bolwarra enterprises capability statement (april 2019) · page 3 of 12 b:\1 proposals &...

12
Page 1 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises Capability Statement (April 2019).docx Bolwarra Enterprises Pty Ltd A.B.N. 54 009 853 221 Capability Statement Contact Details Bolwarra Enterprises Pty Ltd T/A Wongabel Quarries N Concrete 458 Wongabel Road, Atherton Queensland 4883 PO Box 1336, Atherton Queensland 4883 Phone: 07 4091 5188 Email: [email protected] Website: www.bolwarra.net.au A.B.N. 54 009 853 221 Ian Kidner – Managing Director (SSE Jubilee Quarry and Routh Quarry) Mobile: 0418 771 517 Graeme Kelly – Jubilee Quarry (Croydon) and Routh Quarry (Georgetown) Site Supervisor Mobile: 0491 222 343 Peter Green – Concrete Manager and Wongabel Quarry (SSE) Mobile: 0428 976 762 Keoni Kidner – Project & Office Manager – Civil Engineer Mobile: 0417 616 956 Steve Johnson – Wongabel Quarries – Product Sales & Equipment Hire Phone: 07 4091 5188

Upload: others

Post on 13-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 1 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

Capability Statement

Contact Details

Bolwarra Enterprises Pty Ltd T/A Wongabel Quarries N Concrete

458 Wongabel Road, Atherton Queensland 4883

PO Box 1336, Atherton Queensland 4883

Phone: 07 4091 5188

Email: [email protected]

Website: www.bolwarra.net.au

A.B.N. 54 009 853 221

Ian Kidner – Managing Director (SSE Jubilee Quarry and Routh Quarry)

Mobile: 0418 771 517

Graeme Kelly – Jubilee Quarry (Croydon) and Routh Quarry (Georgetown)

Site Supervisor

Mobile: 0491 222 343

Peter Green – Concrete Manager and Wongabel Quarry (SSE)

Mobile: 0428 976 762

Keoni Kidner – Project & Office Manager – Civil Engineer

Mobile: 0417 616 956

Steve Johnson – Wongabel Quarries – Product Sales & Equipment Hire

Phone: 07 4091 5188

Page 2: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 2 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

Capability Information

Crushing and Screening

Bolwarra Enterprises has the ability to provide crushing and screening services completely

independently, with a fleet of fully mobile crushing and screening plants and the prime movers and

trailer systems to be able to transport the plant to any location. We offer this service preferably on

wet hire terms; however, have in the past provided the equipment for dry hire to suitably qualified

customers.

Hire of Plant

Bolwarra Enterprises offers wet hire of well-maintained plant. Please see table over page for a list of

the plant available including details of our operators.

Page 3: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

Plant Schedule

Please refer to the table below which shows a summary of our plant and equipment. A full

comprehensive list is available upon request.

Plant Type Number

of Units

Excavator (14/ 28/ 36/ 38 tonne) 6

Grader 16G /14H 2

Front-end Loader (Cat 980, 966, 920, 530) 8

Body Trucks 3

Prime Mover (three with excess mass permits) 7

Road Trains (double / triple) 4

Water Truck 2

Semi Side-tipper Trailer 14

Dolly Trailer 9

Dog Trailer 4

Low Loader/ Float Trailer 3

Low Loader Dolly Trailer 2

Concrete Agitator Truck (6m3 and 8m3) 9

Articulated Dump Truck (40T) 2

Hydraulic Rock-Breaker 3

Roller (Smooth drum plus pad ft) 1

Crane (Franna) 1

Jaw Crusher 2

Gyro Crusher 2

Impactor Rotary Crusher 3

Cone Crusher 2

Screening Plant 4

Drill Rig 1

Mobile Concrete Batch Plant 1

Page 4: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 4 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

Quarry Materials – Wongabel Quarries N Concrete & Bolwarra Enterprises Pty Ltd

We offer a wide range of quarry products from our quarries located in Atherton, Tolga, Croydon, Cardwell and Georgetown in North Queensland. Our three

major quarries (Wongabel, Croydon and Georgetown) all hold current Department of Transport and Main Roads Quarry Assessment Certificates. Please

refer to the table below which shows the products that carry DTMR certification for each quarry.

Products available are listed below:

• Type 2 and 3 Road-bases

• Cover Aggregates (various sizes)

• Concrete Aggregates

• Crusher Dust, Deco and Maintenance Gravels

• All size rock – Ballast, Trench, Mattress, Gabion

Concrete Products – Wongabel Concrete

We offer a range of pre-mixed concrete products for all applications delivered directly to site by our fleet of nine concrete agitator trucks (three of which

are eight-wheel vehicles with larger 8 m3 bowls). All products are tested regularly by NATA certified laboratory.

Our mobile concrete batching plant enables us to be able to batch concrete anywhere, therefore being able to affordably supply concrete for large remote

work sites.

Quarry Products covered by DTMR Quarry Certificate

Wongabel Quarry, Atherton Type 2 and 3 Road Base

Cover Aggregate

Jubilee Quarry, Croydon Type 2 and 3 Road Base

Cover Aggregate

Routh Quarry, Georgetown Type 2 and 3 Road Base

Cover Aggregate

• All pre-mixed concrete requirements, delivered directly to your site by our fleet of eight concrete

agitator trucks.

• Access to additional concrete trucks using sub-contractors.

• Exposed aggregates and a range of oxides for coloured concrete, for all your decorative requirements.

• Highest quality raw materials, ensures the highest quality concrete products.

• Made to specific certified mix designs and quality tested routinely to ensure the high quality is

consistent.

• Dependable service, competitive prices for locals.

• Free quotes.

Page 5: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 5 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

Management Systems

Safety Management System

Bolwarra Enterprises follows a comprehensive safety management system which can be provided on request.

Insurance

Bolwarra Enterprises Pty Ltd T/A Wongabel Quarries N Concrete is covered by:

• Product & Public Liability Insurance (Policy No. AQA348130PLB)

• Workers Compensation Insurance (Policy No. WPR171240262)

• Heavy Motor Insurance (Policy No. CPG20048567)

• Carriers Liability Insurance (Policy No. 46335685)

Environmental Management Plan

Bolwarra Enterprises follows a comprehensive Environmental Management System that can be provided on request.

Page 6: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 6 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

Track Record – Projects Completed

The following projects from the past three years have been provided as a demonstration of performance. All these projects were delivered within agreed

timelines and according to main roads specifications (where applicable). Additional project history can be provided upon request.

Year/ Quarry/ Trading Division Product/ Service Date/s Project/ Delivery Site Customer

2019

Bolwarra Enterprises Pty Ltd Supply, Deliver and Place: 2000 tonne Clean Fill 100 tonne Top Course Relocate Fence & Supply & Install New Gate

February 2019 Multi Sports Centre Georgetown

Extend Existing Pad by 5m

Ethridge Shire Council

Wongabel Quarries N Concrete Supply & Deliver: 6800t Type 2.1 ROADBASE @ 2% Cement Modified

February 2019 Kennedy Highway Tolga – Road Rehabilitation

RoadTek North (Cairns)

2018

Wongabel Quarries N Concrete Supply & Deliver: 360 tonnes Road base Type 2.1 22 tonnes Sized Rock 25-50

December 2018 Tolga Scrub, Tolga RoadTek North (Cairns)

Wongabel Quarries N Concrete Supply & Deliver: 770 tonnes Road base Type 2.5

December 2018 Atherton Disaster Centre Complex Hutchinson Builders

Bolwarra Enterprises Pty Ltd Wet Hire: Truck & Float Hire (37 hours) wet hire - 360 Excavator Double Road Train Hire (117 hrs) 980C Loader Hire (88 hrs) 16G Grader Hire (61.5 hrs) Cat Grader 14H Hire (55 hrs) Tandem Water Truck (123 hrs) Roller Pad & Smooth Drum (40 hrs)

Supply & Deliver: 786 tonnes Road base Type 2.1

December 2018 Construction of Multi Sports Centre Georgetown

Ethridge Shire Council

Bolwarra Enterprises Pty Ltd Supply & Deliver: 105 hours wet hire - 380 Excavator Truck and Float Hire 50 t TRENCH ROCK 20-60MM 50 t Subbase 2.3

November 2018 Furbers Crossing Croydon 4 Mile Normanton

Queensland Rail

Page 7: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 7 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

108 t GABION Rock 120-200MM

Wongabel Quarries N Concrete Supply & Deliver: 200 m3 pre-mixed concrete 280 t clean fill 50 t Decomposed granite

November 2018 452 Powely Road, Atherton Quality Sheds

Bolwarra Enterprises Pty Ltd Supply & Deliver 1352 tonne 16MM PRECOATE Agg 750 tonne 10MM PRECOATE Agg 150 tonne oversized rock > 300 mm 75 tonne 10MM PRECOATE Agg

November 2018 110KM Down Richmond Road Croydon Shire Council

Wongabel Quarries N Concrete Supply and delivery of 50 m3 pre-mixed concrete

November 2018 Mount Emerald Wind Farm, Walkamin QLD

Catcon

Bolwarra Enterprises Pty Ltd Truck & Float Hire Move M140 Grader Padfoot roller

October 2018 Yungaburra To Roaktek Cairns Roadtek Cairns To Fairview Station

RoadTek North (Cairns)

Wongabel Quarries N Concrete Supply and Deliver 1020 t GABION rock120-200MM Truck & Float Hire

October / November 2018

Hahn Highway Etheridge Shire Council

Bolwarra Enterprises Pty Ltd Truck & Float Hire Drake 980C Loader– Wet Hire Double Road Train Hire Triple Roadtrain Hire

October 2018 Pick Up Old Precoat Screenings Take To Jubilee Quarry, Croydon QLD

Croydon Shire Council

Wongabel Quarries N Concrete Supply and Deliver 65 m3 S280 Kerb Concrete

October 2018 Winfield Road - Eacham Clausen Constructions Pty Ltd

Wongabel Quarries N Concrete Supply and delivery of 100 m3 pre-mixed concrete 108 t crusher dust

October 2018 Mount Emerald - Turtle Creek, Walkamin QLD

Catcon

Wongabel Quarries N Concrete 2274 tonnes of oversized rock (200-500) supplied and delivered

September 2018

Kennedy Highway slope stabilisation Tablelands Regional Council

Bolwarra Enterprises Pty Ltd Quarry materials supplied and delivered:

1,454 t clean fill 1090 t road base 215 t precoat aggregate

September 2018

Newcastle Range, Georgetown RoadTek North (Cairns)

Bolwarra Enterprises Pty Ltd 66.5 hours wet hire - 16G Grader 40 hours wet hire – 980 Loader Truck and Float Hire 250 t sized rock 75-150

August/ September 2018

Mittagong Station/ Miranda Downs Supply & Deliver To Prospect Station

North Queensland Resources

Page 8: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 8 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

Bolwarra Enterprises Pty Ltd/ Wongabel Quarries N Concrete

630 hours wet hire - Volvo EC330BLC Excavator and Rock Breaker

July/ August/ September 2018

Mareeba Airport Upgrade FGF Developments Pty Ltd

Bolwarra Enterprises Pty Ltd - 43 hours wet hire – Volvo EC380DL Excavator - 127 tonnes of quarry product supplied and delivered

July 2018 Gilbert River – Pipe Jacking Project RoadTek North (Cairns)

Bolwarra Enterprises Pty Ltd 520 tonnes of quarry product supplied and delivered

July/ August 2018

Delivery to Depot/ Esmeralda Richmond Road

Croydon Shire Council

Wongabel Quarries N Concrete 2729 tonnes of quarry product supplied and delivered

August/ September 2018

Dei Rossi Road (104 tonnes), Kennedy Highway (2625 tonnes)

Tablelands Regional Council

Wongabel Concrete 88 m3 premix concrete products supplied and delivered

July/ August/ September 2018

Various sites Tablelands Regional Council

Bolwarra Enterprises Pty Ltd 390 hours of Wet Grader Hire. June 2018 Grade access roads and drainage either side of railway line, Boon-Moo to Forsayth,

Queensland Rail

Bolwarra Enterprises Pty Ltd Civil Construction Project. Embankment upgrade, cut and fill excavation and surface profiling, rock lined drains, concrete spillway, spillway excavation.

May / June 2018

Irvinebank QLD

Target Gully Remediation Tailings Dam

DNRME (Department of Natural Resources, Mines and Energy)

Bolwarra Enterprises Pty Ltd Crush 60,000 t minus 50 mm on site in Croydon Various Plant wet hire Various concrete supply (site batching)

April - 2018 Savannah Gold Mine (Croydon QLD) GBF Mining Ramex Services Pty Ltd Bost Group North QLD Mining

Routh Quarry, Georgetown Supply and delivery of 5,400 tonnes of Type 2.1 Road Base (2,700 tonnes pugged to 80% OMC)

April 2018 Forsayth Road Upgrade Project (Stage 2)

Etheridge Shire Council

Wongabel Quarries N Concrete Supply and delivery of various amounts fill material and crusher dust. Supply of 471 hours drill rig hire, 423 hours excavator hire and 18 hours rock hammer hire.

January – February 2018

Mt Emerald Wind Farm, Walkamin QLD

Marais Laying Technologies Pty Ltd

Page 9: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 9 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

Wongabel Quarries N Cocnrete Supply of various plant hire including 402 hours excavator hire, 65 hours rock hammer hire and water truck hire. Supply and delivery of various quarry products such as crusher dust and aggregates.

February – March 2018

Mt Emerald Wind Farm, Walkamin QLD

Consolidated Power Projects Australia Pty Ltd

Wongabel Quarries N Concrete Supply and delivery of pre-mixed concrete and fill material.

January – March 2018

Mt Emerald Wind Farm, Walkamin QLD

Catcon

Wongabel Quarries N Concrete Supply and delivery of various quarry and concrete products to the Herberton Fire Station Project.

January – March 2018

Herberton Fire Station project Vis Constructions Pty Ltd

Bolwarra Enterprises Pty Ltd/ Wongabel Quarries N Concrete

Supply and deliver pre-mixed concrete to site, supply and deliver crushed rock, water truck hire, excavator hire, rock breaker hire

922 M3 Pre-mixed concrete supplied and delivered 2018

Mt Emerald Wind Farm, Walkamin QLD

Mobile Concreting Solutions Pty Ltd Marais Laying Technologies Pty Ltd

Bolwarra Enterprises Pty Ltd Ongoing Day works (Two excavators and One water truck).

January – February 2018

Kidston Solar Farm UGL Engineering Pty Ltd (Genex Power)

2017

Wongabel Quarries N Concrete 430 hours of Drill Rig Hire at the Mt Emerald Wind Farm

October – December 2017

Mt Emerald Wind Farm Marais Laying Technologies

Wongabel Quarries N Concrete 304 hours of Rock Breaker/ Hammer Hire at the Mt Emerald Wind Farm.

October - December 2017

Mt Emerald Wind Farm Marais Laying Technologies

Bolwarra Enterprises Pty Ltd 101 hours of Semi Side Tipper and Semi Double Side Tipper Hire.

October – December 2017

Various Various

Bolwarra Enterprises Pty Ltd 934 hours of Excavator Hire. October – Dec 2017

Various Various

Bolwarra Enterprises Pty Ltd 50 hours of Rock Breaker/ Hammer Hire.

October – December 2017

Various Etheridge Shire Council

Bolwarra Enterprises Pty Ltd 4461 hours of Cartage. October 2017 Various Etheridge Shire Council

Wongabel Quarries N Concrete 96 hours of Truck & Dog Hire. October – December 2017

Various Various

Wongabel Concrete 467 hours of Concrete Agi Truck Hire.

October – December 2017

Various Various

Page 10: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 10 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

Jubilee Quarry Croydon 6748 tonnes of various quarry products supplied.

October – December 2017

Various Various

Routh Quarry Georgetown 9520 tonnes of various quarry products supplied.

October – December 2017

Various Various

Wongabel Concrete 2142 m3 of various concrete products supplied.

October – December 2017

Various Various

Wongabel Quarry, Atherton 23,522 tonnes of various quarry products supplied.

October -December 2017

Various Various

Routh Quarry Georgetown Supply and delivery of 1,223 tonnes of various quarry materials to site.

1,223 tonnes Lawnvale Station Pad, Forsayth Road ASPIC Infrastructure Pty Ltd

Routh Quarry Georgetown Supply and delivery of 9,352 tonnes of Pugged 2.2 Road Base to the Forsayth Road Upgrade Project.

9,352 tonnes over 3 weeks

Forsayth Road Upgrade Project Etheridge Shire Council

Jubilee Quarry Croydon Supply and deliver:

Gabion Rock, 16mm Cover Aggregate and 7mm Pre-coated Aggregate.

579 tonnes Gabion Rock 251 tonnes of Cover Agg and 168 tonnes of 7mm Pre-coated Aggregate

M Creek Pad 93.5 CH Croydon Shire Council

Bolwarra Enterprises Pty Ltd Construction of internal road works and lay down pad. On site Crushing & screening of 50,000 tonnes of gravel. Ongoing Day works (Two excavators and One water truck).

50,000 tonnes Kidston Solar Farm UGL Engineering Pty Ltd

(Genex Power)

Wongabel Quarry Atherton Supply and deliver maintenance gravel.

46 tonnes Mareeba Depot Queensland Rail

Routh Quarry Georgetown Supply and deliver 20-30mm Trench Rock.

51 tonnes Logans Crossing, Mt Surprise Queensland Rail

Wongabel Quarry Atherton Sub-base/ Rock 1,500/ 400 tonnes

Rocky Creek Brown Contractors

Wongabel Quarry Atherton 2.1 Pugged Road Base 6,890 tonnes Upper Barron Road Tablelands Regional Council

Page 11: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 11 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

2016

Wongabel Concrete Atherton Supply and deliver 40/20 concrete. 14 m3 Almaden Queensland Rail

Routh Quarry Georgetown Supply and deliver 20-60mm Trench Rock.

98 tonnes Various Queensland Rail

Jubilee Quarry Croydon Supply and deliver maintenance gravel.

73 tonnes 28 Mile Telecom 110km west of Croydon

Queensland Rail

Bolwarra Enterprises Pty Ltd

Caterpillar 16G Grader Hire. 50 hours Rail line between Dimbulah and Einsleigh.

Queensland Rail Supply and deliver red ridge gravel.

402 tonnes Golden Gate Railway Pad

Wongabel Quarry Atherton Type 2 Road Base 2,830 tonnes Atherton Transfer Station FGF Developments

Wongabel Quarry Atherton Type 2 Sub-bases 23,000 tonnes Upper Barron Road Tablelands Regional Council

Wongabel Quarry Atherton

Maintenance Gravel/ 2.1 Road Base

1,900/ 2,720 tonnes

Herberton Range

RoadTek Various Rock 1,152 tonnes Merragallan Road/ Upper Barron

Road

Wongabel Quarry Atherton Road Base 1,860 tonnes Northey Road

Routh Quarry Georgetown Type 2 Road Base 37,260 tonnes Roads west of Georgetown Etheridge Shire Council

Routh Quarry Georgetown Aggregates 3,685 tonnes Various sites Carpentaria Shire Council

Jubilee Quarry Croydon Pre-coated Aggregates 1,075/ 890 tonnes

Various sites Carpentaria Shire Council

Jubilee Quarry Croydon Concrete Aggregate 3,375 tonnes Normanton Airport Carpentaria Shire Council

Jubilee Quarry Croydon 2.2 Road Base 16,000 tonnes Karumba RoadTek

Jubilee Quarry Croydon

Pre-coated Aggregate 2,270 tonnes Richmond Road

Croydon Shire Council Pre-coated Aggregate 1,020 tonnes Various

2.1 Road Base/ Pre-coated Aggregate

20,605/ 850 tonnes

Log Creek, Georgetown

Jubilee Quarry Croydon Rock 8,552 tonnes Glenmore Weir, Normanton Koppens Developments

Page 12: Bolwarra Enterprises Capability Statement (April 2019) · Page 3 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises

Page 12 of 12 B:\1 Proposals & Plans\1.4 Tenders & Quotes\1.4.1 Supporting Docs\Capability Statement\Bolwarra Enterprises Capability Statement (April 2019).docx

Bolwarra Enterprises Pty Ltd

A.B.N. 54 009 853 221

Major Clients

• Tablelands Regional Council

• Croydon Shire Council

• FGF Developments

• Queensland Rail

• Stabilised Pavements of Australia

• Marais Laying Technologies

• Consolidated Power Projects Australia Pty Ltd

• Carpentaria Shire Council

• Etheridge Shire Council

• RoadTek/ Department of Transport and Main Roads

• Koppens Developments

• UGL Limited (under Genex Power)

• Ramex Services Pty Ltd

• Vis Constructions Pty Ltd