biomass gasification chp pilot project lessons learned...pilot project –lessons learned 27...
TRANSCRIPT
Biomass Gasification CHP Pilot Project – Lessons Learned
FNSB and ACEP
Ben Loeffler, Energy Management Engineer
October 31, 2018
1
OUTLINE
1. FNSB-ACEP Partnership2. Biomass CHP Pilot Project Motivations3. Intro to Biomass Gasification CHP4. Pilot Project Outcome5. Lessons Learned
2
FNSB-ACEP Partnership
ObjectiveProvide coordination of programs and projects
involving the development, implementation, and evaluation of
energy efficiency, energy delivery, and alternative and renewable energy systems in FNSB.
3
Energy Management Engineer“Work with Borough stakeholders and ACEP researchers to evaluate emerging and existing energy efficient technologies relevant to the
Borough.”
ACEPMission: “Develop and
disseminate practical, cost-effective, and innovative energy
solutions for Alaska and beyond”
Vision: “Alaska leading the way in innovative production,
distribution, and management of energy”
Fairbanks Comprehensive
Economic Development Strategy (CEDS)
COMMUNITY PRIORITY #1:
“Lower and stabilize FNSB energy costs by expanding the energy portfolio with a focus on local
resources.”
4
Biomass Pilot Project Motivations
5
Biomass Pilot Project Motivations
6 http://alaskarenewableenergy.org/index.php/programs/renewable-energy-atlas/
Biomass Pilot Project Motivations
7
Biomass Pilot Project MotivationsS
ola
r E
ne
rgy
Pro
du
ctio
n
8
Biomass Pilot Project Motivations
Win
d E
ne
rgy
Pro
du
ctio
n
9
Biomass Pilot Project MotivationsB
iom
ass
En
erg
y P
rod
uct
ion
Fairbanks Galena
Electricity Cost $/kWh $0.20 $0.67
Fuel Cost $/Gallon $2.20 $5.76
Value of 280,000 kWh $ $56,000 $164,000
Value of 2,380 MMBTU $ $45,000 $102,000
Cost of 370 tons Wood Chips $ -$32,000 -$37,000
Cost of Maintenance $ -$30,000 -$40,000
Annual Savings $ $39,000 $187,000
Annual Local Impact $ $64,000 $77,000
10
Biomass Pilot Project Motivations
Biomass CHP Pilot Project Goals
Evaluate and Disseminate:
Fuel Suitability
Performance
Reliability
Maintenance Costs
Emissions
Islanded-grid Compatibility
11
FNSB Testing Objectives
Fuel Consumption
Ash Production
Integration with Building
System Reliability
Track every fault event and system downtime
O&M Costs
Track all consumables and parts
Track all labor hours
12
ACEP Testing Objectives
Instrumentation of Heat and Power
Grid-Connected Monitoring
Islanded Mode Performance Testing
Disconnect from Grid
Operate in Parallel with Diesel Genset and Load Bank
Data Processing and Analysis
13
14
Intro to Biomass Gasification CHP
• 25% Carbon Monoxide• 17% Hydrogen• 8% Carbon Dioxide• 2.5% Methane• 47.5% Nitrogen
15
Intro to Biomass Gasification CHP
Intro to Biomass Gasification CHP
16
Pilot Project Progress and Plan
17
Identify potential pilot project sites
Select an appropriate system
Secure external funding to support pilot installation
Design and build installation
Purchase and install equipment
Operate system and collect data
Analyze performance data, disseminate results
Proposed Site – Big Dipper Ice Rink
• Demand Charges
• Year round heat load
• Chip Access
18
Proposed Technology – Volter 40
– Operates on wood chips (spruce and aspen)
– 40kW Electric
– 340,000 BTU/hr Thermal
– Small-scale, packaged unit suited for both railbelt and rural installations
– Load-following, but not grid-forming
19
20
Proposed Site – Big Dipper Ice Rink
0
20
40
60
80
100
120
140
160
180
200
10/26/2016 10/28/2016 10/30/2016 11/1/2016 11/3/2016 11/5/2016
Ele
ctri
city
[k
W]
Grid
Volter
21
Proposed Site – Big Dipper Ice Rink
0
100
200
300
400
500
600
700
800
900
1,000
July
Au
gu
st
Sep
tem
ber
Oct
ob
er
No
vem
ber
Dec
emb
er
Jan
uar
y
Feb
ruar
y
Mar
ch
Ap
ril
May
Jun
e
En
erg
y U
sag
e [
MM
BT
U]
Estimated Heat Usage with Volter
Volter Heat Utility Heat
0
100
200
300
400
500
600
700
800
900
1,000
July
Au
gu
st
Sep
tem
ber
Oct
ob
er
No
vem
ber
Dec
emb
er
Jan
uar
y
Feb
ruar
y
Mar
ch
Ap
ril
May
Jun
e
En
erg
y U
sag
e [
MM
BT
U]
Estimated Electricity Usage with Volter
Volter Power Utility Power
PM2.5 Emissions
22
64
8.763
0.010
10
20
30
40
50
60
70
Hydronic Heater EPA CertifiedWood Stove
Pellet Stove WoodGasification CHP
PM
2.5
em
issi
on
s [l
b/t
on
]
PM2.5 Emissions
23
0.03
0.0022
0
0.005
0.01
0.015
0.02
0.025
0.03
0.035
Tier IV Diesel Wood Gasification CHP
PM
2.5
em
issi
on
s [g
/kW
h]
PM2.5 Emissions
24
2.69 2.59
0.844
0
0.5
1
1.5
2
2.5
3
Oil Boiler Wood GasificationCHP
Natural Gas Boiler
PM
2.5
em
issi
on
s [g
/BT
U]
Pilot Project Progress and Plan
25
Funding Sources:
$290,000 in EETF Grant + $290,000 required FNSB Match = $580,000
$218,000 USFS Wood Innovations Grant award
$120,000 FNSB Energy Reductions Projects Fund
Pilot Project – What Happened
26
Things that we did right: Identified site and technology and testing plan. Funding awarded and appropriated. EPA, DEC, UL, GVEA Electrical Interconnection, Customs,
compliance plans. Assembly approval of non-competitive procurement to meet grant
scope of work.
Project discontinued by FNSB: Original Scope of Work exceeded budget, FNSB procurement
standards limited ability to negotiate. Equipment provider not comfortable with standard contract
language.
Pilot Project – Lessons Learned
27
Evaluate internal structure for suitability for research type project. Look for cost drivers.
If partnering, carefully consider which entity can best serve as lead.
Stress consensus on legal terms and conditions as early as possible in project.
Why a Pilot Project should still be pursued
Alaska energy costs are high
Biomass is plentiful and sustainable
New technology to produce commercial scale electricity from wood
Reduced costs to building operators
Commercial economic activity
Reduce impact of biomass energy on air quality
28