Item 8 Resolution No 2296
June 27 2019
RESOLUTION OF THE CITY UNIVERSITY CONSTRUCTION FUND AUTHORIZING BOILER PLANT REPLACEMENT AT QUEENS COLLEGE
WHEREAS the City University Construction Fund (CUCF) is authorized to provide facilities for use by the City University of New York (the University) and to cause such facilities to be designed constructed acquired reconstructed rehabilitated improved operated maintained furnished and equipped
WHEREAS the Dormitory Authority of the State of New York (DASNY) is authorized to design acquire contract finance or otherwise provide facilities for the use by the University in accordance with the terms of any agreement entered into by DASNY with CUCF and to issue bonds to finance the costs of such facilities
WHEREAS CUCF DASNY and the University entered into a Program Management Agreement on June 30 2008 (the Program Management Agreement) pursuant to which CUCF can designate which capital projects are managed by CUCF DASNY or the University
WHEREAS the boilers and major equipment in the boiler plant at Queens College are at the end of their useful life are in poor condition and need replacement (Queens College Boiler Replacement Project)
WHEREAS New York State has appropriated capital funding to CUCF for the Queens College Boiler Replacement Project
WHEREAS the Universitys Board of Trustees has requested CUCF to effectuate and provide funding for the Queens College Boiler Replacement Project in an amount not to exceed $40000000 and
WHEREAS pursuant to the Program Management Agreement CUCF selects DASNY to manage the Queens College Boiler Replacement Project
NOW THEREFORE BE IT
RESOLVED that CUCFs Board of Trustees approves the selection of DASNY to manage the Queens College Boiler Replacement Project and
RESOLVED that CUCFs Board of Trustees approves the funding for the Queens College Boiler Replacement Project in an amount not to exceed $40000000
Item 8 Resolution No 2296
June 27 2019
EXPLANATION
The Boiler Plant at Queens College is at the end of its useful life the equipment is in poor condition and is in need of replacement The boiler plant consists of four (4) large steam boilers-three (3) of the boilers are almost 70 years old and the other boiler is 24 years old The Boiler Plant supplies steam for heat and hot water to almost every building on campus Thus it is vital that the plant be maintained in good operating condition In colder weather if the Boiler Plant were unable to provide steam the entire campus would be without heat and would need to be shut down until repairs were completed
The scope of the Boiler Plant Replacement project includes the replacement of the boilers burners boiler breeching feed water pumps condensate tanks deaerator tank deaerator pumps piping and all control systems
The construction of the Queens College Boiler Replacement Project will be managed by DASNY and the contract(s) will be held by DASNY
The undersigned hereby certifies that (i) the foregoing is a true and correct copy of the resolution adopted at the regular meeting of the Trustees of the City University Construction Fund held on June 27 2019 (ii) at such meeting a quorum of Trustees was present (iii) the resolution was adopted by the affirmative vote of not less than four Trustees present at such meeting and (iv) the resolution has not been amended or rescinded since the date of adoption
Date June 27 2019
Item 8 Resolution No 2296
June 27 2019
QUEENS COLLEGE - BOILER PLANT REPLACEMENT
Exhibit A - Project Summary
Exhibit B - Site Plan
1 Nature of Action
2 Project History
3 Project Scope
4 Net-to-Gross Efficiency
5 Schedule
6 Project Funding
7 Cost Estimate
8 Cost Per Square Foot
Item 8 Resolution No 2296
June 27 2019
EXHIBIT A
PROJECT SUMMARY
Queens College Replacement of the Boiler Plant
Request for permission to replace the boiler plant at Queens College
The boiler plant consists of 4 large steam boilers 3 of the boilers are almost 70 years old and the other one is 24 years old The boilers and the major equipment in the boiler plant are at the end of their useful life and are in poor condition The Boiler Plant supplies steam for heat and hot water to almost every building on campus Thus it is vital that the plant be maintained in good operating condition In colder weather if the Central Boiler Plant were unable to provide steam the entire campus would be without heat and may need to be shut down until repairs are completed
The scope includes the replacement of boiler plant The major equipment and components of the boiler plant are boilers burners boiler breeching feed water pumps condensate tanks deaerator tank deaerator pumps all piping and control system
Not Applicable
Design Complete May 2019 Construction Start December 2019 Construction End January 2022
Source State Bonded Funds
Amounts Equipment Replacement $ 4000000000
NA
NA
--
Exhibit B
-
B-8
BUILDING KEY M AUMN1HAU
DmlElREHElJRSHIP CENTER
AF ATHLpound11C AQD HOUIS[
BG IIIIILOIIIGS 6 GROINOS
~~LWI PIAIIT
C1 CEJgt1
CZ CEP-2
oc ltXJlDfN AUOmllllM
a OIMPSru DOME
cH INJRA ARTMJR 00lWIN HAU
II DINNG IWJADCIT10N
DB WMgtTDElANYHAU
DE DMSION Of EDUCATION fACMY llUl1JRfl
DH DINING HAU
OT IWiNllllAILEII
D fXlNSION(HllJI (OflQIl
fG llllGEIWI) GYMNASIUM
Fllt VIRGINA FRESE HAU
FP FUpound1CIL PUMP -
a G BUIUJNG
oc GEllSlEEQI CUNIC
GIi
GT GOLD6WN lIEATEll
GU OUAAD HOU6E (MUlpoundl
111 HONOR$1WJ
I HP HEATING PLANT
18 IIUILOING
IP IRIIIQUlON PIMP HOU9E
JH JpoundflERSONHALL
KG IIINGHAII
Kl PAULIIINlpoundRHAU
KS 1115581AHAU
KY MARGARCT KIELY IWJ
u L-1 NG IDMINISlRATICN
L2 LZMGLDCRRS
L3 L-lNGIAIIOIIEISamp STATlON ENGINEERS
L4 L lampO SIIOPlltSlORMlpound
16 16 MG EQUIPMOO
LA tOUl8-IIOU8E (Dff-ampm)
MC MEgtIA cemR (MUApound)
MU SCltOOL OF MUSIC
ltt POWDEIIMAIWI HAU PAIIIIING FACILITY (flllURE)
QH QUEENS HAII
RA RATHAIJS HAU
RE RpoundMSDIHAU
RO --NR05ElIHILUINWY
Ill ltHOOIIYRAZRAHHAU
88 SCIENCE ULDING
8F lCIENCE FACILITY (FIIIUAf)
SM THESIJMMIT (N~MCIUn
SU ll1UDEIIT UNION
1S TENNIS $TJIUCMIE
LEGEND
DISIIHG FACU11ES lEMPORARY FAOUTIES - D $-IEASED FACILITIES FVlURE F ACIU11poundS 11 ~NY FACIUTIES PROPERTY UNE D
~
QUEENS COLLEGE
Item 8 Resolution No 2296
June 27 2019
EXPLANATION
The Boiler Plant at Queens College is at the end of its useful life the equipment is in poor condition and is in need of replacement The boiler plant consists of four (4) large steam boilers-three (3) of the boilers are almost 70 years old and the other boiler is 24 years old The Boiler Plant supplies steam for heat and hot water to almost every building on campus Thus it is vital that the plant be maintained in good operating condition In colder weather if the Boiler Plant were unable to provide steam the entire campus would be without heat and would need to be shut down until repairs were completed
The scope of the Boiler Plant Replacement project includes the replacement of the boilers burners boiler breeching feed water pumps condensate tanks deaerator tank deaerator pumps piping and all control systems
The construction of the Queens College Boiler Replacement Project will be managed by DASNY and the contract(s) will be held by DASNY
The undersigned hereby certifies that (i) the foregoing is a true and correct copy of the resolution adopted at the regular meeting of the Trustees of the City University Construction Fund held on June 27 2019 (ii) at such meeting a quorum of Trustees was present (iii) the resolution was adopted by the affirmative vote of not less than four Trustees present at such meeting and (iv) the resolution has not been amended or rescinded since the date of adoption
Date June 27 2019
Item 8 Resolution No 2296
June 27 2019
QUEENS COLLEGE - BOILER PLANT REPLACEMENT
Exhibit A - Project Summary
Exhibit B - Site Plan
1 Nature of Action
2 Project History
3 Project Scope
4 Net-to-Gross Efficiency
5 Schedule
6 Project Funding
7 Cost Estimate
8 Cost Per Square Foot
Item 8 Resolution No 2296
June 27 2019
EXHIBIT A
PROJECT SUMMARY
Queens College Replacement of the Boiler Plant
Request for permission to replace the boiler plant at Queens College
The boiler plant consists of 4 large steam boilers 3 of the boilers are almost 70 years old and the other one is 24 years old The boilers and the major equipment in the boiler plant are at the end of their useful life and are in poor condition The Boiler Plant supplies steam for heat and hot water to almost every building on campus Thus it is vital that the plant be maintained in good operating condition In colder weather if the Central Boiler Plant were unable to provide steam the entire campus would be without heat and may need to be shut down until repairs are completed
The scope includes the replacement of boiler plant The major equipment and components of the boiler plant are boilers burners boiler breeching feed water pumps condensate tanks deaerator tank deaerator pumps all piping and control system
Not Applicable
Design Complete May 2019 Construction Start December 2019 Construction End January 2022
Source State Bonded Funds
Amounts Equipment Replacement $ 4000000000
NA
NA
--
Exhibit B
-
B-8
BUILDING KEY M AUMN1HAU
DmlElREHElJRSHIP CENTER
AF ATHLpound11C AQD HOUIS[
BG IIIIILOIIIGS 6 GROINOS
~~LWI PIAIIT
C1 CEJgt1
CZ CEP-2
oc ltXJlDfN AUOmllllM
a OIMPSru DOME
cH INJRA ARTMJR 00lWIN HAU
II DINNG IWJADCIT10N
DB WMgtTDElANYHAU
DE DMSION Of EDUCATION fACMY llUl1JRfl
DH DINING HAU
OT IWiNllllAILEII
D fXlNSION(HllJI (OflQIl
fG llllGEIWI) GYMNASIUM
Fllt VIRGINA FRESE HAU
FP FUpound1CIL PUMP -
a G BUIUJNG
oc GEllSlEEQI CUNIC
GIi
GT GOLD6WN lIEATEll
GU OUAAD HOU6E (MUlpoundl
111 HONOR$1WJ
I HP HEATING PLANT
18 IIUILOING
IP IRIIIQUlON PIMP HOU9E
JH JpoundflERSONHALL
KG IIINGHAII
Kl PAULIIINlpoundRHAU
KS 1115581AHAU
KY MARGARCT KIELY IWJ
u L-1 NG IDMINISlRATICN
L2 LZMGLDCRRS
L3 L-lNGIAIIOIIEISamp STATlON ENGINEERS
L4 L lampO SIIOPlltSlORMlpound
16 16 MG EQUIPMOO
LA tOUl8-IIOU8E (Dff-ampm)
MC MEgtIA cemR (MUApound)
MU SCltOOL OF MUSIC
ltt POWDEIIMAIWI HAU PAIIIIING FACILITY (flllURE)
QH QUEENS HAII
RA RATHAIJS HAU
RE RpoundMSDIHAU
RO --NR05ElIHILUINWY
Ill ltHOOIIYRAZRAHHAU
88 SCIENCE ULDING
8F lCIENCE FACILITY (FIIIUAf)
SM THESIJMMIT (N~MCIUn
SU ll1UDEIIT UNION
1S TENNIS $TJIUCMIE
LEGEND
DISIIHG FACU11ES lEMPORARY FAOUTIES - D $-IEASED FACILITIES FVlURE F ACIU11poundS 11 ~NY FACIUTIES PROPERTY UNE D
~
QUEENS COLLEGE
Item 8 Resolution No 2296
June 27 2019
QUEENS COLLEGE - BOILER PLANT REPLACEMENT
Exhibit A - Project Summary
Exhibit B - Site Plan
1 Nature of Action
2 Project History
3 Project Scope
4 Net-to-Gross Efficiency
5 Schedule
6 Project Funding
7 Cost Estimate
8 Cost Per Square Foot
Item 8 Resolution No 2296
June 27 2019
EXHIBIT A
PROJECT SUMMARY
Queens College Replacement of the Boiler Plant
Request for permission to replace the boiler plant at Queens College
The boiler plant consists of 4 large steam boilers 3 of the boilers are almost 70 years old and the other one is 24 years old The boilers and the major equipment in the boiler plant are at the end of their useful life and are in poor condition The Boiler Plant supplies steam for heat and hot water to almost every building on campus Thus it is vital that the plant be maintained in good operating condition In colder weather if the Central Boiler Plant were unable to provide steam the entire campus would be without heat and may need to be shut down until repairs are completed
The scope includes the replacement of boiler plant The major equipment and components of the boiler plant are boilers burners boiler breeching feed water pumps condensate tanks deaerator tank deaerator pumps all piping and control system
Not Applicable
Design Complete May 2019 Construction Start December 2019 Construction End January 2022
Source State Bonded Funds
Amounts Equipment Replacement $ 4000000000
NA
NA
--
Exhibit B
-
B-8
BUILDING KEY M AUMN1HAU
DmlElREHElJRSHIP CENTER
AF ATHLpound11C AQD HOUIS[
BG IIIIILOIIIGS 6 GROINOS
~~LWI PIAIIT
C1 CEJgt1
CZ CEP-2
oc ltXJlDfN AUOmllllM
a OIMPSru DOME
cH INJRA ARTMJR 00lWIN HAU
II DINNG IWJADCIT10N
DB WMgtTDElANYHAU
DE DMSION Of EDUCATION fACMY llUl1JRfl
DH DINING HAU
OT IWiNllllAILEII
D fXlNSION(HllJI (OflQIl
fG llllGEIWI) GYMNASIUM
Fllt VIRGINA FRESE HAU
FP FUpound1CIL PUMP -
a G BUIUJNG
oc GEllSlEEQI CUNIC
GIi
GT GOLD6WN lIEATEll
GU OUAAD HOU6E (MUlpoundl
111 HONOR$1WJ
I HP HEATING PLANT
18 IIUILOING
IP IRIIIQUlON PIMP HOU9E
JH JpoundflERSONHALL
KG IIINGHAII
Kl PAULIIINlpoundRHAU
KS 1115581AHAU
KY MARGARCT KIELY IWJ
u L-1 NG IDMINISlRATICN
L2 LZMGLDCRRS
L3 L-lNGIAIIOIIEISamp STATlON ENGINEERS
L4 L lampO SIIOPlltSlORMlpound
16 16 MG EQUIPMOO
LA tOUl8-IIOU8E (Dff-ampm)
MC MEgtIA cemR (MUApound)
MU SCltOOL OF MUSIC
ltt POWDEIIMAIWI HAU PAIIIIING FACILITY (flllURE)
QH QUEENS HAII
RA RATHAIJS HAU
RE RpoundMSDIHAU
RO --NR05ElIHILUINWY
Ill ltHOOIIYRAZRAHHAU
88 SCIENCE ULDING
8F lCIENCE FACILITY (FIIIUAf)
SM THESIJMMIT (N~MCIUn
SU ll1UDEIIT UNION
1S TENNIS $TJIUCMIE
LEGEND
DISIIHG FACU11ES lEMPORARY FAOUTIES - D $-IEASED FACILITIES FVlURE F ACIU11poundS 11 ~NY FACIUTIES PROPERTY UNE D
~
QUEENS COLLEGE
1 Nature of Action
2 Project History
3 Project Scope
4 Net-to-Gross Efficiency
5 Schedule
6 Project Funding
7 Cost Estimate
8 Cost Per Square Foot
Item 8 Resolution No 2296
June 27 2019
EXHIBIT A
PROJECT SUMMARY
Queens College Replacement of the Boiler Plant
Request for permission to replace the boiler plant at Queens College
The boiler plant consists of 4 large steam boilers 3 of the boilers are almost 70 years old and the other one is 24 years old The boilers and the major equipment in the boiler plant are at the end of their useful life and are in poor condition The Boiler Plant supplies steam for heat and hot water to almost every building on campus Thus it is vital that the plant be maintained in good operating condition In colder weather if the Central Boiler Plant were unable to provide steam the entire campus would be without heat and may need to be shut down until repairs are completed
The scope includes the replacement of boiler plant The major equipment and components of the boiler plant are boilers burners boiler breeching feed water pumps condensate tanks deaerator tank deaerator pumps all piping and control system
Not Applicable
Design Complete May 2019 Construction Start December 2019 Construction End January 2022
Source State Bonded Funds
Amounts Equipment Replacement $ 4000000000
NA
NA
--
Exhibit B
-
B-8
BUILDING KEY M AUMN1HAU
DmlElREHElJRSHIP CENTER
AF ATHLpound11C AQD HOUIS[
BG IIIIILOIIIGS 6 GROINOS
~~LWI PIAIIT
C1 CEJgt1
CZ CEP-2
oc ltXJlDfN AUOmllllM
a OIMPSru DOME
cH INJRA ARTMJR 00lWIN HAU
II DINNG IWJADCIT10N
DB WMgtTDElANYHAU
DE DMSION Of EDUCATION fACMY llUl1JRfl
DH DINING HAU
OT IWiNllllAILEII
D fXlNSION(HllJI (OflQIl
fG llllGEIWI) GYMNASIUM
Fllt VIRGINA FRESE HAU
FP FUpound1CIL PUMP -
a G BUIUJNG
oc GEllSlEEQI CUNIC
GIi
GT GOLD6WN lIEATEll
GU OUAAD HOU6E (MUlpoundl
111 HONOR$1WJ
I HP HEATING PLANT
18 IIUILOING
IP IRIIIQUlON PIMP HOU9E
JH JpoundflERSONHALL
KG IIINGHAII
Kl PAULIIINlpoundRHAU
KS 1115581AHAU
KY MARGARCT KIELY IWJ
u L-1 NG IDMINISlRATICN
L2 LZMGLDCRRS
L3 L-lNGIAIIOIIEISamp STATlON ENGINEERS
L4 L lampO SIIOPlltSlORMlpound
16 16 MG EQUIPMOO
LA tOUl8-IIOU8E (Dff-ampm)
MC MEgtIA cemR (MUApound)
MU SCltOOL OF MUSIC
ltt POWDEIIMAIWI HAU PAIIIIING FACILITY (flllURE)
QH QUEENS HAII
RA RATHAIJS HAU
RE RpoundMSDIHAU
RO --NR05ElIHILUINWY
Ill ltHOOIIYRAZRAHHAU
88 SCIENCE ULDING
8F lCIENCE FACILITY (FIIIUAf)
SM THESIJMMIT (N~MCIUn
SU ll1UDEIIT UNION
1S TENNIS $TJIUCMIE
LEGEND
DISIIHG FACU11ES lEMPORARY FAOUTIES - D $-IEASED FACILITIES FVlURE F ACIU11poundS 11 ~NY FACIUTIES PROPERTY UNE D
~
QUEENS COLLEGE
--
Exhibit B
-
B-8
BUILDING KEY M AUMN1HAU
DmlElREHElJRSHIP CENTER
AF ATHLpound11C AQD HOUIS[
BG IIIIILOIIIGS 6 GROINOS
~~LWI PIAIIT
C1 CEJgt1
CZ CEP-2
oc ltXJlDfN AUOmllllM
a OIMPSru DOME
cH INJRA ARTMJR 00lWIN HAU
II DINNG IWJADCIT10N
DB WMgtTDElANYHAU
DE DMSION Of EDUCATION fACMY llUl1JRfl
DH DINING HAU
OT IWiNllllAILEII
D fXlNSION(HllJI (OflQIl
fG llllGEIWI) GYMNASIUM
Fllt VIRGINA FRESE HAU
FP FUpound1CIL PUMP -
a G BUIUJNG
oc GEllSlEEQI CUNIC
GIi
GT GOLD6WN lIEATEll
GU OUAAD HOU6E (MUlpoundl
111 HONOR$1WJ
I HP HEATING PLANT
18 IIUILOING
IP IRIIIQUlON PIMP HOU9E
JH JpoundflERSONHALL
KG IIINGHAII
Kl PAULIIINlpoundRHAU
KS 1115581AHAU
KY MARGARCT KIELY IWJ
u L-1 NG IDMINISlRATICN
L2 LZMGLDCRRS
L3 L-lNGIAIIOIIEISamp STATlON ENGINEERS
L4 L lampO SIIOPlltSlORMlpound
16 16 MG EQUIPMOO
LA tOUl8-IIOU8E (Dff-ampm)
MC MEgtIA cemR (MUApound)
MU SCltOOL OF MUSIC
ltt POWDEIIMAIWI HAU PAIIIIING FACILITY (flllURE)
QH QUEENS HAII
RA RATHAIJS HAU
RE RpoundMSDIHAU
RO --NR05ElIHILUINWY
Ill ltHOOIIYRAZRAHHAU
88 SCIENCE ULDING
8F lCIENCE FACILITY (FIIIUAf)
SM THESIJMMIT (N~MCIUn
SU ll1UDEIIT UNION
1S TENNIS $TJIUCMIE
LEGEND
DISIIHG FACU11ES lEMPORARY FAOUTIES - D $-IEASED FACILITIES FVlURE F ACIU11poundS 11 ~NY FACIUTIES PROPERTY UNE D
~
QUEENS COLLEGE