biogas asia pacific forum 2015

30
Biogas Asia Pacific Forum 2015 Case Study : Key elements in start-up and optimisation of Biogas Capture Plant towards achieving desired KPIs Yusriady bin Che Saad 28 – 29 April 2015, Sunway Pyramid Convention Centre, Kuala Lumpur KONZEN CLEAN ENERGY SDN BHD

Upload: others

Post on 24-Dec-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Biogas Asia Pacific Forum 2015

Case Study : Key elements in start-up and optimisation of Biogas Capture Plant towards achieving desired KPIs

Yusriady bin Che Saad 28 – 29 April 2015, Sunway Pyramid Convention Centre, Kuala Lumpur

KONZEN CLEAN ENERGY SDN BHD

OBJECTIVES

Objectives

• To ensure the plant continuously delivered the desired Biogas production output base on its performances.

• To highlight the important of the plant performances monitoring management towards optimization of the Biogas captured.

3

INTRODUCTION

Introduction

KONZEN® Clean Energy • A BioNexus Status company focusing in high organic

loading wastewater treatment such as POME • Technology developed through a series of R&D and

collaboration with university • KONZEN® GROUP has been providing total solution

for industrial water and wastewater engineering > 20 years. 3 main operating divisions: • Konzen SE Asia (KL, Penang and Kuching) • Konzen China (Tianjin and Shanghai) • Konzen Clean Energy Sdn Bhd, KCE

5

Introduction

6

• Provides biogas system end-to-end turnkey services.

Introduction

7

Introduction Our Technology

• The technology developed by KONZEN® is a closed anaerobic digester tank of Continuous Stirred Tank Reactor (CSTR) type under mesophilic condition.

8

Key features: • CSTR of Biogas-POME vertical mixing. • 10 days Hydraulic Retention Time • No moving parts inside digester • Heat recovered for optimum operating

temperature • sludge recycled to maintain the pH

and MLSS in the tank

The Project

9

• The anaerobic digester plant is designed and built with required instrumentation and detailed programming in order to enable effective plant management and consequently maintaining consistent process deliverables.

• The Programmable Logic Control (PLC) and Supervisory Control and Data Acquisition (SCADA) system have been incorporated into the plant operation.

10

• The project is divided into two phases; • 1st phase is for methane capture and flaring as the new

mill goes into production,

• 2nd phase is planned for biogas power generation when the mill reaches its full production capacity.

• The remoteness of this site makes this project extremely challenging to execute Careful planning for material selection, construction methodology and logistics was crucial.

11

• Anaerobic process conducted in tank digesters would be the most suitable system for the anaerobic treatment of POME for it enables better system control and consistency.

• The key strategies to manage an anaerobic digestion system:

1. Detailing out the anaerobic operation system 2. Installing a comprehensive anaerobic process

management control system 3. Administration and process monitoring in practice

• Optimization of the operational conditions can only be executed on a well-controlled and well-monitored anaerobic system.

12

1. DETAILING OUT THE ANAEROBIC OPERATING

SYSTEM

13

• The main four systems

• Sectioning the plant into few systems • ease plant control implementation

• enable efficient plant troubleshooting procedures

14

1. Pre- treatment system

2. Anaerobic digestion system

3. Biogas handling system

4. Post- treatment system

15

Incoming raw effluent

Pre-treatment system

Anaerobic digestion system

Biogas handling system

Biogas utilization

Post-treatment

system

Biogas recycle

Supernatant discharge to aerobic treatment

Sludge

Sludge recycle

Sludge discharge to sludge collection pond

2. INSTALLING A COMPREHENSIVE

ANAEROBIC PROCESS MANAGEMENT CONTROL

SYSTEM

16

• The anaerobic digester plant is designed and built with required instrumentation and detailed programming in order to enable effective plant management and consequently maintaining consistent process deliverables.

• The Programmable Logic Control (PLC) and Supervisory Control and Data Acquisition (SCADA) system have been incorporated into the plant operation.

17

• Benefits of an anaerobic treatment plant with process control and monitoring management:

18

Consistent anaerobic treatment process

Orderly bookkeeping of input and output

Enable maximum utilization of biogas

Reduce plant downtime

Improve general working environment

Easy and safe operation

• Parameter control regime:

19

• pH

• Temperature

• Nutrients and COD

• Inhibition/ toxicity

Environmental

• Solids retention time

• Hydraulic retention time

• Organic loading rate

• Mixing

Operational

20

VFA TA pH

Average 371.38 3,994.78 7.37

Maximum 670.46 4,393.92 7.52

Minimum 205.57 3,492.51 7.18

5.0

5.5

6.0

6.5

7.0

7.5

8.0

8.5

9.0

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

5,000

1/1

5

1/2

4

2/2

2/1

1

2/2

0

3/1

3/1

0

3/1

9

3/2

8

4/6

4/1

5

4/2

4

pH

VF

A a

nd

TA

(p

pm

)

Operation Date

Monitoring VFA, TA and pH

VFA TA pH

21

CH4 CO2 H2S

Average 60 39 446

Maximum 67 46 943

Minimum 49 35 66

0

100

200

300

400

500

600

700

800

900

1,000

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

1/1

5

1/2

4

2/2

2/1

1

2/2

0

3/1

3/1

0

3/1

9

3/2

8

4/6

4/1

5

4/2

4

H2S

(p

pm

)

CH

4 a

nd

CO

2 (

%)

Operation Date

Monitoring CH4, CO2 and H2S

CH4 CO2 H2S

22

Biogas

(Nm3/day) SS (%) Temperature (oC)

Average 9,005.53 41.17 32.89

Maximum 16,562.00 66.92 37.20

Minimum 3,201.00 29.34 27.65

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

0

5,000

10,000

15,000

20,000

25,000

1/1

5

1/2

4

2/2

2/1

1

2/2

0

3/1

3/1

0

3/1

9

3/2

8

4/6

4/1

5

4/2

4

SS

(%

) an

d T

em

p. (d

eg

Cel)

Bio

gas (

Nm

3/D

ay)

Operation Date

Monitoring Biogas, % SS and Temperature

Biogas %SS T

23

Biogas

(Nm3/day) CH4 (%)

Average 9,311 60

Maximum 3,201 67

Minimum 16,562 49

0

10

20

30

40

50

60

70

80

0

1,700

3,400

5,100

6,800

8,500

10,200

11,900

13,600

15,300

17,000

1 3 5 7 9

11

13

15

17

19

21

23

25

27

29

31

33

35

37

39

41

43

45

47

49

51

53

55

57

59

61

63

65

67

69

71

73

75

77

79

81

83

85

87

89

CH

4 (

%)

Bio

gas (

Nm

3/d

ay)

Operation Days

Monitoring Biogas & Methane

Biogas CH4 Linear (Biogas) Linear (CH4)

KPI = 55 %

24

COD LR Eff. COD

Rem.

Average 5.06 77.86

Maximum 7.35 93.66

Minimum 2.42 58.09

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

80.00

90.00

100.00

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

1/1

5

1/2

4

2/2

2/1

1

2/2

0

3/1

3/1

0

3/1

9

3/2

8

4/6

4/1

5

4/2

4

Eff

. C

D R

em

ov

ed

(%

)

CO

D L

R (

kg

/m3/d

ay)

Operation Date

Monitoring COD LR & Efficiency COD Removed

COD LR Eff. COD Rem.

3. ADIMINISTRATION AND PROCESS MONITORING

25

• Standard procedures and guidelines • Operational routine and maintenance schedule • Troubleshooting and corrective measures

• Information management and data processing • Hydrodynamic study • Comparison of data collected • Identification of a progression through the system

• Personnel administration • Effective communication • Organization chart and scopes • Assessment and training

• Operational safety • Safety information and best practices • Emergency action plant

26

CONCLUDING REMARKS

27

• Primary optimization objectives: • Wastewater treatment targets

• Methane yield and consistency

• Optimizing factors: • Process stability

• Nutrients

• Toxic substrates

• Loading rate

• Digester mixing

• Digester start-up

28

29

Cost effective, accurate real time

monitoring

Programmed control system

Well-trained plant

operators

Practical plant management

strategy

Optimum anaerobic treatment and consistent biogas yield!

• Optimization Strategy:

Today’s Creativity, Tomorrow’s Energy