bored pile/drilled shaft synthesis project: an overvie · five subtopics of bp/ds industry: design,...
TRANSCRIPT
AUTHOR
slow. It has often taken decades to move a
skill set from Europe to North America or
even to move a technology from another
industry to the construction sector.
Through this project, the hope was that the
movement of innovations or underutilized
practice from one jurisdiction to another
could be accelerated.
To address these questions, a task force
met at the DFI Annual Conference in Phoenix,
Ariz., in October 2013. It was agreed that
the task force would examine the following
five subtopics of BP/DS Industry: Design,
Construction, Quality Assurance/Quality
Control (QA/QC), Innovative Technologies
and Trends, and Procurement Methods.
Authors/ResearchersEach of these subtopics was examined by a
pair of authors, one knowledgeable with
North American practice, and the other
knowledgeable with European practice.
The following author pairs were
developed:
DEEP FOUNDATIONS • NOV/DEC 2016 • 103
Alan Macnab, P. Eng., D.GE
The Bored Pile/Drilled Shaft (BP/DS)
Synthesis Project, endorsed by the DFI
Dril led Shaft Committee, was the
brainchild of James Johnson, trustee liaison
to the committee. Johnson felt that DFI
members in the European Union (EU) and
North America (NA) would benefit from a
comparison of the state of practice for
drilled shafts (called bored piles in Europe)
in those two regions.
Johnson posed several key questions:
• Is the design and construction of BP/DS
similar in both regions?
• If not, why not? Is it because of
regulatory drivers, environmental
drivers or financial drivers?
• Or is it just different and could those
differences offer opportunities to learn
from those differences?
From past history in the geotechnical con-
struction industry, transfer of knowledge
bases and technology is often painfully
Bored Pile/Drilled Shaft Synthesis Project: An Overview
Topic North American Author European Author
Design Dr. Dan Brown, D.GE., P.E. Maurice Bottiau, ir (Belgium)
(Tennessee)
Construction Dr. Antonio Marinucci, P.E. Vince Jue (Italy)
(Rhode Island)
QA/QC Bernie Hertlein, FACI (Illinois) Gerald Verbeek (Netherlands)
Innovation Ray Fassett (California) Dr. Michael Arnold (Germany)
Procurement David Coleman, P.E. (New York) Arthur Tipter, Dipl. Ing. (Germany)
Installing bored piles in Dresden, Germany (photo courtesy Zueblin)
104 • DEEP FOUNDATIONS • NOV/DEC 2016 DEEP FOUNDATIONS • NOV/DEC 2016 • 105
Alan Macnab, P.Eng., D.GE.
public private partnerships or Build, Oper-
ate, Transfer) many, if not all, risks are borne
by the DB contractor, who then either shares
them within its team on an ability-to-pay
basis or finds insurance protection for them.
DB contractors in NA tend to be larger
conglomerates that coordinate design,
construction, testing and often financing
issues as well as long-term maintenance. In
the end, decisions are made based on
economic reasons. Short-term efficiencies
often do not equate to long-term
economies. Even conventional contracts,
which are awarded based on a value rather
than price basis, usually come with
increased builder liability and responsibility.
If one accepts the premise that, to the
DB contractor, the long-term economic
decision is paramount, then some of the
differences identified in this study are easier
to understand. It is a basic assumption
contained herein that this premise governs
DB in both the EU and NA.
For example, slurry protected shafts are
often cheaper to construct than cased
shafts, but suffer a higher incidence of
anomalies. Anomalies drive schedule
losses, which are often not considered by
DBB contractors. However a DB contractor,
who is responsible for financing, has a
different perspective. If cased shafts are
practice using fewer diameters for its
designs and, in general, the diameters used
in the EU tend to be smaller than in NA.
The use of Design Build (DB) or variations
thereof as opposed to Design Bid Build
(DBB) are far more prevalent in the EU than
in NA. In addition, the EU seems more
advanced in selecting contractors based on
value versus price. QA/QC testing is
performed on a smaller percentage of shafts
in the EU than in NA. The EU depends
more on analytical design and in some
cases load testing rather than integrity
testing for design assurance.
Why do we see these differences? The
task force concluded that many of these
differences can be attributed to risk issues
including: quality, productivity, safety,
schedule, cost, public disruption and
sustainability.
Risks are often the direct result of
decisions related to specialty subcontractor
selection, and/or design type selection.
Influence of Project Delivery MethodsIn the NA low bid environment of DBB,
risks are shared or volleyed between the
various entities. In contrast the DB
environment (including such things as
Bored pile construction in Switzerland (photo courtesy BAUER Spezialtiefbau GmbH)
Drilled shafts to support a concrete plant in Calgary, Canada (photo courtesy BAUER Spezialtiefbau GmbH)
Some authors recruited additional con-
tributors for their sections. Alan Macnab,
P.Eng., D.GE. (Canada) was appointed chair.
A follow-up meeting was held at the
EFFC (European Federation of Foundation
Contractors) Conference in Stockholm,
Sweden, in May 2014. Preliminary reports
were presented at the DFI Annual Confer-
ence in Atlanta, Ga., in October 2014. A
presentation of the final findings was made
at the International Foundations Congress
and Equipment Exposition (IFCEE) in San
Antonio, Texas, in March 2015.
The DFI Journal, Volume 10, Issue 2,
includes four papers that represent the
findings of the task force. Because of
significant overlap in the subject matter the
papers for QA/QC and Innovative Tech-
nologies and Trends were combined and
are presented as one paper.
Challenges FacedOne of the challenges the task force
encountered was defining the state of prac-
tice in each region and determining
whether it was possible to define a single
state of practice for each region. North
America, including Central America and
the Caribbean Islands, consists of 38
countries, 22.5 million sq km (8.7 million
sq mi) and 556 million people. Europe
consists of 50 countries, 12.5 million sq km
(4.8 million sq mi) and 742 million people.
It became apparent that it was unrealistic to
expect that practice in either North America
or Europe would be consistent, and it was
also not possible to accurately define
overarching behaviors in such large regions.
It was conceded that the task force
would compare Canada/U.S. and the EU.
The EU consists of 28 countries, 4.3 mil-
lion sq km (1.6 million sq mi) and 507
million people. By comparison, Canada
and the U.S. appear to be similar, however
practices are very regional and diverse;
both have weak central governments and
many operat ions, regulat ions and
practices are performed independently by
states or provinces. As such Canada/U.S.
combined consist of 60 states/provinces,
19.8 million sq km (7.6 million sq mi) and
352 million people. These are staggering
numbers and to describe unique trends or
discrete behaviour patterns required some
gross generalizations.
The task force knew from the start that
the U.S. has the American Association of
State Highway and Transportation
Officials (AASHTO) publications, which
guide transportation sector work, a very
large piece of the drilled shaft market, and
that the EU has the Eurocode for
guidance/regulation in its bored pile
market. The group also knew that there
was unprecedented entry into each
other’s markets from equipment manu-
facturers, which should give some clues
as to any differences which might exist.
The key was to concentrate on these
differences, explaining why they existed,
and determine if these explanations
warranted using the “idea” in other
jurisdictions.
In order to research the variations in
practice in the subject areas, a survey was
distributed to members of DFI, DFI
Europe, ADSC (International Association
of Foundation Drilling) and EFFC. Initial
returns were quite low and heavily
skewed toward NA. The survey was
modified and sent out again. This elicited
more EU response, but the results were
still heavily dominated by feedback from
NA. In order to reconcile this problem,
interviews were carried out with select
European construction representatives
and the task force eventually had
sufficient data to proceed.
FindingsPractice in both NA and the EU is governed
by overarching design and construction
documents that are heavily influenced by
local practices and local codes. Both regions
utilize the same equipment and similar
design methodologies, and both are
developing new innovations. EU innovation
is more focused on drilling and construction
site activities such as in-boom locating
devices. Representatives from the EU are
currently examining concreting practices
and plan to publish their conclusions in the
near future. In NA, the innovations are
focused on QA/QC, or post process needs
such as in-cab readouts, hole measurement
devices, and Thermal Integrity Profiling.
Although many of these measurement
devices are more widely used in NA, often
they were developed in Europe. Both
regions exhibit less conservatism in design
when stronger, more realistic geotechnical
investigation materials are available.
In general, the EU utilizes a larger
percentage of cased shafts while NA
constructs a higher percentage of shafts
using slurry protection. In the slurry
practice, the use of mineral slurries is
predominant in the EU while polymer is
prevalent in NA. The EU has standardized (Top Row L-R) Dr. Michael Arnold, Dr. Dan Brown, P.E., D.GE., Maurice Bottiau, ir, David Coleman, P.E., Ray Fassett(Bottom Row L-R) Bernie Hertlein, FACI, Vince Jue, Dr. Antonio Marinucci, P.E., Arthur Tipter, Dipl. Ing., Gerald Verbeek
104 • DEEP FOUNDATIONS • NOV/DEC 2016 DEEP FOUNDATIONS • NOV/DEC 2016 • 105
Alan Macnab, P.Eng., D.GE.
public private partnerships or Build, Oper-
ate, Transfer) many, if not all, risks are borne
by the DB contractor, who then either shares
them within its team on an ability-to-pay
basis or finds insurance protection for them.
DB contractors in NA tend to be larger
conglomerates that coordinate design,
construction, testing and often financing
issues as well as long-term maintenance. In
the end, decisions are made based on
economic reasons. Short-term efficiencies
often do not equate to long-term
economies. Even conventional contracts,
which are awarded based on a value rather
than price basis, usually come with
increased builder liability and responsibility.
If one accepts the premise that, to the
DB contractor, the long-term economic
decision is paramount, then some of the
differences identified in this study are easier
to understand. It is a basic assumption
contained herein that this premise governs
DB in both the EU and NA.
For example, slurry protected shafts are
often cheaper to construct than cased
shafts, but suffer a higher incidence of
anomalies. Anomalies drive schedule
losses, which are often not considered by
DBB contractors. However a DB contractor,
who is responsible for financing, has a
different perspective. If cased shafts are
practice using fewer diameters for its
designs and, in general, the diameters used
in the EU tend to be smaller than in NA.
The use of Design Build (DB) or variations
thereof as opposed to Design Bid Build
(DBB) are far more prevalent in the EU than
in NA. In addition, the EU seems more
advanced in selecting contractors based on
value versus price. QA/QC testing is
performed on a smaller percentage of shafts
in the EU than in NA. The EU depends
more on analytical design and in some
cases load testing rather than integrity
testing for design assurance.
Why do we see these differences? The
task force concluded that many of these
differences can be attributed to risk issues
including: quality, productivity, safety,
schedule, cost, public disruption and
sustainability.
Risks are often the direct result of
decisions related to specialty subcontractor
selection, and/or design type selection.
Influence of Project Delivery MethodsIn the NA low bid environment of DBB,
risks are shared or volleyed between the
various entities. In contrast the DB
environment (including such things as
Bored pile construction in Switzerland (photo courtesy BAUER Spezialtiefbau GmbH)
Drilled shafts to support a concrete plant in Calgary, Canada (photo courtesy BAUER Spezialtiefbau GmbH)
Some authors recruited additional con-
tributors for their sections. Alan Macnab,
P.Eng., D.GE. (Canada) was appointed chair.
A follow-up meeting was held at the
EFFC (European Federation of Foundation
Contractors) Conference in Stockholm,
Sweden, in May 2014. Preliminary reports
were presented at the DFI Annual Confer-
ence in Atlanta, Ga., in October 2014. A
presentation of the final findings was made
at the International Foundations Congress
and Equipment Exposition (IFCEE) in San
Antonio, Texas, in March 2015.
The DFI Journal, Volume 10, Issue 2,
includes four papers that represent the
findings of the task force. Because of
significant overlap in the subject matter the
papers for QA/QC and Innovative Tech-
nologies and Trends were combined and
are presented as one paper.
Challenges FacedOne of the challenges the task force
encountered was defining the state of prac-
tice in each region and determining
whether it was possible to define a single
state of practice for each region. North
America, including Central America and
the Caribbean Islands, consists of 38
countries, 22.5 million sq km (8.7 million
sq mi) and 556 million people. Europe
consists of 50 countries, 12.5 million sq km
(4.8 million sq mi) and 742 million people.
It became apparent that it was unrealistic to
expect that practice in either North America
or Europe would be consistent, and it was
also not possible to accurately define
overarching behaviors in such large regions.
It was conceded that the task force
would compare Canada/U.S. and the EU.
The EU consists of 28 countries, 4.3 mil-
lion sq km (1.6 million sq mi) and 507
million people. By comparison, Canada
and the U.S. appear to be similar, however
practices are very regional and diverse;
both have weak central governments and
many operat ions, regulat ions and
practices are performed independently by
states or provinces. As such Canada/U.S.
combined consist of 60 states/provinces,
19.8 million sq km (7.6 million sq mi) and
352 million people. These are staggering
numbers and to describe unique trends or
discrete behaviour patterns required some
gross generalizations.
The task force knew from the start that
the U.S. has the American Association of
State Highway and Transportation
Officials (AASHTO) publications, which
guide transportation sector work, a very
large piece of the drilled shaft market, and
that the EU has the Eurocode for
guidance/regulation in its bored pile
market. The group also knew that there
was unprecedented entry into each
other’s markets from equipment manu-
facturers, which should give some clues
as to any differences which might exist.
The key was to concentrate on these
differences, explaining why they existed,
and determine if these explanations
warranted using the “idea” in other
jurisdictions.
In order to research the variations in
practice in the subject areas, a survey was
distributed to members of DFI, DFI
Europe, ADSC (International Association
of Foundation Drilling) and EFFC. Initial
returns were quite low and heavily
skewed toward NA. The survey was
modified and sent out again. This elicited
more EU response, but the results were
still heavily dominated by feedback from
NA. In order to reconcile this problem,
interviews were carried out with select
European construction representatives
and the task force eventually had
sufficient data to proceed.
FindingsPractice in both NA and the EU is governed
by overarching design and construction
documents that are heavily influenced by
local practices and local codes. Both regions
utilize the same equipment and similar
design methodologies, and both are
developing new innovations. EU innovation
is more focused on drilling and construction
site activities such as in-boom locating
devices. Representatives from the EU are
currently examining concreting practices
and plan to publish their conclusions in the
near future. In NA, the innovations are
focused on QA/QC, or post process needs
such as in-cab readouts, hole measurement
devices, and Thermal Integrity Profiling.
Although many of these measurement
devices are more widely used in NA, often
they were developed in Europe. Both
regions exhibit less conservatism in design
when stronger, more realistic geotechnical
investigation materials are available.
In general, the EU utilizes a larger
percentage of cased shafts while NA
constructs a higher percentage of shafts
using slurry protection. In the slurry
practice, the use of mineral slurries is
predominant in the EU while polymer is
prevalent in NA. The EU has standardized (Top Row L-R) Dr. Michael Arnold, Dr. Dan Brown, P.E., D.GE., Maurice Bottiau, ir, David Coleman, P.E., Ray Fassett(Bottom Row L-R) Bernie Hertlein, FACI, Vince Jue, Dr. Antonio Marinucci, P.E., Arthur Tipter, Dipl. Ing., Gerald Verbeek
106 • DEEP FOUNDATIONS • NOV/DEC 2016
regimes of the fluid concrete stream.
Additionally, bored pile or drilled shaft
concrete can be subjected to stringent test
methods not used on concrete structures
poured in environments that permit visual
inspection. Added research in the field
joining EU and NA knowledge and
resources is underway as a result of the
collaboration of this task force.
In conclusion, the onset of added DB
contracting in NA will probably bring
changes to the methods of contractor
selection as well as design type selection.
From the EU perspective, some of the work
done in NA on slurry techniques has raised
the reliability levels of this technique. This
may present opportunities for financial
economies not previously taken.
To read more details about the findings of the task force, see DFI Journal Volume 10, Issue 2, available for DFI members at MyDFI on the DFI website. Others can join
DFI or subscribe to the Journal at www.tandfonline.com/pricing/journal/ydfi20#.V1B55cr2Y0M.
Drilled shaft construction at Goethals Bridge, NY-NJ (photo courtesy Dan Brown and Associates)
Bored piles in Berlin for the State Opera (photo courtesy BAUER Spezialtiefbau GmbH)
more expensive, but more dependable
from a production schedule point of view, it
is quite easy to understand the EU bias for
cased shafts. There is anecdotal evidence
that the incidence of anomalies is
decreasing in both NA and the EU among
experienced specialty contractors. To
overcome some of the anomaly concerns,
owners have instituted increased use of
integrity testing and shaft measuring
devices, which explains the higher use of
QA/QC testing in NA.
Shaft installation on the Route 1 Gateway project in Canada (photo courtesy BAUER Spezialtiefbau GmbH)
One of the risks associated with DBB is
that the low bidder usually gets the work
regardless of subtrade competency. Drilled
shaft/bored pile contractors are almost
always subcontractors. In the mad dash to
become low bidder, decis ions on
subcontractor selection are often based
entirely on price. In that environment, it is
not surprising that owners would then
require a high degree of QA/QC testing.
When a DB contractor has most of the risk,
its selection of specialty subtrades is
probably based on more rational criteria.
Selecting a specialty subcontractor of
higher competency allows one to focus on
design improvements rather than chasing
quality mistakes.
While no evidence was presented, one
explanation for smaller shafts in the EU
may be that the use of nonredundant
structures such as mono foundations is not
as prevalent in the DB world when the risk
of failure is more catastrophic with
nonredundant structures. It may also be the
result of the use of more load testing in the
EU, which may either lower the assumed
design safety factors or increase the unit
capacity of the drilled shaft/bored pile.
Common Work, Common ProblemsIt became apparent during the work of this
task force that the contractors of the EU and
NA carry a common problem. A core
business activity is one of sophisticated
concrete placement. The specialty
contractors are often called “drillers,” but
that can be the simple part of the work. The
placement of higher-slump, high-strength
concrete in challenging environments
utilizing tremie methods is very difficult.
Problems arise in this type of work that are
often the result of a poor understanding of
critical characteristics necessary for drilled
shaft/bored pile construction by the ready
mix supply industry and inconsistent flow
properties of the resultant product. Some of
these issues are caused by the variation in
materials from supplier to supplier, or even
the variation in ingredients used by the
same supplier. In addition, we have been
placing concrete as an industry by tremie
methods for decades but still really don’t
understand the mechanics and flow
106 • DEEP FOUNDATIONS • NOV/DEC 2016
regimes of the fluid concrete stream.
Additionally, bored pile or drilled shaft
concrete can be subjected to stringent test
methods not used on concrete structures
poured in environments that permit visual
inspection. Added research in the field
joining EU and NA knowledge and
resources is underway as a result of the
collaboration of this task force.
In conclusion, the onset of added DB
contracting in NA will probably bring
changes to the methods of contractor
selection as well as design type selection.
From the EU perspective, some of the work
done in NA on slurry techniques has raised
the reliability levels of this technique. This
may present opportunities for financial
economies not previously taken.
To read more details about the findings of the task force, see DFI Journal Volume 10, Issue 2, available for DFI members at MyDFI on the DFI website. Others can join
DFI or subscribe to the Journal at www.tandfonline.com/pricing/journal/ydfi20#.V1B55cr2Y0M.
Drilled shaft construction at Goethals Bridge, NY-NJ (photo courtesy Dan Brown and Associates)
Bored piles in Berlin for the State Opera (photo courtesy BAUER Spezialtiefbau GmbH)
more expensive, but more dependable
from a production schedule point of view, it
is quite easy to understand the EU bias for
cased shafts. There is anecdotal evidence
that the incidence of anomalies is
decreasing in both NA and the EU among
experienced specialty contractors. To
overcome some of the anomaly concerns,
owners have instituted increased use of
integrity testing and shaft measuring
devices, which explains the higher use of
QA/QC testing in NA.
Shaft installation on the Route 1 Gateway project in Canada (photo courtesy BAUER Spezialtiefbau GmbH)
One of the risks associated with DBB is
that the low bidder usually gets the work
regardless of subtrade competency. Drilled
shaft/bored pile contractors are almost
always subcontractors. In the mad dash to
become low bidder, decis ions on
subcontractor selection are often based
entirely on price. In that environment, it is
not surprising that owners would then
require a high degree of QA/QC testing.
When a DB contractor has most of the risk,
its selection of specialty subtrades is
probably based on more rational criteria.
Selecting a specialty subcontractor of
higher competency allows one to focus on
design improvements rather than chasing
quality mistakes.
While no evidence was presented, one
explanation for smaller shafts in the EU
may be that the use of nonredundant
structures such as mono foundations is not
as prevalent in the DB world when the risk
of failure is more catastrophic with
nonredundant structures. It may also be the
result of the use of more load testing in the
EU, which may either lower the assumed
design safety factors or increase the unit
capacity of the drilled shaft/bored pile.
Common Work, Common ProblemsIt became apparent during the work of this
task force that the contractors of the EU and
NA carry a common problem. A core
business activity is one of sophisticated
concrete placement. The specialty
contractors are often called “drillers,” but
that can be the simple part of the work. The
placement of higher-slump, high-strength
concrete in challenging environments
utilizing tremie methods is very difficult.
Problems arise in this type of work that are
often the result of a poor understanding of
critical characteristics necessary for drilled
shaft/bored pile construction by the ready
mix supply industry and inconsistent flow
properties of the resultant product. Some of
these issues are caused by the variation in
materials from supplier to supplier, or even
the variation in ingredients used by the
same supplier. In addition, we have been
placing concrete as an industry by tremie
methods for decades but still really don’t
understand the mechanics and flow