blackout

51
30-31 st July, 2012 Power Blackout in India A review Compiled from the CERC investigation report

Upload: madhavanvee

Post on 19-Dec-2014

2.139 views

Category:

Documents


4 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Blackout

30-31st July, 2012 Power Blackout in India

A review

Compiled from the CERC investigation report

Page 2: Blackout

2

Contents1. Overview2. Indian Grid System

– Types of Transmission lines– Layout of the Indian Grid– What is grid disturbance?

3. Blackout 30th July 2012– Reasons for Blackout -30th July 2012– Restoration

4. Blackout 31st July 2012– Reasons for Blackout -31st July 2012– Restoration

5. Technical Recommendations (1,2,3 and 4)6. Policy Recommendations (1 & 2)7. Proposed changes8. Need for Smart Grids - Future

Page 3: Blackout

3

July 30-31,2012 -Biggest Power Blackout in Indian History

1. Overview

Page 4: Blackout

4

CERC conducted an investigation on the causes

• Full report on grid disturbance (CERC Order in Petition No. 167/Suo-Motu/2012 dated 1st Aug2012).

• CERC released the report titled “Status of action taken on recommendation of the enquiry committee on grid disturbance in northern region on 30th July 2012 and in Northern, Eastern & North-Eastern Region on 31st JULY 2012”

CERC report

Page 5: Blackout

5

2. India National Grid – Hierarchy

Indian Grid - NLDC

New Grid

Northern Region -RLDC

SLDC

Western Region - RLDC

SLDC

Eastern Region - RLDC

SLDC

North-Eastern Region - RLDC

SLDC

Southern Region - RLDC

SLDC

Page 6: Blackout

6

Types of Transmission line

220kV

• Mostly within the state

400KV

• Long distance (State-State, Region – Region)

765KV

• Long distance state – Region- Region transmission

500 KV -

HVDC

• Latest technology for long distance power transmission with minimum losses.

• These are much popular in the off-shore wind farm transmission lines in the UK

Page 7: Blackout

7

Layout – The NEW GRID

Page 8: Blackout

8

What is grid disturbance? A grid is said to

be disturbed when :

a) there is an under voltage

(U/V)

b) there is over voltage (O/V)

c) there is under frequency (U/F)

d) there is over frequency (O/F)

e) there is a rapid fall or rise in frequency (

+dF/dT or -dF/dT )

f) there is a power failure in the grid

Page 9: Blackout

9

Blackout - Affected Regions (30 & 31st July)

Page 10: Blackout

10

29th July – evening before blackout

28th July 2012

10:18pm

9:45pm 3:40pm

3:15pm

The 400 kV Bina- Gwalior-Agra-

2 was under planned shutdown since 28thJuly 2012

for up-gradation work to 765kV.

At 3:15pm, 29th July - 220 kV Kota-Badod Tripped due

to operation of distance protection three phase

Zone-1 indications at Badod end.

At 3:40pm, 220 kV Binmal (PG)- Sirohi - Phase to earth

fault. The two 220 kV outlets to Bhinmal(RVPNL) and one to Sanchore were in service from Bhinmal.

At 9:45pm, 400 kV Bhinmal- Kankroli Tripped due to insulator de-capping.

At 10:18pm, 400 kV Zerda- Kankroli Emergency outage for a period of two hours to take out one Tool & Plant (T

& P) which got stuck with one polymer insulator.

Page 11: Blackout

11

3. 30th July – 1st blackout

Page 12: Blackout

12

Frequency profile as captured by IIT Bombay

Page 13: Blackout

13

Reason for blackout -30th July 2012 Summary

REASON – 30th Jul

400kV Bina-Gwalior-Agra 2 line was under planned

shutdown. This caused stress on other lines. Failure in load

management and planning

Large amount of unscheduled import of power by the Northern

region from western and eastern region.

Action was not taken to reduce the Total Transfer Capability (TTC) after shut

down of Zerda-Kankroli 400 KV line, . The TTC is shown

as 2000 MW before and after the shutdown of 400

KV line. Lack of observation and

coordination! Some gas and thermal plants where tripped in NR due to forced outage and shortage

of coal. Irregular Maintenance and

lack of monitoring

Sipat stage-1 plant was under trial operation and

caused unscheduled injection of power.

Once almost all the 400kV lines tripped overnight

(from WR to NR) and even many 200kV lines tripped, now the power from WR

started to flow to NR though ER. This caused

power swings in the ER and more lines started tripping

and caused a complete blackout.

Page 14: Blackout

14

After Blackout – 30th July 2:33am

Page 15: Blackout

15

Restoration – after blackout 30th July

• The Black out happened exactly at time – 2.33am . This affected 8 states and 1 U.T (Rajasthan, Haryana, New Delhi, J&K, Punjab, U.P, Himachal Pradesh, Uttarakhand and Chandigarh)

• Emergency loads like railway station, hospitals, airport were supplied with power by 8am

• By 10am 40% of the loads where restored.

• 100% load was restored by 4pm evening the same day.

Following slides shows how the restoration process was carried out!

Page 16: Blackout

16

Self supported Islands – After blackout

Page 17: Blackout

17

Restoration – from Eastern Region

Page 18: Blackout

18

Restoration – from Western Region

Page 19: Blackout

19

4. 31ST July Blackout • The Black out happened exactly at time – 1.00pm . This

affected 21 states and 1 Union Territory. This caused much bigger effect than the 30th July Blackout.

• The following states were affected by the grid failure:– States on the northern grid: Delhi, Haryana, Himachal Pradesh,

Jammu & Kashmir, Punjab, Rajasthan, Uttar Pradesh, Uttarakhand

– States on the eastern grid: Bihar, Jharkhand, Orissa, West Bengal– States on the northeast grid: Arunanchal Pradesh, Assam,

Manipur, Meghalaya, Mizoram, Nagaland, Sikkim

• The worst sufferers were 265 miners who got trapped in coal mines in West Bengal and Jharkhand due to the power outage. They were evacuated after hours of agony.

Page 20: Blackout

20

31st July -2nd blackout

Page 21: Blackout

21

Frequency shoot up at western region (WR)

In the Western Region due to loss of export to rest of the NEW grid, the frequency shot up to 51.46 Hz and many generating units and transmission lines tripped due to process related issues and high voltage respectively.

The frequency stabilized at around 51.0 Hz. The rise in frequency only illustrates the poor level of primary response.

Page 22: Blackout

22

Reason for blackout 31st July 2012 SummaryLoss of 400 kV Bina-Gwalior link: Similar to the initiation of

the disturbance on 30th July, 2012, tripping of 400 kV Bina-

Gwalior line on zone-3 protection of distance relay, due to load

encroachment, caused the NR system to separate from the WR

system.

Weak Inter-regional Corridors

due to multiple outages

High Loading on 400 kV Bina-

Gwalior-Agra link-NR utilized Unscheduled

Interchange (UI) and this lead to overloading

Inadequate Response by

SLDCs to RLDCs’ instructions on this day also to reduce

overdrawl by the NR utilities and

underdrawal by the WR utilities

The UFR load shedding was not adequate to bring the frequency back to a safer level of

49.5 Hz and above.REASON – 31st Jul

Page 23: Blackout

23

Restoration after blackout -31st July

• Total affected load because of Blackout was 48,000MW

• Emergency loads like railway station, hospitals were supplied with power by 3:30pm

• 100% load was restored by 9.30pm evening, the same day.

Page 24: Blackout

24

Recommendations of the Committee

Page 25: Blackout

25

5. Technical Recommendations -1 • Review protection schemes along with Immediate review of zone-3

philosophy

• Synchro-phasor measurements from PMUs should be explored for protection systems

• A complete independent audit of time synchronization of DRs, ELs and PMUs

• Frequency band tightening up close to 50 Hz

• Review of UI mechanism

• STUs should immediately enable under frequency and df/dt based load shedding schemes

• Faster algorithm for calculation of TTC.

• The regulatory provisions regarding absorption of reactive power by generating units needs to be implemented

Page 26: Blackout

26

Technical Recommendations -2• Installation of adequate static and dynamic reactive power

compensators should be planned.

• Functioning of existing PMUs and availability of their output to RLDCs and accuracy of time synchronization should be monitored on daily basis and, if required, corrective actions should be taken on priority basis.

• The Synchro-phasor based WAMS employing PMUs offer a wide applications for real time monitoring and control of the system, specially under the dynamic conditions.

• Adequate number of PMUs should be installed to improve the visibility and real time monitoring of the system.

• Possibility of voltage collapse prediction, sensing global power system conditions derived from local measurements may be explored

Page 27: Blackout

27

Technical Recommendations -3• Islands: Efforts should be made to design islanding scheme

based on frequency sensing relays so that in case of imminent grid failure, electrical islands can be formed. This will also help in faster restoration of grid.

• The Communication network should be strengthened by putting fiber optic communication system. Further, the Communication network should be maintained properly to ensure reliability of data.

• UPS - RTUs and communication equipment should have uninterrupted power supply with proper battery backup so that in case of total power failure, supervisory control and data acquisition channels do not fail.

• Telemetry facility at all generating station and transmission liens – at the earliest.

Page 28: Blackout

28

Technical Recommendations -4• A standard procedure for preparatory activities and

sequence of start up may be put in place by the stations to restore units as early as possible particularly in contingencies

• An audit of devices such as HVDC, TCSC, SVC and to ensure their stability features are enabled.

• For smooth operation of grid systems, it is absolutely important that all the power generating and distributing stations are connected on a very reliable telecom network.

(i) A proper network may be built up preferably using MPLS (Multi Protocol Label Switching)

(ii) IT network may be built using dedicated fibres to avoid any cyber attack on the power system.

Page 29: Blackout

29

6. Policy Recommendations-1

• Implementation of various regulations issued under the Electricity Act, 2003 and look into violation SERIOUSLY.

• Real-time security desk in all the shifts to be manned by engineer capable of carrying out TTC calculations (in NLDC and RLDC).

• LDC and Regulatory Commissions related to non-compliance of regulatory provisions including that for noncompliance of directions and non-payment of UI charges, need review.

• The present organizational set up of Load Dispatch Centres need to be reviewed.

• Training and certification of system operators need to be given focused attention.

Page 30: Blackout

30

Policy Recommendations-2• There is need to reinforce system study groups in power sector

organizations to analyze the system behavior under different network status/ tripping of lines/outage of generators. Where these do not exist, these should be created.

• Intra-State transmission system needs to be planned and strengthened in a better way to avoid problems of frequent congestion

• Special task force - involving experts from academics, power utilities and system operators, to carry out a detailed analysis of the present grid conditions and anticipated scenarios which might lead to any such disturbances in future.

• Sufficient financial incentives need to be given to certified system operators so that system operation gets recognized as specialized activity.

Page 31: Blackout

31

7. Proposed protection studyInstallation of

PMUs :

• Phasor Measurement Units (PMU)• These are highly sophisticated instruments to measure

change in voltage/current in milliseconds.

Page 32: Blackout

32

Relay Protection

Distance Relays

:

• These connected on the transmission lines• Distance relays will sense a fault/disturbance in the grid and

give a trip command to the incomer breaker whenever the grid disturbance exceeds a set limit.

• By opening the incomer breaker, the plant/line is isolated from the grid.

Numeric Relays

:

• These perform mathematical algorithms and to offer very high accuracy & resolution.

• These help in detection of df/dt fault (change in frequency)

Page 33: Blackout

33

Study of Zone 3 faulty tripping by DR

• Line Fault - Usually any fault in the zone 3 region due to phase-phase fault, phase-ground or other faults will activate the distance relay to open the circuit (Circuit Breaker – VCB/SF6-CB)

• Overloading - If there is overloading this will also create a low impedance on the lines and lead to zone 3 fault alert. Before the far distance relays operate, the local relays should sense this and the appropriate load shedding should be done.

• Failure - If failure of load shedding, the far distance relay operate and this leads to blackout of the entire distribution lines. (This can be a major reason for 30,31st July blackout, So proper considerations should be made for load characteristics)

Please find a example picture in the next slide.

Page 34: Blackout

34

Distance Relay Operation

Page 35: Blackout

35

Study of UFR /df/dt under load encroachment conditions

• What really happened – to the protective UFR and df/dt relays? Why didn’t they help in load shedding to improve the declining frequency in Northern region (NR and ER during 31st) on 30th blackout.

• Similarly in the western region the frequency rose up to 51.4Hz, and none of the generators units responded to this frequency hike.

• A separate study has been proposed by the authorities to study regarding the settings of these relays and fix the issues associated.

Page 36: Blackout

Study on effects of : TCSC and SVC

What is a compensator?

• A compensator is used in transmission lines/grid/load for voltage stability, reducing net losses, limiting short circuit currents, damping power oscillations by compensation of real and reactive power.

How these compensators affect the protection

distance relay operation?

• The Distance Relays (DR) use impedance measurement to determine the presence of faults.

• The capacitance cancels or compensates some of the inductance of the line and therefore the relay (DR) may perceive a fault to be in its first zone when the fault is actually in the second or third zone of protection.

36

TCSC – Thyristor Controlled Series Capacitors

SVC – Static VAR Compensator

Page 37: Blackout

37

FUTURE?

Page 38: Blackout

38

8. Why Smart Grids?

To avoid unscheduled transfer of power and blackouts

To monitor the loads and shed loads when stress increase or frequency decrease rapidly.

To improve communication between various LDS’

To maximize cyber safety

To improve efficient Distribution Generation

If you can measure it, you can manage it…

Page 39: Blackout

39

Smart Grid for India

T&D Losses >30%

BESCOM has begun work on its Rs 87-crore

smart grid project in the

City.

Page 40: Blackout

40

Features of Smart Grids

Here are some slides on Smart Grid solution from GE

Local Load level

• Smart Metering • On line monitoring portal – with help of SCADA systems• Home automation • Public charging stations – for electric cars/bikes

T & D

level

• Smart Distribution • Load/demand management• Energy Audit • Smart protection controls

Smart

Generatio

n

• Renewable energy source integration or Distribution Generation

Page 41: Blackout

41

Smart Metering

source: GE

Page 42: Blackout

42

Smart Substation

source: GE

Page 43: Blackout

43

Smart Solutions

source: GE

Page 44: Blackout

44

Smart Communication

source: GE

Page 45: Blackout

45

Distributed Power Generation

• Distributed Generation is nothing but Generation at site. • The most popular source for distributed generation is solar PV• Germany has the largest percentage mix of solar PV DG at LV

level in their total energy mix. Germany has also developed their own grid codes for LV generation and grid connection (recent policy– reactive power control, using solar grid inverter).

Source: BELELECTRIC

Page 46: Blackout

46

Distribution level voltage issues (LV)

• The voltage level at the end consumer side face voltage drop due to transmission losses, line impedance (R+JXL) and increase in load.

source: GE

Page 47: Blackout

47

Pros and Cons of Distributed Generation

• Here the voltage level gets stabilized due to the feed in power from solar. This can greatly reduce the stress and disturbance on transmission lines.

• This can also increase the voltage above a certain level when more solar generators are present and the inverters are forced to trip (overvoltage). This is dangerous and can cause blackouts.

• In 2011, Germany came up with some modifications in their grid codes with reactive power controlled solar inverters.

• Distribution Generation can reduce the overall T&D losses (from HV, MV, to distribution LV).

source: GE

Page 48: Blackout

48

LV level frequency and voltage control

• Recently grid tie solar inverters come with intelligent active and reactive power control to keep the LV grid voltage and frequency under control.

• As shown in the graph below , when the frequency exceed a certain limit - the active power control comes into play and reduces the overall power output to stabilize the local grid.

• Similarly when there is a voltage increase, the reactive power is absorbed by the GT solar inverters and this stabilizes the output accordingly (check image down).

Page 49: Blackout

49

Summary• In this presentation we had a look at the various events,

issues and recovery process carried out before and after the 2012,July blackout.

• The recommendation from the committee was also discussed.

• Study on the various protection relays and fault tripping

• Study on effects of capacitor compensators (SVC, TCSC) on protection relays

• Required changes for the future – Smart Grids (Smart metering, communication and renewable energy / distribution generation)

Page 50: Blackout

50

Thank you

Giridaran Srinivasan Project Engineer

RESolve Energy Consultants [email protected]

Page 51: Blackout

51

Reference and CreditsConcept papers:

TCSC FOR PROTECTION OF TRANSMISSION LINEP.S.Chaudhari#i, P. P.Kulkarni#2, R.M.Holmukhe#3, Mrs.P.A.Kulkarni #4 #iScientist, DRDO, Pune,

India, #2DRDO, Pune, India #,,3,4 Bharati Vidyapeeth University College of Engineering, Pune, India.

Pictures and other data: • PMU -

http://www.qualitrolcorp.com/Products/Q_PMU9/18/36_Phasor_measurement_units_%28PMU%29/

• www.erlphase.com(http://www.erlphase.com/downloads/data_sheets/L_PRO_4000_line_protection_relay_ds.pdf)

• http://phasormeasurements.blogspot.in/• Distributed Generation – BELELECTRIC• Blackout picture:

http://www.desismartgrid.com/2012/08/indian-power-grid-blackout-reasons-and-future-requirements/

Blackout official data:• Full report on grid disturbance (CERC Order in Petition No. 167/Suo-Motu/2012 dated 1st

Aug2012). • Status of action taken on recommendation of the enquiry committee on grid disturbance in

northern region on 30th July 2012 and in Northern, Eastern & North-Eastern Region on 31st July 2012.

Smart Grid:• GE - http://www.gedigitalenergy.com/communications.htm• GE - http://www.gedigitalenergy.com/multilin/catalog/Transmission.htm#prl • L&T - http://www.larsentoubro.com/lntcorporate/ebg/html/grid_islanding.htm • SMA• BESCOM - http://www.deccanherald.com/content/288701/bescom-ropes-us-firm-smart.html • Indian Smart Grid Task Force