bowie state university fine and performing arts center

23
Bowie State University Fine and Performing Arts Center Zachary Lippert Faculty Advisor: Dr. Stephen Treado

Upload: hali

Post on 06-Feb-2016

47 views

Category:

Documents


0 download

DESCRIPTION

Bowie State University Fine and Performing Arts Center. Zachary Lippert Faculty Advisor: Dr. Stephen Treado. Bowie State University Fine and Performing Arts Center. Project Team Owner: University of Maryland CM: Holder Construction Company - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Bowie State University  Fine  and Performing Arts  Center

Bowie State University Fine and Performing Arts Center

Zachary LippertFaculty Advisor: Dr. Stephen Treado

Page 2: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Project Team 

Owner: University of Maryland

CM: Holder Construction Company

Architect: EYP Architecture and Engineering

Mechanical Contractor: W.E. Bowers

Electrical Contractor: Mona Electric

Controls Contractor: Seimens

Commissioning Authority: EMC/Eaton

MEP Engineer: EYP Architecture and Engineering

Bowie State University Fine and Performing Arts Center

Zachary LippertFaculty Advisor: Dr. Stephen Treado

Page 3: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Project Overview• Site

• Bowie, Maryland• Southeast corner of campus

• Project Information• 123,000 square feet• $79 million• Design-Bid-Build delivery method

• Architecture• Large expanse of glass• Mixed use building• Multiple large performance spaces• Art gallery Courtesy of Google Maps

Page 4: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Existing Mechanical System

• 3 Mixed Air Units with enthalpy wheels• 16 Air Handling Units• 64 VAV boxes (40 to 1,200 CFM)

Page 5: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Existing Mechanical System

• Two 1712 MBH gas fired boilers• Four heating water pumps• 305 ton air cooled chiller• Four chilled water pumps

Page 6: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

500,964.00

472,963.00

183,266.00

1,038,262.00

284,900.00

Energy Consumption by System

Heating

Cooling

Auxiliary

Lighting

Receptacle

Existing Mechanical System

Page 7: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Proposed Redesign

• Goals for the redesign• Improve the mechanical efficiency• Reduce utility bills

• Redesign Components• Ground source heat pump• Underfloor air distribution• Energy efficient lighting system

Page 8: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Ground Source Heat Pump

• Soil type• Cretaceous• Diffusivity = .9 ft2 /day• Conductivity = 1.1 Btu/h*ft*°F

• Calculations

No. of Bores Depth (ft)450 616.1480 577.6510 543.6540 513.4570 486.4

Page 9: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Ground Source Heat Pump

• Equipment• 510 bores at 544 ft• 2 gpm/ton• System flow rate: 410 gpm• 5” headers and 1” U-tube piping• Total head loss: 54 ft of water• Two 10 HP 1750 RPM pumps

• Energy Model• Heating: Saved 411,164 kBtu/year• Cooling: Saved 153,327 kBtu/year• Auxiliary: Used additional 237,532 kBtu/year• Net Savings: 326,959 kBtu/year

Page 10: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Underfloor Air Distribution

• Location of the systems• Large volume spaces• Encourage stratification

• Duct layout• Less ductwork• Lower pressure drop• Less fan power

Page 11: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Underfloor Air Distribution

• Energy Usage• Minor reduction in cooling load• Significant increase in heating load

Heating (MBh)

Cooling (tons)

Existing 587 212

UFAD 1,037 199

Difference 450 MBh 13 tons• System Sizing

• Increased duct length ~20%• Increased fan power and size

• System Drawbacks• Raised floor system• Larger fan• More materials• Longer construction time• Uses more energy

• This system was not further investigated

Page 12: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Energy Efficient Lighting

• Redesign Goal• Reduce the yearly kWh in the offices and

classrooms• Provide adequate light for required tasks

• Methods• Energy efficient luminaires• T5HO lamps• Occupancy sensors

Page 13: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Energy Efficient Lighting

• Existing Lighting Design

• Offices• Recessed direct luminaires• Two foot luminaires with two 40 Watt TT5 lamps• 1.55 Watts/sq. ft.

• Classrooms• Recessed direct luminaires• Four foot luminaires with two 32 Watt T8 lamps• 1.47 Watts/sq. ft.

• Proposed Lighting Design

• Offices and classrooms• Suspended direct/indirect luminaires• Four foot luminaires with one 54 Watt T5HO

lamps

Page 14: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Energy Efficient Lighting

• Illuminance Values• Office: 30 foot-candles• Music Classrooms: 15 foot-candles

• AGI Model• Less watts per luminaire• Half as many luminaires• Excellent energy savings

Page 15: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Energy Efficient Lighting

• Occupancy Sensors• Offices: Passive infrared• Classrooms: Ultrasonic

• Equivalent Full Load Hours• Offices: 2870• Classrooms: 2522

• Hours Saved• Offices: 1091• Classrooms: 1463

Page 16: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Office Energy Savings Classroom Energy Savings

Existing ProposedTotal Watts 19414 6552

EFLH 2522 2522Total kWh 48962 16524

kWh with Sensors - 6940

Total Savings 42,022 kWh

Existing ProposedTotal Watts 7564 3829

EFLH 2870 2870Total kWh 21709 10989

kWh with Sensors - 6813

Total Savings 14,896 kWh

Page 17: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Ground Source Heat Pump Cost and Savings

• Total System Cost: $2,938,000• BG&E Incentive: $1,000,000• Net Cost: $1,938,000

• Total Utility Savings: -$665.27

Existing System

GSHP

Electric Consumption (kWh)

619509 634582

Electric Cost $57,428.48 $58,825.75Gas Consumption (therms)

3660 0

Gas Cost $732.00 $0.00Total Utility Cost $58,160.48 $58,825.75

Page 18: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Lighting Redesign Cost and Savings

No. of Fixture

s

Price/Fixture

Total Cost

Old Luminaires

317 $212.00$67,204.0

0New Luminaires

159 $352.00$55,968.0

0

Savings$11,236.0

0

  Classrooms

Offices

kWh Saved per Year

32437 10718

Cost/kWh $0.0927 $0.0927Money Saved/Year

$3006.88 $993.57

Total Savings/Year

$4000.45

Page 19: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Occupancy Sensor Cost and Savings

• Initial cost of sensors: $4,480• BG&E 75% Incentive: $1,120• Cost of Installation: $10,080• Net Total Cost: $11,200

• Simple Payback

Classrooms Offices

Cost Without Sensors

$1,531.81 $1,018.73

Cost With Sensor $643.36 $631.61

Utility Savings $888.45 $387.12

Total Savings per Year

$1,275.56

Page 20: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Recommendations

• Ground Source Heat Pump• Reduced energy consumption• Expensive to install• Increased utility costs• Explore other options

• Underfloor Air Distribution• Expensive to install• Increased energy consumption• Increased construction time• Explore other options

• Lighting Redesign• Less expensive to install• Reduced energy consumption and costs• Implement this design

• Occupancy Sensors• Reduced energy consumption and costs• More expensive to install• 8.8 year payback• Implement this design

Page 21: Bowie State University  Fine  and Performing Arts  Center

Presentation Outline

• Project Overview

• Existing Mechanical System

• Proposed Redesign

• Ground Source Heat Pump

• Underfloor Air Distribution System

• Lighting Breadth

• Cost and Savings

• Recommendations

• Conclusion

Acknowledgements

Architectural Engineering Faculty and Staff

Dr. Stephen Treado

Adam Seigrist and Mike Luffred of EMC/Eaton

Hayes Todd of Holder Construction

My Friends and Family

Questions?

Page 22: Bowie State University  Fine  and Performing Arts  Center
Page 23: Bowie State University  Fine  and Performing Arts  Center