![Page 1: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/1.jpg)
1
BP Terminal – Greenpoint, NYProject Update Meeting
David Lates, NYSDEC
January 25, 2016
![Page 2: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/2.jpg)
2
ExxonMobil Greenpoint Remediation Project (GPRP)
Public MeetingWednesday, 1/27/2016 at 6:00 – 9:00 PM
Brooklyn Public LibraryGreenpoint Branch107 Norman Ave.
Brooklyn, NY 11222
Presentation at 7:00 PM followed by Q&A session
![Page 3: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/3.jpg)
3
Presentation Overview• History of the Greenpoint Area
• Greenpoint Project Remediation Sites
• BP Terminal – Remediation Update
• Upcoming Transfer of Ownership/Operation
• Questions & Comments
![Page 4: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/4.jpg)
44
History of the GreenpointProject
![Page 5: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/5.jpg)
5
Greenpoint History• Pre 1860’s: Whale Oil Refining
• 1860’s-1960’s: Petroleum Refining 1890’s: Standard Oil Refinery
Consolidation (broken up in 1911)
• 1966: Refinery Operations Cease
• 1978: Seep into Newtown Creek Noted by U.S. Coast Guard andRemediation Begins.
![Page 6: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/6.jpg)
6
Standard Oil Refinery (1950s)
BP Terminal
Midtown Manhattan
![Page 7: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/7.jpg)
7
BP Terminal
Newtown Creek WPCP
![Page 8: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/8.jpg)
8
Historical and
Current Extent
of Free-
ProductPlume
![Page 9: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/9.jpg)
9
GPRP Free-Product Estimates (gallons)Ecology and Environment
Original Plume Volume………………………….. 20,000,000
Product Recovery to Date………………………. 12,200,000
BP Product Recovered to Date..………………… 3,534,000
![Page 10: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/10.jpg)
1010
GreenpointRemediation Sites
![Page 11: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/11.jpg)
11
Greenpoint Remediation SitesSince the initial 1978 investigation, remediation has occurred and is active at the following Sites in Greenpoint:
• ExxonMobil GPRP (1978 – Present)• BP Terminal (1980 - Present)• Former Paragon Oil Terminal (2005 - Present)• Apollo Street Creek Parcels (2009 - Present)
![Page 12: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/12.jpg)
12
![Page 13: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/13.jpg)
13
ExxonMobil GPRP
• 174 acres, 8 Operating Units (OUs)
• NYSDEC Project Manager: Ben Rung
![Page 14: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/14.jpg)
14
Former Paragon Oil Terminal & Apollo
Street Creek Parcels
• 16, 42, 50 Bridgewater St.; 100 – 120 Apollo St.
• NYSDEC Project Manager: Zac Russo
![Page 15: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/15.jpg)
15
BP Terminal
• 125 Apollo Street• 10 acre petroleum
bulk storage terminal
• NYSDEC Project Manager: Dave Lates
![Page 16: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/16.jpg)
1616
BP TerminalRemediation Update
![Page 17: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/17.jpg)
17
Brooklyn Terminal Operations
• Active petroleum bulk storage facility
• 12 tanks for a total of 5.9 million gallons of storage
![Page 18: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/18.jpg)
18
BP Terminal Order on Consent• Between 1986 and 1999, BP had petroleum releases
totaling 124,973 gallons. The releases were contained or deemed recovered by the remediation system.
• In 2006 BP signed a consent order with the NYSDEC agreeing to continue to remediate the historic contamination on their property:
“BP agrees to continue to operate this [recovery] system… until the liquid phase free product that is currently at the Site is removed to levels that do not represent a threat to human health or the environment…”
![Page 19: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/19.jpg)
19
Remediation Goals
• Protect Public Health & Safety• Recover Free Product• Prevent Seepage to Newtown Creek• Accelerate Soil Restoration• Accelerate Ground Water Restoration• Prevent Vapor Intrusion
![Page 20: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/20.jpg)
20
BP Terminal Remediation• Onsite management:
Antea Group• Remediation Summary: Product recovery Groundwater treatment and
discharge Vapor monitoring
![Page 21: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/21.jpg)
21
Product Recovery System
• 11 active product recovery wells
• Aboveground or subsurface vaults
• Dual phase wells pump both groundwater and free-product
![Page 22: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/22.jpg)
22
![Page 23: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/23.jpg)
23
Groundwater Treatment System
• SPDES Equivalency• Components: Oil/water separator Bag filters Air stripper Carbon column
![Page 24: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/24.jpg)
24
Vapor Monitoring
• Annual screening for methane across site
• Monthly indoor air sampling in occupied buildings.
![Page 25: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/25.jpg)
25
Remedial Milestones• 2012 Recovery wells RW-14 and MW-
24 added• 2013 Groundwater treatment system
• 2014 Recovery well rehabilitation study Air compressor system
• 2015 Interim wells OW-11 and MW-6
![Page 26: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/26.jpg)
26
050,000
100,000150,000200,000250,000300,000350,000400,000450,000500,000
1980 1985 1990 1995 2000 2005 2010 2015
Free-Product Recovery at BP Terminal
![Page 27: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/27.jpg)
27
Upcoming Projects
• Site Characterization Report
• Decision Document for Entire Site (all media)
![Page 28: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/28.jpg)
2828
Upcoming Property Transfer
February 1, 2016
![Page 29: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/29.jpg)
29
Sale of Brooklyn TerminalIn October 2015, BP entered into an asset sale agreement with Kinder Morgan.
Includes the transfer and sale of 15 storage terminal properties (including the Brooklyn Terminal) and the creation of a joint venture LLC: KM Phoenix Holdings LLC.
Transfer date is February 1, 2016.
![Page 30: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/30.jpg)
30
What Does This Mean For Remediation?• Consent Order amended to add Kinder Morgan
• New Project Manager:R.J. Sherman, P.G.Remediation ManagerKinder Morgan
• Antea Group will remain as the on-site consultant.
• Current operations and future goals remain consistent: progress will continue as planned.
![Page 31: BP Terminal – Greenpoint, NYnysdecgreenpoint.com/PublicFiles/BP Terminal 1-25-16 Presentation...Presentation at 7:00 PM followed by Q&A session. 3 Presentation Overview ... Standard](https://reader035.vdocuments.net/reader035/viewer/2022062908/5ac0e1fb7f8b9ae45b8cb5f4/html5/thumbnails/31.jpg)
31
Thank YouDavid LatesNYS Department of Environmental Conservation625 Broadway, 12th FloorAlbany, NY [email protected](518) 402-9819