bim for highways
TRANSCRIPT
-
8/12/2019 Bim for Highways
1/64
Steve Jarvis MEng MCIHT
HDS BIM Coordinator Mott MacDonald
Adding Value through
utilising BIM in the highwaysand transportation sector:
Case Studies
-
8/12/2019 Bim for Highways
2/64
The Mott MacDonald BIM definition
A co-ordinated set of processes,
supported by technology, that add
value through creating managing and
sharing the properties of an asset
throughout its lifecycle
-
8/12/2019 Bim for Highways
3/64
BIM is more than fabulous 3-D design
London 2012 Olympic Shooting Venue
-
8/12/2019 Bim for Highways
4/64
BIM is more than just stunning 3D visualisation
Virtual world
Real world
Image: Hatch Mott MacDonald
-
8/12/2019 Bim for Highways
5/64
BIM is not just about buildings
Image: Hatch Mott MacDonald
-
8/12/2019 Bim for Highways
6/64
Process/workflow
Data
BIM
Model
BIM is all about information
Deliverables
2D drawings
Schedules
-
8/12/2019 Bim for Highways
7/64
Designers
BIM
Model
BIM is about collaboration
Customers
Suppliers Contractors
-
8/12/2019 Bim for Highways
8/64
BIM is all about outcomes
BIM
modelDefine desiredoutcomes
See that they
are delivered
Put in place a PROCESS and audit to make it happen
-
8/12/2019 Bim for Highways
9/64
BIM is for the whole lifecycle
Source: Autodesk
BIM
Model
-
8/12/2019 Bim for Highways
10/64
BIM in asset management
The biggest potential value is over the life of the
asset.
design
build
operate
-
8/12/2019 Bim for Highways
11/64
LifeCycle
Capital
Energy
Inspections Cleaning
RedecorationsOccupancy
Asset ReplacementReactive maintenance
Planned maintenance
-
8/12/2019 Bim for Highways
12/64
10 benefits we are bringing with BIM
Better outcomes through collaboration
Enhanced performanceOptimised solutions
Greater predictability
Faster project delivery
-
8/12/2019 Bim for Highways
13/64
10 benefits we are bringing with BIM
Reduced safety risk
Fits first timeReduced waste
Whole life asset
Continual improvement
-
8/12/2019 Bim for Highways
14/64
Highways has done BIM since the 1990s
Processes
3D model
Sharing
Whole life cycle
Data integration
Interoperability
4D (time)
5D (cost)
nD (carbon, sustainability, etc)
Data richGIS
Visualisation
Clash detection
3d model for quantities
Drawings
3D model for
construction Planning
Facilities management
Etc.
Direct Outcomes: By-products:
-
8/12/2019 Bim for Highways
15/64
Highways has done BIM since the 1990s
Processes
3D model
Sharing
Whole life cycle
Data integration
Interoperability
4D (time)
5D (cost)
nD (carbon, sustainability, etc)
Data richGIS
Visualisation
Clash detection
3d model for quantities
Drawings
3D model for
construction Planning
Facilities management
Etc.
Direct Outcomes: By-products:
Yes
Yes
Yes
Yes
Yes Partly
Partly
-
8/12/2019 Bim for Highways
16/64
The benefits are
already here
-
8/12/2019 Bim for Highways
17/64
London Underground: Victoria Station Upgrade
-
8/12/2019 Bim for Highways
18/64
-
8/12/2019 Bim for Highways
19/64
Design co-ordination
-
8/12/2019 Bim for Highways
20/64
Clash detection
-
8/12/2019 Bim for Highways
21/64
-
8/12/2019 Bim for Highways
22/64
New applications: ground treatment
Clashes and voids eliminated before site works
-
8/12/2019 Bim for Highways
23/64
New applications: ground treatment
Auto report extraction from model listing
unique reference coordinates
-
8/12/2019 Bim for Highways
24/64
-
8/12/2019 Bim for Highways
25/64
Digital setting out
GPS or LPS 3D total station system
Advanced Excavator Control
System works directly from 3Ddesign data
-
8/12/2019 Bim for Highways
26/64
Working around existing assets
laser scan imported to model
-
8/12/2019 Bim for Highways
27/64
Communication using 3D prints
-
8/12/2019 Bim for Highways
28/64
CDM Workshops & Inductions
Improved visualisation
3D walk-throughs
Construction sequences
testedSite inductions
-
8/12/2019 Bim for Highways
29/64
Port Mann/ Highway 1
Improvement Project
Vancouver, British Columbia
-
8/12/2019 Bim for Highways
30/64
Project Objectives
Reduce congestion at entry and exit points toHighway 1;
Reduce travel times for trips across the corridor
and improve connections within and betweencommunities;
Improve access to and egress from the corridorfor goods movement;
Facilitate the introduction of transit service alongthe corridor and the improvement of transitservice across the corridor;
Expand HOV, cycling and pedestrian networksalong or in the vicinity of the corridor
Improve safety for vehicle operators andpassengers, cyclists and pedestrians.
www.pmh1project.com
-
8/12/2019 Bim for Highways
31/64
Project Background and Timeline
Teaming Summer/Fall 2006
RFP Released - July 2007
Technical Submittal February 2008Financial Submittal July 2008
Preferred Proponent Announced August 2008
LNTP / Mobilization September 2008
Design Complete Early 2011
Bridge opens to Traffic December 2012
Substantial Completion December 2013
Final Completion December 2014
-
8/12/2019 Bim for Highways
32/64
The Project
-
8/12/2019 Bim for Highways
33/64
-
8/12/2019 Bim for Highways
34/64
Key Traffic Capacity
Improvements
-
8/12/2019 Bim for Highways
35/64
Model Based Design
Cape Horn Interchange Civil3D Model
-
8/12/2019 Bim for Highways
36/64
-
8/12/2019 Bim for Highways
37/64
Model Based Design
M d l B d D i
-
8/12/2019 Bim for Highways
38/64
Model Based Design
-
8/12/2019 Bim for Highways
39/64
3D Design for Bybanen
LRT
Bergen, Norway
-
8/12/2019 Bim for Highways
40/64
Bybanen Operation Dates
Phase 1
(2010)
Phase 2(2013)
Phase 3(2015)
Depot(2015)
Flesland
Terminal(2017?)
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
41/64
Mott MacDonald Team Locations
Dublin : Civils / LRT Systems / Coordination
Cork : Roads / Retaining Structures
Croydon : Tunnels
Budapest : Tunnels
Bristol : Geotechnical
Prague : Bridges
Bergen : Project Management
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
42/64
Project Challenges
Multiple Design Disciplines and
Locations
New Client and Territory for MM
3D from Ground Up
Language
Localisation and Standards
Stakeholders
Sub-consultants
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
43/64
Design Coordination - ProjectWise
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
44/64
3D & 2D Workflow
-
8/12/2019 Bim for Highways
45/64
Preliminary Concept : Agree Basics
3D Coordination : Early Stage review
from all Project Stakeholders in 3D
2D Extractions and Drawings : Once
3D designs clash checked and fullycoordinated
3D & 2D Workflow
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
46/64
3D PDFs Early Stage Reviews
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
47/64
3D & 2D Workflow
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
48/64
Novapoint - Norwegian Design
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
49/64
Novapoint - Norwegian Design
Water/Drainage/Cabling & Roads & Tunnels
Design Modules
3D Product Libraries
Cross Sections Defined
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
50/64
Terrains Defined & Design in Plan & Profile
Norwegian Drawing Standards
Quantity Take-offs
Novapoint - Norwegian Design
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
51/64
Novapoint - 3D Model
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
52/64
Novapoint - Setting Out
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
53/64
Setting Out From 3D Model 360 Glue on iPads
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
54/64
Setting Out From 3D Model
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
55/64
Information directly from 3D model
Appreciation of construction interfaces
Maintain Project Controls
Setting Out From 3D Model
Project 3D Design Construction Controls
-
8/12/2019 Bim for Highways
56/64
Site Clearance
Project 3D Design Construction Controls
Site Clearance
-
8/12/2019 Bim for Highways
57/64
Project 3D Design Construction Controls
R d & T k G
-
8/12/2019 Bim for Highways
58/64
Road & Track Geometry
Project 3D Design Construction Controls
Surfaces and Strings in 3D Model
Supplemented with LandXML and Genio
Files
-
8/12/2019 Bim for Highways
59/64
P j t C t l D fi Ch
-
8/12/2019 Bim for Highways
60/64
Project Controls Define Change
Project 3D Design Construction Controls
Project Controls Define Change
-
8/12/2019 Bim for Highways
61/64
Project 3D Design Construction Controls
Project Controls Define Change
-
8/12/2019 Bim for Highways
62/64
Project 3D Design Construction Controls
Project Controls Define Change
-
8/12/2019 Bim for Highways
63/64
Project 3D Design Construction Controls
3D Design for Bybanen LRT
-
8/12/2019 Bim for Highways
64/64
3D Design for Bybanen LRT
Bergen, Norway