richmond Road 0.46
Both
Sides 15.12.2019
1. Utilities Completed
2. Chamber Final Lift
Concreting & FRP
Cover Fixing
3. Kerbstone Laying
4. Paver Block laying
31.12.2020
11 Convent Road from Richmond
Road to Residency Road 0.42
Both
Sides 01.05.2020
LHS Utilities
Completed & in RHS
70% utilities
completed & Chamber
concreting
31.12.2020
12 Hayes Road from Richmond
Road to Residency Road 0.31
Both
Sides 15.12.2019
1. Utilities Completed
2. Chamber Final Lift
Concreting & FRP
Cover Fixing
3. Kerb Laying
4. Paver Block laying
31.12.2020
13 Wood Street from Museum
Road to Richmond Road 0.28
Both
Sides 15.01.2020
1. Utilities Completed
2. Chamber Final Lift
Concreting & FRP
Cover Fixing
3. Kerb Laying
4. Paver Block laying
31.01.2021
14 Castle Street from Museum Road
to Richmond Road 0.38
Both
Sides 01.05.2020
RHS Utilities
Completed & in LHS
30% utilities
completed & RHS
Chamber Concreting
31.01.2021
15 Tate Lane - From Richmond road
to castle street 0.13
Both
Sides 06.03.2020
1. Utilities Completed
2. Chamber Final Lift
Concreting & FRP
Cover Fixing
31.01.2021
16
Kasturba Road from
Siddalingaiah Circle to Minsk
Square via Queens Statue (M G
Road)
0.74 LHS 18.12.2019
1. Chamber excavation
2. Chamber concreting
3. Steel reinforcement
4. Raft
15.12.2020
17 Queens Road from M G Road to
Cantonment Railway Station 1.83 RHS 22.12.2019
1. Chamber excavation
2. Chamber concreting
3. Steel reinforcement
4. Deck slab
30.11.2020
18
Raja Ram Mohan Roy Road
from Richmond Circle to Hudson
Circle.
1.00 Both
Sides 15.12.2019
1. Utilities Completed
2. Chamber Final Lift
Concreting & FRP
Cover Fixing
3. Kerb Laying
4. Paver Block Laying
31.01.2021
19 Lavelle Road from M.G.Road to
Richmond Circle. 1.38
Both
sides 15.05.2020
LHS Utilities
completed & in RHS
70% utilities
completed & Chamber
concreting
31.01.2021
BENSCL / STATUS OF WORKS 19.10.2020
20
St. John’s Road - from
Kensington Road to St. John’s
Church Road
1.09 LHS 15.09.2020 Chamber Excavation 15.12.2020
21
Miller's Road Extension (from
Miller's Road Underpass to
Haines Circle)
1.14 RHS 06.05.2020
1. Footpath formation
(PCC laying)
2. Special chamber for
SWD.
31.10.2020
22 Cantonment Road (from Millers
Road to Queens Road) 0.57 RHS 10.07.2020
1. Excavation for
utilities
2. Chamber
construction
30.11.2020
23 HKP Road (from Queens Road
to Russel Market) 0.9 LHS 17.08.2020 - 31.12.2020
24 Chandni Chowk Road - from
HKP Road to Shivaji Road 0.45 RHS 22.06.2020 - 30.11.2020
25
NR Road (from SJP Road
Junction to Cutchery Road
Junction)
0.48 LHS 18.07.2020 - -
26 Race Course Road (from Palace
Road to Hare Krishna Road) 0.66 LHS 15.06.2020
1. Laying Water
supply Line
2. SWD Chamber
reinforcement
31.10.2020
27
Raj Bhavan Road (from Millers
Road Intersection to Ali Asker
Road Intersection)
0.48 LHS 15.06.2020
1. Fixing of kerbstones
2. Power chamber
reinforcement
31.10.2020
28
Rhenius Street - from General
KS Thimmaya Road to Langford
Road
0.57 RHS 20.06.2020
1. Laying Water
supply Line
2. SWD Chamber
(reinforcement)
30.11.2020
17. The works are being monitored constantly and the road works on the above
mentioned sides will be completed as per the scheduled timeline with the due
coordination with all the stakeholders on war-footing round the clock.
18. The activities are in a critical phase and major utility shifting along one side of the
roads has already been tackled. It is a request for the citizens to kindly bear with the
temporary inconvenience being caused because of the digging and construction of
roads.
19. Several place-making themes have been included as part of the road works and
Bengaluru Smart City Limited is targeting to complete the works in good quality in
the scheduled time.
20. The roads once completed shall be a vital part of permanent Public Infrastructure
for Bengaluru City.