bi.bsw chicane magnets
DESCRIPTION
BI.BSW Chicane Magnets. D. Aguglia, J. Borburgh , B. Balhan, C. Baud, C. Bracco, C. C arli, M. Cieslak, M. Hourican, D. Nisbet, W. Weterings. Chicane layout. Beta beating mitigation. S-bend Only effective for a fixed angle, not throughout the ramp - PowerPoint PPT PresentationTRANSCRIPT
BI.BSW Chicane MagnetsD. Aguglia, J. Borburgh,
B. Balhan, C. Baud, C. Bracco, C. Carli, M. Cieslak, M. Hourican, D. Nisbet, W. Weterings
0 336 1032 1296 1560 2256 2654
0
20
40
60
80
100
120
140
160
Drift Space [mm]
Am
plit
ud
e [m
m]
PSB Injection Geometry for 380mm magnets, 316mm magnetic length, 66mrad, 340mT, 126mTm
35
149
InjectedH- Beam
CirculatingH+ Beam
BSW1 BSW2 BSW3 BSW4
StrippingFoil
H0
Dump
H-
Chicane layout
9/11/2011 J. Borburgh BSW magnets 2Review on PSB 160 MeV H- injection
Beta beating mitigation
• S-bend– Only effective for a fixed angle, not throughout the ramp– More difficult to implement mechanically, in particular on
short magnets
• Combined function magnets – Only effective for a fixed angle, not throughout the ramp
• R-bend and active compensation – Chosen as baseline solution
9/11/2011 J. Borburgh BSW magnets 3Review on PSB 160 MeV H- injection
Powering• Ramp down time ~ 5 ms.• Controlled ramp down to allow active compensation.• All four magnets per ring powered in series.• Each power converter will occupy either 2 or 3 19’’ standard
racks.• 4 power converters + 1 spare = 10 to 15 racks.• Controllable switch mode power converter + current step-up
transformer in the tunnel• Transformers to be placed near magnets, assuming 10μH
margin (for cables + uncertainty on magnet inductance + transformer leakage inductance) → transformers must be placed not farther than ~5m from magnets!
9/11/2011 J. Borburgh BSW magnets 4Review on PSB 160 MeV H- injection
0.045 0.05 0.055 0.06 0.065-1000
-500
0
500
1000
Time [s]
Prim
ary
vo
ltag
e [V
]
0.045 0.05 0.055 0.06 0.065-500
0
500
1000
1500
Time [s]
Prim
ary
Cu
rre
nt [
A]
Topology : AC/DC conversion to 1kVDC & DC/DC conversion via two interleaved IGBTs H-Bridges.Interleaved topology allows using standard IGBTs (current share) and reduces current ripple.Magnetic energy regenerated into the capacitor banks (minimized losses & power consumption)
Ma
gn
ets400VAC
Racks in Building 361 (ground flor)
Tunnel
Simulated primary voltage and current
Power converter output:1kV - 1.5kA 1.5MW peak power
Power converters
Bump closure flexibility
• Following recommendation of “PS Booster with Linac4” review (January 2009), magnets are assumed to be powered in series per ring.
→All magnets will have to provide same ∫B.dl/I.→Magnets should be aligned precisely at their
position longitudinally.
Would trim power supplies be desirable?
9/11/2011 J. Borburgh BSW magnets 6Review on PSB 160 MeV H- injection
Space constraints
9/11/2011 J. Borburgh BSW magnets 7Review on PSB 160 MeV H- injection
Magnets must be removable from ring without breaking vacuum. Permissible septum thickness limited.Longitudinal space limited to 380 mm, to allow sufficient space for stripping foil mechanism.Magnetic length maximised (↘β beating).
Baseline magnet parameters
Magnet Aperture
H x V[mm x mm]
Magnetic Length
[mm]
Physical Length
[mm]
∫Bydl[Tm]
Deflection[mrad]
BSW1 162 x 85 316 373 0.126 66.0
BSW2 218 x 85 316 380 0.126 66.0
BSW3 218 x 85 316 380 0.126 66.0
BSW4 242 x 85 316 380 0.126 66.0
Assumes ceramic vacuum chamber with a vertical beam acceptance ~ 65 mm.
9/11/2011 J. Borburgh BSW magnets 8Review on PSB 160 MeV H- injection
Parameters per magnet typeMagnetic Properties BSW1 BSW2/
BSW3BSW4
Field in the center of the magnet [T] 0.399 0.399 0.399
∫Bydl at magnet centre [m.Tm] 126 126 126
Electric current [kA] 13.5 13.5 13.5
Field homogeneity [%] 1 1 1
Good field region (h x v) [mm] 85x140 85x196 85x220
R (mΩ) 0.3 0.3 0.32
L (μH) 3.3 4.2 4.7
Number of turns 2 2 2
Mechanical properties
Physical length [mm] 373 380 380
Septum conductor thickness [mm] 7 n.a. n.a.
Pole face length [mm] 297.8 301 296
Endplate thickness [mm] 13.6 15.5 12
Yoke cross section [mm] 260x260 390x220 390x220
Aperture [mm] 162x85 218x85 242x85
Water cooling [ l/min.] 4 3.4 3.3
Water cooling pressure [bar] 12 12 12
9/11/2011 J. Borburgh BSW magnets 9Review on PSB 160 MeV H- injection
How to describe field imperfections• What to calculate?• How to take into account field
perturbations by dump and beam instrumentation?
• Vacuum chamber coating neglected so far.
• All calculations refer to By. 4500 6500 8500 10500 12500 14500315.99
316
316.01
316.02
316.03
316.04
316.05
316.06
316.07
316.08
316.09
316.1
0.009326
0.009327
0.009328
0.009329
0.00933
0.009331
0.009332
0.009333
0.009334
0.009335
Leq [mm]∫Bdl/I
I [A]
Lm [m
m]
6 26 46 66 86 106 126 146 1660
5
10
15
20
25
30
35
40
45
By homogenity [mT.m]
-100 -80 -60 -40 -20 0 20 40 60 80121.5
122122.5
123123.5
124124.5
125125.5
126126.5
f(x) = − 0.000000127286 x⁴ − 0.00000127088 x³ + 0.000183605 x² + 0.00269541 x + 125.94756
BSW1 ∫Bydl [mT.m]
ByPolynomial (By)
9/11/2011 J. Borburgh BSW magnets 10Review on PSB 160 MeV H- injection Blue area within 1% of ∫Bnom.dl
How to take into account field imperfections
Static field imperfection can be described as dipole with higher orders, but these are position dependant during the ramp.Influence of eddy currents could be neglected if sufficiently low (dump, vacuum chamber coating).Field maps could be used, but would have to be calculated for each turn. Imposing a maximum limit on the field imperfections (in space and time)? May lead to unrealistic values for such short magnets (magnetic length is less than 4 gap heights).
9/11/2011 J. Borburgh BSW magnets 11Review on PSB 160 MeV H- injection
BSW1 leak field
• Requirement not formalised.• Targeted leak field: 10-3∫Bnominal.dl.• External magnetic screen foreseen.
• Count on injection steerers to compensate remaining leak field.
9/11/2011 J. Borburgh BSW magnets 12Review on PSB 160 MeV H- injection
• 2D and 3D simulations performed.
• Both solid as well as segmented dumps evaluated.
Influence of dump on field in BS4
Field distortion by dump eddy currents
Simulation Parameters
Value units
Dump material conductivity
1.0E+05 S/m
Eddy current in dump
0.37 A
Simulated magnet Field
0.422 T
Switch off time 5 ms
9/11/2011 J. Borburgh BSW magnets 13Review on PSB 160 MeV H- injection
DUMP and its monitoring
H0
H-
e-
2e-
p+
p+
Dump block
Monitors
BI equipment not taken into account for simulations as yet.Dump specification defines a limit on the field disturbance due to presence of dump (1%).Dump material suggested in specification: Carbon with resistivity in 1-510-5 Ωm range.
9/11/2011 J. Borburgh BSW magnets 14Review on PSB 160 MeV H- injection
Magnetic field on stripping foil
Jmod < 0.7 μA rose coloured
9/11/2011 J. Borburgh BSW magnets 15Review on PSB 160 MeV H- injection
Bmod < 6 mT rose coloured areas.
• Forces induced on the foil not evaluated yet, but J and B rather low.
• How to track electrons escaping from the foil?
Mechanical integration (1/3)
2 turn coil, split-able magnets, outer dimensions, support developmentInterference with neighbouring equipment (BI, Stripping, Vacuum equipment).
Mechanical integration (2/3)2 turn coil, split-able magnets. 0.35 mm thick laminations, glued magnets blocks.Glued end plates, same material as yoke.
Is the use of glued laminated magnets a reliable over time?Fixation to be studied. Outer dimensions limited in height and length.Magnet support and bus bars to be developed and integrated.Transformers to be integrated in vicinity:
dimensions to be evaluated, but rough estimation 80cmx80cmx80cm!Interference with neighbouring equipment (BI, stripping foils,
vacuum equipment). Ease of maintenance required (RP ALARA)!
9/11/2011 J. Borburgh BSW magnets 17Review on PSB 160 MeV H- injection
Mechanical integration (3/3)
9/11/2011 J. Borburgh BSW magnets 18Review on PSB 160 MeV H- injection
• Mechanical concept design started• Coil and yoke design to be completed at CERN• Coil and yoke manufacture to be subcontracted to
industry• Mechanical support and installation jig to be designed and
built in house
What if we adopt Inconel vacuum chambers? (1/2)
+ Mechanically more robust+ Less costly+ Potentially less activation
Field deformation due to induced eddy currents:
- delay (depending on vacuum chamber width)- deformed field shape
Approximate field delays vary from 47μs (BSW1) to 90 μs (BSW4).
9/11/2011 J. Borburgh BSW magnets 19Review on PSB 160 MeV H- injection
Current distribution in race track shaped vacuum chamber.
What if we adopt Inconel vacuum chambers? (2/2)
― Field quality deterioration.― Introduction of higher order field components, magnetic centre
not on the central orbit.± Sextupolar components manageable, but quadrupolar
component potentially dangerous (needs precise compensation to avoid resonance).
± Field delay depends on width of vacuum chamber! ― 3 field delays implies three power supplies per ring -> space for
transformers (12!) ?± Try to design all magnets same gap and vacuum chamber width
(inductance ↗, BS1 may become too tall or even more non-linear)?
9/11/2011 J. Borburgh BSW magnets 21Review on PSB 160 MeV H- injection
Summary of outstanding questions
• Would trim power supplies be recommended when powering all BSW per ring in series?
• What to calculate to simulate the impact of field imperfections?• How to add the field deformation provoked by dump and its measurement
systems?• Would imposing a limit on the absolute field imperfections (in space and
time) be realistic?• Is septum (BSW1) leak field critical?• Is it necessary and how to track the electrons escaping from the stripping
foil?• Are glued laminated yoke reliable over time in a radioactive environment?• What should be the preferred vacuum chamber material?• Have we overlooked anything else?9/11/2011 J. Borburgh BSW magnets 22Review on PSB 160 MeV H- injection