board presentation - east park and creekside park …...2020/05/11  · board presentation - east...

19
Park Board Committee Meeting EAST PARK AND CREEKSIDE PARK SOUTH Design Contract Monday, May 11, 2020

Upload: others

Post on 06-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Park Board Committee Meeting

EAST PARK AND

CREEKSIDE PARK

SOUTH Design Contract

Monday, May 11, 2020

Page 2: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Purpose of Presentation

To seek Board decision on

negotiating and entering into a

park planning and conceptual

design contract for East Park

and Creekside Park South.

2

Page 3: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Background

Page 4: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Background: Vision

To complete the North

East and South East False

Creek (NEFC and SEFC)

waterfront parks and open

spaces.

To create a cohesive,

legible, and connected

urban park system with

complementary

programming and

amenities.

4

Page 5: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Background: Opportunities

Enhance biodiversity and the

ecological health of the land and

water in False Creek’s east basin.

Increase access to nature.

Demonstrate resiliency to a changing

climate.

Contribute to a contiguous park and

open space system with a strong

network of pedestrian and bicycle

pathways.

5

Page 6: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Background: SEFC Official Development Plan (ODP)

6

Source: SEFC Official Development Plan - 2007

One of three major parks

identified in the South East

False Creek Official

Development Plan (Council

approved in 2007).

Key part of the

transformation of False

Creek from an industrial

waterway to a highly livable,

walkable community.

Page 7: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Background: SEFC ODP Implementation – Built by 2010

7 Source: SEFC Official Development Plan - 2007

Page 8: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Background: SEFC ODP Implementation – Built by 2020

8 Source: SEFC Official Development Plan - 2007

Page 9: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Background: SEFC ODP Implementation – Next Phase

9 Source: SEFC Official Development Plan - 2007

Page 10: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Background: SEFC Neighbourhood

10

Page 11: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Background: The Site

East Park (1.2ha)

New waterfront parkland stitching

together SEFC and NEFC.

Creekside Park South (1.2ha)

Park renewal south of Science

World including parking area.

Expo‘86 legacy, built on deck

approaching end of service-life.

Linking Seaside, Ontario Street,

and Central Valley Greenways. 11

Page 12: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Procurement Overview

Page 13: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Procurement Overview: Project Scope

East Park and Creekside

Park South planning and

design process to deliver a

community-supported

preferred conceptual park

plan to be presented to Park

Board for decision in 2021.

13

Page 14: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

14

Procurement Overview: Process

Request for Proposal (RFP - PS20191588) for Landscape Architectural

Planning and Design for East Park and Creekside Park South.

Posted on BC Bid and City’s website January 6, 2020.

Four qualified responses received February 20, 2020:

• DTAH, Toronto Ontario

• PFS Studio, Vancouver BC

• PWL Partnership Landscape Architects Inc., Vancouver BC

• Space2place Design Inc., Vancouver BC

Page 15: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

15

Procurement Overview: RFP Evaluation

Proposals were evaluated using quantitative and qualitative tools and

criteria - Technical 60%, Financial 35%, Sustainability 5%.

RFP evaluation process concluded that Space2place Design Inc., best

meets the RFP requirements and offers best overall value for the delivery

of this highly complex and challenging project.

Space2place has worked with Park Board to deliver many successful

projects over the past two decades, most recently and notably new parks

in East Fraser Lands (River District) and the People, Parks and Dogs

Strategy.

Page 16: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Procurement Overview

Funding is available in the 2020 Capital Budget.

Next Steps

• 20% of full contract value ($120,000) will be executed in Q3 2020,

including site assessments and analysis.

• Balance of the work will proceed in late Q3 2020, providing public

health measures are eased and the public can be fully engaged in

the park planning process.

• Contract provisions ensure no additional costs to project due to

potential delays.

Page 17: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

Recommendations

Page 18: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development

18

Recommendations

A. THAT the Vancouver Park Board authorize staff to negotiate to the satisfaction of

the Park Board’s General Manager, City’s Director of Legal Services, and the City’s

Chief Purchasing Official and enter into a contract with Space2place Design Inc., for

Landscape Architectural and Planning Design for East Park and Creekside Park

South, for a term of eighteen (18) months, with an estimated contract value of

$596,440.10, plus applicable taxes, to be funded through the current capital budget.

B. FURTHER THAT the Chief Purchasing Official and Park Board General Manager

be authorized to execute on behalf of the Board the contract contemplated by

Recommendation A;

C. THAT no legal rights or obligations will be created by Board adoption of

Recommendations A and B above unless and until such contract is executed by the

authorized signatories of the City as set out in these Recommendations.

Page 19: Board Presentation - East Park and Creekside Park …...2020/05/11  · Board Presentation - East Park and Creekside Park South - Design Contract: 2020 MAY 11 Author Park Development