BROOKLEIGH - A Redevelopment of Johnson Ferry East BROOKLEIGH A Redevelopmen t of Johnson Ferry East Brookleigh Community Update and Status Report February 7, 2012

Upload: kathleen-boettcher

Post on 13-Jan-2015

1.423 views

Category:

Business


3 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

BROOKLEIGH

A

Redevelopment of

Johnson Ferry

East

BrookleighCommunity Update

and Status Report

February 7, 2012

Page 2: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

BROOKLEIGH

A

Redevelopment of

Johnson Ferry

East

The Housing Authority of Dekalb County and its Master Development team, the NorSouth Companies and The Collaborative Firm, are redeveloping the former Johnson Ferry East public housing site into Brookleigh, a model mixed-use, mixed-income community of homes, shops and restaurants.

The concept for Brookleigh is a multi-generational community of neighborhoods centered around a park and a village of stores and restaurants, all built to sustainable standards and connected - with each other and surrounding neighborhoods – by sidewalks and a multipurpose PATH trail.

Page 3: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Review of Development to Date

Original Master Plan (April 2007)

i. 7 components of Mixed Use, Mixed-Income Residential and Commercial Development

ii. DRI (Development of Regional Impact) approval for 836 Housing Units in December 2006

Page 4: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Review of Development to Date

iii. Pc-2 Zoning Plan (approved March 2007)– 182 units for HearthSide Brookleigh– 71,250 s.f. of retail– 52 Townhome & Condo units over retail shops– 208 units of luxury apartments

iv. Tract C: Current zoning of RM- 75 (18 units/ac) planned for 130 Single Family and Townhomes. Zoning allows 220 apartment units

Page 5: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Master Plan

Page 6: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Page 7: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

PC-2 Approved Site Plan

Page 8: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Character Sketches for Proposed Development

Page 9: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Character Sketches for Proposed Development

Page 10: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Character Sketches for Proposed Development

Page 11: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

HearthSide Brookleigh121 units vs 170 on Previous Master Plan

(183 approved in PC-2 Zoning)

Page 12: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

HearthSide Brookleigh• Rents: 1 BR $680 - $750

2 BR/1 BA $760 - $850

2 BR/2 BA $790

• Opening Date – February 24, 2012

Page 13: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

HearthSide Brookleigh

Page 14: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Heights at Brookleigh203 units vs 208 approved in PC-2 Zoning

Page 15: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Revised Master Plan

• Incorporates changes in HearthSide Brookleigh & Heights at Brookleigh and maintains PC-2 zoning.

• Includes 54 fewer housing units of seniors apartments (HearthSide Brookleigh) and luxury apartments (Heights at Brookleigh) than original Master Plan.

Page 16: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Revised Master Plan

• Maintains plan for the Central Park, to be owned by Dekalb County and maintained by the Brookleigh Master Association.

– Phase I (landscaping & street lights) to be completed May 2012

– Phase II (hardscapes, interior sidewalks, gazebo) to be completed December 2012

Page 17: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Revised Master PlanCentral Park

Page 18: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Revised Master PlanTraffic Signalization – Completion July 2012

Page 19: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Revised Master Plan

• Maintains plan for PATH multipurpose trail

• No proposed changes (yet) to Retail/Residential development on Tract B

• No proposed changes (yet) to Tract G (Donaldson and Blair Circle)

Page 20: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Revised Master Plan

Page 21: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Ashton Woods (proposed subdivision)

• No zoning change required– 92 homes proposed vs 220+ apartments allowed

• Ashton Woods track record– Philosophy and Market Distinction– Current, similar development in metro Atlanta

Page 22: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Ashton Woods

• Why Brookleigh? Market perspective and expectations

• Detached single family in addition to 2 types of townhomes

Page 23: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Ashton Woods

Page 24: Brookleigh Community Meeting 2-7-12

BROOKLEIGH - A Redevelopment of Johnson Ferry East

Brookleigh Development Website

• Updates to proposed Master Plan

• Updates to projected Development Schedules

• Development Updates

• Future meeting announcements