binder 9 with uploaded drawings and approved document

1630
123

Upload: samuel-acidri

Post on 11-Apr-2016

16 views

Category:

Documents


0 download

DESCRIPTION

Binder 9 with uploaded drawings and approved document able to read and download this documentPile Construction

TRANSCRIPT

Page 1: Binder 9 with uploaded drawings and approved document

123

Page 2: Binder 9 with uploaded drawings and approved document

PILE BEARING CAPACITY CALCULATION BASED ON S.P.T. VALUE

------------------ ------------------

Project Name :

Location :

Borehole No. : BH-1

Date :

------------------ ------------------

MAYERHOF Formula : K1 K2

Skin, Ps = K1 x Nav x As SAND 2.0 400

Bearing, Pb = K2 x Nb x Ab SILT 2.5 250

Ult. Load, Pu = Ps + Pb CLAY 3.0 100

All. Load, Pa = Ps/Fs + Pb/Fb

Factor of safety : Skin, Fs = 2

Bearing, Fb = 3

------------------ ------------------

To calculate allowable soil bearing capacity :

Pile used : Type : s

(c = circular) Width, b = 0.4 m Perimeter: 1.600

(s = square) (= dia. for type c) Ab: 0.160

Qa(conc): 1800

========== ========== ====== ========== ========== ============ =======================

Depth Soil SPT Skin Total Base Working Load

Type N As Fric Skin Load Fs = 2.0 Fb = 3

(m) (m²) (kN) (kN) (kN) (KN)

------------------ ------------------ ---------- ------------------ ------------------ -------------------- ---------------------------------------

0.0 SAND 0 0.0 0.0 0.0 0.0 0.0

1.5 SAND 11 2.4 52.8 52.8 704.0 261.1

3.0 SAND 12 2.4 57.6 110.4 768.0 311.2

4.5 SAND 15 2.4 72.0 182.4 960.0 411.2

6.0 SILT 17 2.4 102.0 284.4 680.0 368.9

7.5 SILT 19 2.4 114.0 398.4 760.0 452.5

9.0 SILT 19 2.4 114.0 512.4 760.0 509.5

10.5 SILT 17 2.4 102.0 614.4 680.0 533.9

12.0 SILT 19 2.4 114.0 728.4 760.0 617.5

13.5 SILT 11 2.4 66.0 794.4 440.0 543.9

15.0 SILT 18 2.4 108.0 902.4 720.0 691.2

16.5 SILT 17 2.4 102.0 1,004.4 680.0 728.9

18.0 SILT 19 2.4 114.0 1,118.4 760.0 812.5

19.5 SILT 20 2.4 120.0 1,238.4 800.0 885.9

21.0 SILT 18 2.4 108.0 1,346.4 720.0 913.2

22.5 SILT 14 2.4 84.0 1,430.4 560.0 901.9

24.0 SILT 0 2.4 0.0 1,430.4 0.0 715.2

25.5 SILT 22 2.4 132.0 1,562.4 880.0 1,074.5

27.0 SILT 20 2.4 120.0 1,682.4 800.0 1,107.9

28.5 SILT 20 2.4 120.0 1,802.4 800.0 1,167.9

30.0 SILT 22 2.4 132.0 1,934.4 880.0 1,260.5

31.5 SILT 25 2.4 150.0 2,084.4 1,000.0 1,375.5

33.0 SILT 23 2.4 138.0 2,222.4 920.0 1,417.9

34.5 SILT 23 2.4 138.0 2,360.4 920.0 1,486.9

36.0 SILT 24 2.4 144.0 2,504.4 960.0 1,572.2

37.5 SILT 23 2.4 138.0 2,642.4 920.0 1,627.9

39.0 SILT 25 2.4 150.0 2,792.4 1,000.0 1,729.5

40.5 SILT 26 2.4 156.0 2,948.4 1,040.0 1,820.9

42.0 SILT 50 2.4 300.0 3,248.4 2,000.0 2,290.9

43.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

45.0 SILT 2.4 0.0 3,248.4 0.0 1,624.2

46.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

For a designed load of 100 KN, the estimated depth is 16.5m.

Note : 1. The clay skin friction for the top soil layer is assume to be 7.5kN/m2

2. The pile is designed as floating pile where the pile would settle together with the soil and therefore there

is no effective negetive skin friction.

3. The final depth of piles penetration shall be decided on site by load test.

Page 3: Binder 9 with uploaded drawings and approved document

LARSEN & TOUBRO LIMITED E&C DIVISION

GEOTECHNICAL INVESTIGATION REPORT – INSIDE

AREA

DOCUMENT NO. A067-LT-00-CV-04-RP-0004

PROJECT :Additional Gas Processing Facilities (Phase-IV)

REVISION : 01

CUSTOMER : ONGC,HAZIRA

Sheet No.1053

11-06-2012

Page 4: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

TECHNICAL REPORT

OF

GEOTECHNICAL INVESTIGATION

FOR

PROPOSED STRUCTURES INSIDE PLANT AREA UNDER PROJECT OF ADDITIONAL GAS PROCESSING FACILITES (PHASE 4) FOR

ONGC AT HAZIRA, SURAT (INSIDE PLANT AREA)

BY:

DR.K.C.THAKER B.E.(CIVIL) ; M.TECH (S.M.); (I.I .T, BOMBAY) Ph.D.(I.I.T., BOMBAY);F.I .E.(INDIA); F.I.G.S.

K.K.THAKER B.E. (CIVIL) GOLD MEDALIST; M.E (GEOTECH) M.B.A.(FINANCE);M.I.E(INDIA); M.I.G.S; M.G.I.C.E.A.

OFFICE : Plot no.1,Sayona Silver Estate-Part II ,

Behind Si lver Oak Club, Beside Auda Water Tank Opp. Sarjan RMC Plant,

Gota, Ahmedabad 382 481 Phone :- 65103088/89/90,9825064378,

August - 2010

Sheet No.1054

11-06-2012

Page 5: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED STRUCTURES OF ADDITIONAL GAS PROCESSING FACILITES PROECT (PHASE 4 – INSIDE OF PLANT) OF ONGC AT HAjIRA, SURAT

1.0 Introduction For foundation analysis of the structures of Additional Gas Processing Facilities Project (Phase 4) of ONGC at Hajira, Surat, It is necessary, 1. To determine the subsoil profile of the site and to know physical properties and strength

characteristics of soil at various depths. 2. To suggest suitable foundation and to know the safe bearing pressure and probable

settlement of foundation. 3. To know any adverse soil conditions to the foundation structures and to take

precautionary measures.

For this purpose, the geotechnical investigation was entrusted to us by Larsen and Toubro Limited. Following points were decided, 1. No. Bore holes – 4 nos. in side plant boundary 2. Standard penetration tests are conducted at regular interval. 3. Collection of Undisturbed soil samples at regular interval. 4. Collection of disturbed samples during drilling and from SPT. 5. To find physical properties and strength characteristics of samples as per the testing

schedules. 6. To locate ground water table, if any. 7. To conduct block vibration test. 8. To conduct electrical resistivity test. 9. Interpretation of results, Analysis and Recommendations.

Based on the above points the detailed Geotechnical Investigation Program included the following: (A) Field Investigation 1. Drilling of bore hole. 2. Collection of soil samples ( Disturbed and Undisturbed ) 3. Conducting Standard Penetration Test. 4. Conducting Block Vibration Test. 5. Conducting Electrical Resistivity Test

(B) Laboratory Investigation 1. Bulk Density and moisture content 2. Grain size analysis 3. Consistency limits 4. Shear tests 5. Consolidation tests 6. Chemical analysis of soil and water

(C) Recommendations Based on above investigations, the results are to be obtained. The findings would be based on interpretation of results, analysis and computations as per relevant Indian standards.

Sheet No.1055

11-06-2012

Page 6: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

2.0 Field Investigation 2.1 BoringThe exploratory boreholes of 150mm diameter were drilled by rotary drilling method. The depth of the test bore at the proposed location is as under:

Bore Hole No. Co-Ordinates Reduced

Level (m) Depth Investigated

(m) N E BH – 4 365 1025 98.466 20 BH – 5 780 1100 99.423 25 BH – 6 799 1170 99.620 20 BH – 9 1065 1750 99.232 20

2.2 Sampling 2.2.1 Disturbed samples Disturbed samples were collected during boring and from the split spoon sampler. The samples recovered were logged, labeled and placed in polyethylene bags and sent to laboratory for testing.

2.2.2 Undisturbed samples Undisturbed soil samples were collected in thin walled Shelby tubes as per IS 2132 at regular intervals. The samples collected were sealed properly using wax, labeled and transported to the laboratory.

2.2.3 Standard penetration test The standard penetration tests were conduct in accordance with IS:2131-1981 in test bore at regular intervals. The test gives N – Value, the blow counts of last 30 cm penetration of split spoon sampler with 63.5 kg hammer falling from 76 cm height.

2.2.4 Block Vibration Test For determining various parameters influencing the design of machine foundation like physical properties of elastic base of the foundation, block vibration test was conducted. For this purpose Oscillator was fixed on the PCC block cast of size 1.00 x 0.75 x 0.75 m at Co ordinates N 789 and E 1087, and vibration was induced. The vibration peak ups were attached, on this block to measure the frequency and amplitude. The test was conducted as per the provisions of IS 5249 – 1969. Various dynamic properties as listed below were calculated for 10sq.mt area.

Cu - Coefficient of elastic uniform compression ( kg / cu.cm ) Cτ - Coefficient of elastic uniform shear ( Kg / cu.cm ) Cφ - Coefficient of elastic non – uniform compression ( Kg / cu.cm ) Cψ − Coefficient of elastic non – uniform shear ( Kg / cu.cm )

The above coefficients are reported for foundation contact area, A of 10.0 sq. m

2.2.5 Electrical Resistivity Test Geophysical Survey In all geophysical surveys, Electrical Resistivity method is best and reliable to know geological formation of the the area. All geological formations possess properties called electrical resistivity when the current flows through them. Resistivity thus

Sheet No.1056

11-06-2012

Page 7: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

is defined as the resistance offered by a unit cube of material to direct current flowing through it in a direction perpendicular to two of its opposite faces. The numerical value of the resistivity is expressed in ohm. m in general. Thus the electrical resistivity is principally based on the study of resistance offered by the sub-surface formation to the flow of current. The study in turns helps in evaluation of the characteristic of the sub surface layers in terms of electrical resistivity. Vertical electrical soundings (VES) have been conducted by using resistivity meter of I G I S make direct current in deployed during survey as per IS : 3043. Two metal stakes called current electrodes into the sub surface transmit the current and the potential response is observed by means two copper electrodes called potential electrodes. Apparent resistivity is calculated from the equation:-

= 2 SR K = 2 S = Geometric factor for electrode spacing (Wenner’s configuration) R = Resistance in Ohms S = Spacing between adjacent electrodes in (m)

= Resistivity in ohm.m. Test was conducted at Co ordinates: N 762 E 1087

3.0 Laboratory investigation The laboratory tests were conducted on the samples collected. The following laboratory tests were conducted on undisturbed and disturbed soil samples collected from various depths to find physical properties and strength characteristics.

Tests Recomnd procedure Type Samples 1. Sample Preparation IS 2720 Pt I DS / UDS 2. Moisture Content IS 2720 Pt II DS / UDS 3. Dry Unit Weight LAMBE UDS 4. Specific Gravity IS 2720 Pt III DS 5. Liquid Limit IS 2720 DS 6. Plastic Limit IS 2720 Pt V DS 7. Grain Size Analysis IS 2720 Pt IV DS 8. Soil Classification IS 1498 DS / UDS 9. Consolidation IS 2720 Pt XV UDS 10. Triaxial Comp. Test IS 2720 Pt X UDS 11. Laboratory permeability IS 2720 Part XVII UDS

4.0 Results 1. The location plan of Bore hole is shown in fig no.1 2. The bore log details of Bore hole are shown in fig nos. 2 to 5 3. Results of permeability of Bore hole are given in table no 1 4. The Chemical analysis of soil and water is given in table nos.2 & 3 5. Laboratory test results of Bore hole are appended in table nos. 4 to 7 6. Results of BVT are shown in fig nos. 6 & 7 7. Results of ERT are given in fig no. 8

5.0 General stratification The soil deposits at Hajira are alluvial in nature formed by River Tapti and its interaction with the sea over the geological history. The layers consist of plastic clays from stiff to very stiff consistency at top. The subsequent layer consists of plastic clays and silts from very

Sheet No.1057

11-06-2012

Page 8: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

soft to stiff consistency, followed by silty sands with density varying from loose to dense and very dense.

6.0 Discussion

Two foundation options are suggested:

1. Pile Foundations : For heavy equipment and major structures, pile foundations are recommended. Due to proximity to process areas driven piles are not permitted and bored cast-in-situ piles are recommended. Piles of 500 mm diameter with depth of embedment of 16 m are suitable. Pile calculations are given in Appendix – 1. The lateral capacities are 4.5 t for a fixed headed pile and 2.0 t for a free headed pile. The lateral capacity is also to be confirmed by means of a lateral load test on a test pile. The tests have to be carried out as per IS 2911 / Part 4 – 1985.

2. Open foundations for lightly loaded structures and equipment : The possibility of placing the light to intermediate loaded structures and equipment foundations, open shallow foundations can be explored. The minimum depth of foundation recommended is 2 m from FGL. The permissible settlement is 25mm. The recommended bearing capacity values borehole wise for permissible settlements for 25mm are as given in Section 7 (Conclusion) below and the calculations are appended in Appendix 2. 7.0 Conclusions 1) Two foundation options are recommended. Option 1 : For process equipments and heavily loaded structures, Bored cast –in- situ piles, 500 mm diameter, length of embedment of 16 and cutoff level approximately at 2.50 m from NGL having capacities given below may be provided,

Axial Compression 65 TLateral – Fixed Head 4.5 TLateral – Free Head 2.0 TUplift 24 T

Option 2: For light to moderately loaded structures and equipment foundations, open foundations with minimum depth of 2m below FGL is recommended. A 30 cm thick, well compacted coarse sand layer below the bottom of foundation is recommended.

The net safe bearing pressures as tabulated below are recommended.

Size of Foundation Recommended net Safe Bearing

Pressure (T/m2)

Depth (m) Width (m)

2.0 1.0 14 2.0 2.0 8

Sheet No.1058

11-06-2012

Page 9: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

2.0 3.0 62.0 Strip 5 2.5 1.0 15 2.5 2.0 10 2.5 3.0 7 2.5 Strip 6

2) Ground water table is encountered at around 3.50 m from EGL, during investigation, which is likely to rise up to two mt from ground level in monsoon. Design groundwater level shall be at EL 99.500 to account for rain and tidal effects.

3) From results of chemical soil as reported in table 2 & 3, the sub soil is classified in class 2 based on sulphite Content (SO3), as per the table no. 4 under clauses 8.2.2.4 and 9.1.2 of IS: 456, 2000. PPC or PSC with minimum cement content of 330kg/m3 and maximum face water-cement ratio of 0.5 can be used for all RCC in foundation structures. OPC may be used provided the C3A content is within 5 to 8% as per IS 456, Table 4, Note 6. Alternatively, OPC mixed with fly ash as per the provisions of IS 456 and IS 3812 may be used with validation of concrete characteristics through testing. Minimum cement content in piles shall be 400kg/m3 as per the requirements of IS 2911. As the chloride content is high, clear cover to the reinforcement in foundation systems shall at least be 65 mm.

4) Suitable side slope in excavation and any measures if required and so far as is reasonably practicable shall be provided to prevent dislodgement of earth or any other material forming the side of excavation.

5) Considering the swelling characteristic adequate measures shall be taken to mitigate adverse consequences of swelling and shrinking due to moisture movement. A layer of compacted coarse sand having 300 mm thickness shall be provided under the pile caps and aprons around the structures and in plinths under floor finishes.

7) The comments given in this report and the opinion expressed are based on the ground conditions encountered during site work and on the results of tests made in field and in the laboratory. There may however, special conditions prevailing at the site which have not been disclosed by the investigation and which have not been taken in to account in the report. Any variation in stratification in any of the foundation location shall be studied thoroughly before executing the foundation work

(K.K.Thaker) (Dr. K.C.Thaker)

Sheet No.1059

11-06-2012

Page 10: Binder 9 with uploaded drawings and approved document

Calculation of Safe Load on Bored Cast in Situ Pile (As per IS: 2911 (Part I / Sec II))

1) Design StipulationsPile Diameter: 0.50m Existing GWT level: 0.00m Pile Cut-Off level: 2.50m from existing ground level. Pile Termination level: 18.50m from E.G.L For maximum overburden pressure at Pile tip 15 x diameter of pile length of pile has been taken

2) Soil Parameters Considered Layer Thickness

m CohesionKg / cm2

Angle of Internal Friction

Field Densitygm / cc

SPT N Value

5.10 0.39 9 1.76 8 7.50 0.00 25 1.70 10 12.4 0.00 34 1.90 19

3) Ultimate End Bearing Capacity Que = Ap (0.5 * D * γ * Nγ + Pd * Nq) Where, Ap = Cross sectional Area = 0.196 m2

D = Pile Stem Diameter = 0.50 m γ = Bulk Unit Weight of soil at Pile tip = 0.90 T/m3

Nγ = Bearing Capacity factor = 41.06 Pd = Effective overburden pressure at pile tip = 5.56 T/m2

Nq = Bearing Capacity factor = 42.80 Ultimate End Bearing Capacity Que =0.196*(0.5*0.50*0.90*41.06+5.56*42.8) = 48.48 T

Pd Level for this pile = 7.50 m Layer No.1 Effective overburden pressure due to this layer = 0.00 x 1.76 +5.10 x (1.76 - 1) = 3.88 T/m2

Layer No.2 Effective overburden pressure due to this layer = 2.40 x (1.70 - 1) =1.68 T/m2

Layer No.3 No contribution from this layer Total effective overburden pressure up to 7.50m level from EGL= 5.56T/m2.

4) Ultimate Skin Friction Capacity Qsg = Σ [K * Pdi * tan (δ) * Asi] for all layers Where, K = Earth Pressure Coefficient Pdi = Effective Overburden pressure for ith layer δ = Angle of wall friction for ith layer Asi = Surface area of pile stem for ith layer

Qsc = Σ [α * C * as] for all layers Where, α = Reduction factor C = Average Cohesion Asi = Surface area of pile stem for ith layer

Layer no. 1: K: 1.00 Pd1 : 1.94 T/m2 tan (δ) : 0.16 As1 : 4.08 m2

Qsg = K*Pd1*tan (δ)*As1 =1.00*1.94*0.16*4.08 = 1.25 T Reduction factor (α): 0.40 Average Cohesion(C): 3.90 T/m2. Qsc = α*C*As1 = 0.40*3.90*4.08 = 6.37 T Total net skin friction of this layer = 7.62T/m2

Sheet No.1060

11-06-2012

Page 11: Binder 9 with uploaded drawings and approved document

Layer no. 2: K: 1.50 Pd2: 4.72 T/m2. tan (δ) : 0.47 As2 : 11.78 m2. Qsg = K*Pd2*tan (δ)*As2 =1.50*4.72*0.47*11.78 = 38.82 T Reduction factor (α): 0.40 Average Cohesion(C): 0.00 T/m2. Qsc = a*C*As2 =0.40*0.00*11.78 = 0.00 T Total net skin friction of this layer = 38.82 T/m2.

Layer no. 3: K: 2.00 Pd3 : 5.56 T/m2. tan (δ) : 0.67 As3 : 9.26 m2.Qsg = K*Pd3*tan (δ)*As3 =2.00*5.56*0.67*9.26 = 69.38 T Reduction factor (α): 0.30 Average Cohesion(C): 0.00 T/m2. Qsc = α*C*As3 =0.30*0.00*9.26 = 0.00 T Total net skin friction of this layer = 69.38T/m2.

Total Skin Friction Capacity Qus = Qsg + Qsc = 115.82 T Total Ultimate Pile Capacity Qu = Qus + Que = 164.30 T Net Ultimate Pile Capacity Qu/FOS = 65.7 T

5) Safe Load in Compression in Ton

Pile Diameter in m Pile Length after cutoff in m

14.0 16.0 18.0

0.45 45.1 52.8 60.5

0.50 56.3 65.7 75.1

Calculating safe load on pile in uplift for various diameters,

6) Safe Load in Uplift in Ton

Pile Diameter in m Pile Length after cutoff in m

14.0 16.0 18.0

0.45 30.9 38.6 46.2

0.50 36.9 46.4 55.7

7) Computation of Lateral Capacity Lateral capacity is computed based up on the allowable top deflection of 5.0mm. Free Length L1 is 0.00 m and overall nature of soil is clayey.

For a Fixed Head Pile of 500 mm diameter, soil constant K2= 48.8 Kg/cm3 (From IS Code), E = 273861.27 Kg/cm2, I = 306640.63 cm4, R = 203.67, L1/R = 0.00. Depth of Fixity Lf = 443.99 cm = 4.4 m Total Ultimate Horizontal Load Capacity H [As per IS Code] =12EIY/(L1+Lf)3 = 5.76 T Ultimate Horizontal Load Capacity is recommended as 4.50 T Moment Reduction Factor m = 0.825(From IS Code) Total Ultimate Moment Capacity M [As per IS Code] =mH (L1+Lf)/2 = 8.24 ~ 8.2 Tm

Recommended Lateral Capacities For Fixed Head Piles Pile Diameter in m 0.45 0.50

Horizontal Load Capacity in T 4.0 4.5

For a Free Head Pile of 500 mm diameter, soil constant K2= 48.8 Kg/cm3 (From IS Code), E = 273861.27 Kg/cm2, I = 306640.63 cm4, R = 203.67, L1/R = 0.00. Depth of Fixity Lf = 391.05 cm = 3.9 m

Sheet No.1061

11-06-2012

Page 12: Binder 9 with uploaded drawings and approved document

Total Ultimate Horizontal Load Capacity H [As per IS Code] = 3EIY/(L1+Lf)3 = 2.1 T Ultimate Horizontal Load Capacity is recommended as 2.0 T Moment Reduction Factor m = 0.4 (From IS Code) Total Ultimate Moment Capacity M [As per IS Code] = mH (L1+Lf) = 3.13 ~3.0 Tm

Recommended Lateral Capacities For Free Head Piles Pile Diameter in m 0.45 0.50

Horizontal Load Capacity in T 1.9 2.0

8) Notes: 1) Initial and routine pile load tests shall be carried out on the piles at site to confirm the capacity of pile worked out theoretically.

(K.K.Thaker)

Sheet No.1062

11-06-2012

Page 13: Binder 9 with uploaded drawings and approved document

Sr.

Leng

thW

idth

CN

cN

q - 1

NS

cS

qS

dcdq

dic

iqi

0.5

No.

mm

mK

g/cm

2de

gree

gm/c

cW

qW

t / m

2

11.

001.

002.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.44

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

1.00

15

22.

002.

002.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.22

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.75

13

33.

003.

002.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.15

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.67

12

44.

004.

002.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.11

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.63

12

51.

001.

002.

500.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.56

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.75

16

62.

002.

002.

500.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.28

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.63

14

73.

003.

002.

500.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.19

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.58

13

84.

004.

002.

500.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.14

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.56

12

91.

001.

003.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.67

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.50

17

102.

002.

003.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.33

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.50

14

113.

003.

003.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.22

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.50

13

124.

004.

003.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.17

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.50

13

1) F

acto

r of s

afet

y is

2.5

2) D

epth

of f

ound

atio

n sh

all b

e fr

om E

G L

Dep

th o

f Fo

unda

tion

Wat

er T

able

C

orre

ctio

nB

earin

g C

apac

ity F

acto

rsS

hape

Fac

tors

Not

e :-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (P

hase

4 )

of O

NG

C a

t Haz

ira, S

urat

, L &

T L

tdFo

r Is

olat

ed S

quar

e Fo

otin

g

Proj

ect :

Dep

th F

acto

rsIn

clin

atio

n Fa

ctor

sU

nit W

eigh

tS

afe

Bea

ring

Cap

acity

Siz

e of

Fou

ndat

ion

She

ar P

aram

eter

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

adA

PP

EN

DIX

- 2

a (B

oreh

ole

No.

4)

Cal

cula

tion

of n

et S

afe

Bea

ring

Cap

acity

Bas

ed o

n Sh

ear P

aram

eter

s C

- qu

= 1

/ FS

[ 2

/ 3 C

Nc

dc S

c ic

+

d (N

q - 1

) Sq

dq iq

Wq

+ 0.

5 B

N S

di

W]

She

et N

o.10

63

11-0

6-20

12

Page 14: Binder 9 with uploaded drawings and approved document

Sr.

Leng

thW

idth

CN

cN

q - 1

NS

cS

qS

dcdq

dic

iqi

0.5

No.

mm

mK

g/cm

2de

gree

gm/c

cW

qW

t / m

2

11.

001.

002.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.46

1.23

1.23

1.00

1.00

1.00

1.71

0.86

1.00

1.00

20

22.

002.

002.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.23

1.12

1.12

1.00

1.00

1.00

1.71

0.86

1.00

0.75

17

33.

003.

002.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.15

1.08

1.08

1.00

1.00

1.00

1.71

0.86

1.00

0.67

16

44.

004.

002.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.12

1.06

1.06

1.00

1.00

1.00

1.71

0.86

1.00

0.63

16

51.

001.

002.

500.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.58

1.29

1.29

1.00

1.00

1.00

1.71

0.86

1.00

0.75

22

62.

002.

002.

500.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.29

1.14

1.14

1.00

1.00

1.00

1.71

0.86

1.00

0.63

18

73.

003.

002.

500.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.19

1.10

1.10

1.00

1.00

1.00

1.71

0.86

1.00

0.58

17

84.

004.

002.

500.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.14

1.07

1.07

1.00

1.00

1.00

1.71

0.86

1.00

0.56

17

91.

001.

003.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.69

1.35

1.35

1.00

1.00

1.00

1.71

0.86

1.00

0.50

24

102.

002.

003.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.35

1.17

1.17

1.00

1.00

1.00

1.71

0.86

1.00

0.50

20

113.

003.

003.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.23

1.12

1.12

1.00

1.00

1.00

1.71

0.86

1.00

0.50

18

124.

004.

003.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.17

1.09

1.09

1.00

1.00

1.00

1.71

0.86

1.00

0.50

18

1) F

acto

r of s

afet

y is

2.5

2) D

epth

of f

ound

atio

n sh

all b

e fr

om E

G L

Dep

th o

f Fo

unda

tion

Wat

er T

able

C

orre

ctio

nB

earin

g C

apac

ity F

acto

rsS

hape

Fac

tors

Not

e :-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (P

hase

4 )

of O

NG

C a

t Haz

ira, S

urat

, L &

T L

tdFo

r Is

olat

ed S

quar

e Fo

otin

g

Proj

ect :

Dep

th F

acto

rsIn

clin

atio

n Fa

ctor

sU

nit W

eigh

tS

afe

Bea

ring

Cap

acity

Siz

e of

Fou

ndat

ion

She

ar P

aram

eter

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad AP

PE

ND

IX -

2 b

(Bor

ehol

e N

o. 5

)

Cal

cula

tion

of n

et S

afe

Bea

ring

Cap

acity

Bas

ed o

n Sh

ear P

aram

eter

s C

- qu

= 1

/ FS

[ 2

/ 3 C

Nc

dc S

c ic

+

d (N

q - 1

) Sq

dq iq

Wq

+ 0.

5 B

N S

di

W]

She

et N

o.10

64

11-0

6-20

12

Page 15: Binder 9 with uploaded drawings and approved document

Sr.

Leng

thW

idth

CN

cN

q - 1

NS

cS

qS

dcdq

dic

iqi

0.5

No.

mm

mK

g/cm

2de

gree

gm/c

cW

qW

t / m

2

11.

001.

002.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.41

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

1.00

7

22.

002.

002.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.20

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.75

6

33.

003.

002.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.14

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.67

5

44.

004.

002.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.10

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.63

5

51.

001.

002.

500.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.51

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.75

7

62.

002.

002.

500.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.26

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.63

6

73.

003.

002.

500.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.17

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.58

6

84.

004.

002.

500.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.13

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.56

5

91.

001.

003.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.61

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.50

8

102.

002.

003.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.31

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.50

6

113.

003.

003.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.20

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.50

6

124.

004.

003.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.15

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.50

6

1) F

acto

r of s

afet

y is

2.5

2) D

epth

of f

ound

atio

n sh

all b

e fr

om E

G L

Dep

th o

f Fo

unda

tion

Wat

er T

able

C

orre

ctio

nB

earin

g C

apac

ity F

acto

rsS

hape

Fac

tors

Not

e :-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (P

hase

4 )

of O

NG

C a

t Haz

ira, S

urat

, L &

T L

tdFo

r Is

olat

ed S

quar

e Fo

otin

g

Proj

ect :

Dep

th F

acto

rsIn

clin

atio

n Fa

ctor

sU

nit W

eigh

tS

afe

Bea

ring

Cap

acity

Siz

e of

Fou

ndat

ion

She

ar P

aram

eter

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad AP

PE

ND

IX -

2 C

(B

oreh

ole

No.

6)

Cal

cula

tion

of n

et S

afe

Bea

ring

Cap

acity

Bas

ed o

n Sh

ear P

aram

eter

s C

- qu

= 1

/ FS

[ 2

/ 3 C

Nc

dc S

c ic

+

d (N

q - 1

) Sq

dq iq

Wq

+ 0.

5 B

N S

di

W]

She

et N

o.10

65

11-0

6-20

12

Page 16: Binder 9 with uploaded drawings and approved document

Sr.

Leng

thW

idth

CN

cN

q - 1

NS

cS

qS

dcdq

dic

iqi

0.5

No.

mm

mK

g/cm

2de

gree

gm/c

cW

qW

t / m

2

11.

001.

002.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.47

1.23

1.23

1.00

1.00

1.00

1.76

0.88

1.00

1.00

18

22.

002.

002.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.23

1.12

1.12

1.00

1.00

1.00

1.76

0.88

1.00

0.75

15

33.

003.

002.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.16

1.08

1.08

1.00

1.00

1.00

1.76

0.88

1.00

0.67

15

44.

004.

002.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.12

1.06

1.06

1.00

1.00

1.00

1.76

0.88

1.00

0.63

14

51.

001.

002.

500.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.58

1.29

1.29

1.00

1.00

1.00

1.76

0.88

1.00

0.75

20

62.

002.

002.

500.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.29

1.15

1.15

1.00

1.00

1.00

1.76

0.88

1.00

0.63

17

73.

003.

002.

500.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.19

1.10

1.10

1.00

1.00

1.00

1.76

0.88

1.00

0.58

16

84.

004.

002.

500.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.15

1.07

1.07

1.00

1.00

1.00

1.76

0.88

1.00

0.56

15

91.

001.

003.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.70

1.35

1.35

1.00

1.00

1.00

1.76

0.88

1.00

0.50

22

102.

002.

003.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.35

1.17

1.17

1.00

1.00

1.00

1.76

0.88

1.00

0.50

18

113.

003.

003.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.23

1.12

1.12

1.00

1.00

1.00

1.76

0.88

1.00

0.50

17

124.

004.

003.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.17

1.09

1.09

1.00

1.00

1.00

1.76

0.88

1.00

0.50

16

1) F

acto

r of s

afet

y is

2.5

2) D

epth

of f

ound

atio

n sh

all b

e fr

om E

G L

Dep

th o

f Fo

unda

tion

Wat

er T

able

C

orre

ctio

nB

earin

g C

apac

ity F

acto

rsS

hape

Fac

tors

Not

e :-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (P

hase

4 )

of O

NG

C a

t Haz

ira, S

urat

, L &

T L

tdFo

r Is

olat

ed S

quar

e Fo

otin

g

Proj

ect :

Dep

th F

acto

rsIn

clin

atio

n Fa

ctor

sU

nit W

eigh

tS

afe

Bea

ring

Cap

acity

Siz

e of

Fou

ndat

ion

She

ar P

aram

eter

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad AP

PE

ND

IX -

2 d

(Bor

ehol

e N

o. 9

)

Cal

cula

tion

of n

et S

afe

Bea

ring

Cap

acity

Bas

ed o

n Sh

ear P

aram

eter

s C

- qu

= 1

/ FS

[ 2

/ 3 C

Nc

dc S

c ic

+

d (N

q - 1

) Sq

dq iq

Wq

+ 0.

5 B

N S

di

W]

She

et N

o.10

66

11-0

6-20

12

Page 17: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

ofFo

otin

g D

W

idth

ofFo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0SB

Cp

(p+

p 0)/p

0C

orre

ctio

nfo

r dep

thC

onso

lidat

ion

Settl

emen

t Sc

mm

mgm

/ cc

mT

/ m2

T / m

2T

/ m2

mm

10.

152.

001.

002.

000.

821.

763.

005.

2815

3.68

1.70

0.7

0.66

17.5

20.

152.

002.

003.

150.

821.

763.

586.

2913

3.98

1.63

0.7

0.73

28.2

30.

152.

003.

003.

150.

821.

763.

586.

2912

5.22

1.83

0.7

0.80

38.0

40.

152.

004.

003.

150.

821.

763.

586.

2912

6.11

1.97

0.7

0.85

45.5

50.

152.

501.

002.

000.

821.

763.

506.

1616

4.00

1.65

0.7

0.65

16.2

60.

152.

502.

002.

650.

821.

763.

836.

7314

4.89

1.73

0.7

0.73

26.4

70.

152.

503.

002.

650.

821.

763.

836.

7313

6.13

1.91

0.7

0.75

32.4

80.

152.

504.

002.

150.

821.

763.

586.

2912

7.70

2.22

0.7

0.81

34.8

90.

153.

001.

002.

000.

821.

764.

007.

0417

4.32

1.61

0.7

0.63

15.2

100.

153.

002.

002.

150.

821.

764.

087.

1714

6.04

1.84

0.7

0.73

24.0

110.

153.

003.

002.

150.

821.

764.

087.

1713

7.23

2.01

0.7

0.73

27.4

120.

153.

004.

002.

150.

821.

764.

087.

1713

8.02

2.12

0.7

0.77

31.3

fact

orre

late

dto

pore

pres

sure

para

met

er

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Cal

cula

tion

of S

ettle

men

t (B

H 4

)Se

ttlem

ent S

C =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P 0

+

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

67

11-0

6-20

12

Page 18: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

ofFo

otin

g D

W

idth

ofFo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0SB

Cp

(p+

p 0)/p

0C

orre

ctio

nfo

rde

pth

Con

solid

atio

nSe

ttlem

ent S

c

mm

mgm

/ cc

mT

/ m2

T / m

2T

/ m2

mm

10.

182.

001.

002.

000.

911.

713.

005.

1320

5.01

1.98

0.7

0.66

25.8

20.

182.

002.

003.

150.

911.

713.

586.

1117

5.38

1.88

0.7

0.73

41.5

30.

182.

003.

003.

150.

911.

713.

586.

1116

7.01

2.15

0.7

0.80

54.9

40.

182.

004.

003.

150.

911.

713.

586.

1116

8.19

2.34

0.7

0.85

65.2

50.

182.

501.

002.

000.

911.

713.

505.

9922

5.51

1.92

0.7

0.65

24.2

60.

182.

502.

002.

650.

911.

713.

836.

5418

6.64

2.02

0.7

0.73

38.8

70.

182.

503.

002.

650.

911.

713.

836.

5417

8.28

2.27

0.7

0.75

46.9

80.

182.

504.

002.

150.

911.

713.

586.

1117

10.3

82.

700.

70.

8149

.5

90.

183.

001.

002.

000.

911.

714.

006.

8424

6.02

1.88

0.7

0.63

23.0

100.

183.

002.

002.

150.

911.

714.

086.

9720

8.28

2.19

0.7

0.73

35.2

110.

183.

003.

002.

150.

911.

714.

086.

9718

9.84

2.41

0.7

0.73

39.6

120.

183.

004.

002.

150.

911.

714.

086.

9718

10.8

72.

560.

70.

7744

.8

fact

orre

late

dto

pore

pres

sure

para

met

er

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Cal

cula

tion

of S

ettle

men

t (B

H 5

)Se

ttlem

ent S

C =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P

0 +

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

68

11-0

6-20

12

Page 19: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

ofFo

otin

g D

W

idth

ofFo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0SB

Cp

(p+

p 0)/p

0C

orre

ctio

nfo

rde

pth

Con

solid

atio

nSe

ttlem

ent S

c

mm

mgm

/ cc

mT

/ m2

T / m

2T

/ m2

mm

10.

292.

001.

002.

000.

921.

73.

005.

107

1.66

1.33

0.7

0.66

17.1

20.

292.

002.

002.

000.

921.

73.

005.

106

2.54

1.50

0.7

0.73

27.1

30.

292.

003.

002.

000.

921.

73.

005.

105

3.05

1.60

0.7

0.80

34.2

40.

292.

004.

002.

000.

921.

73.

005.

105

3.38

1.66

0.7

0.85

39.6

50.

292.

501.

001.

500.

921.

73.

255.

537

2.33

1.42

0.7

0.65

15.7

60.

292.

502.

001.

500.

921.

73.

255.

536

3.17

1.57

0.7

0.73

22.8

70.

292.

503.

001.

500.

921.

73.

255.

536

3.60

1.65

0.7

0.75

26.0

80.

292.

504.

001.

500.

921.

73.

255.

535

3.86

1.70

0.7

0.81

29.5

90.

293.

001.

001.

000.

921.

73.

505.

958

3.40

1.57

0.7

0.63

13.2

100.

293.

002.

001.

000.

921.

73.

505.

956

4.02

1.68

0.7

0.73

17.3

110.

293.

003.

001.

000.

921.

73.

505.

956

4.28

1.72

0.7

0.73

18.1

120.

293.

004.

001.

000.

921.

73.

505.

956

4.43

1.74

0.7

0.77

19.7

fact

orre

late

dto

pore

pres

sure

para

met

er

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Cal

cula

tion

of S

ettle

men

t (B

H 6

)Se

ttlem

ent S

C =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P

0 +

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

69

11-0

6-20

12

Page 20: Binder 9 with uploaded drawings and approved document

Sr. N

o.D

epth

of

Foot

ing

D

Wid

th o

f Fo

otin

g B

m

vH

pSB

Cfa

ctor

rela

ted

to p

ore

pres

sure

para

met

er

Cor

rect

ion

for

dept

hC

onso

lidat

ion

Settl

emen

t Sc

mm

mT

/ m2

T / m

2m

m

12.

001.

000.

121.

505.

8818

0.3

0.73

23.2

22.

002.

000.

121.

507.

9315

0.3

0.76

32.6

32.

003.

000.

121.

509.

6015

0.3

0.80

41.3

42.

004.

000.

121.

509.

9314

0.3

0.83

44.3

52.

501.

000.

121.

008.

8920

0.3

0.73

23.3

62.

502.

000.

121.

0010

.88

170.

30.

7328

.6

72.

503.

000.

121.

0011

.76

160.

30.

7531

.9

82.

504.

000.

121.

0011

.85

150.

30.

7833

.4

93.

001.

000.

120.

5014

.08

220.

30.

7318

.5

103.

002.

000.

120.

5014

.22

180.

30.

7318

.7

113.

003.

000.

120.

5014

.49

170.

30.

7319

.0

123.

004.

000.

120.

5014

.17

160.

30.

7519

.1

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Cal

cula

tion

of S

ettle

men

t (B

H 9

)

Settl

emen

t SC =

mv

H P

Proj

ect:-

Prop

osed

stru

ctur

esof

plan

tofA

dditi

onal

gas

proc

essi

ngfa

cilit

ies

proj

ect(

Phas

e4

)ofO

NG

Cat

Haz

ira,

Sura

t, L

& T

Ltd

She

et N

o.10

70

11-0

6-20

12

Page 21: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

of

Foot

ing

D

Wid

th o

f Fo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0p

(p+

p 0)/p

0fa

ctor

rela

ted

to

pore

pres

sure

para

met

er

Cor

rect

ion

for d

epth

Con

solid

atio

nSe

ttlem

ent S

cA

llow

able

Bea

ring

Pres

sure

mm

mgm

/ cc

mT

/ m2

T / m

2m

mT

/ m2

10.

152.

001.

002.

000.

821.

763.

005.

285.

942.

130.

70.

6625

24

20.

152.

002.

003.

150.

821.

763.

586.

293.

421.

540.

70.

7325

11

30.

152.

003.

003.

150.

821.

763.

586.

293.

071.

490.

70.

8025

7

40.

152.

004.

003.

150.

821.

763.

586.

292.

841.

450.

70.

8525

6

50.

152.

501.

002.

000.

821.

763.

506.

167.

172.

160.

70.

6525

29

60.

152.

502.

002.

650.

821.

763.

836.

734.

551.

680.

70.

7325

13

70.

152.

503.

002.

650.

821.

763.

836.

734.

361.

650.

70.

7525

9

80.

152.

504.

002.

150.

821.

763.

586.

294.

871.

770.

70.

8125

8

90.

153.

001.

002.

000.

821.

764.

007.

048.

412.

190.

70.

6325

34

100.

153.

002.

002.

150.

821.

764.

087.

176.

381.

890.

70.

7325

15

110.

153.

003.

002.

150.

821.

764.

087.

176.

381.

890.

70.

7325

12

120.

153.

004.

002.

150.

821.

764.

087.

175.

891.

820.

70.

7725

9

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Allo

wab

le B

earin

g Pr

essu

re fo

r 25

mm

Set

tlem

ent (

BH

4)

Settl

emen

t SC =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P

0 +

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

71

11-0

6-20

12

Page 22: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

of

Foot

ing

D

Wid

th o

f Fo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0p

(p+

p 0)/p

0fa

ctor

rela

ted

to

pore

pres

sure

para

met

er

Cor

rect

ion

for d

epth

Con

solid

atio

nSe

ttlem

ent S

cA

llow

able

Bea

ring

Pres

sure

mm

mgm

/ cc

mT

/ m2

T / m

2m

mT

/ m2

10.

182.

001.

002.

000.

911.

713.

005.

134.

791.

930.

70.

6625

19

20.

182.

002.

003.

150.

911.

713.

586.

112.

821.

460.

70.

7325

9

30.

182.

003.

003.

150.

911.

713.

586.

112.

541.

420.

70.

8025

6

40.

182.

004.

003.

150.

911.

713.

586.

112.

361.

390.

70.

8525

5

50.

182.

501.

002.

000.

911.

713.

505.

995.

781.

960.

70.

6525

23

60.

182.

502.

002.

650.

911.

713.

836.

543.

731.

570.

70.

7325

10

70.

182.

503.

002.

650.

911.

713.

836.

543.

581.

550.

70.

7525

7

80.

182.

504.

002.

150.

911.

713.

586.

113.

981.

650.

70.

8125

6

90.

183.

001.

002.

000.

911.

714.

006.

846.

761.

990.

70.

6325

27

100.

183.

002.

002.

150.

911.

714.

086.

975.

191.

740.

70.

7325

12

110.

183.

003.

002.

150.

911.

714.

086.

975.

191.

740.

70.

7325

10

120.

183.

004.

002.

150.

911.

714.

086.

974.

811.

690.

70.

7725

8

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Allo

wab

le B

earin

g Pr

essu

re fo

r 25

mm

Set

tlem

ent (

BH

5)

Settl

emen

t SC =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P

0 +

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

72

11-0

6-20

12

Page 23: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

of

Foot

ing

D

Wid

th o

f Fo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0p

(p+

p 0)/p

0fa

ctor

rela

ted

to

pore

pres

sure

para

met

er

Cor

rect

ion

for d

epth

Con

solid

atio

nSe

ttlem

ent S

cA

llow

able

Bea

ring

Pres

sure

mm

mgm

/ cc

mT

/ m2

T / m

2m

mT

/ m2

10.

292.

001.

002.

000.

921.

703.

005.

102.

601.

510.

70.

6625

.010

.4

20.

292.

002.

002.

000.

921.

703.

005.

102.

311.

450.

70.

7325

.05.

2

30.

292.

003.

002.

000.

921.

703.

005.

102.

081.

410.

70.

8025

.03.

7

40.

292.

004.

002.

000.

921.

703.

005.

101.

931.

380.

70.

8525

.03.

0

50.

292.

501.

001.

500.

921.

703.

255.

534.

181.

760.

70.

6525

.012

.8

60.

292.

502.

001.

500.

921.

703.

255.

533.

571.

650.

70.

7325

.06.

8

70.

292.

503.

001.

500.

921.

703.

255.

533.

421.

620.

70.

7525

.05.

3

80.

292.

504.

001.

500.

921.

703.

255.

533.

141.

570.

70.

8125

.04.

4

90.

293.

001.

001.

000.

921.

703.

505.

958.

102.

360.

70.

6325

.018

.2

100.

293.

002.

001.

000.

921.

703.

505.

956.

622.

110.

70.

7325

.010

.3

110.

293.

003.

001.

000.

921.

703.

505.

956.

622.

110.

70.

7325

.09.

0

120.

293.

004.

001.

000.

921.

703.

505.

956.

092.

020.

70.

7725

.07.

7

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Allo

wab

le B

earin

g Pr

essu

re fo

r 25

mm

Set

tlem

ent (

BH

6)

Settl

emen

t SC =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P

0 +

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

73

11-0

6-20

12

Page 24: Binder 9 with uploaded drawings and approved document

Sr. N

o.D

epth

of

Foot

ing

D

Wid

th o

f Fo

otin

g B

m

vH

pfa

ctor

rela

ted

to

pore

pres

sure

para

met

er

Cor

rect

ion

for

dept

h S

ettle

men

t Sc

Allo

wab

le

Bea

ring

Pres

sure

mm

mT

/ m2

mm

T / m

2

12.

001.

000.

121.

506.

350.

30.

7325

.019

22.

002.

000.

121.

506.

080.

30.

7625

.011

32.

003.

000.

121.

505.

810.

30.

8025

.09

42.

004.

000.

121.

505.

610.

30.

8325

.08

52.

501.

000.

121.

009.

520.

30.

7325

.021

62.

502.

000.

121.

009.

520.

30.

7325

.015

72.

503.

000.

121.

009.

210.

30.

7525

.013

82.

504.

000.

121.

008.

870.

30.

7825

.011

93.

001.

000.

120.

5019

.04

0.3

0.73

25.0

30

103.

002.

000.

120.

5019

.04

0.3

0.73

25.0

24

113.

003.

000.

120.

5019

.04

0.3

0.73

25.0

22

123.

004.

000.

120.

5018

.53

0.3

0.75

25.0

21

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Cal

cula

tion

of S

ettle

men

t (B

H 9

)

Settl

emen

t SC =

mv

H P

Proj

ect:-

Prop

osed

stru

ctur

esof

plan

tofA

dditi

onal

gas

proc

essi

ngfa

cilit

ies

proj

ect(

Phas

e4

)ofO

NG

Cat

Haz

ira,

Sura

t, L

& T

Ltd

She

et N

o.10

74

11-0

6-20

12

Page 25: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services.,Ahmedabad

NOTATIONS C Cohesion

Angle of internal f r ic t ion of soi l DS Disturbed Sample UDS Undisturbed Sample NMC Natural Moisture Content NP Non Plast ic Soi ls G Specif ic Gravity G Gravel Content M Si l t Content S Sand Content C Clay Content LL Liquid Limit PL Plast ic L imit PI Plast ic i ty Index Cc Compression Index K Coeff ic ient of Permeabi l i ty UCS Unconf ined Compression N SPT Value BH Bore Hole Suff ix The Number of Bore Holes Nc,Nq,N Bearing Capacity Factor Sc,Sq,S Shape Factors D Depth of foundat ion FS Factor of Safety Cv Coeff ic ient of consol idat ion UU Unconsol idated undrained t r iaxial test CU Consol idated undrained t r iaxial test CD Consol idated drained t r iaxial test GC Clayey Gravels GP Poorely Graded Gravels GW Wel l Graded Gravels SC Clayey Sand SM Si l ty Sand SW Wel Graded Sand SP Poorly Graded Sand CH Clays of High Plast ic i ty CI Clays of Intermediate Plast ic i ty CL Clays of Low Plast ic i ty MH Si l ts of High Plast ic i ty MI Si l ts of Intermediate Plast ic i ty ML Si l ts of Low Plast ic i ty

Sheet No.1075

11-06-2012

Page 26: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services.,Ahmedabad

REFERENCE Indian Standards Murthy V.N.S. Lambe T.W. Peck, R.S.Hanson W.E. Nayak, N.V. Kaniraj S.R. Alam Singh

IS 2720 Pt I I , I I I , IV, V, XII I , XXXI,XXVII,XXVIS1498,IS6403,IS 1904 Soi l Mechanics and Foundat ion engineering Dhanpat Rai and Sons Delhi Soi l test ing for Engineers Wi ley Easter Ltd. , New Delhi Foundat ion Engineering Asia Publ ishing House Foundat ion Engineering Manual Dhanpat Rai & Sons. Design Aids in soi l mechanics and Foundat ion Engineering Tata Mc Graw Hi l l Publ ishing Co. Ltd. Modern Geotechnical Eng. IBT Publ ishing & Distr ibutors Delhi .

Sheet No.1076

11-06-2012

Page 27: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

TABLE NO. – 1

RESULTS OF LABORATORY PERMEABILITY

Sr. No.

Bore Hole No.

Depth (m) Permeabil ity (mm/s)

1.

BH – 4 2.50

0.66 x 10- 6

2.

BH – 5 2.50

0.68 x 10- 6

3.

BH – 6 2.50

0.60 x 10- 6

4.

BH – 9 5.50

0.58 x 10- 6

( K K Thaker)

Sheet No.1077

11-06-2012

Page 28: Binder 9 with uploaded drawings and approved document

Sr. No. BH No. Depth (m) pH SO3 in 2:1 Water : Soil

Extract(mg/l)

Chlorides

1 BH 4 2.50 7.45 886 2013

2 BH 5 4.50 7.63 926 2003

3 BH 6 2.50 7.72 947 2014

4 BH 9 2.50 7.75 868 2045

Sr. No. Location pH Sulphate (SO3) (mg/l)

Chloride(mg/l)

Organic Inorganic

1 BH 4 7.65 Nil 905 1081 1036

2 BH 5 7.72 Nil 895 1015 1028

3 BH 6 7.53 Nil 907 1059 1053

4 BH 9 7.63 Nil 884 1083 1026

For KCT Consultancy Services

(K K Thaker)

Total Dissolved Solids

Table No. 2Results of Chemical Analysis of Soil

Table No. 3Results of Chemical Analysis of Ground Water

Sheet No.1078

11-06-2012

Page 29: Binder 9 with uploaded drawings and approved document

4

mgm

/ cc

%%

%%

%%

%%

%K

g/cm

2%

Kg/

cm2

Deg

ree

Kg/

cm2

%%

10.

00D

S-

10.6

4-

13

5442

5529

26-

--

CH

--

--

--

--

20.

50S

PT

--

-1

1047

4254

2826

--

-C

H-

--

-19

--

-

31.

50S

PT

--

-1

844

4754

2529

--

-C

H-

--

-16

--

-

42.

50U

DS

1.76

21.3

42.

642

646

4655

2629

80.

2654

.3C

H0.

399

-0.

15-

-0.

8245

.1

53.

00S

PT

--

-2

943

4657

3126

--

-C

H-

--

-8

--

-

64.

50S

PT

--

-2

1071

1751

3615

--

-M

H-

--

-2

--

-

75.

50U

DS

1.70

35.7

02.

642

7915

4N

PN

PN

P-

--

SM

-25

--

--

1.11

52.6

86.

00S

PT

--

-1

876

1550

3911

--

-M

H-

--

-10

--

-

97.

50S

PT

--

-0

972

1955

4114

--

-M

H-

--

-8

--

-

108.

50U

DS

1.76

22.0

62.

660

1679

550

428

--

-M

H-

28-

--

-0.

8445

.7

119.

00S

PT

--

-1

8313

3N

PN

PN

P-

--

SM

--

--

15-

--

1210

.50

SP

T-

--

082

144

NP

NP

NP

--

-S

M-

--

-19

--

-

1311

.50

DS

--

-1

8213

4N

PN

PN

P-

--

SM

--

--

--

--

1412

.00

SP

T-

--

083

143

NP

NP

NP

--

-S

M-

--

-22

--

-

1513

.50

SP

T-

--

180

154

NP

NP

NP

--

-S

M-

--

-28

--

-

1614

.50

DS

--

-2

7915

4N

PN

PN

P-

--

SM

--

--

--

--

1715

.00

SP

T-

--

082

153

NP

NP

NP

--

-S

M-

--

-41

--

-

1816

.50

SP

T-

--

482

122

21N

PN

P-

--

SM

--

--

59-

--

1917

.50

DS

--

-4

8212

220

NP

NP

--

-S

M-

--

--

--

-

2018

.00

SP

T-

--

133

3432

4029

11-

--

CI

--

--

> 10

0-

--

2120

.00

SP

T-

--

478

144

24N

PN

P-

--

SM

--

--

94-

--

Gravel

Sand

Type

of

Sam

ple

BH

No.

:-

Dep

th

Soil Classification

Proj

ect :

-

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

adR

ES

ULT

S O

F LA

BO

RA

TO

RY

TE

ST

Prop

osed

str

uctu

res

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

Gra

in S

ize

Ana

lysi

sFi

eld

Den

sity

Nat

ural

Moi

stur

eC

onte

nt

Specific Gravity

ShrinkageLimit

SPT N Value

Void Ratio

Silt

Clay

LiquidLimit

PlasticLimit

Shea

r Par

amet

er

SwellingPressure

Con

sist

ancy

lim

its

Porosity

Sr No

Rock Quality Designation

C

UnconfinedCompression

Test

Compression Index CC

Free Swell Index

PlasticityIndex

She

et N

o.10

79

11-0

6-20

12

Page 30: Binder 9 with uploaded drawings and approved document

5

mgm

/ cc

%%

%%

%%

%%

%K

g/cm

2%

Kg/

cm2

Deg

ree

Kg/

cm2

%%

10.

00D

S-

--

-

21.

50S

PT

--

-1

1342

4459

3029

--

-C

H-

--

-16

--

-

32.

50U

DS

1.71

23.2

42.

650

1044

4658

2929

70.

2246

.3C

H0.

4612

-0.

18-

-0.

9147

.6

43.

00S

PT

--

-1

1343

4355

2629

--

-C

H-

--

-4

--

-

54.

50S

PT

--

-0

8612

2N

PN

PN

P-

--

SM

--

--

6-

--

65.

50U

DS

1.76

31.5

42.

642

8412

2N

PN

PN

P-

--

SM

-26

--

--

0.97

49.3

76.

00S

PT

--

-0

1450

3653

4013

--

-M

H-

--

-9

--

-

87.

50S

PT

--

-6

7912

3N

PN

PN

P-

--

SM

--

--

27-

--

98.

50U

DS

1.95

28.4

32.

656

7912

3N

PN

PN

P-

--

SM

-32

--

--

0.75

42.7

109.

00S

PT

--

-6

7715

2N

PN

PN

P-

--

SM

--

--

30-

--

1110

.50

SP

T-

--

478

153

NP

NP

NP

--

-S

M-

--

-23

--

-

1211

.50

DS

--

-5

7814

3N

PN

PN

P-

--

SM

--

--

--

--

1312

.00

SP

T-

--

381

133

NP

NP

NP

--

-S

M-

--

-45

--

-

1413

.50

SP

T-

--

383

122

NP

NP

NP

--

-S

M-

--

-39

--

-

1514

.50

DS

--

-6

8012

2N

PN

PN

P-

--

SM

--

--

--

--

1615

.00

SP

T-

--

056

2420

2415

9-

--

SC

--

--

38-

--

1716

.50

SP

T-

--

283

123

NP

NP

NP

--

-S

M-

--

-80

--

-

1817

.50

DS

--

-0

8512

3N

PN

PN

P-

--

SM

--

--

--

--

1918

.00

SP

T-

--

083

152

NP

NP

NP

--

-S

M-

--

-92

--

-

2019

.50

SP

T-

--

030

3832

3530

5-

--

MI

--

--

77-

--

2120

.50

DS

--

-7

7614

3N

PN

PN

P-

--

SM

--

--

--

--

2221

.00

SP

T-

--

328

3732

3630

6-

--

MI

--

--

83-

--

2322

.50

SP

T-

--

1619

3233

3832

6-

--

MI

--

--

91-

--

2423

.50

UD

S2.

2623

.51

2.65

1225

3033

3629

7-

--

MI

0.10

36-

--

-0.

4531

.0

2525

.00

SP

T-

--

1525

3030

3631

5-

--

MI

--

--

> 10

0-

--

Fille

d up

Cla

y of

hig

h pl

astic

ity w

ith d

ebris

and

gra

vels

-

Gravel

Sand

Type

of

Sam

ple

BH

No.

:-

Dep

th

Soil Classification

Proj

ect :

-

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

adR

ES

ULT

S O

F LA

BO

RA

TO

RY

TE

ST

Prop

osed

str

uctu

res

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

Gra

in S

ize

Ana

lysi

sFi

eld

Den

sity

Nat

ural

Moi

stur

eC

onte

nt

Specific Gravity

ShrinkageLimit

SPT N Value

Void Ratio

Silt

Clay

LiquidLimit

Plastic Limit

Shea

r Par

amet

er

SwellingPressure

Con

sist

ancy

lim

its

Porosity

Sr No

Rock Quality Designation

C

UnconfinedCompression

Test

Compression Index CC

Free Swell Index

Plasticity Index

She

et N

o.10

80

11-0

6-20

12

Page 31: Binder 9 with uploaded drawings and approved document

6

mgm

/ cc

%%

%%

%%

%%

%K

g/cm

2%

Kg/

cm2

Deg

ree

Kg/

cm2

%%

10.

00D

S-

--

-

21.

50S

PT

--

-0

2539

3656

2729

7-

61.3

CH

--

--

18-

--

32.

50U

DS

1.70

23.4

02.

650

2437

3954

2628

80.

2152

.4C

H0.

242

-0.

29-

-0.

9248

.0

43.

00S

PT

--

-1

1943

3751

2625

--

-C

H-

--

-4

--

-

54.

50S

PT

--

-1

8610

3N

PN

PN

P-

--

SM

--

--

6-

--

65.

50D

S-

--

016

6420

5239

13-

--

MH

--

--

--

--

76.

00S

PT

--

-1

1867

1454

4014

--

-M

H-

--

-4

--

-

87.

50S

PT

--

-0

8214

4N

PN

PN

P-

--

SM

--

--

12-

--

98.

50U

DS

1.78

29.3

42.

671

8214

3N

PN

PN

P-

--

SM

-28

--

--

0.94

48.5

109.

00S

PT

--

-13

7112

4N

PN

PN

P-

--

SM

--

--

20-

--

1110

.50

SP

T-

--

1269

154

NP

NP

NP

--

-S

M-

--

-33

--

-

1211

.50

DS

--

-1

8710

2N

PN

PN

P-

--

SM

--

--

--

--

1312

.00

SP

T-

--

183

133

NP

NP

NP

--

-S

M-

--

-42

--

-

1413

.50

SP

T-

--

285

103

NP

NP

NP

--

-S

M-

--

-44

--

-

1514

.50

DS

--

-56

2216

6N

PN

PN

P-

--

GM

--

--

--

--

1615

.00

SP

T-

--

085

123

NP

NP

NP

--

-S

M-

--

-48

--

-

1716

.50

SP

T-

--

157

2418

2113

8-

--

SC

--

--

52-

--

1817

.50

UD

S1.

9921

.34

2.66

221

3839

5527

28-

--

CH

0.41

18-

0.11

--

0.62

38.3

1918

.00

SP

T-

--

126

3637

5122

29-

--

CH

--

--

51-

--

2020

.00

SP

T-

--

025

3936

5628

28-

--

CH

--

--

72-

--

Fille

d up

Cla

y of

hig

h pl

astic

ity w

ith d

ebris

and

gra

vels

-

Gravel

Sand

Type

of

Sam

ple

BH

No.

:-

Dep

th

Soil Classification

Proj

ect :

-

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

adR

ES

ULT

S O

F LA

BO

RA

TO

RY

TE

ST

Prop

osed

str

uctu

res

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

Gra

in S

ize

Ana

lysi

sFi

eld

Den

sity

Nat

ural

Moi

stur

eC

onte

nt

Specific Gravity

ShrinkageLimit

SPT N Value

Void Ratio

Silt

Clay

Liquid Limit

PlasticLimit

Shea

r Par

amet

er

Swelling Pressure

Con

sist

ancy

lim

its

Porosity

Sr No

Rock Quality Designation

C

Unconfined Compression

Test

Compression Index CC

Free Swell Index

PlasticityIndex

She

et N

o.10

81

11-0

6-20

12

Page 32: Binder 9 with uploaded drawings and approved document

9

mgm

/ cc

%%

%%

%%

%%

%K

g/cm

2%

Kg/

cm2

Deg

ree

Kg/

cm2

%%

10.

00D

S-

--

-

21.

50S

PT

--

-0

2238

4057

3027

--

-C

H-

--

-15

--

-

32.

50U

DS

1.76

26.5

72.

640

1248

4054

2727

70.

2853

.1C

H0.

3813

-0.

17-

-0.

9047

.3

43.

00S

PT

--

-2

1545

3858

2929

--

-C

H-

--

-8

--

-

54.

50S

PT

--

-0

8215

3N

PN

PN

P-

--

SM

--

--

13-

--

65.

50U

DS

1.86

31.0

52.

632

8113

4N

PN

PN

P-

--

SM

-29

--

--

0.85

46.0

76.

00S

PT

--

-2

8610

2N

PN

PN

P-

--

SM

--

--

21-

--

87.

50S

PT

--

-2

7915

4N

PN

PN

P-

--

SM

--

--

24-

--

98.

50U

DS

1.95

24.6

12.

642

8212

4N

PN

PN

P-

--

SM

-33

--

--

0.69

40.7

109.

00S

PT

--

-2

8014

4N

PN

PN

P-

--

SM

--

--

28-

--

1110

.50

SP

T-

--

1667

134

21N

PN

P-

--

SM

--

--

32-

--

1211

.50

DS

--

-5

7714

4N

PN

PN

P-

--

SM

--

--

--

--

1312

.00

SP

T-

--

384

103

NP

NP

NP

--

-S

M-

--

-44

--

-

1413

.50

SP

T-

--

577

153

NP

NP

NP

--

-S

M-

--

-43

--

-

1514

.50

DS

--

-15

6813

4N

PN

PN

P-

--

SM

--

--

--

--

1615

.00

SP

T-

--

5820

166

NP

NP

NP

--

-G

M-

--

-54

--

-

1716

.50

SP

T-

--

5619

196

NP

NP

NP

--

-G

M-

--

-64

--

-

1817

.50

DS

--

-16

4222

2029

209

--

-S

C-

--

--

--

-

1918

.00

SP

T-

--

1323

3133

3630

6-

--

MI

--

--

59-

--

2020

.00

SP

T-

--

225

4033

3832

6-

--

MI

--

--

94-

--

Fille

d up

Cla

yey

San

d w

ith d

ebris

and

gra

vels

-

Gravel

Sand

Type

of

Sam

ple

BH

No.

:-

Dep

th

Soil Classification

Proj

ect :

-

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

adR

ES

ULT

S O

F LA

BO

RA

TO

RY

TE

ST

Prop

osed

str

uctu

res

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

Gra

in S

ize

Ana

lysi

sFi

eld

Den

sity

Nat

ural

Moi

stur

eC

onte

nt

Specific Gravity

ShrinkageLimit

SPT N Value

Void Ratio

Silt

Clay

Liquid Limit

PlasticLimit

Shea

r Par

amet

er

Swelling Pressure

Con

sist

ancy

lim

its

Porosity

Sr No

Rock Quality Designation

C

Unconfined Compression

Test

Compression Index CC

Free Swell Index

PlasticityIndex

She

et N

o.10

82

11-0

6-20

12

Page 33: Binder 9 with uploaded drawings and approved document

She

et N

o.10

83

11-0

6-20

12

Page 34: Binder 9 with uploaded drawings and approved document

4N-365, E-102598.466m20.0 m

From To

m m m N 1 N 2 N 3 N0.00 0.00 0.00 0.50 DS - - - - - -0.50 0.50 0.50 1.50 SPT 6 9 10 19 - -1.001.50 1.50 1.50 2.50 SPT 5 6 10 16 - -2.002.50 2.50 2.50 3.00 UDS - - - - - -3.00 0.00 to 3.50 m 3.00 3.00 4.50 SPT 2 3 5 8 - -3.504.004.50 4.50 4.50 5.50 SPT 1 1 1 2 - -5.005.50 5.50 5.50 6.00 UDS - - - - - -

6.00 6.00 6.00 7.50 SPT 2 4 6 10 - -6.507.007.50 7.50 7.50 8.50 SPT 2 3 5 8 - -8.00 6.70 to 8.70 m8.50 8.50 8.50 9.00 UDS - - - - - -9.00 9.00 9.00 10.50 SPT 5 5 10 15 - -9.5010.0010.50 10.50 10.50 11.50 SPT 6 8 11 19 - -11.0011.50 11.50 11.50 12.00 DS - - - - - -12.00 8.70 to 12.60 m 12.00 12.00 13.50 SPT 7 9 13 22 - -12.5013.0013.50 13.50 13.50 14.50 SPT 12 13 15 28 - -14.0014.50 14.50 14.50 15.00 DS - - - - - -15.00 15.00 15.00 16.50 SPT 17 20 21 41 - -15.5016.00 12.60 to 16.00 m16.50

16.50 16.50 17.50 SPT 13 21 38 59 - -

17.0017.50 17.50 17.50 18.00 DS - - - - - -18.00 18.00 18.00 20.00 SPT 42 52 - >100 - -18.50 10cm19.0019.50

20.00 20.00 20.00 20.45 SPT 33 42 52 94 - -19.60 to 20.00 m

Rot

ary

Dril

ling

by m

ud c

ircul

atio

n

Not

Use

d Blackish, fine to medium grained, silty sand withoccational gravels (SM)

Blackish, fine to very fine grained, silt of highcompressibility with occational gravels (MH)

Blackish grey, fine to very fine grained, silty sand with occational gravels (SM) 5.15 to 6.70 m

Blackish grey, fine to very fine grained, silt ofhigh compressibility with occational gravels (MH)3.50 to 5.15m

Dark brownish, fine to very fine grained, siltyclays of high plasticity with occational gravels(CH)

Reddish brown, fine to coarse grained, silty sand with little plastic fines and litttel gravels (SM)

Dark brown,fine to very fine grained, sandy clays of intermediate plasticity with occational gravels(CI) 17.90 to 19.60 m

Dark brownish, fine to medium grained, siltysand with little plastic fines and little gravels (SM)16.00 to 17.90 m

Blackish, fine to medium grained, silty sand withoccational gravels (SM)

Core Reco-very (%)

RQD (%) Remarks

m

BORE LOG DATA SHEET

Method of Boring

Depth

Cas

ing

Not

atio

n

Soil DescriptionDepth ofSample

Drill RunType ofSample

SPT N Value/Penetration of S.S.S

Depth of Termination : Diameter of Bore : 150 mmDepth of Water Table : Encountered at m depth during investigation

Co-ordinates: Date of Completion: 07-07-10Reduced Level:

KCT Consultancy Services, AhmedabadProject : L & T , HAZIRA

Bore Hole No. : Date of commencement: 07-02-10

water table encountered at m depth during investigation

Fig. No.( )

Sheet No.1084

11-06-2012

Page 35: Binder 9 with uploaded drawings and approved document

5N-780, E-110099.423m25.0 m

From To

m m m N 1 N 2 N 3 N0.00

0.00 0.00 1.50 DS - - - - - -

0.501.00

1.50 1.50 1.50 2.50 SPT 4 7 9 16 - -2.002.50 2.50 2.50 3.00 UDS - - - - - -3.00 3.00 3.00 4.50 SPT 1 2 2 4 - -3.504.004.50 4.50 4.50 5.50 SPT 2 3 3 6 - -5.005.50 3.70 to 6.00 m 5.50 5.50 6.00 UDS - - - - - -6.00

6.00 6.00 7.50 SPT 4 4 5 9 - -

6.507.007.50 7.50 7.50 8.50 SPT 7 12 15 27 - -8.008.50 8.50 8.50 9.00 UDS - - - - - -9.00 9.00 9.00 10.50 SPT 10 14 16 30 - -9.5010.0010.50 10.50 10.50 11.50 SPT 9 11 12 23 - -11.0011.50 11.50 11.50 12.00 DS - - - - - -12.00 12.00 12.00 13.50 SPT 18 20 25 45 - -12.5013.0013.50 13.50 13.50 14.50 SPT 11 17 22 39 - -14.00 7.25 to 14.95 m14.50 14.50 14.50 15.00 DS - - - - - -15.00 15.00 15.00 16.50 SPT 10 18 20 38 - -15.5016.0016.50 16.50 16.50 17.50 SPT 20 35 45 80 - -17.0017.50 17.50 17.50 18.00 DS - - - - - -18.00 18.00 18.00 19.50 SPT 21 40 52 92 - -18.50 15.30 to 19.20 m19.0019.50

19.50 19.50 20.50 SPT 18 32 45 77 - -

20.0020.50

Dark brownish, fine to coarse grained, siltysand with some gravels (SM) 20.50 to 21.00 m 20.50 20.50 21.00 DS - - - - - -

21.00 21.00 21.00 22.50 SPT 20 35 48 83 - -

21.5022.0022.50 22.50 22.50 23.50 SPT 23 41 50 91 - -23.0023.50 23.50 23.50 25.00 UDS - - - - - -24.0024.5025.00 25.00 25.00 25.50 SPT 20 65 40 >100 - -

22.10 to 25.00 m 5cm

Co-ordinates: Date of Completion: 19/7/2010

Diameter of Bore : 150 mm

KCT Consultancy Services, AhmedabadProject : L & T , HAZIRA

Bore Hole No. : Date of commencement: 15/7/2010

Soil DescriptionDepth ofSample

Drill Run

Reduced Level:Depth of Termination :

SPT N Value/Penetration of S.S.SCore Reco-very (%)

RQD (%)

Depth of Water Table : Encountered at 3.40m depth during investigationBORE LOG DATA SHEET

Method of Boring

DepthC

asin

g

Not

atio

n

Remarks

m

Rot

ary

Dril

ling

by m

ud c

ircul

atio

n

Not

Use

d

Dark brownish, fine to coarse grained, silt ofintermediate compressibility with much gravels(MI)

Dark brownish, fine to medium grained, silt ofintermediate compressibility with little gravels(MI) 21.00 to 22.10 m

Dark brownish, fine to very fine grained, silt ofintermediate compressibility with occationalgravels(MI) 19.20 to 20.50 m

Blackish grey, fine to medium grained, sisltysand with little gravels (SM)

Type ofSample

Dark brownish, fine to very fine grained, siltyclays of high plasticity with occational gravels(CH) 2.20 to 3.70 m

Dark brownish, fine to very fine grained, siltyclays of high plasticity with occational gravelsand occational fine sand (CH) 0.70 to 2.20 m

Dark brownish, fine to medium grained, filledup clayey sand with debries 0.00 to 0.70 m

Blackish brown, fine to very fine grained, siltysand with occational gravels (SM)

Blackish grey, fine to very fine grained, silt ofhigh compressibility with occational gravels(MH) 6.00 to 7.25 m

Blackish grey, fine to coarse grained, clayeysand (SC) 14.95 to 15.30 m

Blackish grey, fine to very fine grained, siltysand with occational gravels (SM)

water table encountered at 340m depth during

Fig. No.( )

Sheet No.1085

11-06-2012

Page 36: Binder 9 with uploaded drawings and approved document

6N-799, E-117099.620m20.0 m

From To

m m m N 1 N 2 N 3 N0.00

0.00 0.00 1.50 DS - - - - - -

0.501.001.50 1.50 1.50 2.50 SPT 5 8 10 18 - -2.002.50 2.50 2.50 3.00 UDS - - - - - -3.00 0.65 to 3.60 m 3.00 3.00 4.50 SPT 1 2 2 4 - -3.504.004.50 4.50 4.50 5.50 SPT 2 3 3 6 - -5.005.50

5.50 5.50 6.00 DS - - - - - -

6.00 6.00 6.00 7.50 SPT 2 2 2 4 - -6.507.007.50 7.50 7.50 8.50 SPT 4 5 7 12 - -8.008.50 8.50 8.50 9.00 UDS - - - - - -9.00 9.00 9.00 10.50 SPT 7 9 11 20 - -9.5010.0010.50 10.50 10.50 11.50 SPT 10 15 18 33 - -11.0011.50 11.50 11.50 12.00 DS - - - - - -12.00 12.00 12.00 13.50 SPT 12 19 23 42 - -12.5013.0013.50 13.50 13.50 14.50 SPT 12 20 24 44 - -14.00

14.50 14.50 14.50 15.00 DS - - - - - -15.00 Brownish grey, fine to very fine grained, silty

sand with occational gravels (SM) 14.80 to15.50 m

15.00 15.00 16.50 SPT 15 22 26 48 - -

15.5016.0016.50 16.50 16.50 17.50 SPT 17 24 28 52 - -17.0017.50 17.50 17.50 18.00 UDS - - - - - -18.00 18.00 18.00 20.00 SPT 15 21 30 51 - -18.5019.0019.5020.00 20.00 20.00 20.45 SPT 23 32 40 72 - -

17.45 to 20.00 m

KCT Consultancy Services, AhmedabadProject : L & T , HAZIRA

Bore Hole No. : Date of commencement: 19/7/2010Co-ordinates: Date of Completion: 20/7/2010

Reduced Level:Depth of Termination : Diameter of Bore : 150 mmDepth of Water Table : Encountered at 3.60m depth during investigation

Method of Boring

DepthC

asin

g

Not

atio

n Core Reco-very (%)

RQD (%) Remarks

m

Soil DescriptionDepth ofSample

Drill RunType ofSample

SPT N Value/Penetration of S.S.S

Rot

ary

Dril

ling

by m

ud c

ircul

atio

n

Not

Use

d

Dark brownish, fine to very fine grained, siltyclays of high plasticity with occationalgravels(CH)

Brownish grey, fine to very fine grained, clayeysand with little plastic fines and occationalgravels (SC) 15.50 to 17.45 m

Dark brownish with whitish grey coarse sand,fine to coarse grained, silty sand with somegravels (SM) 12.60 to 14.00 m

Blackish, fine to very fine grained, silt of highcompressibility with occational gravels(MH)5.20 to 6.60 m

Blackish brown, fine to very fine grained, siltysand with occational gravels (SM) 3.60 to 5.20m

Blackish brown, fine to very fine grained, siltyclays of high plasticity with occational gravelsand some fine sand (CH)

BORE LOG DATA SHEET

Brownish, coarse grained, silty gravels (GM)14.00 to 14.80 m

Blackish brown, fine to very fine grained, filledup silty clays of high plasticity with occationalgravels and some fine sand with debries 0.00 to 0.65 m

Blackish, fine to very fine grained, silty sandwith occational gravels(SM) 6.60 to 8.90m

Blackish, fine to very fine grained, silty sandwith much gravels(SM) 8.90 to 10.70 m

Blackish, fine to very fine grained, silty sandwith occational gravels(SM) 10.70 to 12.60 m

water table encountered at 3.60m depth during

Fig. No.( )

Sheet No.1086

11-06-2012

Page 37: Binder 9 with uploaded drawings and approved document

9N-1095, E-175099.232m20.0 m

From To

m m m N 1 N 2 N 3 N0.00

0.00 0.00 1.50 DS - - - - - -

0.501.001.50 1.50 1.50 2.50 SPT 4 7 8 15 - -2.002.50 2.50 2.50 3.00 UDS - - - - - -3.00 3.00 3.00 4.50 SPT 5 3 5 8 - -3.504.004.50 4.50 4.50 5.50 SPT 4 6 7 13 - -5.005.50 5.50 5.50 6.00 UDS - - - - - -6.00 6.00 6.00 7.50 SPT 7 9 12 21 - -6.507.007.50 7.50 7.50 8.50 SPT 6 10 14 24 - -8.008.50 8.50 8.50 9.00 UDS - - - - - -9.00 9.00 9.00 10.50 SPT 5 14 14 28 - -9.5010.00 5.95 to 10.50 m10.50

10.50 10.50 11.50 SPT 8 15 17 32 - -

11.0011.50 11.50 11.50 12.00 DS - - - - - -12.00 12.00 12.00 13.50 SPT 10 18 22 44 - -12.5013.0013.50 11.35 to 14.10 m 13.50 13.50 14.50 SPT 11 18 25 43 - -14.00

14.50 14.50 14.50 15.00 DS - - - - - -15.00 15.00 15.00 16.50 SPT 15 24 30 54 - -15.5016.0016.50 15.00 to 17.05 m 16.50 16.50 17.50 SPT 18 30 34 64 - -17.00

17.50 17.50 17.50 18.00 DS - - - - - -18.00 18.00 18.00 20.00 SPT 15 26 33 59 - -18.5019.0019.5020.00 20.00 20.00 20.45 SPT 16 46 48 94 - -

18.00 to 20.00 m

KCT Consultancy Services, AhmedabadProject : L & T , HAZIRA

Bore Hole No. : Date of commencement: 07-12-10Co-ordinates: Date of Completion: 13/7/2010

Reduced Level:Depth of Termination : Diameter of Bore : 150 mmDepth of Water Table : Encountered at 3.50m depth during investigation

BORE LOG DATA SHEET

Method of Boring

Depth

Cas

ing

Not

atio

n

Soil DescriptionDepth ofSample

Drill RunType ofSample

SPT N Value/Penetration of S.S.SCore Reco-very (%)

RQD (%) Remarks

m

Rot

ary

Dril

ling

by m

ud c

ircul

atio

n

Not

Use

d

Blackish, coarse grained, silty gravels (GM)

Brownish, fine to coarse grained, clayey sandwith much gravels (SC) 17.05 to 18.00 m

Dark brownish, fine to medium grained, silt ofintermediate compressibility with occationalgravels (MI)

Blackish, fine to very fine grained, filled upclayey sand with debries 0.00 to 0.70 m

Blackish, fine to very fine grained, silty clays ofhigh plasticity with occational gravels (CH) 0.70 to 3.45 m

Backish, fine to very fine grained, silty sand withoccational gravels (SM) 3.45 to 5.95 m

Blackish brown, fine to very fine grained, siltysand with occational gravels (SM)

Blackish brown, fine to coarse grained, siltysand with little plastic fines and much gravels(SM) 10.50 to 11.35 m

Blackish brown, fine to medium grained, siltysand with little gravels (SM)

Dark brownish and slightly blackish, fine tocoarse grained, silty sand with much gravels(SM) 14.10 to 15.00 m

water table encountered at 3.50m depth during

Fig. No.( )

Sheet No.1087

11-06-2012

Page 38: Binder 9 with uploaded drawings and approved document

TerminologyCu -C - = 0.50 X Cu

C - = 1.73 X CuC - = 0.75 X Cu

G -- 0.4

E -fnz -

-

21.6 0.09

= 1406.25 kg= 37.0 kg= Mass of block + mass of vibrator =1443.25 kg= 9.81 m/sec2

1 (N 789, E 1087 )

Size of the block = 0.75 m wide, 1.00 m long and 0.75 m deepData

Calculations

Mass of the vibratorTotal vibrating mass (M)Acceleration due to gravity (g)

Coefficient of elastic uniform shear in kg / cm3

Coefficient of elastic non uniform compression in kg / cm3

Coefficient of elastic non uniform shear in kg / cm3

Results of Block Vibration Test(As per IS : 5249, 1992, reaffirmed 1995)

Project :Proposed structures of plant of Additional gas processing facilities project (Phase 4 )of ONGC at Hazira, Surat, L & T Ltd

Coefficient of elastic uniform compression in kg / cm3

Test No.

Depth of Conducting testBase Area of the Block (A1)Mass of the block

= 2.50 m from EGL= 0.75 sq. m

Damping coefficient

The above coefficients are reported for foundation contact area, A of 10.0 m2 (1,00,000cm2) or more

4 X 2 X fnz2 X M / (A1 X g)} X 10-6 kg / cm3

Modulus of rigidity of strata in Kg / cm2, G = Cu X A X (1 - ) / 2.13Poisson's ratio = for this particular situation

Coefficient of elastic uniform compression in kg / cm3 for block of size 0.75m wide,1.00m long and 0.75m deep= Cu / Cu1 -

Modulus of elasticity of strata in kg / cm2 = G X 2 X (1 + )Resonance frequency of foundation block – soil system in cycles / sec

Modulus of elasticity of strata E= 88.2* 2 * (1 + 0.40) = 246.9 kg/sq. cm

cycles / sec and = From chart between amp v/s. freq fnz =

Coefficient of elastic non – uniform shear C = 0.75*0.99 = 0.74 kg/cu.cmModulus of rigidity of strata G = 0.99 * 100000* (1.0 – 0.40) / 2.13 = 88.2 kg/sq.cm

Coefficient of elastic uniform shear C = 0.5*0.99 = 0.49 kg/cu.cmCoefficient of elastic non–uniform compression C = 1.73*0.99 = 1.71 kg/cu.cm

Coefficient of Elastic uniform compression

Cu1 = {4 * 2*21.62*1443.25 / (0.75 * 9.81)} * 10-6 = 3.61 kg/cu.cmCu = 3.61 * 0.75/10.0 = 0.99 kg/cu.cm

Sheet No.1088

11-06-2012

Page 39: Binder 9 with uploaded drawings and approved document

0.270 0.09

0.191

19.7

23.7

21.6f nz =

damping coefficientAmax =

A max / sqrt ( 2 ) =

f 1 =

f 2 =

Response Curve (Block Vibration Test No. 1 Inside Plant Area )

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0 5 10 15 20 25 30 35

Frequency (cycles / sec)

Am

plitu

de (1

0 -5

mm

)

= f 2 - f 1 / 2 fnz = 0.09

A max / ( 2 ) 0.5 = 0.049f1 f2 fnz

Sheet No.1089

11-06-2012

Page 40: Binder 9 with uploaded drawings and approved document

= =

S =R =V = =

1 4.542 7.473 8.774 10.335 11.216 12.857 19.038 18.819 18.69

10 18.49

12.5712.4412.57

N - S E - W

11.3112.5714.3313.19

Resistivity in m

5.227.929.42

0.300.250.220.20

0.500.450.400.38

43.1044.2344.1142.73

12.8214.8315.7118.10

0.980.880.780.68

0.680.590.500.48

Resistence Observed in

0.990.88

Resistivity in m

6.2211.06

Resistence Observed in

0.830.63

KCT Consultancy ServicesRESULTS OF ELECTRICAL RESISTIVITY

( IS : 3043, 1987 )

Average Resistivity ( - m )

Where

ERT No. :Name of Project :

Battery Condition :Climatic Condition :

3Proposed structures of plant of Additional gas processing facilities project (Phase4) of ONGC at Hazira, Surat, L&T Ltd (Inside Plant area)GoodHumid and moderately hot

Resistivity at given depth = 2 S R

Voltage Drop between inner electrodes in VoltCurrent applied in outer electrodes in Amp.

Direction

Resistivity in ohm - m ( m )Value of pi - 22 / 7 Electrode Spacing ( equal to the depth at which resistivity is determined ) in mV / in ohm (

Spacing of Electrode in (

m )

Average Reistivity V/S. Depth

1

2

3

4

5

6

7

8

9

10

0.00 5.00 10.00 15.00 20.00 25.00

Average Resistivity in - m

Dep

th in

m

( K K Thaker ) ( )

Sheet No.1090

11-06-2012

Page 41: Binder 9 with uploaded drawings and approved document

LARSEN & TOUBRO LIMITED E&C DIVISION

GEOTECHNICAL INVESTIGATION REPORT – INSIDE

AREA

DOCUMENT NO. A067-LT-00-CV-04-RP-0004

PROJECT :Additional Gas Processing Facilities (Phase-IV)

REVISION : 01

CUSTOMER : ONGC,HAZIRA

Sheet No.1091

11-06-2012

Page 42: Binder 9 with uploaded drawings and approved document

Sheet No.1092

11-06-2012

Page 43: Binder 9 with uploaded drawings and approved document

ProjectSpreadsheets to BS 8110etc

Client Advisory Group Made by Date Page Location Grid line 1 rc 19-Nov-2015 101

RETAINING WALL design to BS 8110:1997, BS 8002:1994. BS 8004:1986 etc.Checked Revision Job No

Originated from 'RCC62.xls' on CD © 1999 BCA for RCC chg R68

IDEALISED STRUCTURE and FORCE DIAGRAMS DESIGN STATUS: VALID

WARNING :

Passive pressure should

only be considered if it

can be guaranteed that

there will be no future

excavation in front of

the wall.

DIMENSIONS (mm)

H = 3200 B = 2750 Tw = 250

Hw = 100 BI = 1000 Tb = 400

Hp = 200 BN = 0 TN = 0

Hn = 0

MATERIAL PROPERTIES

fcu = 35 N/mm² gm = 1.5 concrete

fy = 460 N/mm² gm = 1.05 steel

cover to tension steel = 50 mm

Max allowable design surface crack width (W) = 0.3 mm

Concrete density = 24 kN/m³

SOIL PROPERTIES Wall Geometry

Design angle of int'l friction of retained mat'l (Ø) = 30 degree

Design cohesion of retained mat'l (C ) = 0 kN/m² (Only granular backfil considered, "C" = zero)

Density of retained mat'l (q ) = 20 kN/m³

Submerged Density of retained mat'l (qs ) = 13.33 kN/m³ [default=2/3*q (only apply when Hw >0) ] =13.33

Design angle of int'l friction of base mat'l (Øb) = 20 degree ASSUMPTIONS

Design cohesion of base material (Cb ) = 10 kN/m² a) Wall friction is zero

Density of base material (qb ) = 10 kN/m³ b) Minimum active earth pressure = 0.25qH

Allowable gross ground bearing pressure (GBP) = 200 kN/m² c) Granular backfill

LOADINGS Surcharge load -- live (SQK) = 10 kN/m² e)Does not include effect of seepage of ground

Surcharge load -- dead (SGK) = 10 water beneath the wall.

Line load -- live (LQK) = 15 kN/m f)Does not include deflection check of wall due to

Line load -- dead (LGK) = 20 kN/m lateral earth pressures

Distance of line load from wall (X) = 1000 mm h) Design not intended for walls over 3.0 m high

LATERAL FORCES (unfactored) Ka = 0.33 [ default ka = (1-SIN Ø)/(1+SIN Ø) ] =0.33

Kp = 2.04 [ default kp = (1+SIN Øb)/(1-SIN Øb) ] =2.04

Kpc = 2.86 [ default kpc = 2kp0.5

] = 2.86

Kac = 1.15 [ 2ka0.5

]

Force Lever arm Moment about TOE gf Fult Mult

(kN) (m) (kNm) (kN) (kNm)

PE = 34.12 LE = 1.067 36.41 1.40 47.77 50.97

PS(GK) = 10.67 LS = 1.60 17.07 1.40 14.93 23.89

PS(QK) = 10.67 LS = 1.60 17.07 1.60 17.07 27.31

PL(GK) = 6.67 LL = 2.36 15.74 1.40 9.33 22.03

PL(QK) = 5.00 LL = 2.36 11.80 1.60 8.00 18.89

PW = 0.05 LW = 0.03 0.00 1.40 0.07 0.00

Total 67.17 98.09 97.17 143.10

PP = -6.12 (LP-HN) = 0.10 -0.60 1.00 -6.12 -0.60

-

REINFORCED CONCRETE COUNCIL

d)Does not include check of rotational slide/slope failure

S u r c h a r g e S , S i n k N / mG K Q K2

L i n e L o a d L , L i n k N / mG K Q K

X

B 1

B N T N

T W

B

HW

Hn

Tb

LP

HP

LL

LS

LW

H

LE

W A T E R

Page 44: Binder 9 with uploaded drawings and approved document

BEAM DEFLECTION FORMULAE

BEAM TYPE SLOPE AT FREE END DEFLECTION AT ANY SECTION IN TERMS OF x MAXIMUM DEFLECTION1. Cantilever Beam – Concentrated load P at the free end

2

2PlEI

θ = ( )2

36Pxy l xEI

= − 3

max 3PlEI

δ =

2. Cantilever Beam – Concentrated load P at any point

2

2Pa

EIθ =

( )2

3 for 06Pxy a x x aEI

= − < <

( )2

3 for6Pay x a a x l

EI= − < <

( )2

max 36Pa l a

EIδ = −

3. Cantilever Beam – Uniformly distributed load ω (N/m)

3

6lEIω

θ = ( )2

2 26 424

xy x l lxEI

ω= + −

4

max 8lEIω

δ =

4. Cantilever Beam – Uniformly varying load: Maximum intensity ωo (N/m)

3o

24lEI

ωθ = ( )

23 2 2 3o 10 10 5

120xy l l x lx xlEI

ω= − + −

4o

max 30lEI

ωδ =

5. Cantilever Beam – Couple moment M at the free end

MlEI

θ = 2

2Mxy

EI=

2

max 2Ml

EIδ =

Page 45: Binder 9 with uploaded drawings and approved document

BEAM DEFLECTION FORMULAS

BEAM TYPE SLOPE AT ENDS DEFLECTION AT ANY SECTION IN TERMS OF x MAXIMUM AND CENTER DEFLECTION

6. Beam Simply Supported at Ends – Concentrated load P at the center

2

1 2 16Pl

EIθ = θ =

223 for 0

12 4 2Px l ly x xEI

⎛ ⎞= − < <⎜ ⎟

⎝ ⎠

3

max 48Pl

EIδ =

7. Beam Simply Supported at Ends – Concentrated load P at any point

2 2

1( )6

Pb l blEI−

θ =

2(2 )

6Pab l b

lEI−

θ =

( )2 2 2 for 06Pbxy l x b x alEI

= − − < <

( ) ( )3 2 2 3

6for

Pb ly x a l b x xlEI b

a x l

⎡ ⎤= − + − −⎢ ⎥⎣ ⎦< <

( )3 22 2

max 9 3

Pb l b

lEI

−δ = at ( )2 2 3x l b= −

( )2 2 at the center, if 3 448

Pb l bEI

δ = − a b>

8. Beam Simply Supported at Ends – Uniformly distributed load ω (N/m)

3

1 2 24lEI

ωθ = θ = ( )3 2 32

24xy l lx xEI

ω= − +

4

max5

384lEI

ωδ =

9. Beam Simply Supported at Ends – Couple moment M at the right end

1 6MlEI

θ =

2 3MlEI

θ =

2

216Mlx xy

EI l⎛ ⎞

= −⎜ ⎟⎝ ⎠

2

max 9 3Ml

EIδ = at

3lx =

2

16Ml

EIδ = at the center

10. Beam Simply Supported at Ends – Uniformly varying load: Maximum intensity ωo (N/m)

3o

17360

lEI

ωθ =

3o

2 45lEI

ωθ =

( )4 2 2 4o 7 10 3360

xy l l x xlEI

ω= − +

4o

max 0.00652 lEIω

δ = at 0.519x l=

4o0.00651 l

EIω

δ = at the center

Page 46: Binder 9 with uploaded drawings and approved document

123

Page 47: Binder 9 with uploaded drawings and approved document

123

Page 48: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 49: Binder 9 with uploaded drawings and approved document

123

Page 50: Binder 9 with uploaded drawings and approved document

123

Page 51: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 52: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 53: Binder 9 with uploaded drawings and approved document

123

Page 54: Binder 9 with uploaded drawings and approved document

123

Page 55: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 56: Binder 9 with uploaded drawings and approved document

123

Page 57: Binder 9 with uploaded drawings and approved document

123

Page 58: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 59: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 60: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 61: Binder 9 with uploaded drawings and approved document

123

Page 62: Binder 9 with uploaded drawings and approved document

123

Page 63: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 64: Binder 9 with uploaded drawings and approved document

123

Page 65: Binder 9 with uploaded drawings and approved document

123

Page 66: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 67: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 68: Binder 9 with uploaded drawings and approved document

123

Page 69: Binder 9 with uploaded drawings and approved document

123

Page 70: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 71: Binder 9 with uploaded drawings and approved document

123

Page 72: Binder 9 with uploaded drawings and approved document

123

Page 73: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 74: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 75: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 76: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 77: Binder 9 with uploaded drawings and approved document

123

Page 78: Binder 9 with uploaded drawings and approved document

123

Page 79: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 80: Binder 9 with uploaded drawings and approved document

123

Page 81: Binder 9 with uploaded drawings and approved document

123

Page 82: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 83: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 84: Binder 9 with uploaded drawings and approved document

123

Page 85: Binder 9 with uploaded drawings and approved document

123

Page 86: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 87: Binder 9 with uploaded drawings and approved document

123

Page 88: Binder 9 with uploaded drawings and approved document

123

Page 89: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 90: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 91: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 92: Binder 9 with uploaded drawings and approved document

123

Page 93: Binder 9 with uploaded drawings and approved document

123

Page 94: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 95: Binder 9 with uploaded drawings and approved document

123

Page 96: Binder 9 with uploaded drawings and approved document

123

Page 97: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 98: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 99: Binder 9 with uploaded drawings and approved document

123

Page 100: Binder 9 with uploaded drawings and approved document

123

Page 101: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 102: Binder 9 with uploaded drawings and approved document

123

Page 103: Binder 9 with uploaded drawings and approved document

123

Page 104: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 105: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 106: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 107: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 108: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 109: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 110: Binder 9 with uploaded drawings and approved document

ProjectSpreadsheets to BS 8110etc

Client Advisory Group Made by Date Page Location Grid line 1 rc 19-Nov-2015 101

RETAINING WALL design to BS 8110:1997, BS 8002:1994. BS 8004:1986 etc.Checked Revision Job No

Originated from 'RCC62.xls' on CD © 1999 BCA for RCC chg R68

IDEALISED STRUCTURE and FORCE DIAGRAMS DESIGN STATUS: VALID

WARNING :

Passive pressure should

only be considered if it

can be guaranteed that

there will be no future

excavation in front of

the wall.

DIMENSIONS (mm)

H = 3200 B = 2750 Tw = 250

Hw = 100 BI = 1000 Tb = 400

Hp = 200 BN = 0 TN = 0

Hn = 0

MATERIAL PROPERTIES

fcu = 35 N/mm² gm = 1.5 concrete

fy = 460 N/mm² gm = 1.05 steel

cover to tension steel = 50 mm

Max allowable design surface crack width (W) = 0.3 mm

Concrete density = 24 kN/m³

SOIL PROPERTIES Wall Geometry

Design angle of int'l friction of retained mat'l (Ø) = 30 degree

Design cohesion of retained mat'l (C ) = 0 kN/m² (Only granular backfil considered, "C" = zero)

Density of retained mat'l (q ) = 20 kN/m³

Submerged Density of retained mat'l (qs ) = 13.33 kN/m³ [default=2/3*q (only apply when Hw >0) ] =13.33

Design angle of int'l friction of base mat'l (Øb) = 20 degree ASSUMPTIONS

Design cohesion of base material (Cb ) = 10 kN/m² a) Wall friction is zero

Density of base material (qb ) = 10 kN/m³ b) Minimum active earth pressure = 0.25qH

Allowable gross ground bearing pressure (GBP) = 200 kN/m² c) Granular backfill

LOADINGS Surcharge load -- live (SQK) = 10 kN/m² e)Does not include effect of seepage of ground

Surcharge load -- dead (SGK) = 10 water beneath the wall.

Line load -- live (LQK) = 15 kN/m f)Does not include deflection check of wall due to

Line load -- dead (LGK) = 20 kN/m lateral earth pressures

Distance of line load from wall (X) = 1000 mm h) Design not intended for walls over 3.0 m high

LATERAL FORCES (unfactored) Ka = 0.33 [ default ka = (1-SIN Ø)/(1+SIN Ø) ] =0.33

Kp = 2.04 [ default kp = (1+SIN Øb)/(1-SIN Øb) ] =2.04

Kpc = 2.86 [ default kpc = 2kp0.5

] = 2.86

Kac = 1.15 [ 2ka0.5

]

Force Lever arm Moment about TOE gf Fult Mult

(kN) (m) (kNm) (kN) (kNm)

PE = 34.12 LE = 1.067 36.41 1.40 47.77 50.97

PS(GK) = 10.67 LS = 1.60 17.07 1.40 14.93 23.89

PS(QK) = 10.67 LS = 1.60 17.07 1.60 17.07 27.31

PL(GK) = 6.67 LL = 2.36 15.74 1.40 9.33 22.03

PL(QK) = 5.00 LL = 2.36 11.80 1.60 8.00 18.89

PW = 0.05 LW = 0.03 0.00 1.40 0.07 0.00

Total 67.17 98.09 97.17 143.10

PP = -6.12 (LP-HN) = 0.10 -0.60 1.00 -6.12 -0.60

-

REINFORCED CONCRETE COUNCIL

d)Does not include check of rotational slide/slope failure

S u r c h a r g e S , S i n k N / mG K Q K2

L i n e L o a d L , L i n k N / mG K Q K

X

B 1

B N T N

T W

B

HW

Hn

Tb

LP

HP

LL

LS

LW

H

LE

W A T E R

Page 111: Binder 9 with uploaded drawings and approved document

123

Page 112: Binder 9 with uploaded drawings and approved document

PILE BEARING CAPACITY CALCULATION BASED ON S.P.T. VALUE

------------------ ------------------

Project Name :

Location :

Borehole No. : BH-1

Date :

------------------ ------------------

MAYERHOF Formula : K1 K2

Skin, Ps = K1 x Nav x As SAND 2.0 400

Bearing, Pb = K2 x Nb x Ab SILT 2.5 250

Ult. Load, Pu = Ps + Pb CLAY 3.0 100

All. Load, Pa = Ps/Fs + Pb/Fb

Factor of safety : Skin, Fs = 2

Bearing, Fb = 3

------------------ ------------------

To calculate allowable soil bearing capacity :

Pile used : Type : s

(c = circular) Width, b = 0.4 m Perimeter: 1.600

(s = square) (= dia. for type c) Ab: 0.160

Qa(conc): 1800

========== ========== ====== ========== ========== ============ =======================

Depth Soil SPT Skin Total Base Working Load

Type N As Fric Skin Load Fs = 2.0 Fb = 3

(m) (m²) (kN) (kN) (kN) (KN)

------------------ ------------------ ---------- ------------------ ------------------ -------------------- ---------------------------------------

0.0 SAND 0 0.0 0.0 0.0 0.0 0.0

1.5 SAND 11 2.4 52.8 52.8 704.0 261.1

3.0 SAND 12 2.4 57.6 110.4 768.0 311.2

4.5 SAND 15 2.4 72.0 182.4 960.0 411.2

6.0 SILT 17 2.4 102.0 284.4 680.0 368.9

7.5 SILT 19 2.4 114.0 398.4 760.0 452.5

9.0 SILT 19 2.4 114.0 512.4 760.0 509.5

10.5 SILT 17 2.4 102.0 614.4 680.0 533.9

12.0 SILT 19 2.4 114.0 728.4 760.0 617.5

13.5 SILT 11 2.4 66.0 794.4 440.0 543.9

15.0 SILT 18 2.4 108.0 902.4 720.0 691.2

16.5 SILT 17 2.4 102.0 1,004.4 680.0 728.9

18.0 SILT 19 2.4 114.0 1,118.4 760.0 812.5

19.5 SILT 20 2.4 120.0 1,238.4 800.0 885.9

21.0 SILT 18 2.4 108.0 1,346.4 720.0 913.2

22.5 SILT 14 2.4 84.0 1,430.4 560.0 901.9

24.0 SILT 0 2.4 0.0 1,430.4 0.0 715.2

25.5 SILT 22 2.4 132.0 1,562.4 880.0 1,074.5

27.0 SILT 20 2.4 120.0 1,682.4 800.0 1,107.9

28.5 SILT 20 2.4 120.0 1,802.4 800.0 1,167.9

30.0 SILT 22 2.4 132.0 1,934.4 880.0 1,260.5

31.5 SILT 25 2.4 150.0 2,084.4 1,000.0 1,375.5

33.0 SILT 23 2.4 138.0 2,222.4 920.0 1,417.9

34.5 SILT 23 2.4 138.0 2,360.4 920.0 1,486.9

36.0 SILT 24 2.4 144.0 2,504.4 960.0 1,572.2

37.5 SILT 23 2.4 138.0 2,642.4 920.0 1,627.9

39.0 SILT 25 2.4 150.0 2,792.4 1,000.0 1,729.5

40.5 SILT 26 2.4 156.0 2,948.4 1,040.0 1,820.9

42.0 SILT 50 2.4 300.0 3,248.4 2,000.0 2,290.9

43.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

45.0 SILT 2.4 0.0 3,248.4 0.0 1,624.2

46.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

For a designed load of 100 KN, the estimated depth is 16.5m.

Note : 1. The clay skin friction for the top soil layer is assume to be 7.5kN/m2

2. The pile is designed as floating pile where the pile would settle together with the soil and therefore there

is no effective negetive skin friction.

3. The final depth of piles penetration shall be decided on site by load test.

Page 113: Binder 9 with uploaded drawings and approved document

123

Page 114: Binder 9 with uploaded drawings and approved document

123

Page 115: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 116: Binder 9 with uploaded drawings and approved document

123

Page 117: Binder 9 with uploaded drawings and approved document

123

Page 118: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 119: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 120: Binder 9 with uploaded drawings and approved document

123

Page 121: Binder 9 with uploaded drawings and approved document

123

Page 122: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 123: Binder 9 with uploaded drawings and approved document

123

Page 124: Binder 9 with uploaded drawings and approved document

123

Page 125: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 126: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 127: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 128: Binder 9 with uploaded drawings and approved document

123

Page 129: Binder 9 with uploaded drawings and approved document

123

Page 130: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 131: Binder 9 with uploaded drawings and approved document

123

Page 132: Binder 9 with uploaded drawings and approved document

123

Page 133: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 134: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 135: Binder 9 with uploaded drawings and approved document

123

Page 136: Binder 9 with uploaded drawings and approved document

123

Page 137: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 138: Binder 9 with uploaded drawings and approved document

123

Page 139: Binder 9 with uploaded drawings and approved document

123

Page 140: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 141: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 142: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 143: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 144: Binder 9 with uploaded drawings and approved document

123

Page 145: Binder 9 with uploaded drawings and approved document

123

Page 146: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 147: Binder 9 with uploaded drawings and approved document

123

Page 148: Binder 9 with uploaded drawings and approved document

123

Page 149: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 150: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 151: Binder 9 with uploaded drawings and approved document

123

Page 152: Binder 9 with uploaded drawings and approved document

123

Page 153: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 154: Binder 9 with uploaded drawings and approved document

123

Page 155: Binder 9 with uploaded drawings and approved document

123

Page 156: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 157: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 158: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 159: Binder 9 with uploaded drawings and approved document

123

Page 160: Binder 9 with uploaded drawings and approved document

123

Page 161: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 162: Binder 9 with uploaded drawings and approved document

123

Page 163: Binder 9 with uploaded drawings and approved document

123

Page 164: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 165: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 166: Binder 9 with uploaded drawings and approved document

123

Page 167: Binder 9 with uploaded drawings and approved document

123

Page 168: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 169: Binder 9 with uploaded drawings and approved document

123

Page 170: Binder 9 with uploaded drawings and approved document

123

Page 171: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 172: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 173: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 174: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 175: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 176: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 177: Binder 9 with uploaded drawings and approved document

123

Page 178: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 179: Binder 9 with uploaded drawings and approved document

123

Page 180: Binder 9 with uploaded drawings and approved document

123

Page 181: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 182: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 183: Binder 9 with uploaded drawings and approved document

123

Page 184: Binder 9 with uploaded drawings and approved document

123

Page 185: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 186: Binder 9 with uploaded drawings and approved document

123

Page 187: Binder 9 with uploaded drawings and approved document

123

Page 188: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 189: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 190: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 191: Binder 9 with uploaded drawings and approved document

123

Page 192: Binder 9 with uploaded drawings and approved document

123

Page 193: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 194: Binder 9 with uploaded drawings and approved document

123

Page 195: Binder 9 with uploaded drawings and approved document

123

Page 196: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 197: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 198: Binder 9 with uploaded drawings and approved document

123

Page 199: Binder 9 with uploaded drawings and approved document

123

Page 200: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 201: Binder 9 with uploaded drawings and approved document

123

Page 202: Binder 9 with uploaded drawings and approved document

123

Page 203: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 204: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 205: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 206: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 207: Binder 9 with uploaded drawings and approved document

123

Page 208: Binder 9 with uploaded drawings and approved document

123

Page 209: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 210: Binder 9 with uploaded drawings and approved document

123

Page 211: Binder 9 with uploaded drawings and approved document

123

Page 212: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 213: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 214: Binder 9 with uploaded drawings and approved document

123

Page 215: Binder 9 with uploaded drawings and approved document

123

Page 216: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 217: Binder 9 with uploaded drawings and approved document

123

Page 218: Binder 9 with uploaded drawings and approved document

123

Page 219: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 220: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 221: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 222: Binder 9 with uploaded drawings and approved document

123

Page 223: Binder 9 with uploaded drawings and approved document

123

Page 224: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 225: Binder 9 with uploaded drawings and approved document

123

Page 226: Binder 9 with uploaded drawings and approved document

123

Page 227: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 228: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 229: Binder 9 with uploaded drawings and approved document

123

Page 230: Binder 9 with uploaded drawings and approved document

123

Page 231: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 232: Binder 9 with uploaded drawings and approved document

123

Page 233: Binder 9 with uploaded drawings and approved document

123

Page 234: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 235: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 236: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 237: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 238: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 239: Binder 9 with uploaded drawings and approved document

123

Page 240: Binder 9 with uploaded drawings and approved document

123

Page 241: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 242: Binder 9 with uploaded drawings and approved document

123

Page 243: Binder 9 with uploaded drawings and approved document

123

Page 244: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 245: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 246: Binder 9 with uploaded drawings and approved document

123

Page 247: Binder 9 with uploaded drawings and approved document

123

Page 248: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 249: Binder 9 with uploaded drawings and approved document

123

Page 250: Binder 9 with uploaded drawings and approved document

123

Page 251: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 252: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 253: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 254: Binder 9 with uploaded drawings and approved document

123

Page 255: Binder 9 with uploaded drawings and approved document

123

Page 256: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 257: Binder 9 with uploaded drawings and approved document

123

Page 258: Binder 9 with uploaded drawings and approved document

123

Page 259: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 260: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 261: Binder 9 with uploaded drawings and approved document

123

Page 262: Binder 9 with uploaded drawings and approved document

123

Page 263: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 264: Binder 9 with uploaded drawings and approved document

123

Page 265: Binder 9 with uploaded drawings and approved document

123

Page 266: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 267: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 268: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 269: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 270: Binder 9 with uploaded drawings and approved document

123

Page 271: Binder 9 with uploaded drawings and approved document

123

Page 272: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 273: Binder 9 with uploaded drawings and approved document

123

Page 274: Binder 9 with uploaded drawings and approved document

123

Page 275: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 276: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 277: Binder 9 with uploaded drawings and approved document

123

Page 278: Binder 9 with uploaded drawings and approved document

123

Page 279: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 280: Binder 9 with uploaded drawings and approved document

123

Page 281: Binder 9 with uploaded drawings and approved document

123

Page 282: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 283: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 284: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 285: Binder 9 with uploaded drawings and approved document

123

Page 286: Binder 9 with uploaded drawings and approved document

123

Page 287: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 288: Binder 9 with uploaded drawings and approved document

123

Page 289: Binder 9 with uploaded drawings and approved document

123

Page 290: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 291: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 292: Binder 9 with uploaded drawings and approved document

123

Page 293: Binder 9 with uploaded drawings and approved document

123

Page 294: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 295: Binder 9 with uploaded drawings and approved document

123

Page 296: Binder 9 with uploaded drawings and approved document

123

Page 297: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 298: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 299: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 300: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 301: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 302: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 303: Binder 9 with uploaded drawings and approved document

PILE BEARING CAPACITY CALCULATION BASED ON S.P.T. VALUE

------------------ ------------------

Project Name :

Location :

Borehole No. : BH-1

Date :

------------------ ------------------

MAYERHOF Formula : K1 K2

Skin, Ps = K1 x Nav x As SAND 2.0 400

Bearing, Pb = K2 x Nb x Ab SILT 2.5 250

Ult. Load, Pu = Ps + Pb CLAY 3.0 100

All. Load, Pa = Ps/Fs + Pb/Fb

Factor of safety : Skin, Fs = 2

Bearing, Fb = 3

------------------ ------------------

To calculate allowable soil bearing capacity :

Pile used : Type : s

(c = circular) Width, b = 0.4 m Perimeter: 1.600

(s = square) (= dia. for type c) Ab: 0.160

Qa(conc): 1800

========== ========== ====== ========== ========== ============ =======================

Depth Soil SPT Skin Total Base Working Load

Type N As Fric Skin Load Fs = 2.0 Fb = 3

(m) (m²) (kN) (kN) (kN) (KN)

------------------ ------------------ ---------- ------------------ ------------------ -------------------- ---------------------------------------

0.0 SAND 0 0.0 0.0 0.0 0.0 0.0

1.5 SAND 11 2.4 52.8 52.8 704.0 261.1

3.0 SAND 12 2.4 57.6 110.4 768.0 311.2

4.5 SAND 15 2.4 72.0 182.4 960.0 411.2

6.0 SILT 17 2.4 102.0 284.4 680.0 368.9

7.5 SILT 19 2.4 114.0 398.4 760.0 452.5

9.0 SILT 19 2.4 114.0 512.4 760.0 509.5

10.5 SILT 17 2.4 102.0 614.4 680.0 533.9

12.0 SILT 19 2.4 114.0 728.4 760.0 617.5

13.5 SILT 11 2.4 66.0 794.4 440.0 543.9

15.0 SILT 18 2.4 108.0 902.4 720.0 691.2

16.5 SILT 17 2.4 102.0 1,004.4 680.0 728.9

18.0 SILT 19 2.4 114.0 1,118.4 760.0 812.5

19.5 SILT 20 2.4 120.0 1,238.4 800.0 885.9

21.0 SILT 18 2.4 108.0 1,346.4 720.0 913.2

22.5 SILT 14 2.4 84.0 1,430.4 560.0 901.9

24.0 SILT 0 2.4 0.0 1,430.4 0.0 715.2

25.5 SILT 22 2.4 132.0 1,562.4 880.0 1,074.5

27.0 SILT 20 2.4 120.0 1,682.4 800.0 1,107.9

28.5 SILT 20 2.4 120.0 1,802.4 800.0 1,167.9

30.0 SILT 22 2.4 132.0 1,934.4 880.0 1,260.5

31.5 SILT 25 2.4 150.0 2,084.4 1,000.0 1,375.5

33.0 SILT 23 2.4 138.0 2,222.4 920.0 1,417.9

34.5 SILT 23 2.4 138.0 2,360.4 920.0 1,486.9

36.0 SILT 24 2.4 144.0 2,504.4 960.0 1,572.2

37.5 SILT 23 2.4 138.0 2,642.4 920.0 1,627.9

39.0 SILT 25 2.4 150.0 2,792.4 1,000.0 1,729.5

40.5 SILT 26 2.4 156.0 2,948.4 1,040.0 1,820.9

42.0 SILT 50 2.4 300.0 3,248.4 2,000.0 2,290.9

43.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

45.0 SILT 2.4 0.0 3,248.4 0.0 1,624.2

46.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

For a designed load of 100 KN, the estimated depth is 16.5m.

Note : 1. The clay skin friction for the top soil layer is assume to be 7.5kN/m2

2. The pile is designed as floating pile where the pile would settle together with the soil and therefore there

is no effective negetive skin friction.

3. The final depth of piles penetration shall be decided on site by load test.

Page 304: Binder 9 with uploaded drawings and approved document

123

Page 305: Binder 9 with uploaded drawings and approved document

123

Page 306: Binder 9 with uploaded drawings and approved document

123

Page 307: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 308: Binder 9 with uploaded drawings and approved document

123

Page 309: Binder 9 with uploaded drawings and approved document

123

Page 310: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 311: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 312: Binder 9 with uploaded drawings and approved document

123

Page 313: Binder 9 with uploaded drawings and approved document

123

Page 314: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 315: Binder 9 with uploaded drawings and approved document

123

Page 316: Binder 9 with uploaded drawings and approved document

123

Page 317: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 318: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 319: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 320: Binder 9 with uploaded drawings and approved document

123

Page 321: Binder 9 with uploaded drawings and approved document

123

Page 322: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 323: Binder 9 with uploaded drawings and approved document

123

Page 324: Binder 9 with uploaded drawings and approved document

123

Page 325: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 326: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 327: Binder 9 with uploaded drawings and approved document

123

Page 328: Binder 9 with uploaded drawings and approved document

123

Page 329: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 330: Binder 9 with uploaded drawings and approved document

123

Page 331: Binder 9 with uploaded drawings and approved document

123

Page 332: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 333: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 334: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 335: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 336: Binder 9 with uploaded drawings and approved document

123

Page 337: Binder 9 with uploaded drawings and approved document

123

Page 338: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 339: Binder 9 with uploaded drawings and approved document

123

Page 340: Binder 9 with uploaded drawings and approved document

123

Page 341: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 342: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 343: Binder 9 with uploaded drawings and approved document

123

Page 344: Binder 9 with uploaded drawings and approved document

123

Page 345: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 346: Binder 9 with uploaded drawings and approved document

123

Page 347: Binder 9 with uploaded drawings and approved document

123

Page 348: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 349: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 350: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 351: Binder 9 with uploaded drawings and approved document

123

Page 352: Binder 9 with uploaded drawings and approved document

123

Page 353: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 354: Binder 9 with uploaded drawings and approved document

123

Page 355: Binder 9 with uploaded drawings and approved document

123

Page 356: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 357: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 358: Binder 9 with uploaded drawings and approved document

123

Page 359: Binder 9 with uploaded drawings and approved document

123

Page 360: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 361: Binder 9 with uploaded drawings and approved document

123

Page 362: Binder 9 with uploaded drawings and approved document

123

Page 363: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 364: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 365: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 366: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 367: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 368: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 369: Binder 9 with uploaded drawings and approved document

123

Page 370: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 371: Binder 9 with uploaded drawings and approved document

123

Page 372: Binder 9 with uploaded drawings and approved document

123

Page 373: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 374: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 375: Binder 9 with uploaded drawings and approved document

123

Page 376: Binder 9 with uploaded drawings and approved document

123

Page 377: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 378: Binder 9 with uploaded drawings and approved document

123

Page 379: Binder 9 with uploaded drawings and approved document

123

Page 380: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 381: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 382: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 383: Binder 9 with uploaded drawings and approved document

123

Page 384: Binder 9 with uploaded drawings and approved document

123

Page 385: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 386: Binder 9 with uploaded drawings and approved document

123

Page 387: Binder 9 with uploaded drawings and approved document

123

Page 388: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 389: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 390: Binder 9 with uploaded drawings and approved document

123

Page 391: Binder 9 with uploaded drawings and approved document

123

Page 392: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 393: Binder 9 with uploaded drawings and approved document

123

Page 394: Binder 9 with uploaded drawings and approved document

123

Page 395: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 396: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 397: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 398: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 399: Binder 9 with uploaded drawings and approved document

123

Page 400: Binder 9 with uploaded drawings and approved document

123

Page 401: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 402: Binder 9 with uploaded drawings and approved document

123

Page 403: Binder 9 with uploaded drawings and approved document

123

Page 404: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 405: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 406: Binder 9 with uploaded drawings and approved document

123

Page 407: Binder 9 with uploaded drawings and approved document

123

Page 408: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 409: Binder 9 with uploaded drawings and approved document

123

Page 410: Binder 9 with uploaded drawings and approved document

123

Page 411: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 412: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 413: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 414: Binder 9 with uploaded drawings and approved document

123

Page 415: Binder 9 with uploaded drawings and approved document

123

Page 416: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 417: Binder 9 with uploaded drawings and approved document

123

Page 418: Binder 9 with uploaded drawings and approved document

123

Page 419: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 420: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 421: Binder 9 with uploaded drawings and approved document

123

Page 422: Binder 9 with uploaded drawings and approved document

123

Page 423: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 424: Binder 9 with uploaded drawings and approved document

123

Page 425: Binder 9 with uploaded drawings and approved document

123

Page 426: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 427: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 428: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 429: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 430: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 431: Binder 9 with uploaded drawings and approved document

123

Page 432: Binder 9 with uploaded drawings and approved document

123

Page 433: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 434: Binder 9 with uploaded drawings and approved document

123

Page 435: Binder 9 with uploaded drawings and approved document

123

Page 436: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 437: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 438: Binder 9 with uploaded drawings and approved document

123

Page 439: Binder 9 with uploaded drawings and approved document

123

Page 440: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 441: Binder 9 with uploaded drawings and approved document

123

Page 442: Binder 9 with uploaded drawings and approved document

123

Page 443: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 444: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 445: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 446: Binder 9 with uploaded drawings and approved document

123

Page 447: Binder 9 with uploaded drawings and approved document

123

Page 448: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 449: Binder 9 with uploaded drawings and approved document

123

Page 450: Binder 9 with uploaded drawings and approved document

123

Page 451: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 452: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 453: Binder 9 with uploaded drawings and approved document

123

Page 454: Binder 9 with uploaded drawings and approved document

123

Page 455: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 456: Binder 9 with uploaded drawings and approved document

123

Page 457: Binder 9 with uploaded drawings and approved document

123

Page 458: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 459: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 460: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 461: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 462: Binder 9 with uploaded drawings and approved document

123

Page 463: Binder 9 with uploaded drawings and approved document

123

Page 464: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 465: Binder 9 with uploaded drawings and approved document

123

Page 466: Binder 9 with uploaded drawings and approved document

123

Page 467: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 468: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 469: Binder 9 with uploaded drawings and approved document

123

Page 470: Binder 9 with uploaded drawings and approved document

123

Page 471: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 472: Binder 9 with uploaded drawings and approved document

123

Page 473: Binder 9 with uploaded drawings and approved document

123

Page 474: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 475: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 476: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 477: Binder 9 with uploaded drawings and approved document

123

Page 478: Binder 9 with uploaded drawings and approved document

123

Page 479: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 480: Binder 9 with uploaded drawings and approved document

123

Page 481: Binder 9 with uploaded drawings and approved document

123

Page 482: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 483: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 484: Binder 9 with uploaded drawings and approved document

123

Page 485: Binder 9 with uploaded drawings and approved document

123

Page 486: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 487: Binder 9 with uploaded drawings and approved document

123

Page 488: Binder 9 with uploaded drawings and approved document

123

Page 489: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 490: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 491: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 492: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 493: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 494: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 495: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 496: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 497: Binder 9 with uploaded drawings and approved document

123

Page 498: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 499: Binder 9 with uploaded drawings and approved document

123

Page 500: Binder 9 with uploaded drawings and approved document

123

Page 501: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 502: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 503: Binder 9 with uploaded drawings and approved document

123

Page 504: Binder 9 with uploaded drawings and approved document

123

Page 505: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 506: Binder 9 with uploaded drawings and approved document

123

Page 507: Binder 9 with uploaded drawings and approved document

123

Page 508: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 509: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 510: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 511: Binder 9 with uploaded drawings and approved document

123

Page 512: Binder 9 with uploaded drawings and approved document

123

Page 513: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 514: Binder 9 with uploaded drawings and approved document

123

Page 515: Binder 9 with uploaded drawings and approved document

123

Page 516: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 517: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 518: Binder 9 with uploaded drawings and approved document

123

Page 519: Binder 9 with uploaded drawings and approved document

123

Page 520: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 521: Binder 9 with uploaded drawings and approved document

123

Page 522: Binder 9 with uploaded drawings and approved document

123

Page 523: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 524: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 525: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 526: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 527: Binder 9 with uploaded drawings and approved document

123

Page 528: Binder 9 with uploaded drawings and approved document

123

Page 529: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 530: Binder 9 with uploaded drawings and approved document

123

Page 531: Binder 9 with uploaded drawings and approved document

123

Page 532: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 533: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 534: Binder 9 with uploaded drawings and approved document

123

Page 535: Binder 9 with uploaded drawings and approved document

123

Page 536: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 537: Binder 9 with uploaded drawings and approved document

123

Page 538: Binder 9 with uploaded drawings and approved document

123

Page 539: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 540: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 541: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 542: Binder 9 with uploaded drawings and approved document

123

Page 543: Binder 9 with uploaded drawings and approved document

123

Page 544: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 545: Binder 9 with uploaded drawings and approved document

123

Page 546: Binder 9 with uploaded drawings and approved document

123

Page 547: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 548: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 549: Binder 9 with uploaded drawings and approved document

123

Page 550: Binder 9 with uploaded drawings and approved document

123

Page 551: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 552: Binder 9 with uploaded drawings and approved document

123

Page 553: Binder 9 with uploaded drawings and approved document

123

Page 554: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 555: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 556: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 557: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 558: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 559: Binder 9 with uploaded drawings and approved document

123

Page 560: Binder 9 with uploaded drawings and approved document

123

Page 561: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 562: Binder 9 with uploaded drawings and approved document

123

Page 563: Binder 9 with uploaded drawings and approved document

123

Page 564: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 565: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 566: Binder 9 with uploaded drawings and approved document

123

Page 567: Binder 9 with uploaded drawings and approved document

123

Page 568: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 569: Binder 9 with uploaded drawings and approved document

123

Page 570: Binder 9 with uploaded drawings and approved document

123

Page 571: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 572: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 573: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 574: Binder 9 with uploaded drawings and approved document

123

Page 575: Binder 9 with uploaded drawings and approved document

123

Page 576: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 577: Binder 9 with uploaded drawings and approved document

123

Page 578: Binder 9 with uploaded drawings and approved document

123

Page 579: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 580: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 581: Binder 9 with uploaded drawings and approved document

123

Page 582: Binder 9 with uploaded drawings and approved document

123

Page 583: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 584: Binder 9 with uploaded drawings and approved document

123

Page 585: Binder 9 with uploaded drawings and approved document

123

Page 586: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 587: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 588: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 589: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 590: Binder 9 with uploaded drawings and approved document

123

Page 591: Binder 9 with uploaded drawings and approved document

123

Page 592: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 593: Binder 9 with uploaded drawings and approved document

123

Page 594: Binder 9 with uploaded drawings and approved document

123

Page 595: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 596: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 597: Binder 9 with uploaded drawings and approved document

123

Page 598: Binder 9 with uploaded drawings and approved document

123

Page 599: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 600: Binder 9 with uploaded drawings and approved document

123

Page 601: Binder 9 with uploaded drawings and approved document

123

Page 602: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 603: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 604: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 605: Binder 9 with uploaded drawings and approved document

123

Page 606: Binder 9 with uploaded drawings and approved document

123

Page 607: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 608: Binder 9 with uploaded drawings and approved document

123

Page 609: Binder 9 with uploaded drawings and approved document

123

Page 610: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 611: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 612: Binder 9 with uploaded drawings and approved document

123

Page 613: Binder 9 with uploaded drawings and approved document

123

Page 614: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 615: Binder 9 with uploaded drawings and approved document

123

Page 616: Binder 9 with uploaded drawings and approved document

123

Page 617: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 618: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 619: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 620: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 621: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 622: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 623: Binder 9 with uploaded drawings and approved document

123

Page 624: Binder 9 with uploaded drawings and approved document

PILE BEARING CAPACITY CALCULATION BASED ON S.P.T. VALUE

------------------ ------------------

Project Name :

Location :

Borehole No. : BH-1

Date :

------------------ ------------------

MAYERHOF Formula : K1 K2

Skin, Ps = K1 x Nav x As SAND 2.0 400

Bearing, Pb = K2 x Nb x Ab SILT 2.5 250

Ult. Load, Pu = Ps + Pb CLAY 3.0 100

All. Load, Pa = Ps/Fs + Pb/Fb

Factor of safety : Skin, Fs = 2

Bearing, Fb = 3

------------------ ------------------

To calculate allowable soil bearing capacity :

Pile used : Type : s

(c = circular) Width, b = 0.4 m Perimeter: 1.600

(s = square) (= dia. for type c) Ab: 0.160

Qa(conc): 1800

========== ========== ====== ========== ========== ============ =======================

Depth Soil SPT Skin Total Base Working Load

Type N As Fric Skin Load Fs = 2.0 Fb = 3

(m) (m²) (kN) (kN) (kN) (KN)

------------------ ------------------ ---------- ------------------ ------------------ -------------------- ---------------------------------------

0.0 SAND 0 0.0 0.0 0.0 0.0 0.0

1.5 SAND 11 2.4 52.8 52.8 704.0 261.1

3.0 SAND 12 2.4 57.6 110.4 768.0 311.2

4.5 SAND 15 2.4 72.0 182.4 960.0 411.2

6.0 SILT 17 2.4 102.0 284.4 680.0 368.9

7.5 SILT 19 2.4 114.0 398.4 760.0 452.5

9.0 SILT 19 2.4 114.0 512.4 760.0 509.5

10.5 SILT 17 2.4 102.0 614.4 680.0 533.9

12.0 SILT 19 2.4 114.0 728.4 760.0 617.5

13.5 SILT 11 2.4 66.0 794.4 440.0 543.9

15.0 SILT 18 2.4 108.0 902.4 720.0 691.2

16.5 SILT 17 2.4 102.0 1,004.4 680.0 728.9

18.0 SILT 19 2.4 114.0 1,118.4 760.0 812.5

19.5 SILT 20 2.4 120.0 1,238.4 800.0 885.9

21.0 SILT 18 2.4 108.0 1,346.4 720.0 913.2

22.5 SILT 14 2.4 84.0 1,430.4 560.0 901.9

24.0 SILT 0 2.4 0.0 1,430.4 0.0 715.2

25.5 SILT 22 2.4 132.0 1,562.4 880.0 1,074.5

27.0 SILT 20 2.4 120.0 1,682.4 800.0 1,107.9

28.5 SILT 20 2.4 120.0 1,802.4 800.0 1,167.9

30.0 SILT 22 2.4 132.0 1,934.4 880.0 1,260.5

31.5 SILT 25 2.4 150.0 2,084.4 1,000.0 1,375.5

33.0 SILT 23 2.4 138.0 2,222.4 920.0 1,417.9

34.5 SILT 23 2.4 138.0 2,360.4 920.0 1,486.9

36.0 SILT 24 2.4 144.0 2,504.4 960.0 1,572.2

37.5 SILT 23 2.4 138.0 2,642.4 920.0 1,627.9

39.0 SILT 25 2.4 150.0 2,792.4 1,000.0 1,729.5

40.5 SILT 26 2.4 156.0 2,948.4 1,040.0 1,820.9

42.0 SILT 50 2.4 300.0 3,248.4 2,000.0 2,290.9

43.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

45.0 SILT 2.4 0.0 3,248.4 0.0 1,624.2

46.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

For a designed load of 100 KN, the estimated depth is 16.5m.

Note : 1. The clay skin friction for the top soil layer is assume to be 7.5kN/m2

2. The pile is designed as floating pile where the pile would settle together with the soil and therefore there

is no effective negetive skin friction.

3. The final depth of piles penetration shall be decided on site by load test.

Page 625: Binder 9 with uploaded drawings and approved document

LARSEN & TOUBRO LIMITED E&C DIVISION

GEOTECHNICAL INVESTIGATION REPORT – INSIDE

AREA

DOCUMENT NO. A067-LT-00-CV-04-RP-0004

PROJECT :Additional Gas Processing Facilities (Phase-IV)

REVISION : 01

CUSTOMER : ONGC,HAZIRA

Sheet No.1053

11-06-2012

Page 626: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

TECHNICAL REPORT

OF

GEOTECHNICAL INVESTIGATION

FOR

PROPOSED STRUCTURES INSIDE PLANT AREA UNDER PROJECT OF ADDITIONAL GAS PROCESSING FACILITES (PHASE 4) FOR

ONGC AT HAZIRA, SURAT (INSIDE PLANT AREA)

BY:

DR.K.C.THAKER B.E.(CIVIL) ; M.TECH (S.M.); (I.I .T, BOMBAY) Ph.D.(I.I.T., BOMBAY);F.I .E.(INDIA); F.I.G.S.

K.K.THAKER B.E. (CIVIL) GOLD MEDALIST; M.E (GEOTECH) M.B.A.(FINANCE);M.I.E(INDIA); M.I.G.S; M.G.I.C.E.A.

OFFICE : Plot no.1,Sayona Silver Estate-Part II ,

Behind Si lver Oak Club, Beside Auda Water Tank Opp. Sarjan RMC Plant,

Gota, Ahmedabad 382 481 Phone :- 65103088/89/90,9825064378,

August - 2010

Sheet No.1054

11-06-2012

Page 627: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED STRUCTURES OF ADDITIONAL GAS PROCESSING FACILITES PROECT (PHASE 4 – INSIDE OF PLANT) OF ONGC AT HAjIRA, SURAT

1.0 Introduction For foundation analysis of the structures of Additional Gas Processing Facilities Project (Phase 4) of ONGC at Hajira, Surat, It is necessary, 1. To determine the subsoil profile of the site and to know physical properties and strength

characteristics of soil at various depths. 2. To suggest suitable foundation and to know the safe bearing pressure and probable

settlement of foundation. 3. To know any adverse soil conditions to the foundation structures and to take

precautionary measures.

For this purpose, the geotechnical investigation was entrusted to us by Larsen and Toubro Limited. Following points were decided, 1. No. Bore holes – 4 nos. in side plant boundary 2. Standard penetration tests are conducted at regular interval. 3. Collection of Undisturbed soil samples at regular interval. 4. Collection of disturbed samples during drilling and from SPT. 5. To find physical properties and strength characteristics of samples as per the testing

schedules. 6. To locate ground water table, if any. 7. To conduct block vibration test. 8. To conduct electrical resistivity test. 9. Interpretation of results, Analysis and Recommendations.

Based on the above points the detailed Geotechnical Investigation Program included the following: (A) Field Investigation 1. Drilling of bore hole. 2. Collection of soil samples ( Disturbed and Undisturbed ) 3. Conducting Standard Penetration Test. 4. Conducting Block Vibration Test. 5. Conducting Electrical Resistivity Test

(B) Laboratory Investigation 1. Bulk Density and moisture content 2. Grain size analysis 3. Consistency limits 4. Shear tests 5. Consolidation tests 6. Chemical analysis of soil and water

(C) Recommendations Based on above investigations, the results are to be obtained. The findings would be based on interpretation of results, analysis and computations as per relevant Indian standards.

Sheet No.1055

11-06-2012

Page 628: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

2.0 Field Investigation 2.1 BoringThe exploratory boreholes of 150mm diameter were drilled by rotary drilling method. The depth of the test bore at the proposed location is as under:

Bore Hole No. Co-Ordinates Reduced

Level (m) Depth Investigated

(m) N E BH – 4 365 1025 98.466 20 BH – 5 780 1100 99.423 25 BH – 6 799 1170 99.620 20 BH – 9 1065 1750 99.232 20

2.2 Sampling 2.2.1 Disturbed samples Disturbed samples were collected during boring and from the split spoon sampler. The samples recovered were logged, labeled and placed in polyethylene bags and sent to laboratory for testing.

2.2.2 Undisturbed samples Undisturbed soil samples were collected in thin walled Shelby tubes as per IS 2132 at regular intervals. The samples collected were sealed properly using wax, labeled and transported to the laboratory.

2.2.3 Standard penetration test The standard penetration tests were conduct in accordance with IS:2131-1981 in test bore at regular intervals. The test gives N – Value, the blow counts of last 30 cm penetration of split spoon sampler with 63.5 kg hammer falling from 76 cm height.

2.2.4 Block Vibration Test For determining various parameters influencing the design of machine foundation like physical properties of elastic base of the foundation, block vibration test was conducted. For this purpose Oscillator was fixed on the PCC block cast of size 1.00 x 0.75 x 0.75 m at Co ordinates N 789 and E 1087, and vibration was induced. The vibration peak ups were attached, on this block to measure the frequency and amplitude. The test was conducted as per the provisions of IS 5249 – 1969. Various dynamic properties as listed below were calculated for 10sq.mt area.

Cu - Coefficient of elastic uniform compression ( kg / cu.cm ) Cτ - Coefficient of elastic uniform shear ( Kg / cu.cm ) Cφ - Coefficient of elastic non – uniform compression ( Kg / cu.cm ) Cψ − Coefficient of elastic non – uniform shear ( Kg / cu.cm )

The above coefficients are reported for foundation contact area, A of 10.0 sq. m

2.2.5 Electrical Resistivity Test Geophysical Survey In all geophysical surveys, Electrical Resistivity method is best and reliable to know geological formation of the the area. All geological formations possess properties called electrical resistivity when the current flows through them. Resistivity thus

Sheet No.1056

11-06-2012

Page 629: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

is defined as the resistance offered by a unit cube of material to direct current flowing through it in a direction perpendicular to two of its opposite faces. The numerical value of the resistivity is expressed in ohm. m in general. Thus the electrical resistivity is principally based on the study of resistance offered by the sub-surface formation to the flow of current. The study in turns helps in evaluation of the characteristic of the sub surface layers in terms of electrical resistivity. Vertical electrical soundings (VES) have been conducted by using resistivity meter of I G I S make direct current in deployed during survey as per IS : 3043. Two metal stakes called current electrodes into the sub surface transmit the current and the potential response is observed by means two copper electrodes called potential electrodes. Apparent resistivity is calculated from the equation:-

= 2 SR K = 2 S = Geometric factor for electrode spacing (Wenner’s configuration) R = Resistance in Ohms S = Spacing between adjacent electrodes in (m)

= Resistivity in ohm.m. Test was conducted at Co ordinates: N 762 E 1087

3.0 Laboratory investigation The laboratory tests were conducted on the samples collected. The following laboratory tests were conducted on undisturbed and disturbed soil samples collected from various depths to find physical properties and strength characteristics.

Tests Recomnd procedure Type Samples 1. Sample Preparation IS 2720 Pt I DS / UDS 2. Moisture Content IS 2720 Pt II DS / UDS 3. Dry Unit Weight LAMBE UDS 4. Specific Gravity IS 2720 Pt III DS 5. Liquid Limit IS 2720 DS 6. Plastic Limit IS 2720 Pt V DS 7. Grain Size Analysis IS 2720 Pt IV DS 8. Soil Classification IS 1498 DS / UDS 9. Consolidation IS 2720 Pt XV UDS 10. Triaxial Comp. Test IS 2720 Pt X UDS 11. Laboratory permeability IS 2720 Part XVII UDS

4.0 Results 1. The location plan of Bore hole is shown in fig no.1 2. The bore log details of Bore hole are shown in fig nos. 2 to 5 3. Results of permeability of Bore hole are given in table no 1 4. The Chemical analysis of soil and water is given in table nos.2 & 3 5. Laboratory test results of Bore hole are appended in table nos. 4 to 7 6. Results of BVT are shown in fig nos. 6 & 7 7. Results of ERT are given in fig no. 8

5.0 General stratification The soil deposits at Hajira are alluvial in nature formed by River Tapti and its interaction with the sea over the geological history. The layers consist of plastic clays from stiff to very stiff consistency at top. The subsequent layer consists of plastic clays and silts from very

Sheet No.1057

11-06-2012

Page 630: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

soft to stiff consistency, followed by silty sands with density varying from loose to dense and very dense.

6.0 Discussion

Two foundation options are suggested:

1. Pile Foundations : For heavy equipment and major structures, pile foundations are recommended. Due to proximity to process areas driven piles are not permitted and bored cast-in-situ piles are recommended. Piles of 500 mm diameter with depth of embedment of 16 m are suitable. Pile calculations are given in Appendix – 1. The lateral capacities are 4.5 t for a fixed headed pile and 2.0 t for a free headed pile. The lateral capacity is also to be confirmed by means of a lateral load test on a test pile. The tests have to be carried out as per IS 2911 / Part 4 – 1985.

2. Open foundations for lightly loaded structures and equipment : The possibility of placing the light to intermediate loaded structures and equipment foundations, open shallow foundations can be explored. The minimum depth of foundation recommended is 2 m from FGL. The permissible settlement is 25mm. The recommended bearing capacity values borehole wise for permissible settlements for 25mm are as given in Section 7 (Conclusion) below and the calculations are appended in Appendix 2. 7.0 Conclusions 1) Two foundation options are recommended. Option 1 : For process equipments and heavily loaded structures, Bored cast –in- situ piles, 500 mm diameter, length of embedment of 16 and cutoff level approximately at 2.50 m from NGL having capacities given below may be provided,

Axial Compression 65 TLateral – Fixed Head 4.5 TLateral – Free Head 2.0 TUplift 24 T

Option 2: For light to moderately loaded structures and equipment foundations, open foundations with minimum depth of 2m below FGL is recommended. A 30 cm thick, well compacted coarse sand layer below the bottom of foundation is recommended.

The net safe bearing pressures as tabulated below are recommended.

Size of Foundation Recommended net Safe Bearing

Pressure (T/m2)

Depth (m) Width (m)

2.0 1.0 14 2.0 2.0 8

Sheet No.1058

11-06-2012

Page 631: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

2.0 3.0 62.0 Strip 5 2.5 1.0 15 2.5 2.0 10 2.5 3.0 7 2.5 Strip 6

2) Ground water table is encountered at around 3.50 m from EGL, during investigation, which is likely to rise up to two mt from ground level in monsoon. Design groundwater level shall be at EL 99.500 to account for rain and tidal effects.

3) From results of chemical soil as reported in table 2 & 3, the sub soil is classified in class 2 based on sulphite Content (SO3), as per the table no. 4 under clauses 8.2.2.4 and 9.1.2 of IS: 456, 2000. PPC or PSC with minimum cement content of 330kg/m3 and maximum face water-cement ratio of 0.5 can be used for all RCC in foundation structures. OPC may be used provided the C3A content is within 5 to 8% as per IS 456, Table 4, Note 6. Alternatively, OPC mixed with fly ash as per the provisions of IS 456 and IS 3812 may be used with validation of concrete characteristics through testing. Minimum cement content in piles shall be 400kg/m3 as per the requirements of IS 2911. As the chloride content is high, clear cover to the reinforcement in foundation systems shall at least be 65 mm.

4) Suitable side slope in excavation and any measures if required and so far as is reasonably practicable shall be provided to prevent dislodgement of earth or any other material forming the side of excavation.

5) Considering the swelling characteristic adequate measures shall be taken to mitigate adverse consequences of swelling and shrinking due to moisture movement. A layer of compacted coarse sand having 300 mm thickness shall be provided under the pile caps and aprons around the structures and in plinths under floor finishes.

7) The comments given in this report and the opinion expressed are based on the ground conditions encountered during site work and on the results of tests made in field and in the laboratory. There may however, special conditions prevailing at the site which have not been disclosed by the investigation and which have not been taken in to account in the report. Any variation in stratification in any of the foundation location shall be studied thoroughly before executing the foundation work

(K.K.Thaker) (Dr. K.C.Thaker)

Sheet No.1059

11-06-2012

Page 632: Binder 9 with uploaded drawings and approved document

Calculation of Safe Load on Bored Cast in Situ Pile (As per IS: 2911 (Part I / Sec II))

1) Design StipulationsPile Diameter: 0.50m Existing GWT level: 0.00m Pile Cut-Off level: 2.50m from existing ground level. Pile Termination level: 18.50m from E.G.L For maximum overburden pressure at Pile tip 15 x diameter of pile length of pile has been taken

2) Soil Parameters Considered Layer Thickness

m CohesionKg / cm2

Angle of Internal Friction

Field Densitygm / cc

SPT N Value

5.10 0.39 9 1.76 8 7.50 0.00 25 1.70 10 12.4 0.00 34 1.90 19

3) Ultimate End Bearing Capacity Que = Ap (0.5 * D * γ * Nγ + Pd * Nq) Where, Ap = Cross sectional Area = 0.196 m2

D = Pile Stem Diameter = 0.50 m γ = Bulk Unit Weight of soil at Pile tip = 0.90 T/m3

Nγ = Bearing Capacity factor = 41.06 Pd = Effective overburden pressure at pile tip = 5.56 T/m2

Nq = Bearing Capacity factor = 42.80 Ultimate End Bearing Capacity Que =0.196*(0.5*0.50*0.90*41.06+5.56*42.8) = 48.48 T

Pd Level for this pile = 7.50 m Layer No.1 Effective overburden pressure due to this layer = 0.00 x 1.76 +5.10 x (1.76 - 1) = 3.88 T/m2

Layer No.2 Effective overburden pressure due to this layer = 2.40 x (1.70 - 1) =1.68 T/m2

Layer No.3 No contribution from this layer Total effective overburden pressure up to 7.50m level from EGL= 5.56T/m2.

4) Ultimate Skin Friction Capacity Qsg = Σ [K * Pdi * tan (δ) * Asi] for all layers Where, K = Earth Pressure Coefficient Pdi = Effective Overburden pressure for ith layer δ = Angle of wall friction for ith layer Asi = Surface area of pile stem for ith layer

Qsc = Σ [α * C * as] for all layers Where, α = Reduction factor C = Average Cohesion Asi = Surface area of pile stem for ith layer

Layer no. 1: K: 1.00 Pd1 : 1.94 T/m2 tan (δ) : 0.16 As1 : 4.08 m2

Qsg = K*Pd1*tan (δ)*As1 =1.00*1.94*0.16*4.08 = 1.25 T Reduction factor (α): 0.40 Average Cohesion(C): 3.90 T/m2. Qsc = α*C*As1 = 0.40*3.90*4.08 = 6.37 T Total net skin friction of this layer = 7.62T/m2

Sheet No.1060

11-06-2012

Page 633: Binder 9 with uploaded drawings and approved document

Layer no. 2: K: 1.50 Pd2: 4.72 T/m2. tan (δ) : 0.47 As2 : 11.78 m2. Qsg = K*Pd2*tan (δ)*As2 =1.50*4.72*0.47*11.78 = 38.82 T Reduction factor (α): 0.40 Average Cohesion(C): 0.00 T/m2. Qsc = a*C*As2 =0.40*0.00*11.78 = 0.00 T Total net skin friction of this layer = 38.82 T/m2.

Layer no. 3: K: 2.00 Pd3 : 5.56 T/m2. tan (δ) : 0.67 As3 : 9.26 m2.Qsg = K*Pd3*tan (δ)*As3 =2.00*5.56*0.67*9.26 = 69.38 T Reduction factor (α): 0.30 Average Cohesion(C): 0.00 T/m2. Qsc = α*C*As3 =0.30*0.00*9.26 = 0.00 T Total net skin friction of this layer = 69.38T/m2.

Total Skin Friction Capacity Qus = Qsg + Qsc = 115.82 T Total Ultimate Pile Capacity Qu = Qus + Que = 164.30 T Net Ultimate Pile Capacity Qu/FOS = 65.7 T

5) Safe Load in Compression in Ton

Pile Diameter in m Pile Length after cutoff in m

14.0 16.0 18.0

0.45 45.1 52.8 60.5

0.50 56.3 65.7 75.1

Calculating safe load on pile in uplift for various diameters,

6) Safe Load in Uplift in Ton

Pile Diameter in m Pile Length after cutoff in m

14.0 16.0 18.0

0.45 30.9 38.6 46.2

0.50 36.9 46.4 55.7

7) Computation of Lateral Capacity Lateral capacity is computed based up on the allowable top deflection of 5.0mm. Free Length L1 is 0.00 m and overall nature of soil is clayey.

For a Fixed Head Pile of 500 mm diameter, soil constant K2= 48.8 Kg/cm3 (From IS Code), E = 273861.27 Kg/cm2, I = 306640.63 cm4, R = 203.67, L1/R = 0.00. Depth of Fixity Lf = 443.99 cm = 4.4 m Total Ultimate Horizontal Load Capacity H [As per IS Code] =12EIY/(L1+Lf)3 = 5.76 T Ultimate Horizontal Load Capacity is recommended as 4.50 T Moment Reduction Factor m = 0.825(From IS Code) Total Ultimate Moment Capacity M [As per IS Code] =mH (L1+Lf)/2 = 8.24 ~ 8.2 Tm

Recommended Lateral Capacities For Fixed Head Piles Pile Diameter in m 0.45 0.50

Horizontal Load Capacity in T 4.0 4.5

For a Free Head Pile of 500 mm diameter, soil constant K2= 48.8 Kg/cm3 (From IS Code), E = 273861.27 Kg/cm2, I = 306640.63 cm4, R = 203.67, L1/R = 0.00. Depth of Fixity Lf = 391.05 cm = 3.9 m

Sheet No.1061

11-06-2012

Page 634: Binder 9 with uploaded drawings and approved document

Total Ultimate Horizontal Load Capacity H [As per IS Code] = 3EIY/(L1+Lf)3 = 2.1 T Ultimate Horizontal Load Capacity is recommended as 2.0 T Moment Reduction Factor m = 0.4 (From IS Code) Total Ultimate Moment Capacity M [As per IS Code] = mH (L1+Lf) = 3.13 ~3.0 Tm

Recommended Lateral Capacities For Free Head Piles Pile Diameter in m 0.45 0.50

Horizontal Load Capacity in T 1.9 2.0

8) Notes: 1) Initial and routine pile load tests shall be carried out on the piles at site to confirm the capacity of pile worked out theoretically.

(K.K.Thaker)

Sheet No.1062

11-06-2012

Page 635: Binder 9 with uploaded drawings and approved document

Sr.

Leng

thW

idth

CN

cN

q - 1

NS

cS

qS

dcdq

dic

iqi

0.5

No.

mm

mK

g/cm

2de

gree

gm/c

cW

qW

t / m

2

11.

001.

002.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.44

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

1.00

15

22.

002.

002.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.22

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.75

13

33.

003.

002.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.15

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.67

12

44.

004.

002.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.11

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.63

12

51.

001.

002.

500.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.56

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.75

16

62.

002.

002.

500.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.28

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.63

14

73.

003.

002.

500.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.19

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.58

13

84.

004.

002.

500.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.14

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.56

12

91.

001.

003.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.67

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.50

17

102.

002.

003.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.33

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.50

14

113.

003.

003.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.22

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.50

13

124.

004.

003.

000.

399

6.82

0.72

0.57

1.30

1.20

0.80

1.17

1.00

1.00

1.00

1.00

1.00

1.76

0.88

1.00

0.50

13

1) F

acto

r of s

afet

y is

2.5

2) D

epth

of f

ound

atio

n sh

all b

e fr

om E

G L

Dep

th o

f Fo

unda

tion

Wat

er T

able

C

orre

ctio

nB

earin

g C

apac

ity F

acto

rsS

hape

Fac

tors

Not

e :-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (P

hase

4 )

of O

NG

C a

t Haz

ira, S

urat

, L &

T L

tdFo

r Is

olat

ed S

quar

e Fo

otin

g

Proj

ect :

Dep

th F

acto

rsIn

clin

atio

n Fa

ctor

sU

nit W

eigh

tS

afe

Bea

ring

Cap

acity

Siz

e of

Fou

ndat

ion

She

ar P

aram

eter

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

adA

PP

EN

DIX

- 2

a (B

oreh

ole

No.

4)

Cal

cula

tion

of n

et S

afe

Bea

ring

Cap

acity

Bas

ed o

n Sh

ear P

aram

eter

s C

- qu

= 1

/ FS

[ 2

/ 3 C

Nc

dc S

c ic

+

d (N

q - 1

) Sq

dq iq

Wq

+ 0.

5 B

N S

di

W]

She

et N

o.10

63

11-0

6-20

12

Page 636: Binder 9 with uploaded drawings and approved document

Sr.

Leng

thW

idth

CN

cN

q - 1

NS

cS

qS

dcdq

dic

iqi

0.5

No.

mm

mK

g/cm

2de

gree

gm/c

cW

qW

t / m

2

11.

001.

002.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.46

1.23

1.23

1.00

1.00

1.00

1.71

0.86

1.00

1.00

20

22.

002.

002.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.23

1.12

1.12

1.00

1.00

1.00

1.71

0.86

1.00

0.75

17

33.

003.

002.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.15

1.08

1.08

1.00

1.00

1.00

1.71

0.86

1.00

0.67

16

44.

004.

002.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.12

1.06

1.06

1.00

1.00

1.00

1.71

0.86

1.00

0.63

16

51.

001.

002.

500.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.58

1.29

1.29

1.00

1.00

1.00

1.71

0.86

1.00

0.75

22

62.

002.

002.

500.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.29

1.14

1.14

1.00

1.00

1.00

1.71

0.86

1.00

0.63

18

73.

003.

002.

500.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.19

1.10

1.10

1.00

1.00

1.00

1.71

0.86

1.00

0.58

17

84.

004.

002.

500.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.14

1.07

1.07

1.00

1.00

1.00

1.71

0.86

1.00

0.56

17

91.

001.

003.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.69

1.35

1.35

1.00

1.00

1.00

1.71

0.86

1.00

0.50

24

102.

002.

003.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.35

1.17

1.17

1.00

1.00

1.00

1.71

0.86

1.00

0.50

20

113.

003.

003.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.23

1.12

1.12

1.00

1.00

1.00

1.71

0.86

1.00

0.50

18

124.

004.

003.

000.

4612

7.55

1.07

0.87

1.30

1.20

0.80

1.17

1.09

1.09

1.00

1.00

1.00

1.71

0.86

1.00

0.50

18

1) F

acto

r of s

afet

y is

2.5

2) D

epth

of f

ound

atio

n sh

all b

e fr

om E

G L

Dep

th o

f Fo

unda

tion

Wat

er T

able

C

orre

ctio

nB

earin

g C

apac

ity F

acto

rsS

hape

Fac

tors

Not

e :-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (P

hase

4 )

of O

NG

C a

t Haz

ira, S

urat

, L &

T L

tdFo

r Is

olat

ed S

quar

e Fo

otin

g

Proj

ect :

Dep

th F

acto

rsIn

clin

atio

n Fa

ctor

sU

nit W

eigh

tS

afe

Bea

ring

Cap

acity

Siz

e of

Fou

ndat

ion

She

ar P

aram

eter

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad AP

PE

ND

IX -

2 b

(Bor

ehol

e N

o. 5

)

Cal

cula

tion

of n

et S

afe

Bea

ring

Cap

acity

Bas

ed o

n Sh

ear P

aram

eter

s C

- qu

= 1

/ FS

[ 2

/ 3 C

Nc

dc S

c ic

+

d (N

q - 1

) Sq

dq iq

Wq

+ 0.

5 B

N S

di

W]

She

et N

o.10

64

11-0

6-20

12

Page 637: Binder 9 with uploaded drawings and approved document

Sr.

Leng

thW

idth

CN

cN

q - 1

NS

cS

qS

dcdq

dic

iqi

0.5

No.

mm

mK

g/cm

2de

gree

gm/c

cW

qW

t / m

2

11.

001.

002.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.41

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

1.00

7

22.

002.

002.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.20

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.75

6

33.

003.

002.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.14

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.67

5

44.

004.

002.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.10

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.63

5

51.

001.

002.

500.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.51

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.75

7

62.

002.

002.

500.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.26

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.63

6

73.

003.

002.

500.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.17

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.58

6

84.

004.

002.

500.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.13

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.56

5

91.

001.

003.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.61

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.50

8

102.

002.

003.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.31

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.50

6

113.

003.

003.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.20

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.50

6

124.

004.

003.

000.

242

5.46

0.13

0.10

1.30

1.20

0.80

1.15

1.00

1.00

1.00

1.00

1.00

1.70

0.85

1.00

0.50

6

1) F

acto

r of s

afet

y is

2.5

2) D

epth

of f

ound

atio

n sh

all b

e fr

om E

G L

Dep

th o

f Fo

unda

tion

Wat

er T

able

C

orre

ctio

nB

earin

g C

apac

ity F

acto

rsS

hape

Fac

tors

Not

e :-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (P

hase

4 )

of O

NG

C a

t Haz

ira, S

urat

, L &

T L

tdFo

r Is

olat

ed S

quar

e Fo

otin

g

Proj

ect :

Dep

th F

acto

rsIn

clin

atio

n Fa

ctor

sU

nit W

eigh

tS

afe

Bea

ring

Cap

acity

Siz

e of

Fou

ndat

ion

She

ar P

aram

eter

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad AP

PE

ND

IX -

2 C

(B

oreh

ole

No.

6)

Cal

cula

tion

of n

et S

afe

Bea

ring

Cap

acity

Bas

ed o

n Sh

ear P

aram

eter

s C

- qu

= 1

/ FS

[ 2

/ 3 C

Nc

dc S

c ic

+

d (N

q - 1

) Sq

dq iq

Wq

+ 0.

5 B

N S

di

W]

She

et N

o.10

65

11-0

6-20

12

Page 638: Binder 9 with uploaded drawings and approved document

Sr.

Leng

thW

idth

CN

cN

q - 1

NS

cS

qS

dcdq

dic

iqi

0.5

No.

mm

mK

g/cm

2de

gree

gm/c

cW

qW

t / m

2

11.

001.

002.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.47

1.23

1.23

1.00

1.00

1.00

1.76

0.88

1.00

1.00

18

22.

002.

002.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.23

1.12

1.12

1.00

1.00

1.00

1.76

0.88

1.00

0.75

15

33.

003.

002.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.16

1.08

1.08

1.00

1.00

1.00

1.76

0.88

1.00

0.67

15

44.

004.

002.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.12

1.06

1.06

1.00

1.00

1.00

1.76

0.88

1.00

0.63

14

51.

001.

002.

500.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.58

1.29

1.29

1.00

1.00

1.00

1.76

0.88

1.00

0.75

20

62.

002.

002.

500.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.29

1.15

1.15

1.00

1.00

1.00

1.76

0.88

1.00

0.63

17

73.

003.

002.

500.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.19

1.10

1.10

1.00

1.00

1.00

1.76

0.88

1.00

0.58

16

84.

004.

002.

500.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.15

1.07

1.07

1.00

1.00

1.00

1.76

0.88

1.00

0.56

15

91.

001.

003.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.70

1.35

1.35

1.00

1.00

1.00

1.76

0.88

1.00

0.50

22

102.

002.

003.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.35

1.17

1.17

1.00

1.00

1.00

1.76

0.88

1.00

0.50

18

113.

003.

003.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.23

1.12

1.12

1.00

1.00

1.00

1.76

0.88

1.00

0.50

17

124.

004.

003.

000.

3813

7.82

1.20

0.99

1.30

1.20

0.80

1.17

1.09

1.09

1.00

1.00

1.00

1.76

0.88

1.00

0.50

16

1) F

acto

r of s

afet

y is

2.5

2) D

epth

of f

ound

atio

n sh

all b

e fr

om E

G L

Dep

th o

f Fo

unda

tion

Wat

er T

able

C

orre

ctio

nB

earin

g C

apac

ity F

acto

rsS

hape

Fac

tors

Not

e :-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (P

hase

4 )

of O

NG

C a

t Haz

ira, S

urat

, L &

T L

tdFo

r Is

olat

ed S

quar

e Fo

otin

g

Proj

ect :

Dep

th F

acto

rsIn

clin

atio

n Fa

ctor

sU

nit W

eigh

tS

afe

Bea

ring

Cap

acity

Siz

e of

Fou

ndat

ion

She

ar P

aram

eter

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad AP

PE

ND

IX -

2 d

(Bor

ehol

e N

o. 9

)

Cal

cula

tion

of n

et S

afe

Bea

ring

Cap

acity

Bas

ed o

n Sh

ear P

aram

eter

s C

- qu

= 1

/ FS

[ 2

/ 3 C

Nc

dc S

c ic

+

d (N

q - 1

) Sq

dq iq

Wq

+ 0.

5 B

N S

di

W]

She

et N

o.10

66

11-0

6-20

12

Page 639: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

ofFo

otin

g D

W

idth

ofFo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0SB

Cp

(p+

p 0)/p

0C

orre

ctio

nfo

r dep

thC

onso

lidat

ion

Settl

emen

t Sc

mm

mgm

/ cc

mT

/ m2

T / m

2T

/ m2

mm

10.

152.

001.

002.

000.

821.

763.

005.

2815

3.68

1.70

0.7

0.66

17.5

20.

152.

002.

003.

150.

821.

763.

586.

2913

3.98

1.63

0.7

0.73

28.2

30.

152.

003.

003.

150.

821.

763.

586.

2912

5.22

1.83

0.7

0.80

38.0

40.

152.

004.

003.

150.

821.

763.

586.

2912

6.11

1.97

0.7

0.85

45.5

50.

152.

501.

002.

000.

821.

763.

506.

1616

4.00

1.65

0.7

0.65

16.2

60.

152.

502.

002.

650.

821.

763.

836.

7314

4.89

1.73

0.7

0.73

26.4

70.

152.

503.

002.

650.

821.

763.

836.

7313

6.13

1.91

0.7

0.75

32.4

80.

152.

504.

002.

150.

821.

763.

586.

2912

7.70

2.22

0.7

0.81

34.8

90.

153.

001.

002.

000.

821.

764.

007.

0417

4.32

1.61

0.7

0.63

15.2

100.

153.

002.

002.

150.

821.

764.

087.

1714

6.04

1.84

0.7

0.73

24.0

110.

153.

003.

002.

150.

821.

764.

087.

1713

7.23

2.01

0.7

0.73

27.4

120.

153.

004.

002.

150.

821.

764.

087.

1713

8.02

2.12

0.7

0.77

31.3

fact

orre

late

dto

pore

pres

sure

para

met

er

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Cal

cula

tion

of S

ettle

men

t (B

H 4

)Se

ttlem

ent S

C =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P 0

+

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

67

11-0

6-20

12

Page 640: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

ofFo

otin

g D

W

idth

ofFo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0SB

Cp

(p+

p 0)/p

0C

orre

ctio

nfo

rde

pth

Con

solid

atio

nSe

ttlem

ent S

c

mm

mgm

/ cc

mT

/ m2

T / m

2T

/ m2

mm

10.

182.

001.

002.

000.

911.

713.

005.

1320

5.01

1.98

0.7

0.66

25.8

20.

182.

002.

003.

150.

911.

713.

586.

1117

5.38

1.88

0.7

0.73

41.5

30.

182.

003.

003.

150.

911.

713.

586.

1116

7.01

2.15

0.7

0.80

54.9

40.

182.

004.

003.

150.

911.

713.

586.

1116

8.19

2.34

0.7

0.85

65.2

50.

182.

501.

002.

000.

911.

713.

505.

9922

5.51

1.92

0.7

0.65

24.2

60.

182.

502.

002.

650.

911.

713.

836.

5418

6.64

2.02

0.7

0.73

38.8

70.

182.

503.

002.

650.

911.

713.

836.

5417

8.28

2.27

0.7

0.75

46.9

80.

182.

504.

002.

150.

911.

713.

586.

1117

10.3

82.

700.

70.

8149

.5

90.

183.

001.

002.

000.

911.

714.

006.

8424

6.02

1.88

0.7

0.63

23.0

100.

183.

002.

002.

150.

911.

714.

086.

9720

8.28

2.19

0.7

0.73

35.2

110.

183.

003.

002.

150.

911.

714.

086.

9718

9.84

2.41

0.7

0.73

39.6

120.

183.

004.

002.

150.

911.

714.

086.

9718

10.8

72.

560.

70.

7744

.8

fact

orre

late

dto

pore

pres

sure

para

met

er

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Cal

cula

tion

of S

ettle

men

t (B

H 5

)Se

ttlem

ent S

C =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P

0 +

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

68

11-0

6-20

12

Page 641: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

ofFo

otin

g D

W

idth

ofFo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0SB

Cp

(p+

p 0)/p

0C

orre

ctio

nfo

rde

pth

Con

solid

atio

nSe

ttlem

ent S

c

mm

mgm

/ cc

mT

/ m2

T / m

2T

/ m2

mm

10.

292.

001.

002.

000.

921.

73.

005.

107

1.66

1.33

0.7

0.66

17.1

20.

292.

002.

002.

000.

921.

73.

005.

106

2.54

1.50

0.7

0.73

27.1

30.

292.

003.

002.

000.

921.

73.

005.

105

3.05

1.60

0.7

0.80

34.2

40.

292.

004.

002.

000.

921.

73.

005.

105

3.38

1.66

0.7

0.85

39.6

50.

292.

501.

001.

500.

921.

73.

255.

537

2.33

1.42

0.7

0.65

15.7

60.

292.

502.

001.

500.

921.

73.

255.

536

3.17

1.57

0.7

0.73

22.8

70.

292.

503.

001.

500.

921.

73.

255.

536

3.60

1.65

0.7

0.75

26.0

80.

292.

504.

001.

500.

921.

73.

255.

535

3.86

1.70

0.7

0.81

29.5

90.

293.

001.

001.

000.

921.

73.

505.

958

3.40

1.57

0.7

0.63

13.2

100.

293.

002.

001.

000.

921.

73.

505.

956

4.02

1.68

0.7

0.73

17.3

110.

293.

003.

001.

000.

921.

73.

505.

956

4.28

1.72

0.7

0.73

18.1

120.

293.

004.

001.

000.

921.

73.

505.

956

4.43

1.74

0.7

0.77

19.7

fact

orre

late

dto

pore

pres

sure

para

met

er

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Cal

cula

tion

of S

ettle

men

t (B

H 6

)Se

ttlem

ent S

C =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P

0 +

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

69

11-0

6-20

12

Page 642: Binder 9 with uploaded drawings and approved document

Sr. N

o.D

epth

of

Foot

ing

D

Wid

th o

f Fo

otin

g B

m

vH

pSB

Cfa

ctor

rela

ted

to p

ore

pres

sure

para

met

er

Cor

rect

ion

for

dept

hC

onso

lidat

ion

Settl

emen

t Sc

mm

mT

/ m2

T / m

2m

m

12.

001.

000.

121.

505.

8818

0.3

0.73

23.2

22.

002.

000.

121.

507.

9315

0.3

0.76

32.6

32.

003.

000.

121.

509.

6015

0.3

0.80

41.3

42.

004.

000.

121.

509.

9314

0.3

0.83

44.3

52.

501.

000.

121.

008.

8920

0.3

0.73

23.3

62.

502.

000.

121.

0010

.88

170.

30.

7328

.6

72.

503.

000.

121.

0011

.76

160.

30.

7531

.9

82.

504.

000.

121.

0011

.85

150.

30.

7833

.4

93.

001.

000.

120.

5014

.08

220.

30.

7318

.5

103.

002.

000.

120.

5014

.22

180.

30.

7318

.7

113.

003.

000.

120.

5014

.49

170.

30.

7319

.0

123.

004.

000.

120.

5014

.17

160.

30.

7519

.1

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Cal

cula

tion

of S

ettle

men

t (B

H 9

)

Settl

emen

t SC =

mv

H P

Proj

ect:-

Prop

osed

stru

ctur

esof

plan

tofA

dditi

onal

gas

proc

essi

ngfa

cilit

ies

proj

ect(

Phas

e4

)ofO

NG

Cat

Haz

ira,

Sura

t, L

& T

Ltd

She

et N

o.10

70

11-0

6-20

12

Page 643: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

of

Foot

ing

D

Wid

th o

f Fo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0p

(p+

p 0)/p

0fa

ctor

rela

ted

to

pore

pres

sure

para

met

er

Cor

rect

ion

for d

epth

Con

solid

atio

nSe

ttlem

ent S

cA

llow

able

Bea

ring

Pres

sure

mm

mgm

/ cc

mT

/ m2

T / m

2m

mT

/ m2

10.

152.

001.

002.

000.

821.

763.

005.

285.

942.

130.

70.

6625

24

20.

152.

002.

003.

150.

821.

763.

586.

293.

421.

540.

70.

7325

11

30.

152.

003.

003.

150.

821.

763.

586.

293.

071.

490.

70.

8025

7

40.

152.

004.

003.

150.

821.

763.

586.

292.

841.

450.

70.

8525

6

50.

152.

501.

002.

000.

821.

763.

506.

167.

172.

160.

70.

6525

29

60.

152.

502.

002.

650.

821.

763.

836.

734.

551.

680.

70.

7325

13

70.

152.

503.

002.

650.

821.

763.

836.

734.

361.

650.

70.

7525

9

80.

152.

504.

002.

150.

821.

763.

586.

294.

871.

770.

70.

8125

8

90.

153.

001.

002.

000.

821.

764.

007.

048.

412.

190.

70.

6325

34

100.

153.

002.

002.

150.

821.

764.

087.

176.

381.

890.

70.

7325

15

110.

153.

003.

002.

150.

821.

764.

087.

176.

381.

890.

70.

7325

12

120.

153.

004.

002.

150.

821.

764.

087.

175.

891.

820.

70.

7725

9

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Allo

wab

le B

earin

g Pr

essu

re fo

r 25

mm

Set

tlem

ent (

BH

4)

Settl

emen

t SC =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P

0 +

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

71

11-0

6-20

12

Page 644: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

of

Foot

ing

D

Wid

th o

f Fo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0p

(p+

p 0)/p

0fa

ctor

rela

ted

to

pore

pres

sure

para

met

er

Cor

rect

ion

for d

epth

Con

solid

atio

nSe

ttlem

ent S

cA

llow

able

Bea

ring

Pres

sure

mm

mgm

/ cc

mT

/ m2

T / m

2m

mT

/ m2

10.

182.

001.

002.

000.

911.

713.

005.

134.

791.

930.

70.

6625

19

20.

182.

002.

003.

150.

911.

713.

586.

112.

821.

460.

70.

7325

9

30.

182.

003.

003.

150.

911.

713.

586.

112.

541.

420.

70.

8025

6

40.

182.

004.

003.

150.

911.

713.

586.

112.

361.

390.

70.

8525

5

50.

182.

501.

002.

000.

911.

713.

505.

995.

781.

960.

70.

6525

23

60.

182.

502.

002.

650.

911.

713.

836.

543.

731.

570.

70.

7325

10

70.

182.

503.

002.

650.

911.

713.

836.

543.

581.

550.

70.

7525

7

80.

182.

504.

002.

150.

911.

713.

586.

113.

981.

650.

70.

8125

6

90.

183.

001.

002.

000.

911.

714.

006.

846.

761.

990.

70.

6325

27

100.

183.

002.

002.

150.

911.

714.

086.

975.

191.

740.

70.

7325

12

110.

183.

003.

002.

150.

911.

714.

086.

975.

191.

740.

70.

7325

10

120.

183.

004.

002.

150.

911.

714.

086.

974.

811.

690.

70.

7725

8

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Allo

wab

le B

earin

g Pr

essu

re fo

r 25

mm

Set

tlem

ent (

BH

5)

Settl

emen

t SC =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P

0 +

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

72

11-0

6-20

12

Page 645: Binder 9 with uploaded drawings and approved document

Sr. N

o.C

omp

Inde

x C

cD

epth

of

Foot

ing

D

Wid

th o

f Fo

otin

g B

H

Void

s R

atio

e0

Fiel

dD

ensi

tyd

p 0p

(p+

p 0)/p

0fa

ctor

rela

ted

to

pore

pres

sure

para

met

er

Cor

rect

ion

for d

epth

Con

solid

atio

nSe

ttlem

ent S

cA

llow

able

Bea

ring

Pres

sure

mm

mgm

/ cc

mT

/ m2

T / m

2m

mT

/ m2

10.

292.

001.

002.

000.

921.

703.

005.

102.

601.

510.

70.

6625

.010

.4

20.

292.

002.

002.

000.

921.

703.

005.

102.

311.

450.

70.

7325

.05.

2

30.

292.

003.

002.

000.

921.

703.

005.

102.

081.

410.

70.

8025

.03.

7

40.

292.

004.

002.

000.

921.

703.

005.

101.

931.

380.

70.

8525

.03.

0

50.

292.

501.

001.

500.

921.

703.

255.

534.

181.

760.

70.

6525

.012

.8

60.

292.

502.

001.

500.

921.

703.

255.

533.

571.

650.

70.

7325

.06.

8

70.

292.

503.

001.

500.

921.

703.

255.

533.

421.

620.

70.

7525

.05.

3

80.

292.

504.

001.

500.

921.

703.

255.

533.

141.

570.

70.

8125

.04.

4

90.

293.

001.

001.

000.

921.

703.

505.

958.

102.

360.

70.

6325

.018

.2

100.

293.

002.

001.

000.

921.

703.

505.

956.

622.

110.

70.

7325

.010

.3

110.

293.

003.

001.

000.

921.

703.

505.

956.

622.

110.

70.

7325

.09.

0

120.

293.

004.

001.

000.

921.

703.

505.

956.

092.

020.

70.

7725

.07.

7

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Allo

wab

le B

earin

g Pr

essu

re fo

r 25

mm

Set

tlem

ent (

BH

6)

Settl

emen

t SC =

{ ( C

C H

) / (

1 +

e0 )

} lo

g 10 {

( P

0 +

P ) /

P0 }

Proj

ect:-

Pro

pose

d st

ruct

ures

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

She

et N

o.10

73

11-0

6-20

12

Page 646: Binder 9 with uploaded drawings and approved document

Sr. N

o.D

epth

of

Foot

ing

D

Wid

th o

f Fo

otin

g B

m

vH

pfa

ctor

rela

ted

to

pore

pres

sure

para

met

er

Cor

rect

ion

for

dept

h S

ettle

men

t Sc

Allo

wab

le

Bea

ring

Pres

sure

mm

mT

/ m2

mm

T / m

2

12.

001.

000.

121.

506.

350.

30.

7325

.019

22.

002.

000.

121.

506.

080.

30.

7625

.011

32.

003.

000.

121.

505.

810.

30.

8025

.09

42.

004.

000.

121.

505.

610.

30.

8325

.08

52.

501.

000.

121.

009.

520.

30.

7325

.021

62.

502.

000.

121.

009.

520.

30.

7325

.015

72.

503.

000.

121.

009.

210.

30.

7525

.013

82.

504.

000.

121.

008.

870.

30.

7825

.011

93.

001.

000.

120.

5019

.04

0.3

0.73

25.0

30

103.

002.

000.

120.

5019

.04

0.3

0.73

25.0

24

113.

003.

000.

120.

5019

.04

0.3

0.73

25.0

22

123.

004.

000.

120.

5018

.53

0.3

0.75

25.0

21

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

ad

Cal

cula

tion

of S

ettle

men

t (B

H 9

)

Settl

emen

t SC =

mv

H P

Proj

ect:-

Prop

osed

stru

ctur

esof

plan

tofA

dditi

onal

gas

proc

essi

ngfa

cilit

ies

proj

ect(

Phas

e4

)ofO

NG

Cat

Haz

ira,

Sura

t, L

& T

Ltd

She

et N

o.10

74

11-0

6-20

12

Page 647: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services.,Ahmedabad

NOTATIONS C Cohesion

Angle of internal f r ic t ion of soi l DS Disturbed Sample UDS Undisturbed Sample NMC Natural Moisture Content NP Non Plast ic Soi ls G Specif ic Gravity G Gravel Content M Si l t Content S Sand Content C Clay Content LL Liquid Limit PL Plast ic L imit PI Plast ic i ty Index Cc Compression Index K Coeff ic ient of Permeabi l i ty UCS Unconf ined Compression N SPT Value BH Bore Hole Suff ix The Number of Bore Holes Nc,Nq,N Bearing Capacity Factor Sc,Sq,S Shape Factors D Depth of foundat ion FS Factor of Safety Cv Coeff ic ient of consol idat ion UU Unconsol idated undrained t r iaxial test CU Consol idated undrained t r iaxial test CD Consol idated drained t r iaxial test GC Clayey Gravels GP Poorely Graded Gravels GW Wel l Graded Gravels SC Clayey Sand SM Si l ty Sand SW Wel Graded Sand SP Poorly Graded Sand CH Clays of High Plast ic i ty CI Clays of Intermediate Plast ic i ty CL Clays of Low Plast ic i ty MH Si l ts of High Plast ic i ty MI Si l ts of Intermediate Plast ic i ty ML Si l ts of Low Plast ic i ty

Sheet No.1075

11-06-2012

Page 648: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services.,Ahmedabad

REFERENCE Indian Standards Murthy V.N.S. Lambe T.W. Peck, R.S.Hanson W.E. Nayak, N.V. Kaniraj S.R. Alam Singh

IS 2720 Pt I I , I I I , IV, V, XII I , XXXI,XXVII,XXVIS1498,IS6403,IS 1904 Soi l Mechanics and Foundat ion engineering Dhanpat Rai and Sons Delhi Soi l test ing for Engineers Wi ley Easter Ltd. , New Delhi Foundat ion Engineering Asia Publ ishing House Foundat ion Engineering Manual Dhanpat Rai & Sons. Design Aids in soi l mechanics and Foundat ion Engineering Tata Mc Graw Hi l l Publ ishing Co. Ltd. Modern Geotechnical Eng. IBT Publ ishing & Distr ibutors Delhi .

Sheet No.1076

11-06-2012

Page 649: Binder 9 with uploaded drawings and approved document

KCT Consultancy Services, Ahmedabad

TABLE NO. – 1

RESULTS OF LABORATORY PERMEABILITY

Sr. No.

Bore Hole No.

Depth (m) Permeabil ity (mm/s)

1.

BH – 4 2.50

0.66 x 10- 6

2.

BH – 5 2.50

0.68 x 10- 6

3.

BH – 6 2.50

0.60 x 10- 6

4.

BH – 9 5.50

0.58 x 10- 6

( K K Thaker)

Sheet No.1077

11-06-2012

Page 650: Binder 9 with uploaded drawings and approved document

Sr. No. BH No. Depth (m) pH SO3 in 2:1 Water : Soil

Extract(mg/l)

Chlorides

1 BH 4 2.50 7.45 886 2013

2 BH 5 4.50 7.63 926 2003

3 BH 6 2.50 7.72 947 2014

4 BH 9 2.50 7.75 868 2045

Sr. No. Location pH Sulphate (SO3) (mg/l)

Chloride(mg/l)

Organic Inorganic

1 BH 4 7.65 Nil 905 1081 1036

2 BH 5 7.72 Nil 895 1015 1028

3 BH 6 7.53 Nil 907 1059 1053

4 BH 9 7.63 Nil 884 1083 1026

For KCT Consultancy Services

(K K Thaker)

Total Dissolved Solids

Table No. 2Results of Chemical Analysis of Soil

Table No. 3Results of Chemical Analysis of Ground Water

Sheet No.1078

11-06-2012

Page 651: Binder 9 with uploaded drawings and approved document

4

mgm

/ cc

%%

%%

%%

%%

%K

g/cm

2%

Kg/

cm2

Deg

ree

Kg/

cm2

%%

10.

00D

S-

10.6

4-

13

5442

5529

26-

--

CH

--

--

--

--

20.

50S

PT

--

-1

1047

4254

2826

--

-C

H-

--

-19

--

-

31.

50S

PT

--

-1

844

4754

2529

--

-C

H-

--

-16

--

-

42.

50U

DS

1.76

21.3

42.

642

646

4655

2629

80.

2654

.3C

H0.

399

-0.

15-

-0.

8245

.1

53.

00S

PT

--

-2

943

4657

3126

--

-C

H-

--

-8

--

-

64.

50S

PT

--

-2

1071

1751

3615

--

-M

H-

--

-2

--

-

75.

50U

DS

1.70

35.7

02.

642

7915

4N

PN

PN

P-

--

SM

-25

--

--

1.11

52.6

86.

00S

PT

--

-1

876

1550

3911

--

-M

H-

--

-10

--

-

97.

50S

PT

--

-0

972

1955

4114

--

-M

H-

--

-8

--

-

108.

50U

DS

1.76

22.0

62.

660

1679

550

428

--

-M

H-

28-

--

-0.

8445

.7

119.

00S

PT

--

-1

8313

3N

PN

PN

P-

--

SM

--

--

15-

--

1210

.50

SP

T-

--

082

144

NP

NP

NP

--

-S

M-

--

-19

--

-

1311

.50

DS

--

-1

8213

4N

PN

PN

P-

--

SM

--

--

--

--

1412

.00

SP

T-

--

083

143

NP

NP

NP

--

-S

M-

--

-22

--

-

1513

.50

SP

T-

--

180

154

NP

NP

NP

--

-S

M-

--

-28

--

-

1614

.50

DS

--

-2

7915

4N

PN

PN

P-

--

SM

--

--

--

--

1715

.00

SP

T-

--

082

153

NP

NP

NP

--

-S

M-

--

-41

--

-

1816

.50

SP

T-

--

482

122

21N

PN

P-

--

SM

--

--

59-

--

1917

.50

DS

--

-4

8212

220

NP

NP

--

-S

M-

--

--

--

-

2018

.00

SP

T-

--

133

3432

4029

11-

--

CI

--

--

> 10

0-

--

2120

.00

SP

T-

--

478

144

24N

PN

P-

--

SM

--

--

94-

--

Gravel

Sand

Type

of

Sam

ple

BH

No.

:-

Dep

th

Soil Classification

Proj

ect :

-

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

adR

ES

ULT

S O

F LA

BO

RA

TO

RY

TE

ST

Prop

osed

str

uctu

res

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

Gra

in S

ize

Ana

lysi

sFi

eld

Den

sity

Nat

ural

Moi

stur

eC

onte

nt

Specific Gravity

ShrinkageLimit

SPT N Value

Void Ratio

Silt

Clay

LiquidLimit

PlasticLimit

Shea

r Par

amet

er

SwellingPressure

Con

sist

ancy

lim

its

Porosity

Sr No

Rock Quality Designation

C

UnconfinedCompression

Test

Compression Index CC

Free Swell Index

PlasticityIndex

She

et N

o.10

79

11-0

6-20

12

Page 652: Binder 9 with uploaded drawings and approved document

5

mgm

/ cc

%%

%%

%%

%%

%K

g/cm

2%

Kg/

cm2

Deg

ree

Kg/

cm2

%%

10.

00D

S-

--

-

21.

50S

PT

--

-1

1342

4459

3029

--

-C

H-

--

-16

--

-

32.

50U

DS

1.71

23.2

42.

650

1044

4658

2929

70.

2246

.3C

H0.

4612

-0.

18-

-0.

9147

.6

43.

00S

PT

--

-1

1343

4355

2629

--

-C

H-

--

-4

--

-

54.

50S

PT

--

-0

8612

2N

PN

PN

P-

--

SM

--

--

6-

--

65.

50U

DS

1.76

31.5

42.

642

8412

2N

PN

PN

P-

--

SM

-26

--

--

0.97

49.3

76.

00S

PT

--

-0

1450

3653

4013

--

-M

H-

--

-9

--

-

87.

50S

PT

--

-6

7912

3N

PN

PN

P-

--

SM

--

--

27-

--

98.

50U

DS

1.95

28.4

32.

656

7912

3N

PN

PN

P-

--

SM

-32

--

--

0.75

42.7

109.

00S

PT

--

-6

7715

2N

PN

PN

P-

--

SM

--

--

30-

--

1110

.50

SP

T-

--

478

153

NP

NP

NP

--

-S

M-

--

-23

--

-

1211

.50

DS

--

-5

7814

3N

PN

PN

P-

--

SM

--

--

--

--

1312

.00

SP

T-

--

381

133

NP

NP

NP

--

-S

M-

--

-45

--

-

1413

.50

SP

T-

--

383

122

NP

NP

NP

--

-S

M-

--

-39

--

-

1514

.50

DS

--

-6

8012

2N

PN

PN

P-

--

SM

--

--

--

--

1615

.00

SP

T-

--

056

2420

2415

9-

--

SC

--

--

38-

--

1716

.50

SP

T-

--

283

123

NP

NP

NP

--

-S

M-

--

-80

--

-

1817

.50

DS

--

-0

8512

3N

PN

PN

P-

--

SM

--

--

--

--

1918

.00

SP

T-

--

083

152

NP

NP

NP

--

-S

M-

--

-92

--

-

2019

.50

SP

T-

--

030

3832

3530

5-

--

MI

--

--

77-

--

2120

.50

DS

--

-7

7614

3N

PN

PN

P-

--

SM

--

--

--

--

2221

.00

SP

T-

--

328

3732

3630

6-

--

MI

--

--

83-

--

2322

.50

SP

T-

--

1619

3233

3832

6-

--

MI

--

--

91-

--

2423

.50

UD

S2.

2623

.51

2.65

1225

3033

3629

7-

--

MI

0.10

36-

--

-0.

4531

.0

2525

.00

SP

T-

--

1525

3030

3631

5-

--

MI

--

--

> 10

0-

--

Fille

d up

Cla

y of

hig

h pl

astic

ity w

ith d

ebris

and

gra

vels

-

Gravel

Sand

Type

of

Sam

ple

BH

No.

:-

Dep

th

Soil Classification

Proj

ect :

-

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

adR

ES

ULT

S O

F LA

BO

RA

TO

RY

TE

ST

Prop

osed

str

uctu

res

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

Gra

in S

ize

Ana

lysi

sFi

eld

Den

sity

Nat

ural

Moi

stur

eC

onte

nt

Specific Gravity

ShrinkageLimit

SPT N Value

Void Ratio

Silt

Clay

LiquidLimit

Plastic Limit

Shea

r Par

amet

er

SwellingPressure

Con

sist

ancy

lim

its

Porosity

Sr No

Rock Quality Designation

C

UnconfinedCompression

Test

Compression Index CC

Free Swell Index

Plasticity Index

She

et N

o.10

80

11-0

6-20

12

Page 653: Binder 9 with uploaded drawings and approved document

6

mgm

/ cc

%%

%%

%%

%%

%K

g/cm

2%

Kg/

cm2

Deg

ree

Kg/

cm2

%%

10.

00D

S-

--

-

21.

50S

PT

--

-0

2539

3656

2729

7-

61.3

CH

--

--

18-

--

32.

50U

DS

1.70

23.4

02.

650

2437

3954

2628

80.

2152

.4C

H0.

242

-0.

29-

-0.

9248

.0

43.

00S

PT

--

-1

1943

3751

2625

--

-C

H-

--

-4

--

-

54.

50S

PT

--

-1

8610

3N

PN

PN

P-

--

SM

--

--

6-

--

65.

50D

S-

--

016

6420

5239

13-

--

MH

--

--

--

--

76.

00S

PT

--

-1

1867

1454

4014

--

-M

H-

--

-4

--

-

87.

50S

PT

--

-0

8214

4N

PN

PN

P-

--

SM

--

--

12-

--

98.

50U

DS

1.78

29.3

42.

671

8214

3N

PN

PN

P-

--

SM

-28

--

--

0.94

48.5

109.

00S

PT

--

-13

7112

4N

PN

PN

P-

--

SM

--

--

20-

--

1110

.50

SP

T-

--

1269

154

NP

NP

NP

--

-S

M-

--

-33

--

-

1211

.50

DS

--

-1

8710

2N

PN

PN

P-

--

SM

--

--

--

--

1312

.00

SP

T-

--

183

133

NP

NP

NP

--

-S

M-

--

-42

--

-

1413

.50

SP

T-

--

285

103

NP

NP

NP

--

-S

M-

--

-44

--

-

1514

.50

DS

--

-56

2216

6N

PN

PN

P-

--

GM

--

--

--

--

1615

.00

SP

T-

--

085

123

NP

NP

NP

--

-S

M-

--

-48

--

-

1716

.50

SP

T-

--

157

2418

2113

8-

--

SC

--

--

52-

--

1817

.50

UD

S1.

9921

.34

2.66

221

3839

5527

28-

--

CH

0.41

18-

0.11

--

0.62

38.3

1918

.00

SP

T-

--

126

3637

5122

29-

--

CH

--

--

51-

--

2020

.00

SP

T-

--

025

3936

5628

28-

--

CH

--

--

72-

--

Fille

d up

Cla

y of

hig

h pl

astic

ity w

ith d

ebris

and

gra

vels

-

Gravel

Sand

Type

of

Sam

ple

BH

No.

:-

Dep

th

Soil Classification

Proj

ect :

-

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

adR

ES

ULT

S O

F LA

BO

RA

TO

RY

TE

ST

Prop

osed

str

uctu

res

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

Gra

in S

ize

Ana

lysi

sFi

eld

Den

sity

Nat

ural

Moi

stur

eC

onte

nt

Specific Gravity

ShrinkageLimit

SPT N Value

Void Ratio

Silt

Clay

Liquid Limit

PlasticLimit

Shea

r Par

amet

er

Swelling Pressure

Con

sist

ancy

lim

its

Porosity

Sr No

Rock Quality Designation

C

Unconfined Compression

Test

Compression Index CC

Free Swell Index

PlasticityIndex

She

et N

o.10

81

11-0

6-20

12

Page 654: Binder 9 with uploaded drawings and approved document

9

mgm

/ cc

%%

%%

%%

%%

%K

g/cm

2%

Kg/

cm2

Deg

ree

Kg/

cm2

%%

10.

00D

S-

--

-

21.

50S

PT

--

-0

2238

4057

3027

--

-C

H-

--

-15

--

-

32.

50U

DS

1.76

26.5

72.

640

1248

4054

2727

70.

2853

.1C

H0.

3813

-0.

17-

-0.

9047

.3

43.

00S

PT

--

-2

1545

3858

2929

--

-C

H-

--

-8

--

-

54.

50S

PT

--

-0

8215

3N

PN

PN

P-

--

SM

--

--

13-

--

65.

50U

DS

1.86

31.0

52.

632

8113

4N

PN

PN

P-

--

SM

-29

--

--

0.85

46.0

76.

00S

PT

--

-2

8610

2N

PN

PN

P-

--

SM

--

--

21-

--

87.

50S

PT

--

-2

7915

4N

PN

PN

P-

--

SM

--

--

24-

--

98.

50U

DS

1.95

24.6

12.

642

8212

4N

PN

PN

P-

--

SM

-33

--

--

0.69

40.7

109.

00S

PT

--

-2

8014

4N

PN

PN

P-

--

SM

--

--

28-

--

1110

.50

SP

T-

--

1667

134

21N

PN

P-

--

SM

--

--

32-

--

1211

.50

DS

--

-5

7714

4N

PN

PN

P-

--

SM

--

--

--

--

1312

.00

SP

T-

--

384

103

NP

NP

NP

--

-S

M-

--

-44

--

-

1413

.50

SP

T-

--

577

153

NP

NP

NP

--

-S

M-

--

-43

--

-

1514

.50

DS

--

-15

6813

4N

PN

PN

P-

--

SM

--

--

--

--

1615

.00

SP

T-

--

5820

166

NP

NP

NP

--

-G

M-

--

-54

--

-

1716

.50

SP

T-

--

5619

196

NP

NP

NP

--

-G

M-

--

-64

--

-

1817

.50

DS

--

-16

4222

2029

209

--

-S

C-

--

--

--

-

1918

.00

SP

T-

--

1323

3133

3630

6-

--

MI

--

--

59-

--

2020

.00

SP

T-

--

225

4033

3832

6-

--

MI

--

--

94-

--

Fille

d up

Cla

yey

San

d w

ith d

ebris

and

gra

vels

-

Gravel

Sand

Type

of

Sam

ple

BH

No.

:-

Dep

th

Soil Classification

Proj

ect :

-

KC

T C

onsu

ltan

cy S

ervi

ces,

Ahm

edab

adR

ES

ULT

S O

F LA

BO

RA

TO

RY

TE

ST

Prop

osed

str

uctu

res

of p

lant

of A

dditi

onal

gas

pro

cess

ing

faci

litie

s pr

ojec

t (Ph

ase

4 ) o

f ON

GC

at H

azira

, Sur

at, L

& T

Ltd

Gra

in S

ize

Ana

lysi

sFi

eld

Den

sity

Nat

ural

Moi

stur

eC

onte

nt

Specific Gravity

ShrinkageLimit

SPT N Value

Void Ratio

Silt

Clay

Liquid Limit

PlasticLimit

Shea

r Par

amet

er

Swelling Pressure

Con

sist

ancy

lim

its

Porosity

Sr No

Rock Quality Designation

C

Unconfined Compression

Test

Compression Index CC

Free Swell Index

PlasticityIndex

She

et N

o.10

82

11-0

6-20

12

Page 655: Binder 9 with uploaded drawings and approved document

She

et N

o.10

83

11-0

6-20

12

Page 656: Binder 9 with uploaded drawings and approved document

4N-365, E-102598.466m20.0 m

From To

m m m N 1 N 2 N 3 N0.00 0.00 0.00 0.50 DS - - - - - -0.50 0.50 0.50 1.50 SPT 6 9 10 19 - -1.001.50 1.50 1.50 2.50 SPT 5 6 10 16 - -2.002.50 2.50 2.50 3.00 UDS - - - - - -3.00 0.00 to 3.50 m 3.00 3.00 4.50 SPT 2 3 5 8 - -3.504.004.50 4.50 4.50 5.50 SPT 1 1 1 2 - -5.005.50 5.50 5.50 6.00 UDS - - - - - -

6.00 6.00 6.00 7.50 SPT 2 4 6 10 - -6.507.007.50 7.50 7.50 8.50 SPT 2 3 5 8 - -8.00 6.70 to 8.70 m8.50 8.50 8.50 9.00 UDS - - - - - -9.00 9.00 9.00 10.50 SPT 5 5 10 15 - -9.5010.0010.50 10.50 10.50 11.50 SPT 6 8 11 19 - -11.0011.50 11.50 11.50 12.00 DS - - - - - -12.00 8.70 to 12.60 m 12.00 12.00 13.50 SPT 7 9 13 22 - -12.5013.0013.50 13.50 13.50 14.50 SPT 12 13 15 28 - -14.0014.50 14.50 14.50 15.00 DS - - - - - -15.00 15.00 15.00 16.50 SPT 17 20 21 41 - -15.5016.00 12.60 to 16.00 m16.50

16.50 16.50 17.50 SPT 13 21 38 59 - -

17.0017.50 17.50 17.50 18.00 DS - - - - - -18.00 18.00 18.00 20.00 SPT 42 52 - >100 - -18.50 10cm19.0019.50

20.00 20.00 20.00 20.45 SPT 33 42 52 94 - -19.60 to 20.00 m

Rot

ary

Dril

ling

by m

ud c

ircul

atio

n

Not

Use

d Blackish, fine to medium grained, silty sand withoccational gravels (SM)

Blackish, fine to very fine grained, silt of highcompressibility with occational gravels (MH)

Blackish grey, fine to very fine grained, silty sand with occational gravels (SM) 5.15 to 6.70 m

Blackish grey, fine to very fine grained, silt ofhigh compressibility with occational gravels (MH)3.50 to 5.15m

Dark brownish, fine to very fine grained, siltyclays of high plasticity with occational gravels(CH)

Reddish brown, fine to coarse grained, silty sand with little plastic fines and litttel gravels (SM)

Dark brown,fine to very fine grained, sandy clays of intermediate plasticity with occational gravels(CI) 17.90 to 19.60 m

Dark brownish, fine to medium grained, siltysand with little plastic fines and little gravels (SM)16.00 to 17.90 m

Blackish, fine to medium grained, silty sand withoccational gravels (SM)

Core Reco-very (%)

RQD (%) Remarks

m

BORE LOG DATA SHEET

Method of Boring

Depth

Cas

ing

Not

atio

n

Soil DescriptionDepth ofSample

Drill RunType ofSample

SPT N Value/Penetration of S.S.S

Depth of Termination : Diameter of Bore : 150 mmDepth of Water Table : Encountered at m depth during investigation

Co-ordinates: Date of Completion: 07-07-10Reduced Level:

KCT Consultancy Services, AhmedabadProject : L & T , HAZIRA

Bore Hole No. : Date of commencement: 07-02-10

water table encountered at m depth during investigation

Fig. No.( )

Sheet No.1084

11-06-2012

Page 657: Binder 9 with uploaded drawings and approved document

5N-780, E-110099.423m25.0 m

From To

m m m N 1 N 2 N 3 N0.00

0.00 0.00 1.50 DS - - - - - -

0.501.00

1.50 1.50 1.50 2.50 SPT 4 7 9 16 - -2.002.50 2.50 2.50 3.00 UDS - - - - - -3.00 3.00 3.00 4.50 SPT 1 2 2 4 - -3.504.004.50 4.50 4.50 5.50 SPT 2 3 3 6 - -5.005.50 3.70 to 6.00 m 5.50 5.50 6.00 UDS - - - - - -6.00

6.00 6.00 7.50 SPT 4 4 5 9 - -

6.507.007.50 7.50 7.50 8.50 SPT 7 12 15 27 - -8.008.50 8.50 8.50 9.00 UDS - - - - - -9.00 9.00 9.00 10.50 SPT 10 14 16 30 - -9.5010.0010.50 10.50 10.50 11.50 SPT 9 11 12 23 - -11.0011.50 11.50 11.50 12.00 DS - - - - - -12.00 12.00 12.00 13.50 SPT 18 20 25 45 - -12.5013.0013.50 13.50 13.50 14.50 SPT 11 17 22 39 - -14.00 7.25 to 14.95 m14.50 14.50 14.50 15.00 DS - - - - - -15.00 15.00 15.00 16.50 SPT 10 18 20 38 - -15.5016.0016.50 16.50 16.50 17.50 SPT 20 35 45 80 - -17.0017.50 17.50 17.50 18.00 DS - - - - - -18.00 18.00 18.00 19.50 SPT 21 40 52 92 - -18.50 15.30 to 19.20 m19.0019.50

19.50 19.50 20.50 SPT 18 32 45 77 - -

20.0020.50

Dark brownish, fine to coarse grained, siltysand with some gravels (SM) 20.50 to 21.00 m 20.50 20.50 21.00 DS - - - - - -

21.00 21.00 21.00 22.50 SPT 20 35 48 83 - -

21.5022.0022.50 22.50 22.50 23.50 SPT 23 41 50 91 - -23.0023.50 23.50 23.50 25.00 UDS - - - - - -24.0024.5025.00 25.00 25.00 25.50 SPT 20 65 40 >100 - -

22.10 to 25.00 m 5cm

Co-ordinates: Date of Completion: 19/7/2010

Diameter of Bore : 150 mm

KCT Consultancy Services, AhmedabadProject : L & T , HAZIRA

Bore Hole No. : Date of commencement: 15/7/2010

Soil DescriptionDepth ofSample

Drill Run

Reduced Level:Depth of Termination :

SPT N Value/Penetration of S.S.SCore Reco-very (%)

RQD (%)

Depth of Water Table : Encountered at 3.40m depth during investigationBORE LOG DATA SHEET

Method of Boring

DepthC

asin

g

Not

atio

n

Remarks

m

Rot

ary

Dril

ling

by m

ud c

ircul

atio

n

Not

Use

d

Dark brownish, fine to coarse grained, silt ofintermediate compressibility with much gravels(MI)

Dark brownish, fine to medium grained, silt ofintermediate compressibility with little gravels(MI) 21.00 to 22.10 m

Dark brownish, fine to very fine grained, silt ofintermediate compressibility with occationalgravels(MI) 19.20 to 20.50 m

Blackish grey, fine to medium grained, sisltysand with little gravels (SM)

Type ofSample

Dark brownish, fine to very fine grained, siltyclays of high plasticity with occational gravels(CH) 2.20 to 3.70 m

Dark brownish, fine to very fine grained, siltyclays of high plasticity with occational gravelsand occational fine sand (CH) 0.70 to 2.20 m

Dark brownish, fine to medium grained, filledup clayey sand with debries 0.00 to 0.70 m

Blackish brown, fine to very fine grained, siltysand with occational gravels (SM)

Blackish grey, fine to very fine grained, silt ofhigh compressibility with occational gravels(MH) 6.00 to 7.25 m

Blackish grey, fine to coarse grained, clayeysand (SC) 14.95 to 15.30 m

Blackish grey, fine to very fine grained, siltysand with occational gravels (SM)

water table encountered at 340m depth during

Fig. No.( )

Sheet No.1085

11-06-2012

Page 658: Binder 9 with uploaded drawings and approved document

6N-799, E-117099.620m20.0 m

From To

m m m N 1 N 2 N 3 N0.00

0.00 0.00 1.50 DS - - - - - -

0.501.001.50 1.50 1.50 2.50 SPT 5 8 10 18 - -2.002.50 2.50 2.50 3.00 UDS - - - - - -3.00 0.65 to 3.60 m 3.00 3.00 4.50 SPT 1 2 2 4 - -3.504.004.50 4.50 4.50 5.50 SPT 2 3 3 6 - -5.005.50

5.50 5.50 6.00 DS - - - - - -

6.00 6.00 6.00 7.50 SPT 2 2 2 4 - -6.507.007.50 7.50 7.50 8.50 SPT 4 5 7 12 - -8.008.50 8.50 8.50 9.00 UDS - - - - - -9.00 9.00 9.00 10.50 SPT 7 9 11 20 - -9.5010.0010.50 10.50 10.50 11.50 SPT 10 15 18 33 - -11.0011.50 11.50 11.50 12.00 DS - - - - - -12.00 12.00 12.00 13.50 SPT 12 19 23 42 - -12.5013.0013.50 13.50 13.50 14.50 SPT 12 20 24 44 - -14.00

14.50 14.50 14.50 15.00 DS - - - - - -15.00 Brownish grey, fine to very fine grained, silty

sand with occational gravels (SM) 14.80 to15.50 m

15.00 15.00 16.50 SPT 15 22 26 48 - -

15.5016.0016.50 16.50 16.50 17.50 SPT 17 24 28 52 - -17.0017.50 17.50 17.50 18.00 UDS - - - - - -18.00 18.00 18.00 20.00 SPT 15 21 30 51 - -18.5019.0019.5020.00 20.00 20.00 20.45 SPT 23 32 40 72 - -

17.45 to 20.00 m

KCT Consultancy Services, AhmedabadProject : L & T , HAZIRA

Bore Hole No. : Date of commencement: 19/7/2010Co-ordinates: Date of Completion: 20/7/2010

Reduced Level:Depth of Termination : Diameter of Bore : 150 mmDepth of Water Table : Encountered at 3.60m depth during investigation

Method of Boring

DepthC

asin

g

Not

atio

n Core Reco-very (%)

RQD (%) Remarks

m

Soil DescriptionDepth ofSample

Drill RunType ofSample

SPT N Value/Penetration of S.S.S

Rot

ary

Dril

ling

by m

ud c

ircul

atio

n

Not

Use

d

Dark brownish, fine to very fine grained, siltyclays of high plasticity with occationalgravels(CH)

Brownish grey, fine to very fine grained, clayeysand with little plastic fines and occationalgravels (SC) 15.50 to 17.45 m

Dark brownish with whitish grey coarse sand,fine to coarse grained, silty sand with somegravels (SM) 12.60 to 14.00 m

Blackish, fine to very fine grained, silt of highcompressibility with occational gravels(MH)5.20 to 6.60 m

Blackish brown, fine to very fine grained, siltysand with occational gravels (SM) 3.60 to 5.20m

Blackish brown, fine to very fine grained, siltyclays of high plasticity with occational gravelsand some fine sand (CH)

BORE LOG DATA SHEET

Brownish, coarse grained, silty gravels (GM)14.00 to 14.80 m

Blackish brown, fine to very fine grained, filledup silty clays of high plasticity with occationalgravels and some fine sand with debries 0.00 to 0.65 m

Blackish, fine to very fine grained, silty sandwith occational gravels(SM) 6.60 to 8.90m

Blackish, fine to very fine grained, silty sandwith much gravels(SM) 8.90 to 10.70 m

Blackish, fine to very fine grained, silty sandwith occational gravels(SM) 10.70 to 12.60 m

water table encountered at 3.60m depth during

Fig. No.( )

Sheet No.1086

11-06-2012

Page 659: Binder 9 with uploaded drawings and approved document

9N-1095, E-175099.232m20.0 m

From To

m m m N 1 N 2 N 3 N0.00

0.00 0.00 1.50 DS - - - - - -

0.501.001.50 1.50 1.50 2.50 SPT 4 7 8 15 - -2.002.50 2.50 2.50 3.00 UDS - - - - - -3.00 3.00 3.00 4.50 SPT 5 3 5 8 - -3.504.004.50 4.50 4.50 5.50 SPT 4 6 7 13 - -5.005.50 5.50 5.50 6.00 UDS - - - - - -6.00 6.00 6.00 7.50 SPT 7 9 12 21 - -6.507.007.50 7.50 7.50 8.50 SPT 6 10 14 24 - -8.008.50 8.50 8.50 9.00 UDS - - - - - -9.00 9.00 9.00 10.50 SPT 5 14 14 28 - -9.5010.00 5.95 to 10.50 m10.50

10.50 10.50 11.50 SPT 8 15 17 32 - -

11.0011.50 11.50 11.50 12.00 DS - - - - - -12.00 12.00 12.00 13.50 SPT 10 18 22 44 - -12.5013.0013.50 11.35 to 14.10 m 13.50 13.50 14.50 SPT 11 18 25 43 - -14.00

14.50 14.50 14.50 15.00 DS - - - - - -15.00 15.00 15.00 16.50 SPT 15 24 30 54 - -15.5016.0016.50 15.00 to 17.05 m 16.50 16.50 17.50 SPT 18 30 34 64 - -17.00

17.50 17.50 17.50 18.00 DS - - - - - -18.00 18.00 18.00 20.00 SPT 15 26 33 59 - -18.5019.0019.5020.00 20.00 20.00 20.45 SPT 16 46 48 94 - -

18.00 to 20.00 m

KCT Consultancy Services, AhmedabadProject : L & T , HAZIRA

Bore Hole No. : Date of commencement: 07-12-10Co-ordinates: Date of Completion: 13/7/2010

Reduced Level:Depth of Termination : Diameter of Bore : 150 mmDepth of Water Table : Encountered at 3.50m depth during investigation

BORE LOG DATA SHEET

Method of Boring

Depth

Cas

ing

Not

atio

n

Soil DescriptionDepth ofSample

Drill RunType ofSample

SPT N Value/Penetration of S.S.SCore Reco-very (%)

RQD (%) Remarks

m

Rot

ary

Dril

ling

by m

ud c

ircul

atio

n

Not

Use

d

Blackish, coarse grained, silty gravels (GM)

Brownish, fine to coarse grained, clayey sandwith much gravels (SC) 17.05 to 18.00 m

Dark brownish, fine to medium grained, silt ofintermediate compressibility with occationalgravels (MI)

Blackish, fine to very fine grained, filled upclayey sand with debries 0.00 to 0.70 m

Blackish, fine to very fine grained, silty clays ofhigh plasticity with occational gravels (CH) 0.70 to 3.45 m

Backish, fine to very fine grained, silty sand withoccational gravels (SM) 3.45 to 5.95 m

Blackish brown, fine to very fine grained, siltysand with occational gravels (SM)

Blackish brown, fine to coarse grained, siltysand with little plastic fines and much gravels(SM) 10.50 to 11.35 m

Blackish brown, fine to medium grained, siltysand with little gravels (SM)

Dark brownish and slightly blackish, fine tocoarse grained, silty sand with much gravels(SM) 14.10 to 15.00 m

water table encountered at 3.50m depth during

Fig. No.( )

Sheet No.1087

11-06-2012

Page 660: Binder 9 with uploaded drawings and approved document

TerminologyCu -C - = 0.50 X Cu

C - = 1.73 X CuC - = 0.75 X Cu

G -- 0.4

E -fnz -

-

21.6 0.09

= 1406.25 kg= 37.0 kg= Mass of block + mass of vibrator =1443.25 kg= 9.81 m/sec2

1 (N 789, E 1087 )

Size of the block = 0.75 m wide, 1.00 m long and 0.75 m deepData

Calculations

Mass of the vibratorTotal vibrating mass (M)Acceleration due to gravity (g)

Coefficient of elastic uniform shear in kg / cm3

Coefficient of elastic non uniform compression in kg / cm3

Coefficient of elastic non uniform shear in kg / cm3

Results of Block Vibration Test(As per IS : 5249, 1992, reaffirmed 1995)

Project :Proposed structures of plant of Additional gas processing facilities project (Phase 4 )of ONGC at Hazira, Surat, L & T Ltd

Coefficient of elastic uniform compression in kg / cm3

Test No.

Depth of Conducting testBase Area of the Block (A1)Mass of the block

= 2.50 m from EGL= 0.75 sq. m

Damping coefficient

The above coefficients are reported for foundation contact area, A of 10.0 m2 (1,00,000cm2) or more

4 X 2 X fnz2 X M / (A1 X g)} X 10-6 kg / cm3

Modulus of rigidity of strata in Kg / cm2, G = Cu X A X (1 - ) / 2.13Poisson's ratio = for this particular situation

Coefficient of elastic uniform compression in kg / cm3 for block of size 0.75m wide,1.00m long and 0.75m deep= Cu / Cu1 -

Modulus of elasticity of strata in kg / cm2 = G X 2 X (1 + )Resonance frequency of foundation block – soil system in cycles / sec

Modulus of elasticity of strata E= 88.2* 2 * (1 + 0.40) = 246.9 kg/sq. cm

cycles / sec and = From chart between amp v/s. freq fnz =

Coefficient of elastic non – uniform shear C = 0.75*0.99 = 0.74 kg/cu.cmModulus of rigidity of strata G = 0.99 * 100000* (1.0 – 0.40) / 2.13 = 88.2 kg/sq.cm

Coefficient of elastic uniform shear C = 0.5*0.99 = 0.49 kg/cu.cmCoefficient of elastic non–uniform compression C = 1.73*0.99 = 1.71 kg/cu.cm

Coefficient of Elastic uniform compression

Cu1 = {4 * 2*21.62*1443.25 / (0.75 * 9.81)} * 10-6 = 3.61 kg/cu.cmCu = 3.61 * 0.75/10.0 = 0.99 kg/cu.cm

Sheet No.1088

11-06-2012

Page 661: Binder 9 with uploaded drawings and approved document

0.270 0.09

0.191

19.7

23.7

21.6f nz =

damping coefficientAmax =

A max / sqrt ( 2 ) =

f 1 =

f 2 =

Response Curve (Block Vibration Test No. 1 Inside Plant Area )

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0 5 10 15 20 25 30 35

Frequency (cycles / sec)

Am

plitu

de (1

0 -5

mm

)

= f 2 - f 1 / 2 fnz = 0.09

A max / ( 2 ) 0.5 = 0.049f1 f2 fnz

Sheet No.1089

11-06-2012

Page 662: Binder 9 with uploaded drawings and approved document

= =

S =R =V = =

1 4.542 7.473 8.774 10.335 11.216 12.857 19.038 18.819 18.69

10 18.49

12.5712.4412.57

N - S E - W

11.3112.5714.3313.19

Resistivity in m

5.227.929.42

0.300.250.220.20

0.500.450.400.38

43.1044.2344.1142.73

12.8214.8315.7118.10

0.980.880.780.68

0.680.590.500.48

Resistence Observed in

0.990.88

Resistivity in m

6.2211.06

Resistence Observed in

0.830.63

KCT Consultancy ServicesRESULTS OF ELECTRICAL RESISTIVITY

( IS : 3043, 1987 )

Average Resistivity ( - m )

Where

ERT No. :Name of Project :

Battery Condition :Climatic Condition :

3Proposed structures of plant of Additional gas processing facilities project (Phase4) of ONGC at Hazira, Surat, L&T Ltd (Inside Plant area)GoodHumid and moderately hot

Resistivity at given depth = 2 S R

Voltage Drop between inner electrodes in VoltCurrent applied in outer electrodes in Amp.

Direction

Resistivity in ohm - m ( m )Value of pi - 22 / 7 Electrode Spacing ( equal to the depth at which resistivity is determined ) in mV / in ohm (

Spacing of Electrode in (

m )

Average Reistivity V/S. Depth

1

2

3

4

5

6

7

8

9

10

0.00 5.00 10.00 15.00 20.00 25.00

Average Resistivity in - m

Dep

th in

m

( K K Thaker ) ( )

Sheet No.1090

11-06-2012

Page 663: Binder 9 with uploaded drawings and approved document

LARSEN & TOUBRO LIMITED E&C DIVISION

GEOTECHNICAL INVESTIGATION REPORT – INSIDE

AREA

DOCUMENT NO. A067-LT-00-CV-04-RP-0004

PROJECT :Additional Gas Processing Facilities (Phase-IV)

REVISION : 01

CUSTOMER : ONGC,HAZIRA

Sheet No.1091

11-06-2012

Page 664: Binder 9 with uploaded drawings and approved document

Sheet No.1092

11-06-2012

Page 665: Binder 9 with uploaded drawings and approved document

ProjectSpreadsheets to BS 8110etc

Client Advisory Group Made by Date Page Location Grid line 1 rc 19-Nov-2015 101

RETAINING WALL design to BS 8110:1997, BS 8002:1994. BS 8004:1986 etc.Checked Revision Job No

Originated from 'RCC62.xls' on CD © 1999 BCA for RCC chg R68

IDEALISED STRUCTURE and FORCE DIAGRAMS DESIGN STATUS: VALID

WARNING :

Passive pressure should

only be considered if it

can be guaranteed that

there will be no future

excavation in front of

the wall.

DIMENSIONS (mm)

H = 3200 B = 2750 Tw = 250

Hw = 100 BI = 1000 Tb = 400

Hp = 200 BN = 0 TN = 0

Hn = 0

MATERIAL PROPERTIES

fcu = 35 N/mm² gm = 1.5 concrete

fy = 460 N/mm² gm = 1.05 steel

cover to tension steel = 50 mm

Max allowable design surface crack width (W) = 0.3 mm

Concrete density = 24 kN/m³

SOIL PROPERTIES Wall Geometry

Design angle of int'l friction of retained mat'l (Ø) = 30 degree

Design cohesion of retained mat'l (C ) = 0 kN/m² (Only granular backfil considered, "C" = zero)

Density of retained mat'l (q ) = 20 kN/m³

Submerged Density of retained mat'l (qs ) = 13.33 kN/m³ [default=2/3*q (only apply when Hw >0) ] =13.33

Design angle of int'l friction of base mat'l (Øb) = 20 degree ASSUMPTIONS

Design cohesion of base material (Cb ) = 10 kN/m² a) Wall friction is zero

Density of base material (qb ) = 10 kN/m³ b) Minimum active earth pressure = 0.25qH

Allowable gross ground bearing pressure (GBP) = 200 kN/m² c) Granular backfill

LOADINGS Surcharge load -- live (SQK) = 10 kN/m² e)Does not include effect of seepage of ground

Surcharge load -- dead (SGK) = 10 water beneath the wall.

Line load -- live (LQK) = 15 kN/m f)Does not include deflection check of wall due to

Line load -- dead (LGK) = 20 kN/m lateral earth pressures

Distance of line load from wall (X) = 1000 mm h) Design not intended for walls over 3.0 m high

LATERAL FORCES (unfactored) Ka = 0.33 [ default ka = (1-SIN Ø)/(1+SIN Ø) ] =0.33

Kp = 2.04 [ default kp = (1+SIN Øb)/(1-SIN Øb) ] =2.04

Kpc = 2.86 [ default kpc = 2kp0.5

] = 2.86

Kac = 1.15 [ 2ka0.5

]

Force Lever arm Moment about TOE gf Fult Mult

(kN) (m) (kNm) (kN) (kNm)

PE = 34.12 LE = 1.067 36.41 1.40 47.77 50.97

PS(GK) = 10.67 LS = 1.60 17.07 1.40 14.93 23.89

PS(QK) = 10.67 LS = 1.60 17.07 1.60 17.07 27.31

PL(GK) = 6.67 LL = 2.36 15.74 1.40 9.33 22.03

PL(QK) = 5.00 LL = 2.36 11.80 1.60 8.00 18.89

PW = 0.05 LW = 0.03 0.00 1.40 0.07 0.00

Total 67.17 98.09 97.17 143.10

PP = -6.12 (LP-HN) = 0.10 -0.60 1.00 -6.12 -0.60

-

REINFORCED CONCRETE COUNCIL

d)Does not include check of rotational slide/slope failure

S u r c h a r g e S , S i n k N / mG K Q K2

L i n e L o a d L , L i n k N / mG K Q K

X

B 1

B N T N

T W

B

HW

Hn

Tb

LP

HP

LL

LS

LW

H

LE

W A T E R

Page 666: Binder 9 with uploaded drawings and approved document

123

Page 667: Binder 9 with uploaded drawings and approved document

123

Page 668: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 669: Binder 9 with uploaded drawings and approved document

123

Page 670: Binder 9 with uploaded drawings and approved document

123

Page 671: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 672: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 673: Binder 9 with uploaded drawings and approved document

123

Page 674: Binder 9 with uploaded drawings and approved document

123

Page 675: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 676: Binder 9 with uploaded drawings and approved document

123

Page 677: Binder 9 with uploaded drawings and approved document

123

Page 678: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 679: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 680: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 681: Binder 9 with uploaded drawings and approved document

123

Page 682: Binder 9 with uploaded drawings and approved document

123

Page 683: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 684: Binder 9 with uploaded drawings and approved document

123

Page 685: Binder 9 with uploaded drawings and approved document

123

Page 686: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 687: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 688: Binder 9 with uploaded drawings and approved document

123

Page 689: Binder 9 with uploaded drawings and approved document

123

Page 690: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 691: Binder 9 with uploaded drawings and approved document

123

Page 692: Binder 9 with uploaded drawings and approved document

123

Page 693: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 694: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 695: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 696: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 697: Binder 9 with uploaded drawings and approved document

123

Page 698: Binder 9 with uploaded drawings and approved document

123

Page 699: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 700: Binder 9 with uploaded drawings and approved document

123

Page 701: Binder 9 with uploaded drawings and approved document

123

Page 702: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 703: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 704: Binder 9 with uploaded drawings and approved document

123

Page 705: Binder 9 with uploaded drawings and approved document

123

Page 706: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 707: Binder 9 with uploaded drawings and approved document

123

Page 708: Binder 9 with uploaded drawings and approved document

123

Page 709: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 710: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 711: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 712: Binder 9 with uploaded drawings and approved document

123

Page 713: Binder 9 with uploaded drawings and approved document

123

Page 714: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 715: Binder 9 with uploaded drawings and approved document

123

Page 716: Binder 9 with uploaded drawings and approved document

123

Page 717: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 718: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 719: Binder 9 with uploaded drawings and approved document

123

Page 720: Binder 9 with uploaded drawings and approved document

123

Page 721: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 722: Binder 9 with uploaded drawings and approved document

123

Page 723: Binder 9 with uploaded drawings and approved document

123

Page 724: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 725: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 726: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 727: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 728: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 729: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 730: Binder 9 with uploaded drawings and approved document

ProjectSpreadsheets to BS 8110etc

Client Advisory Group Made by Date Page Location Grid line 1 rc 19-Nov-2015 101

RETAINING WALL design to BS 8110:1997, BS 8002:1994. BS 8004:1986 etc.Checked Revision Job No

Originated from 'RCC62.xls' on CD © 1999 BCA for RCC chg R68

IDEALISED STRUCTURE and FORCE DIAGRAMS DESIGN STATUS: VALID

WARNING :

Passive pressure should

only be considered if it

can be guaranteed that

there will be no future

excavation in front of

the wall.

DIMENSIONS (mm)

H = 3200 B = 2750 Tw = 250

Hw = 100 BI = 1000 Tb = 400

Hp = 200 BN = 0 TN = 0

Hn = 0

MATERIAL PROPERTIES

fcu = 35 N/mm² gm = 1.5 concrete

fy = 460 N/mm² gm = 1.05 steel

cover to tension steel = 50 mm

Max allowable design surface crack width (W) = 0.3 mm

Concrete density = 24 kN/m³

SOIL PROPERTIES Wall Geometry

Design angle of int'l friction of retained mat'l (Ø) = 30 degree

Design cohesion of retained mat'l (C ) = 0 kN/m² (Only granular backfil considered, "C" = zero)

Density of retained mat'l (q ) = 20 kN/m³

Submerged Density of retained mat'l (qs ) = 13.33 kN/m³ [default=2/3*q (only apply when Hw >0) ] =13.33

Design angle of int'l friction of base mat'l (Øb) = 20 degree ASSUMPTIONS

Design cohesion of base material (Cb ) = 10 kN/m² a) Wall friction is zero

Density of base material (qb ) = 10 kN/m³ b) Minimum active earth pressure = 0.25qH

Allowable gross ground bearing pressure (GBP) = 200 kN/m² c) Granular backfill

LOADINGS Surcharge load -- live (SQK) = 10 kN/m² e)Does not include effect of seepage of ground

Surcharge load -- dead (SGK) = 10 water beneath the wall.

Line load -- live (LQK) = 15 kN/m f)Does not include deflection check of wall due to

Line load -- dead (LGK) = 20 kN/m lateral earth pressures

Distance of line load from wall (X) = 1000 mm h) Design not intended for walls over 3.0 m high

LATERAL FORCES (unfactored) Ka = 0.33 [ default ka = (1-SIN Ø)/(1+SIN Ø) ] =0.33

Kp = 2.04 [ default kp = (1+SIN Øb)/(1-SIN Øb) ] =2.04

Kpc = 2.86 [ default kpc = 2kp0.5

] = 2.86

Kac = 1.15 [ 2ka0.5

]

Force Lever arm Moment about TOE gf Fult Mult

(kN) (m) (kNm) (kN) (kNm)

PE = 34.12 LE = 1.067 36.41 1.40 47.77 50.97

PS(GK) = 10.67 LS = 1.60 17.07 1.40 14.93 23.89

PS(QK) = 10.67 LS = 1.60 17.07 1.60 17.07 27.31

PL(GK) = 6.67 LL = 2.36 15.74 1.40 9.33 22.03

PL(QK) = 5.00 LL = 2.36 11.80 1.60 8.00 18.89

PW = 0.05 LW = 0.03 0.00 1.40 0.07 0.00

Total 67.17 98.09 97.17 143.10

PP = -6.12 (LP-HN) = 0.10 -0.60 1.00 -6.12 -0.60

-

REINFORCED CONCRETE COUNCIL

d)Does not include check of rotational slide/slope failure

S u r c h a r g e S , S i n k N / mG K Q K2

L i n e L o a d L , L i n k N / mG K Q K

X

B 1

B N T N

T W

B

HW

Hn

Tb

LP

HP

LL

LS

LW

H

LE

W A T E R

Page 731: Binder 9 with uploaded drawings and approved document

123

Page 732: Binder 9 with uploaded drawings and approved document

PILE BEARING CAPACITY CALCULATION BASED ON S.P.T. VALUE

------------------ ------------------

Project Name :

Location :

Borehole No. : BH-1

Date :

------------------ ------------------

MAYERHOF Formula : K1 K2

Skin, Ps = K1 x Nav x As SAND 2.0 400

Bearing, Pb = K2 x Nb x Ab SILT 2.5 250

Ult. Load, Pu = Ps + Pb CLAY 3.0 100

All. Load, Pa = Ps/Fs + Pb/Fb

Factor of safety : Skin, Fs = 2

Bearing, Fb = 3

------------------ ------------------

To calculate allowable soil bearing capacity :

Pile used : Type : s

(c = circular) Width, b = 0.4 m Perimeter: 1.600

(s = square) (= dia. for type c) Ab: 0.160

Qa(conc): 1800

========== ========== ====== ========== ========== ============ =======================

Depth Soil SPT Skin Total Base Working Load

Type N As Fric Skin Load Fs = 2.0 Fb = 3

(m) (m²) (kN) (kN) (kN) (KN)

------------------ ------------------ ---------- ------------------ ------------------ -------------------- ---------------------------------------

0.0 SAND 0 0.0 0.0 0.0 0.0 0.0

1.5 SAND 11 2.4 52.8 52.8 704.0 261.1

3.0 SAND 12 2.4 57.6 110.4 768.0 311.2

4.5 SAND 15 2.4 72.0 182.4 960.0 411.2

6.0 SILT 17 2.4 102.0 284.4 680.0 368.9

7.5 SILT 19 2.4 114.0 398.4 760.0 452.5

9.0 SILT 19 2.4 114.0 512.4 760.0 509.5

10.5 SILT 17 2.4 102.0 614.4 680.0 533.9

12.0 SILT 19 2.4 114.0 728.4 760.0 617.5

13.5 SILT 11 2.4 66.0 794.4 440.0 543.9

15.0 SILT 18 2.4 108.0 902.4 720.0 691.2

16.5 SILT 17 2.4 102.0 1,004.4 680.0 728.9

18.0 SILT 19 2.4 114.0 1,118.4 760.0 812.5

19.5 SILT 20 2.4 120.0 1,238.4 800.0 885.9

21.0 SILT 18 2.4 108.0 1,346.4 720.0 913.2

22.5 SILT 14 2.4 84.0 1,430.4 560.0 901.9

24.0 SILT 0 2.4 0.0 1,430.4 0.0 715.2

25.5 SILT 22 2.4 132.0 1,562.4 880.0 1,074.5

27.0 SILT 20 2.4 120.0 1,682.4 800.0 1,107.9

28.5 SILT 20 2.4 120.0 1,802.4 800.0 1,167.9

30.0 SILT 22 2.4 132.0 1,934.4 880.0 1,260.5

31.5 SILT 25 2.4 150.0 2,084.4 1,000.0 1,375.5

33.0 SILT 23 2.4 138.0 2,222.4 920.0 1,417.9

34.5 SILT 23 2.4 138.0 2,360.4 920.0 1,486.9

36.0 SILT 24 2.4 144.0 2,504.4 960.0 1,572.2

37.5 SILT 23 2.4 138.0 2,642.4 920.0 1,627.9

39.0 SILT 25 2.4 150.0 2,792.4 1,000.0 1,729.5

40.5 SILT 26 2.4 156.0 2,948.4 1,040.0 1,820.9

42.0 SILT 50 2.4 300.0 3,248.4 2,000.0 2,290.9

43.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

45.0 SILT 2.4 0.0 3,248.4 0.0 1,624.2

46.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

For a designed load of 100 KN, the estimated depth is 16.5m.

Note : 1. The clay skin friction for the top soil layer is assume to be 7.5kN/m2

2. The pile is designed as floating pile where the pile would settle together with the soil and therefore there

is no effective negetive skin friction.

3. The final depth of piles penetration shall be decided on site by load test.

Page 733: Binder 9 with uploaded drawings and approved document

123

Page 734: Binder 9 with uploaded drawings and approved document

123

Page 735: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 736: Binder 9 with uploaded drawings and approved document

123

Page 737: Binder 9 with uploaded drawings and approved document

123

Page 738: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 739: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 740: Binder 9 with uploaded drawings and approved document

123

Page 741: Binder 9 with uploaded drawings and approved document

123

Page 742: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 743: Binder 9 with uploaded drawings and approved document

123

Page 744: Binder 9 with uploaded drawings and approved document

123

Page 745: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 746: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 747: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 748: Binder 9 with uploaded drawings and approved document

123

Page 749: Binder 9 with uploaded drawings and approved document

123

Page 750: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 751: Binder 9 with uploaded drawings and approved document

123

Page 752: Binder 9 with uploaded drawings and approved document

123

Page 753: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 754: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 755: Binder 9 with uploaded drawings and approved document

123

Page 756: Binder 9 with uploaded drawings and approved document

123

Page 757: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 758: Binder 9 with uploaded drawings and approved document

123

Page 759: Binder 9 with uploaded drawings and approved document

123

Page 760: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 761: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 762: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 763: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 764: Binder 9 with uploaded drawings and approved document

123

Page 765: Binder 9 with uploaded drawings and approved document

123

Page 766: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 767: Binder 9 with uploaded drawings and approved document

123

Page 768: Binder 9 with uploaded drawings and approved document

123

Page 769: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 770: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 771: Binder 9 with uploaded drawings and approved document

123

Page 772: Binder 9 with uploaded drawings and approved document

123

Page 773: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 774: Binder 9 with uploaded drawings and approved document

123

Page 775: Binder 9 with uploaded drawings and approved document

123

Page 776: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 777: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 778: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 779: Binder 9 with uploaded drawings and approved document

123

Page 780: Binder 9 with uploaded drawings and approved document

123

Page 781: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 782: Binder 9 with uploaded drawings and approved document

123

Page 783: Binder 9 with uploaded drawings and approved document

123

Page 784: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 785: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 786: Binder 9 with uploaded drawings and approved document

123

Page 787: Binder 9 with uploaded drawings and approved document

123

Page 788: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 789: Binder 9 with uploaded drawings and approved document

123

Page 790: Binder 9 with uploaded drawings and approved document

123

Page 791: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 792: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 793: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 794: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 795: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 796: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 797: Binder 9 with uploaded drawings and approved document

123

Page 798: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 799: Binder 9 with uploaded drawings and approved document

123

Page 800: Binder 9 with uploaded drawings and approved document

123

Page 801: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 802: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 803: Binder 9 with uploaded drawings and approved document

123

Page 804: Binder 9 with uploaded drawings and approved document

123

Page 805: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 806: Binder 9 with uploaded drawings and approved document

123

Page 807: Binder 9 with uploaded drawings and approved document

123

Page 808: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 809: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 810: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 811: Binder 9 with uploaded drawings and approved document

123

Page 812: Binder 9 with uploaded drawings and approved document

123

Page 813: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 814: Binder 9 with uploaded drawings and approved document

123

Page 815: Binder 9 with uploaded drawings and approved document

123

Page 816: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 817: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 818: Binder 9 with uploaded drawings and approved document

123

Page 819: Binder 9 with uploaded drawings and approved document

123

Page 820: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 821: Binder 9 with uploaded drawings and approved document

123

Page 822: Binder 9 with uploaded drawings and approved document

123

Page 823: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 824: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 825: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 826: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 827: Binder 9 with uploaded drawings and approved document

123

Page 828: Binder 9 with uploaded drawings and approved document

123

Page 829: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 830: Binder 9 with uploaded drawings and approved document

123

Page 831: Binder 9 with uploaded drawings and approved document

123

Page 832: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 833: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 834: Binder 9 with uploaded drawings and approved document

123

Page 835: Binder 9 with uploaded drawings and approved document

123

Page 836: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 837: Binder 9 with uploaded drawings and approved document

123

Page 838: Binder 9 with uploaded drawings and approved document

123

Page 839: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 840: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 841: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 842: Binder 9 with uploaded drawings and approved document

123

Page 843: Binder 9 with uploaded drawings and approved document

123

Page 844: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 845: Binder 9 with uploaded drawings and approved document

123

Page 846: Binder 9 with uploaded drawings and approved document

123

Page 847: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 848: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 849: Binder 9 with uploaded drawings and approved document

123

Page 850: Binder 9 with uploaded drawings and approved document

123

Page 851: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 852: Binder 9 with uploaded drawings and approved document

123

Page 853: Binder 9 with uploaded drawings and approved document

123

Page 854: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 855: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 856: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 857: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 858: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 859: Binder 9 with uploaded drawings and approved document

123

Page 860: Binder 9 with uploaded drawings and approved document

123

Page 861: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 862: Binder 9 with uploaded drawings and approved document

123

Page 863: Binder 9 with uploaded drawings and approved document

123

Page 864: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 865: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 866: Binder 9 with uploaded drawings and approved document

123

Page 867: Binder 9 with uploaded drawings and approved document

123

Page 868: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 869: Binder 9 with uploaded drawings and approved document

123

Page 870: Binder 9 with uploaded drawings and approved document

123

Page 871: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 872: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 873: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 874: Binder 9 with uploaded drawings and approved document

123

Page 875: Binder 9 with uploaded drawings and approved document

123

Page 876: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 877: Binder 9 with uploaded drawings and approved document

123

Page 878: Binder 9 with uploaded drawings and approved document

123

Page 879: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 880: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 881: Binder 9 with uploaded drawings and approved document

123

Page 882: Binder 9 with uploaded drawings and approved document

123

Page 883: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 884: Binder 9 with uploaded drawings and approved document

123

Page 885: Binder 9 with uploaded drawings and approved document

123

Page 886: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 887: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 888: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 889: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 890: Binder 9 with uploaded drawings and approved document

123

Page 891: Binder 9 with uploaded drawings and approved document

123

Page 892: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 893: Binder 9 with uploaded drawings and approved document

123

Page 894: Binder 9 with uploaded drawings and approved document

123

Page 895: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 896: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 897: Binder 9 with uploaded drawings and approved document

123

Page 898: Binder 9 with uploaded drawings and approved document

123

Page 899: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 900: Binder 9 with uploaded drawings and approved document

123

Page 901: Binder 9 with uploaded drawings and approved document

123

Page 902: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 903: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 904: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 905: Binder 9 with uploaded drawings and approved document

123

Page 906: Binder 9 with uploaded drawings and approved document

123

Page 907: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 908: Binder 9 with uploaded drawings and approved document

123

Page 909: Binder 9 with uploaded drawings and approved document

123

Page 910: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 911: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 912: Binder 9 with uploaded drawings and approved document

123

Page 913: Binder 9 with uploaded drawings and approved document

123

Page 914: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 915: Binder 9 with uploaded drawings and approved document

123

Page 916: Binder 9 with uploaded drawings and approved document

123

Page 917: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 918: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 919: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 920: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 921: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 922: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 923: Binder 9 with uploaded drawings and approved document

PILE BEARING CAPACITY CALCULATION BASED ON S.P.T. VALUE

------------------ ------------------

Project Name :

Location :

Borehole No. : BH-1

Date :

------------------ ------------------

MAYERHOF Formula : K1 K2

Skin, Ps = K1 x Nav x As SAND 2.0 400

Bearing, Pb = K2 x Nb x Ab SILT 2.5 250

Ult. Load, Pu = Ps + Pb CLAY 3.0 100

All. Load, Pa = Ps/Fs + Pb/Fb

Factor of safety : Skin, Fs = 2

Bearing, Fb = 3

------------------ ------------------

To calculate allowable soil bearing capacity :

Pile used : Type : s

(c = circular) Width, b = 0.4 m Perimeter: 1.600

(s = square) (= dia. for type c) Ab: 0.160

Qa(conc): 1800

========== ========== ====== ========== ========== ============ =======================

Depth Soil SPT Skin Total Base Working Load

Type N As Fric Skin Load Fs = 2.0 Fb = 3

(m) (m²) (kN) (kN) (kN) (KN)

------------------ ------------------ ---------- ------------------ ------------------ -------------------- ---------------------------------------

0.0 SAND 0 0.0 0.0 0.0 0.0 0.0

1.5 SAND 11 2.4 52.8 52.8 704.0 261.1

3.0 SAND 12 2.4 57.6 110.4 768.0 311.2

4.5 SAND 15 2.4 72.0 182.4 960.0 411.2

6.0 SILT 17 2.4 102.0 284.4 680.0 368.9

7.5 SILT 19 2.4 114.0 398.4 760.0 452.5

9.0 SILT 19 2.4 114.0 512.4 760.0 509.5

10.5 SILT 17 2.4 102.0 614.4 680.0 533.9

12.0 SILT 19 2.4 114.0 728.4 760.0 617.5

13.5 SILT 11 2.4 66.0 794.4 440.0 543.9

15.0 SILT 18 2.4 108.0 902.4 720.0 691.2

16.5 SILT 17 2.4 102.0 1,004.4 680.0 728.9

18.0 SILT 19 2.4 114.0 1,118.4 760.0 812.5

19.5 SILT 20 2.4 120.0 1,238.4 800.0 885.9

21.0 SILT 18 2.4 108.0 1,346.4 720.0 913.2

22.5 SILT 14 2.4 84.0 1,430.4 560.0 901.9

24.0 SILT 0 2.4 0.0 1,430.4 0.0 715.2

25.5 SILT 22 2.4 132.0 1,562.4 880.0 1,074.5

27.0 SILT 20 2.4 120.0 1,682.4 800.0 1,107.9

28.5 SILT 20 2.4 120.0 1,802.4 800.0 1,167.9

30.0 SILT 22 2.4 132.0 1,934.4 880.0 1,260.5

31.5 SILT 25 2.4 150.0 2,084.4 1,000.0 1,375.5

33.0 SILT 23 2.4 138.0 2,222.4 920.0 1,417.9

34.5 SILT 23 2.4 138.0 2,360.4 920.0 1,486.9

36.0 SILT 24 2.4 144.0 2,504.4 960.0 1,572.2

37.5 SILT 23 2.4 138.0 2,642.4 920.0 1,627.9

39.0 SILT 25 2.4 150.0 2,792.4 1,000.0 1,729.5

40.5 SILT 26 2.4 156.0 2,948.4 1,040.0 1,820.9

42.0 SILT 50 2.4 300.0 3,248.4 2,000.0 2,290.9

43.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

45.0 SILT 2.4 0.0 3,248.4 0.0 1,624.2

46.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

For a designed load of 100 KN, the estimated depth is 16.5m.

Note : 1. The clay skin friction for the top soil layer is assume to be 7.5kN/m2

2. The pile is designed as floating pile where the pile would settle together with the soil and therefore there

is no effective negetive skin friction.

3. The final depth of piles penetration shall be decided on site by load test.

Page 924: Binder 9 with uploaded drawings and approved document

123

Page 925: Binder 9 with uploaded drawings and approved document

123

Page 926: Binder 9 with uploaded drawings and approved document

123

Page 927: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 928: Binder 9 with uploaded drawings and approved document

123

Page 929: Binder 9 with uploaded drawings and approved document

123

Page 930: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 931: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 932: Binder 9 with uploaded drawings and approved document

123

Page 933: Binder 9 with uploaded drawings and approved document

123

Page 934: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 935: Binder 9 with uploaded drawings and approved document

123

Page 936: Binder 9 with uploaded drawings and approved document

123

Page 937: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 938: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 939: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 940: Binder 9 with uploaded drawings and approved document

123

Page 941: Binder 9 with uploaded drawings and approved document

123

Page 942: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 943: Binder 9 with uploaded drawings and approved document

123

Page 944: Binder 9 with uploaded drawings and approved document

123

Page 945: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 946: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 947: Binder 9 with uploaded drawings and approved document

123

Page 948: Binder 9 with uploaded drawings and approved document

123

Page 949: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 950: Binder 9 with uploaded drawings and approved document

123

Page 951: Binder 9 with uploaded drawings and approved document

123

Page 952: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 953: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 954: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 955: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 956: Binder 9 with uploaded drawings and approved document

123

Page 957: Binder 9 with uploaded drawings and approved document

123

Page 958: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 959: Binder 9 with uploaded drawings and approved document

123

Page 960: Binder 9 with uploaded drawings and approved document

123

Page 961: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 962: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 963: Binder 9 with uploaded drawings and approved document

123

Page 964: Binder 9 with uploaded drawings and approved document

123

Page 965: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 966: Binder 9 with uploaded drawings and approved document

123

Page 967: Binder 9 with uploaded drawings and approved document

123

Page 968: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 969: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 970: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 971: Binder 9 with uploaded drawings and approved document

123

Page 972: Binder 9 with uploaded drawings and approved document

123

Page 973: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 974: Binder 9 with uploaded drawings and approved document

123

Page 975: Binder 9 with uploaded drawings and approved document

123

Page 976: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 977: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 978: Binder 9 with uploaded drawings and approved document

123

Page 979: Binder 9 with uploaded drawings and approved document

123

Page 980: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 981: Binder 9 with uploaded drawings and approved document

123

Page 982: Binder 9 with uploaded drawings and approved document

123

Page 983: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 984: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 985: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 986: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 987: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 988: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 989: Binder 9 with uploaded drawings and approved document

123

Page 990: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 991: Binder 9 with uploaded drawings and approved document

123

Page 992: Binder 9 with uploaded drawings and approved document

123

Page 993: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 994: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 995: Binder 9 with uploaded drawings and approved document

123

Page 996: Binder 9 with uploaded drawings and approved document

123

Page 997: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 998: Binder 9 with uploaded drawings and approved document

123

Page 999: Binder 9 with uploaded drawings and approved document

123

Page 1000: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1001: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1002: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1003: Binder 9 with uploaded drawings and approved document

123

Page 1004: Binder 9 with uploaded drawings and approved document

123

Page 1005: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1006: Binder 9 with uploaded drawings and approved document

123

Page 1007: Binder 9 with uploaded drawings and approved document

123

Page 1008: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1009: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1010: Binder 9 with uploaded drawings and approved document

123

Page 1011: Binder 9 with uploaded drawings and approved document

123

Page 1012: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1013: Binder 9 with uploaded drawings and approved document

123

Page 1014: Binder 9 with uploaded drawings and approved document

123

Page 1015: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1016: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1017: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1018: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1019: Binder 9 with uploaded drawings and approved document

123

Page 1020: Binder 9 with uploaded drawings and approved document

123

Page 1021: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1022: Binder 9 with uploaded drawings and approved document

123

Page 1023: Binder 9 with uploaded drawings and approved document

123

Page 1024: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1025: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1026: Binder 9 with uploaded drawings and approved document

123

Page 1027: Binder 9 with uploaded drawings and approved document

123

Page 1028: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1029: Binder 9 with uploaded drawings and approved document

123

Page 1030: Binder 9 with uploaded drawings and approved document

123

Page 1031: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1032: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1033: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1034: Binder 9 with uploaded drawings and approved document

123

Page 1035: Binder 9 with uploaded drawings and approved document

123

Page 1036: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1037: Binder 9 with uploaded drawings and approved document

123

Page 1038: Binder 9 with uploaded drawings and approved document

123

Page 1039: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1040: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1041: Binder 9 with uploaded drawings and approved document

123

Page 1042: Binder 9 with uploaded drawings and approved document

123

Page 1043: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1044: Binder 9 with uploaded drawings and approved document

123

Page 1045: Binder 9 with uploaded drawings and approved document

123

Page 1046: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1047: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1048: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1049: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1050: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1051: Binder 9 with uploaded drawings and approved document

123

Page 1052: Binder 9 with uploaded drawings and approved document

123

Page 1053: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1054: Binder 9 with uploaded drawings and approved document

123

Page 1055: Binder 9 with uploaded drawings and approved document

123

Page 1056: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1057: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1058: Binder 9 with uploaded drawings and approved document

123

Page 1059: Binder 9 with uploaded drawings and approved document

123

Page 1060: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1061: Binder 9 with uploaded drawings and approved document

123

Page 1062: Binder 9 with uploaded drawings and approved document

123

Page 1063: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1064: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1065: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1066: Binder 9 with uploaded drawings and approved document

123

Page 1067: Binder 9 with uploaded drawings and approved document

123

Page 1068: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1069: Binder 9 with uploaded drawings and approved document

123

Page 1070: Binder 9 with uploaded drawings and approved document

123

Page 1071: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1072: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1073: Binder 9 with uploaded drawings and approved document

123

Page 1074: Binder 9 with uploaded drawings and approved document

123

Page 1075: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1076: Binder 9 with uploaded drawings and approved document

123

Page 1077: Binder 9 with uploaded drawings and approved document

123

Page 1078: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1079: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1080: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1081: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1082: Binder 9 with uploaded drawings and approved document

123

Page 1083: Binder 9 with uploaded drawings and approved document

123

Page 1084: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1085: Binder 9 with uploaded drawings and approved document

123

Page 1086: Binder 9 with uploaded drawings and approved document

123

Page 1087: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1088: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1089: Binder 9 with uploaded drawings and approved document

123

Page 1090: Binder 9 with uploaded drawings and approved document

123

Page 1091: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1092: Binder 9 with uploaded drawings and approved document

123

Page 1093: Binder 9 with uploaded drawings and approved document

123

Page 1094: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1095: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1096: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1097: Binder 9 with uploaded drawings and approved document

123

Page 1098: Binder 9 with uploaded drawings and approved document

123

Page 1099: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1100: Binder 9 with uploaded drawings and approved document

123

Page 1101: Binder 9 with uploaded drawings and approved document

123

Page 1102: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1103: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1104: Binder 9 with uploaded drawings and approved document

123

Page 1105: Binder 9 with uploaded drawings and approved document

123

Page 1106: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1107: Binder 9 with uploaded drawings and approved document

123

Page 1108: Binder 9 with uploaded drawings and approved document

123

Page 1109: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1110: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1111: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1112: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1113: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1114: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1115: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1116: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1117: Binder 9 with uploaded drawings and approved document

123

Page 1118: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1119: Binder 9 with uploaded drawings and approved document

123

Page 1120: Binder 9 with uploaded drawings and approved document

123

Page 1121: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1122: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1123: Binder 9 with uploaded drawings and approved document

123

Page 1124: Binder 9 with uploaded drawings and approved document

123

Page 1125: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1126: Binder 9 with uploaded drawings and approved document

123

Page 1127: Binder 9 with uploaded drawings and approved document

123

Page 1128: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1129: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1130: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1131: Binder 9 with uploaded drawings and approved document

123

Page 1132: Binder 9 with uploaded drawings and approved document

123

Page 1133: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1134: Binder 9 with uploaded drawings and approved document

123

Page 1135: Binder 9 with uploaded drawings and approved document

123

Page 1136: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1137: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1138: Binder 9 with uploaded drawings and approved document

123

Page 1139: Binder 9 with uploaded drawings and approved document

123

Page 1140: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1141: Binder 9 with uploaded drawings and approved document

123

Page 1142: Binder 9 with uploaded drawings and approved document

123

Page 1143: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1144: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1145: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1146: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1147: Binder 9 with uploaded drawings and approved document

123

Page 1148: Binder 9 with uploaded drawings and approved document

123

Page 1149: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1150: Binder 9 with uploaded drawings and approved document

123

Page 1151: Binder 9 with uploaded drawings and approved document

123

Page 1152: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1153: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1154: Binder 9 with uploaded drawings and approved document

123

Page 1155: Binder 9 with uploaded drawings and approved document

123

Page 1156: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1157: Binder 9 with uploaded drawings and approved document

123

Page 1158: Binder 9 with uploaded drawings and approved document

123

Page 1159: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1160: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1161: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1162: Binder 9 with uploaded drawings and approved document

123

Page 1163: Binder 9 with uploaded drawings and approved document

123

Page 1164: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1165: Binder 9 with uploaded drawings and approved document

123

Page 1166: Binder 9 with uploaded drawings and approved document

123

Page 1167: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1168: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1169: Binder 9 with uploaded drawings and approved document

123

Page 1170: Binder 9 with uploaded drawings and approved document

123

Page 1171: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1172: Binder 9 with uploaded drawings and approved document

123

Page 1173: Binder 9 with uploaded drawings and approved document

123

Page 1174: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1175: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1176: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1177: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1178: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1179: Binder 9 with uploaded drawings and approved document

123

Page 1180: Binder 9 with uploaded drawings and approved document

123

Page 1181: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1182: Binder 9 with uploaded drawings and approved document

123

Page 1183: Binder 9 with uploaded drawings and approved document

123

Page 1184: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1185: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1186: Binder 9 with uploaded drawings and approved document

123

Page 1187: Binder 9 with uploaded drawings and approved document

123

Page 1188: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1189: Binder 9 with uploaded drawings and approved document

123

Page 1190: Binder 9 with uploaded drawings and approved document

123

Page 1191: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1192: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1193: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1194: Binder 9 with uploaded drawings and approved document

123

Page 1195: Binder 9 with uploaded drawings and approved document

123

Page 1196: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1197: Binder 9 with uploaded drawings and approved document

123

Page 1198: Binder 9 with uploaded drawings and approved document

123

Page 1199: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1200: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1201: Binder 9 with uploaded drawings and approved document

123

Page 1202: Binder 9 with uploaded drawings and approved document

123

Page 1203: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1204: Binder 9 with uploaded drawings and approved document

123

Page 1205: Binder 9 with uploaded drawings and approved document

123

Page 1206: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1207: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1208: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1209: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1210: Binder 9 with uploaded drawings and approved document

123

Page 1211: Binder 9 with uploaded drawings and approved document

123

Page 1212: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1213: Binder 9 with uploaded drawings and approved document

123

Page 1214: Binder 9 with uploaded drawings and approved document

123

Page 1215: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1216: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1217: Binder 9 with uploaded drawings and approved document

123

Page 1218: Binder 9 with uploaded drawings and approved document

123

Page 1219: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1220: Binder 9 with uploaded drawings and approved document

123

Page 1221: Binder 9 with uploaded drawings and approved document

123

Page 1222: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1223: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1224: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1225: Binder 9 with uploaded drawings and approved document

123

Page 1226: Binder 9 with uploaded drawings and approved document

123

Page 1227: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1228: Binder 9 with uploaded drawings and approved document

123

Page 1229: Binder 9 with uploaded drawings and approved document

123

Page 1230: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1231: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1232: Binder 9 with uploaded drawings and approved document

123

Page 1233: Binder 9 with uploaded drawings and approved document

123

Page 1234: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1235: Binder 9 with uploaded drawings and approved document

123

Page 1236: Binder 9 with uploaded drawings and approved document

123

Page 1237: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1238: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1239: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1240: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1241: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1242: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1243: Binder 9 with uploaded drawings and approved document

PILE BEARING CAPACITY CALCULATION BASED ON S.P.T. VALUE

------------------ ------------------

Project Name :

Location :

Borehole No. : BH-1

Date :

------------------ ------------------

MAYERHOF Formula : K1 K2

Skin, Ps = K1 x Nav x As SAND 2.0 400

Bearing, Pb = K2 x Nb x Ab SILT 2.5 250

Ult. Load, Pu = Ps + Pb CLAY 3.0 100

All. Load, Pa = Ps/Fs + Pb/Fb

Factor of safety : Skin, Fs = 2

Bearing, Fb = 3

------------------ ------------------

To calculate allowable soil bearing capacity :

Pile used : Type : s

(c = circular) Width, b = 0.4 m Perimeter: 1.600

(s = square) (= dia. for type c) Ab: 0.160

Qa(conc): 1800

========== ========== ====== ========== ========== ============ =======================

Depth Soil SPT Skin Total Base Working Load

Type N As Fric Skin Load Fs = 2.0 Fb = 3

(m) (m²) (kN) (kN) (kN) (KN)

------------------ ------------------ ---------- ------------------ ------------------ -------------------- ---------------------------------------

0.0 SAND 0 0.0 0.0 0.0 0.0 0.0

1.5 SAND 11 2.4 52.8 52.8 704.0 261.1

3.0 SAND 12 2.4 57.6 110.4 768.0 311.2

4.5 SAND 15 2.4 72.0 182.4 960.0 411.2

6.0 SILT 17 2.4 102.0 284.4 680.0 368.9

7.5 SILT 19 2.4 114.0 398.4 760.0 452.5

9.0 SILT 19 2.4 114.0 512.4 760.0 509.5

10.5 SILT 17 2.4 102.0 614.4 680.0 533.9

12.0 SILT 19 2.4 114.0 728.4 760.0 617.5

13.5 SILT 11 2.4 66.0 794.4 440.0 543.9

15.0 SILT 18 2.4 108.0 902.4 720.0 691.2

16.5 SILT 17 2.4 102.0 1,004.4 680.0 728.9

18.0 SILT 19 2.4 114.0 1,118.4 760.0 812.5

19.5 SILT 20 2.4 120.0 1,238.4 800.0 885.9

21.0 SILT 18 2.4 108.0 1,346.4 720.0 913.2

22.5 SILT 14 2.4 84.0 1,430.4 560.0 901.9

24.0 SILT 0 2.4 0.0 1,430.4 0.0 715.2

25.5 SILT 22 2.4 132.0 1,562.4 880.0 1,074.5

27.0 SILT 20 2.4 120.0 1,682.4 800.0 1,107.9

28.5 SILT 20 2.4 120.0 1,802.4 800.0 1,167.9

30.0 SILT 22 2.4 132.0 1,934.4 880.0 1,260.5

31.5 SILT 25 2.4 150.0 2,084.4 1,000.0 1,375.5

33.0 SILT 23 2.4 138.0 2,222.4 920.0 1,417.9

34.5 SILT 23 2.4 138.0 2,360.4 920.0 1,486.9

36.0 SILT 24 2.4 144.0 2,504.4 960.0 1,572.2

37.5 SILT 23 2.4 138.0 2,642.4 920.0 1,627.9

39.0 SILT 25 2.4 150.0 2,792.4 1,000.0 1,729.5

40.5 SILT 26 2.4 156.0 2,948.4 1,040.0 1,820.9

42.0 SILT 50 2.4 300.0 3,248.4 2,000.0 2,290.9

43.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

45.0 SILT 2.4 0.0 3,248.4 0.0 1,624.2

46.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

For a designed load of 100 KN, the estimated depth is 16.5m.

Note : 1. The clay skin friction for the top soil layer is assume to be 7.5kN/m2

2. The pile is designed as floating pile where the pile would settle together with the soil and therefore there

is no effective negetive skin friction.

3. The final depth of piles penetration shall be decided on site by load test.

Page 1244: Binder 9 with uploaded drawings and approved document

123

Page 1245: Binder 9 with uploaded drawings and approved document

123

Page 1246: Binder 9 with uploaded drawings and approved document

123

Page 1247: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1248: Binder 9 with uploaded drawings and approved document

123

Page 1249: Binder 9 with uploaded drawings and approved document

123

Page 1250: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1251: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1252: Binder 9 with uploaded drawings and approved document

123

Page 1253: Binder 9 with uploaded drawings and approved document

123

Page 1254: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1255: Binder 9 with uploaded drawings and approved document

123

Page 1256: Binder 9 with uploaded drawings and approved document

123

Page 1257: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1258: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1259: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1260: Binder 9 with uploaded drawings and approved document

123

Page 1261: Binder 9 with uploaded drawings and approved document

123

Page 1262: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1263: Binder 9 with uploaded drawings and approved document

123

Page 1264: Binder 9 with uploaded drawings and approved document

123

Page 1265: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1266: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1267: Binder 9 with uploaded drawings and approved document

123

Page 1268: Binder 9 with uploaded drawings and approved document

123

Page 1269: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1270: Binder 9 with uploaded drawings and approved document

123

Page 1271: Binder 9 with uploaded drawings and approved document

123

Page 1272: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1273: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1274: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1275: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1276: Binder 9 with uploaded drawings and approved document

123

Page 1277: Binder 9 with uploaded drawings and approved document

123

Page 1278: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1279: Binder 9 with uploaded drawings and approved document

123

Page 1280: Binder 9 with uploaded drawings and approved document

123

Page 1281: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1282: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1283: Binder 9 with uploaded drawings and approved document

123

Page 1284: Binder 9 with uploaded drawings and approved document

123

Page 1285: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1286: Binder 9 with uploaded drawings and approved document

123

Page 1287: Binder 9 with uploaded drawings and approved document

123

Page 1288: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1289: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1290: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1291: Binder 9 with uploaded drawings and approved document

123

Page 1292: Binder 9 with uploaded drawings and approved document

123

Page 1293: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1294: Binder 9 with uploaded drawings and approved document

123

Page 1295: Binder 9 with uploaded drawings and approved document

123

Page 1296: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1297: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1298: Binder 9 with uploaded drawings and approved document

123

Page 1299: Binder 9 with uploaded drawings and approved document

123

Page 1300: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1301: Binder 9 with uploaded drawings and approved document

123

Page 1302: Binder 9 with uploaded drawings and approved document

123

Page 1303: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1304: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1305: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1306: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1307: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1308: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1309: Binder 9 with uploaded drawings and approved document

123

Page 1310: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1311: Binder 9 with uploaded drawings and approved document

123

Page 1312: Binder 9 with uploaded drawings and approved document

123

Page 1313: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1314: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1315: Binder 9 with uploaded drawings and approved document

123

Page 1316: Binder 9 with uploaded drawings and approved document

123

Page 1317: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1318: Binder 9 with uploaded drawings and approved document

123

Page 1319: Binder 9 with uploaded drawings and approved document

123

Page 1320: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1321: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1322: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1323: Binder 9 with uploaded drawings and approved document

123

Page 1324: Binder 9 with uploaded drawings and approved document

123

Page 1325: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1326: Binder 9 with uploaded drawings and approved document

123

Page 1327: Binder 9 with uploaded drawings and approved document

123

Page 1328: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1329: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1330: Binder 9 with uploaded drawings and approved document

123

Page 1331: Binder 9 with uploaded drawings and approved document

123

Page 1332: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1333: Binder 9 with uploaded drawings and approved document

123

Page 1334: Binder 9 with uploaded drawings and approved document

123

Page 1335: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1336: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1337: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1338: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1339: Binder 9 with uploaded drawings and approved document

123

Page 1340: Binder 9 with uploaded drawings and approved document

123

Page 1341: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1342: Binder 9 with uploaded drawings and approved document

123

Page 1343: Binder 9 with uploaded drawings and approved document

123

Page 1344: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1345: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1346: Binder 9 with uploaded drawings and approved document

123

Page 1347: Binder 9 with uploaded drawings and approved document

123

Page 1348: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1349: Binder 9 with uploaded drawings and approved document

123

Page 1350: Binder 9 with uploaded drawings and approved document

123

Page 1351: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1352: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1353: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1354: Binder 9 with uploaded drawings and approved document

123

Page 1355: Binder 9 with uploaded drawings and approved document

123

Page 1356: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1357: Binder 9 with uploaded drawings and approved document

123

Page 1358: Binder 9 with uploaded drawings and approved document

123

Page 1359: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1360: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1361: Binder 9 with uploaded drawings and approved document

123

Page 1362: Binder 9 with uploaded drawings and approved document

123

Page 1363: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1364: Binder 9 with uploaded drawings and approved document

123

Page 1365: Binder 9 with uploaded drawings and approved document

123

Page 1366: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1367: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1368: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1369: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1370: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1371: Binder 9 with uploaded drawings and approved document

123

Page 1372: Binder 9 with uploaded drawings and approved document

123

Page 1373: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1374: Binder 9 with uploaded drawings and approved document

123

Page 1375: Binder 9 with uploaded drawings and approved document

123

Page 1376: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1377: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1378: Binder 9 with uploaded drawings and approved document

123

Page 1379: Binder 9 with uploaded drawings and approved document

123

Page 1380: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1381: Binder 9 with uploaded drawings and approved document

123

Page 1382: Binder 9 with uploaded drawings and approved document

123

Page 1383: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1384: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1385: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1386: Binder 9 with uploaded drawings and approved document

123

Page 1387: Binder 9 with uploaded drawings and approved document

123

Page 1388: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1389: Binder 9 with uploaded drawings and approved document

123

Page 1390: Binder 9 with uploaded drawings and approved document

123

Page 1391: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1392: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1393: Binder 9 with uploaded drawings and approved document

123

Page 1394: Binder 9 with uploaded drawings and approved document

123

Page 1395: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1396: Binder 9 with uploaded drawings and approved document

123

Page 1397: Binder 9 with uploaded drawings and approved document

123

Page 1398: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1399: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1400: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1401: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1402: Binder 9 with uploaded drawings and approved document

123

Page 1403: Binder 9 with uploaded drawings and approved document

123

Page 1404: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1405: Binder 9 with uploaded drawings and approved document

123

Page 1406: Binder 9 with uploaded drawings and approved document

123

Page 1407: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1408: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1409: Binder 9 with uploaded drawings and approved document

123

Page 1410: Binder 9 with uploaded drawings and approved document

123

Page 1411: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1412: Binder 9 with uploaded drawings and approved document

123

Page 1413: Binder 9 with uploaded drawings and approved document

123

Page 1414: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1415: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1416: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1417: Binder 9 with uploaded drawings and approved document

123

Page 1418: Binder 9 with uploaded drawings and approved document

123

Page 1419: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1420: Binder 9 with uploaded drawings and approved document

123

Page 1421: Binder 9 with uploaded drawings and approved document

123

Page 1422: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1423: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1424: Binder 9 with uploaded drawings and approved document

123

Page 1425: Binder 9 with uploaded drawings and approved document

123

Page 1426: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1427: Binder 9 with uploaded drawings and approved document

123

Page 1428: Binder 9 with uploaded drawings and approved document

123

Page 1429: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1430: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1431: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1432: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1433: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1434: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1435: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1436: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1437: Binder 9 with uploaded drawings and approved document

PILE BEARING CAPACITY CALCULATION BASED ON S.P.T. VALUE

------------------ ------------------

Project Name :

Location :

Borehole No. : BH-1

Date :

------------------ ------------------

MAYERHOF Formula : K1 K2

Skin, Ps = K1 x Nav x As SAND 2.0 400

Bearing, Pb = K2 x Nb x Ab SILT 2.5 250

Ult. Load, Pu = Ps + Pb CLAY 3.0 100

All. Load, Pa = Ps/Fs + Pb/Fb

Factor of safety : Skin, Fs = 2

Bearing, Fb = 3

------------------ ------------------

To calculate allowable soil bearing capacity :

Pile used : Type : s

(c = circular) Width, b = 0.4 m Perimeter: 1.600

(s = square) (= dia. for type c) Ab: 0.160

Qa(conc): 1800

========== ========== ====== ========== ========== ============ =======================

Depth Soil SPT Skin Total Base Working Load

Type N As Fric Skin Load Fs = 2.0 Fb = 3

(m) (m²) (kN) (kN) (kN) (KN)

------------------ ------------------ ---------- ------------------ ------------------ -------------------- ---------------------------------------

0.0 SAND 0 0.0 0.0 0.0 0.0 0.0

1.5 SAND 11 2.4 52.8 52.8 704.0 261.1

3.0 SAND 12 2.4 57.6 110.4 768.0 311.2

4.5 SAND 15 2.4 72.0 182.4 960.0 411.2

6.0 SILT 17 2.4 102.0 284.4 680.0 368.9

7.5 SILT 19 2.4 114.0 398.4 760.0 452.5

9.0 SILT 19 2.4 114.0 512.4 760.0 509.5

10.5 SILT 17 2.4 102.0 614.4 680.0 533.9

12.0 SILT 19 2.4 114.0 728.4 760.0 617.5

13.5 SILT 11 2.4 66.0 794.4 440.0 543.9

15.0 SILT 18 2.4 108.0 902.4 720.0 691.2

16.5 SILT 17 2.4 102.0 1,004.4 680.0 728.9

18.0 SILT 19 2.4 114.0 1,118.4 760.0 812.5

19.5 SILT 20 2.4 120.0 1,238.4 800.0 885.9

21.0 SILT 18 2.4 108.0 1,346.4 720.0 913.2

22.5 SILT 14 2.4 84.0 1,430.4 560.0 901.9

24.0 SILT 0 2.4 0.0 1,430.4 0.0 715.2

25.5 SILT 22 2.4 132.0 1,562.4 880.0 1,074.5

27.0 SILT 20 2.4 120.0 1,682.4 800.0 1,107.9

28.5 SILT 20 2.4 120.0 1,802.4 800.0 1,167.9

30.0 SILT 22 2.4 132.0 1,934.4 880.0 1,260.5

31.5 SILT 25 2.4 150.0 2,084.4 1,000.0 1,375.5

33.0 SILT 23 2.4 138.0 2,222.4 920.0 1,417.9

34.5 SILT 23 2.4 138.0 2,360.4 920.0 1,486.9

36.0 SILT 24 2.4 144.0 2,504.4 960.0 1,572.2

37.5 SILT 23 2.4 138.0 2,642.4 920.0 1,627.9

39.0 SILT 25 2.4 150.0 2,792.4 1,000.0 1,729.5

40.5 SILT 26 2.4 156.0 2,948.4 1,040.0 1,820.9

42.0 SILT 50 2.4 300.0 3,248.4 2,000.0 2,290.9

43.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

45.0 SILT 2.4 0.0 3,248.4 0.0 1,624.2

46.5 SILT 2.4 0.0 3,248.4 0.0 1,624.2

For a designed load of 100 KN, the estimated depth is 16.5m.

Note : 1. The clay skin friction for the top soil layer is assume to be 7.5kN/m2

2. The pile is designed as floating pile where the pile would settle together with the soil and therefore there

is no effective negetive skin friction.

3. The final depth of piles penetration shall be decided on site by load test.

Page 1438: Binder 9 with uploaded drawings and approved document

123

Page 1439: Binder 9 with uploaded drawings and approved document

123

Page 1440: Binder 9 with uploaded drawings and approved document

123

Page 1441: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1442: Binder 9 with uploaded drawings and approved document

123

Page 1443: Binder 9 with uploaded drawings and approved document

123

Page 1444: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1445: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1446: Binder 9 with uploaded drawings and approved document

123

Page 1447: Binder 9 with uploaded drawings and approved document

123

Page 1448: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1449: Binder 9 with uploaded drawings and approved document

123

Page 1450: Binder 9 with uploaded drawings and approved document

123

Page 1451: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1452: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1453: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1454: Binder 9 with uploaded drawings and approved document

123

Page 1455: Binder 9 with uploaded drawings and approved document

123

Page 1456: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1457: Binder 9 with uploaded drawings and approved document

123

Page 1458: Binder 9 with uploaded drawings and approved document

123

Page 1459: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1460: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1461: Binder 9 with uploaded drawings and approved document

123

Page 1462: Binder 9 with uploaded drawings and approved document

123

Page 1463: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1464: Binder 9 with uploaded drawings and approved document

123

Page 1465: Binder 9 with uploaded drawings and approved document

123

Page 1466: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1467: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1468: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1469: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1470: Binder 9 with uploaded drawings and approved document

123

Page 1471: Binder 9 with uploaded drawings and approved document

123

Page 1472: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1473: Binder 9 with uploaded drawings and approved document

123

Page 1474: Binder 9 with uploaded drawings and approved document

123

Page 1475: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1476: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1477: Binder 9 with uploaded drawings and approved document

123

Page 1478: Binder 9 with uploaded drawings and approved document

123

Page 1479: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1480: Binder 9 with uploaded drawings and approved document

123

Page 1481: Binder 9 with uploaded drawings and approved document

123

Page 1482: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1483: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1484: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1485: Binder 9 with uploaded drawings and approved document

123

Page 1486: Binder 9 with uploaded drawings and approved document

123

Page 1487: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1488: Binder 9 with uploaded drawings and approved document

123

Page 1489: Binder 9 with uploaded drawings and approved document

123

Page 1490: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1491: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1492: Binder 9 with uploaded drawings and approved document

123

Page 1493: Binder 9 with uploaded drawings and approved document

123

Page 1494: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1495: Binder 9 with uploaded drawings and approved document

123

Page 1496: Binder 9 with uploaded drawings and approved document

123

Page 1497: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1498: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1499: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1500: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1501: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1502: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1503: Binder 9 with uploaded drawings and approved document

123

Page 1504: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1505: Binder 9 with uploaded drawings and approved document

123

Page 1506: Binder 9 with uploaded drawings and approved document

123

Page 1507: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1508: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1509: Binder 9 with uploaded drawings and approved document

123

Page 1510: Binder 9 with uploaded drawings and approved document

123

Page 1511: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1512: Binder 9 with uploaded drawings and approved document

123

Page 1513: Binder 9 with uploaded drawings and approved document

123

Page 1514: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1515: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1516: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1517: Binder 9 with uploaded drawings and approved document

123

Page 1518: Binder 9 with uploaded drawings and approved document

123

Page 1519: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1520: Binder 9 with uploaded drawings and approved document

123

Page 1521: Binder 9 with uploaded drawings and approved document

123

Page 1522: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1523: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1524: Binder 9 with uploaded drawings and approved document

123

Page 1525: Binder 9 with uploaded drawings and approved document

123

Page 1526: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1527: Binder 9 with uploaded drawings and approved document

123

Page 1528: Binder 9 with uploaded drawings and approved document

123

Page 1529: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1530: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1531: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1532: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1533: Binder 9 with uploaded drawings and approved document

123

Page 1534: Binder 9 with uploaded drawings and approved document

123

Page 1535: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1536: Binder 9 with uploaded drawings and approved document

123

Page 1537: Binder 9 with uploaded drawings and approved document

123

Page 1538: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1539: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1540: Binder 9 with uploaded drawings and approved document

123

Page 1541: Binder 9 with uploaded drawings and approved document

123

Page 1542: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1543: Binder 9 with uploaded drawings and approved document

123

Page 1544: Binder 9 with uploaded drawings and approved document

123

Page 1545: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1546: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1547: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1548: Binder 9 with uploaded drawings and approved document

123

Page 1549: Binder 9 with uploaded drawings and approved document

123

Page 1550: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1551: Binder 9 with uploaded drawings and approved document

123

Page 1552: Binder 9 with uploaded drawings and approved document

123

Page 1553: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1554: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1555: Binder 9 with uploaded drawings and approved document

123

Page 1556: Binder 9 with uploaded drawings and approved document

123

Page 1557: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1558: Binder 9 with uploaded drawings and approved document

123

Page 1559: Binder 9 with uploaded drawings and approved document

123

Page 1560: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1561: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1562: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1563: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1564: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1565: Binder 9 with uploaded drawings and approved document

123

Page 1566: Binder 9 with uploaded drawings and approved document

123

Page 1567: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1568: Binder 9 with uploaded drawings and approved document

123

Page 1569: Binder 9 with uploaded drawings and approved document

123

Page 1570: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1571: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1572: Binder 9 with uploaded drawings and approved document

123

Page 1573: Binder 9 with uploaded drawings and approved document

123

Page 1574: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1575: Binder 9 with uploaded drawings and approved document

123

Page 1576: Binder 9 with uploaded drawings and approved document

123

Page 1577: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1578: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1579: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1580: Binder 9 with uploaded drawings and approved document

123

Page 1581: Binder 9 with uploaded drawings and approved document

123

Page 1582: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1583: Binder 9 with uploaded drawings and approved document

123

Page 1584: Binder 9 with uploaded drawings and approved document

123

Page 1585: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1586: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1587: Binder 9 with uploaded drawings and approved document

123

Page 1588: Binder 9 with uploaded drawings and approved document

123

Page 1589: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1590: Binder 9 with uploaded drawings and approved document

123

Page 1591: Binder 9 with uploaded drawings and approved document

123

Page 1592: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1593: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1594: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1595: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1596: Binder 9 with uploaded drawings and approved document

123

Page 1597: Binder 9 with uploaded drawings and approved document

123

Page 1598: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1599: Binder 9 with uploaded drawings and approved document

123

Page 1600: Binder 9 with uploaded drawings and approved document

123

Page 1601: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1602: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1603: Binder 9 with uploaded drawings and approved document

123

Page 1604: Binder 9 with uploaded drawings and approved document

123

Page 1605: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1606: Binder 9 with uploaded drawings and approved document

123

Page 1607: Binder 9 with uploaded drawings and approved document

123

Page 1608: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1609: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1610: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1611: Binder 9 with uploaded drawings and approved document

123

Page 1612: Binder 9 with uploaded drawings and approved document

123

Page 1613: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1614: Binder 9 with uploaded drawings and approved document

123

Page 1615: Binder 9 with uploaded drawings and approved document

123

Page 1616: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1617: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1618: Binder 9 with uploaded drawings and approved document

123

Page 1619: Binder 9 with uploaded drawings and approved document

123

Page 1620: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1621: Binder 9 with uploaded drawings and approved document

123

Page 1622: Binder 9 with uploaded drawings and approved document

123

Page 1623: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1624: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1625: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1626: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1627: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1628: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1629: Binder 9 with uploaded drawings and approved document

Muwesii 123

Page 1630: Binder 9 with uploaded drawings and approved document

Muwesii 123