  • Side 1 av 1

    Application area: The form Variation Order Request shall be used in the following situations:

    1) Additional work: Required by the Company that the Contractor believes is not part of his obligations in

    accordance with the Contract.

    2) Accelerate progress: The Company requires the Contractor to work in accordance with a different progress schedule

    than he is obligated to in the Contract.

    3) Changed conditions for which the Company is responsible and have or will have significance for the Contractors ability to meet current deadlines and/or lead to extra costs.

    An attachment shall be used if required for additional statements/documentation.

    Limitation for use in relation to use of the form Deviation report/application: If the Contractor has carried out contract work in conflict with the contract which is caused by conditions for which the Contractor is responsible, the Contractor shall only use the form Deviation report/application. This form shall also be used if the Contractor wishes to propose an alternative solution.

    Variation Order Request (VOR) Bilag 2b

    1. Contractor:

    VOR No.:

    Rev. No.:

    2. Request for Variation Order title:

    Contract:

    3. Reason for request:

    Date:

    4. Description:

    5. Schedule impact Can also be specified in attachment:

    6. Cost impact Can also be specified in attachments

    7. Other impact Can also be specified in attachments

    8. Contractor

    Date Sgnature