bulding 245 schedule update liu booster meeting 07-11-2013 fulvio boattini te-epc teepc
TRANSCRIPT
Bulding 245 schedule update
LIU Booster Meeting 07-11-2013Fulvio Boattini
TE-EPC
TE EPC
Building 245 Position
07/11/2013 TE-EPC - Fulvio Boattini 2
TE EPC
France-Swiss border
Limit for edification
France
Switzerland
Building 245
07/11/2013 TE-EPC - Fulvio Boattini 3
TE EPC
Converter1 A (19t)
Converter1 B (8t) Trim1 (2t)
Converter2 A (19t)
Converter2 B (8t) Trim2 (2t)
Converter3 A (19t)
Converter3 B (8t) Trim3 (2t)
ACDC1
DCDC1
QPS1
Dum
myLo
ad
1
Dum
myLo
ad
2
Dum
myLo
ad
3
CAPS ROOM 1
90
0
2100
14
20
2000
CONVERTER HALL
MA
GN
ET T
ES
T
AR
EA
HVAC HALL
CAPS ROOM 2
CAPS ROOM 3
ACDC2
DCDC2
QPS2
ACDC3
DCDC3
QPS3
Stairs
Original Design With Booster CV integration
Building 245
07/11/2013 TE-EPC - Fulvio Boattini 4
TE EPC
Original Design With Booster CV integration
Need to find another place for Booster2GeV MPS transformers
Building 245
07/11/2013 TE-EPC - Fulvio Boattini 5
TE EPC
ACD
C1
DC
DC
1Q
PS1
DummyLoad 1
DummyLoad 2
DummyLoad 3
CAP
S R
OO
M 1
900
2 1 0 0
1420
2 0 0 0
CO
NVER
TER
HALL
MAGNET TEST AREA
HVA
C
HALL
CAP
S R
OO
M 2
CAP
S R
OO
M 3
ACD
C2
DC
DC
2Q
PS2
ACD
C3
DC
DC
3
QPS
3
S t a i r s
Booster2GeV transformers.Proposed position
Transformer MVCB station
~60mt
physics LS1 physics LS2 physics
2012 2013 2014 2015 2016 2017 2018 2019
May 2016Building ReadyNo ressources
Services Integration(EL, CV,..)
GS/SE studies and procurement
Building construction
Power converterDesign & specification
Market Survey& Call for tender
Power converterDesign
(supplier)
Power converterconstruction
Power converter
Installation and cold
commissioning
October 2013March 2014 March 2015
FC
August 2016June 2014FC
April 2017Start
Commissioning on dummy load
Power converter
commissioning on test
magnets
2 weeks System pre-commissioning on PSB magnets
2months System final-commissioning on PSB magnets
Power converter
commissioning on test
magnets
TE EPC
MPSB Time Schedule
Switching cabinets and cabling installation
physics LS1 physics LS2 physics
2012 2013 2014 2015 2016 2017 2018 2019
May 2016Building ReadyNo ressources
Services Integration(EL, CV,..)
GS/SE studies and procurement
Building construction
October 2013March 2014 March 2015
FC
April 2017Start
Commissioning on dummy load
TE EPC
MPSB Time Schedule
Switching cabinets and cabling installation
3D building model ready by the end of next week
EPC & CV generated a document for HSE feedback on safety issues for the building EDMS 1319960
EPC & CV & EL are working on a electrical requirements
EPC working on the switching cabinets and cabling installation EDMS 1312226
physics LS1 physics LS2 physics
2015 2016 2017 2018
May 2016Building ReadyBuilding
construction
Cooling installati
on
Air conditioning and cooling
pipes installation
LV cabinets installation.Lights and
other services
18kV cabinets
installation
Cooling and Conditioning operating
Lights and electrical cabinets installed
Overhead Crane installed
Fire alarm system
installation
Fire alarm system installation
April 2017Start
Commissioning on dummy load
Old to new MPS
switching cabinet
installation
TE EPC
MPSB Time Schedule
physics LS1 physics LS2 physics
2012 2013 2014 2015 2016 2017 2018 2019
May 2016Building ReadyNo ressources
Services Integration(EL, CV,..)
GS/SE studies and procurement
Building construction
Cooling installati
on
Air conditioning and cooling
pipes installation
October 2013 March 2014 March 2015
FCLV cabinets installation.Lights and
other services
18kV cabinets
installation
Cooling and Conditioning operating
Lights and electrical cabinets installed
Overhead Crane installed
Fire alarm system
installation
Fire alarm system installation
April 2017Start
Commissioning on dummy load
Old to new MPS
switching cabinet
installation
TE EPC
MPSB Time Schedule
TE-EPC - Serge Pittet, Fulvio Boattini 10
THANKS FOR THE ATTENTION
QUESTIONS?
Bulding 245 schedule update
TE EPC
13/09/2012