Malaysia Airports 2 December 2011 Building a Bigger & Better

Upload: nguyendang

Post on 15-Mar-2018

225 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

Malaysia Airports 2 December 2011

Building a Bigger & Better

Page 2: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

2

45 million passenger terminal

RM3.6b – RM3.9b Built at lowest cost per passenger with aerobridges and enhanced passenger

3. Viability Intact AAA Rating (25 Nov 11)

1. World’s Largest Purpose-

2. Superior Facilities

Built Terminal for LCCs

convenience

Page 3: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

Building a Bigger & Better klia2

3

“…a common hindrance for the full utilization of terminal capacity at most airports is the availability of boarding gates. To mitigate this, 68 gates have been provided in the design even though industry standards dictate that only 55 gates would be sufficient to handle 30 million passengers. With these additional boarding gates and the anticipated future improvements in technology, this terminal will be able to cater for more than 30 million

passengers should the need arise.”

- Malaysia Airports Press Release, 30th August 2010 (Ground Breaking ceremony for klia2)

World’s Largest Purpose-Built Terminal for LCCs

Page 4: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

45 mppa

68 Gates & 8 remote

stands

257,000 m2

terminal size

Designed for future

growth

Fully automated

BHS

Building a Bigger & Better klia2

4

World’s Largest Purpose-Built Terminal for LCCs

Operational Date:

April 2013 + 6 months

Page 5: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

Building a Bigger & Better klia2

5

Regulatory

Airlines Airport

Public

Increase in scope due to additional requirements:

Superior Facilities

Page 6: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

6

Based on airlines requests:

• 45 million passenger capacity

• 68 contact stands & 8 remote stands

• Substantially enhanced comfort level

• Fully-automated BHS

• 4.0km runway with a 2.2km separation from Runway 2

• Provision for A380 operations

• Tune Hotel

• Air Transit Hotel

• Premium lounges

• AirAsia Head Office with apron access

• AirAsia staff multi level parking

• Hub for public transport for ERL, taxis, buses and in future, KTM

Building a Bigger & Better klia2

Others:

• Additional commercial area

• Public shopping mall

• Provisions for 4 hotels

• VIP lounge

• LEED Green Building Certification - Gold Award

World’s Largest Purpose-Built Terminal for LCCs Key Features of klia2

Based on regulatory requests:

• Total international passenger arrival and departure segregation

• No walking on apron

• New ATC Tower for Runway 3 and future Runway 4 and backup for existing Runway 2

Based on public requests:

• Aerobridges

Page 7: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

7

Departure & Arrival at Grade

Original Design

Current Design

Departure

Arrival

2 levels (2-storey)

3 levels (9-storey)

BHS

BHS

GSE area

Building a Bigger & Better klia2 Superior Facilities

Page 8: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

Building a Bigger & Better klia2

8

Increased klia2 Footprint Comparison: Original Design (2009) vs. Current Design (2011)

Original Design

Current Design

Superior Facilities

Page 9: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

Building a Bigger & Better klia2

9

Items Provisional (Feb’ 2009)

RM 2.0 Billion

Revised

RM 3.6 - 3.9 Billion

Increase in Scope (%)

1. Terminal Building GFA – 150,000 m2 GFA – 257,000 m2 71.3%

2. Aircraft Stands Area – 500,000 m2

50 semi contact stands

Area – 803,709 m2

68 gates & 8 remote stands (80 aerobridges)

60.7%

3. Earthworks Area – 4.85 mil m2 Area – 11.19 mil m2 130.7%

4. Runway 3, Taxiway Pavement & AGL System

Code C Length : 2.50 km, Width : 45 m

Code E Length : 3.96 km, Width : 60 m

64.7% (Area)

5. DCA Facilities Apron Control Tower

Height : 77 m Air Traffic Control Tower

Height : 93 m 20.8% (Height)

115.4% (Nav. Aids)

6. Public Infrastructure Length : 8 km

with 1.5 km elevated road Length : 15 km with

5.4 km elevated road 87.5%

260.0%

Major Upgrades in Specifications

Superior Facilities

Page 10: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

Building a Bigger & Better klia2

10

September 2011 April 2012 October 2012 April 2013

klia2 timeline

1. Design competition

2. Open Tender 3. More

packages

Decision for fully-automated BHS

1. More commercial space

2. Runway 3 extension

Superior Facilities

Page 11: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

Building a Bigger & Better klia2

11

August 2012 August 2012

October 2012 September 2012

April 2013

August 2012

September 2012

Superior Facilities

Page 12: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

Building a Bigger & Better klia2

12

• Continued growth in low cost travel

– 30 million passengers by 2017 and 40 million passengers by 2022

• Bringing forward future capex

• 55,000m2 commercial space

• Private sector projects

– Integrated complex

– Privatized hotels

– District cooling

• New South Support Zone

– MRO, hangar

– Cargo

• Additional advertising opportunities

• Royalties on service providers

• Long term car park

• Airline and other offices

• Catalyst for land development opportunities

AAA Rating Reaffirmed 25 Nov 11

Viability Intact : Enhanced Commercial Activities

Page 13: Building a Bigger & Better - KLIA - Malaysia Airports Holdings · PDF file · 2014-04-23th- Malaysia Airports Press Release, ... •AirAsia Head Office with apron access ... Comparison:

Building a Bigger & Better klia2

13

KLIA Overall Traffic - Actual & Forecast

-

10

20

30

40

50

60

70

80

90

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

Mill

ion

s

KUL TOTAL MTB LCCT / klia2 LCCT / klia2

45 million passengers

Opening of klia2

AirAsia Forecast (June 2011)

Passengers per annum

2015 28.7 million

2020 45.3 million

2025 60.3 million