Pick-Up Order Lead Time Project Storyboard
The Bahama Bistro Sample Storyboard
Visit GoLeanSixSigma.com for more Lean Six Sigma Resources
![Page 2: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/2.jpg)
Executive Summary
![Page 3: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/3.jpg)
Key Words(Specific to the Bahama Bistro)
• Pick-Up Order Lead Time: Total cycle time from the moment the customer places their order to the moment they receive their food.
• Packaging Process: All tasks related to placing food into take-out containers, selecting utensils, napkins and condiments and then placing them all into a bag
• Pick-Up Wait Time: The cycle time from the moment a Pick-up customer walks in the door to the moment their order is made available to them
• Condiments: Mini-bottles of hot sauce, limes, salt and pepper
![Page 4: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/4.jpg)
Project Charter
![Page 5: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/5.jpg)
VOC Translation Matrix
Key Take Away: Project needs to address overall Lead time which will impact customer wait time as well as food temperature
![Page 6: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/6.jpg)
SIPOC: Pick-Up Order Process
Key Take Away: The scope of this project goes from the point of receiving the customer order to the point at which food is available
![Page 7: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/7.jpg)
Detailed Map – Pick-Up Process
Key Take Away: The process needs more analysis – packaging segment seems to take longer than expected
![Page 8: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/8.jpg)
Data Collection Plan
Key Take Away: Cashier was largely responsible for all data collection – the team adjusted job duties to accommodate
![Page 9: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/9.jpg)
Gage R&R: Pick-Up Order Wait Time
Key Take Away: The measurement system variation was less than 10% for collection of wait time data – Measurement Systems were good!
![Page 10: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/10.jpg)
Baseline Data• Total Pick-up Order Cycle Time• Average time is 27 minutes
Key Take Away: The baseline process was not capable of reaching project goal of 20 minutes
Goal of 20 minutes
![Page 11: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/11.jpg)
Fishbone Diagram & 5 Whys
Key Take Away: Root Cause Analysis will focus on Packaging process, condiment prep and availability of staff
![Page 12: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/12.jpg)
Process Map Analysis
Key Take Away: Mapping highlighted packaging as a potential root cause of pick-up order delay
![Page 13: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/13.jpg)
One-Sample T-Test
Key Take Away: Packaging pick-up orders was taking longer than 6 minutes. Improvement focused on the packaging process
Null: There is no difference between the current process and the 6 minute historic averageAlternative: The current average is not equal to the historic average
![Page 14: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/14.jpg)
Hypothesis Testing Results
Key Take Away: Hypothesis tests confirmed that the process has gotten worse and that packaging was a key area of focus
![Page 15: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/15.jpg)
Impact Effort Matrix
Key Take Away: The team planned to implement the three solutions in the low effort/high impact quadrant
![Page 16: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/16.jpg)
To-Be Map Segment
Key Take Away: Improvements to materials, process and cross-training resulted in faster lead time overall
![Page 17: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/17.jpg)
Before & After Time Data
Key Take Away: Implemented solutions decreased total cycle time and achieved project goal of less than 20 minutes
![Page 18: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/18.jpg)
Implementation Plan
Key Take Away: This implementation Plan was key in terms of all team members knowing their role in the roll-out
![Page 19: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/19.jpg)
Packing Type DOE
Key Take Away: This Design of Experiments was instrumental in selecting the new Pick-Up order packaging
![Page 20: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/20.jpg)
Risk Management
Key Take Away: Cross-Training mitigated the risk of overloading the chef during peak hours
![Page 21: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/21.jpg)
Monitoring & Response Plan
Key Take Away: The monitoring plan factors in both the leading indicators of packaging time and customer wait time along with the project “Y”
![Page 22: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/22.jpg)
Control Chart of Project Y
Key Take Away: The team is continuing to work on the special causes of variation – and the Upper Control Limit of 23 minutes is the Response Plan trigger
![Page 23: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/23.jpg)
Transfer Opportunities
Key Take Away: The improvements implemented at one location can easily be translated to other locations – time to spread the wealth!
![Page 24: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/24.jpg)
Appendix
![Page 25: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/25.jpg)
Wait Time Hypothesis Test
Key Take Away: There was a difference between the historical median and the current median for customer wait time – it was taking longer!
![Page 26: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/26.jpg)
Communication Plan
Key Take Away: The Communication Plan was instrumental in making sure everyone knew what was happening with the project at all times
![Page 27: Black Belt Project Storyboard Template Example](https://reader030.vdocuments.net/reader030/viewer/2022032613/587552391a28ab00528b4a25/html5/thumbnails/27.jpg)
P- Chart of “Late” PackagingProportion of Late Packaging – June
Key Take Away: The P-Chart turned out to be the best visual for Packaging time – by deriving discrete data from continuous data the positive trend was obvious