bulk earthworks civil engineering design report
TRANSCRIPT
Orange City Council
Bulk Earthworks Civil Engineering Design Report
F3113-16
Orange Regional Sporting Precinct at Jack Brabham Park
June 2021
© Copyright Barker Ryan Stewart Pty Ltd
2021 All Rights Reserved
Project No. 210090R02
Author Scott Brisbin
Checked
Approved Scott Brisbin
Rev No. Status Date Comments
1 For Review 04/06/2021 80% Preliminary Design
COPYRIGHT
Barker Ryan Stewart reserves all copyright of intellectual property in any or all of Barker Ryan Stewart’s documents. No permission,
licence or authority is granted by Barker Ryan Stewart to any person or organisation to use any of Barker Ryan Stewart’s documents
for any purpose without the written consent of Barker Ryan Stewart.
REPORT DISCLAIMER
This report has been prepared for the client identified in Section 1.0 only and cannot be relied on or used by any third party. Any
representation, statement, opinion or advice, expressed or implied in this report is made in good faith but on the basis that Barker
Ryan Stewart are not liable (whether by reason of negligence, lack of care or otherwise) to any person for any damage or loss
whatsoever which has occurred or may occur in relation to that person taking or not taking (as the case may be) action in any
respect of any representation, statement, or advice referred to above.
Table of Contents
1 Introduction ......................................................................................................................................................... 5
2 Project Start Up and Existing Site Description .................................................................................................. 6
2.1 Start Up Inspection and Meeting ............................................................................................................. 6
2.2 Existing Site Description .............................................................................................................................. 6
3 Scope of Bulk Earthworks ................................................................................................................................. 12
4 Detailed Site Survey .......................................................................................................................................... 13
5 Utilities Services .................................................................................................................................................. 14
5.1 Dial Before You Dig Information.............................................................................................................. 14
5.2 Communications (AARNet, APT, NBN, Optus and Telstra) .................................................................. 14
5.3 Essential Energy ......................................................................................................................................... 14
5.4 Jemena Gas .............................................................................................................................................. 14
5.5 Orange City Council (Water and Sewer) .............................................................................................. 14
5.6 Proposed Orange City Council Water and Sewer Works .................................................................... 15
5.7 Utility Potholing .......................................................................................................................................... 15
5.8 Summary of Services ................................................................................................................................ 15
6 Geotechnical Works ........................................................................................................................................ 16
6.1 Geotechnical and Pavement Investigation ......................................................................................... 16
6.2 Contamination Investigation .................................................................................................................. 16
7 Bulk Earthworks Design ..................................................................................................................................... 17
7.1 Bulk Earthworks Design ............................................................................................................................. 17
7.2 Maintenance Compound ....................................................................................................................... 18
7.3 Tree Removal ............................................................................................................................................ 18
7.4 Heritage ..................................................................................................................................................... 18
8 Items for Further Discussion/Consideration .................................................................................................... 19
List of Figures
Figure 1 – Plan view of site (via SixMaps) ................................................................................................................. 7
Figure 2 – Aerial image of site (via SixMaps) ........................................................................................................... 7
Figure 3 – Aerial image of site (via NearMap) ........................................................................................................ 8
Figure 4 – View looking north along former fairway parallel to Forest Road ...................................................... 8
Figure 5 – View looking south over former golf green toward Forest Road and Bloomfield heritage gates .. 9
Figure 6 – View looking east with proposed site on the right and existing Jack Brabham Park on the left .... 9
Figure 7 – Semi-formal channel through centre of site and path crossing ....................................................... 10
Figure 8 – View looking west from eastern portion of site .................................................................................... 10
Figure 9 – Maintenance compound at interface of proposed site and Jack Brabham Park ........................ 11
Figure 10 – Bloomfield heritage gates adjoining Forest Road ............................................................................ 11
Figure 11 – Extent of Topographical Survey .......................................................................................................... 13
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 4
List of Tables
Table 1 - Summary of Known Utility Services ......................................................................................................... 15
Table 2 – Bulk Earthworks Volume Summary ......................................................................................................... 17
Table 3 – Topsoil Volume Summary ........................................................................................................................ 17
Table 4 – Bulk Earthworks Volume Summary ......................................................................................................... 18
Appendix List
Appendix A - Site Masterplan
Appendix B – Detailed Site Survey
Appendix C – Geotechnical Report
Appendix D – Preliminary Contamination Report
Appendix E – Bloomfield Precinct Service Infrastructure Redevelopment
Appendix F – Bulk Earthworks Engineering Drawings
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 5
1 Introduction
Barker Ryan Stewart Pty Ltd (BRS) was engaged by Orange City Council (OCC) to prepare a preliminary
bulk earthworks (BEW) design for the proposed Orange Regional Sporting Precinct at Jack Brabham Park
(The Project). The site bulk earthworks will be undertaken ahead of the site’s main civil works package.
Design works have been carried out under Project Number F3113-16. The Project is funded by the NSW
State Government.
The site primarily comprises of a disused golf course with the former fairways and greens overcome with
weed and associated vegetation growth. A number of existing structures and site improvements remain
on the site. Existing sports fields and a maintenance compound are located to the north of the site.
The overall Project includes the following components:
a. Bulk earthworks ‘early works’ package;
b. Main stadium with grandstand and forecourt;
c. Athletics stadium with grandstand;
d. Car parking areas; and
e. Sporting fields for use by cricket, softball, summer football, athletics, rugby league, touch football
and other sports, and community events.
The site will be accessed via Forest Road and Huntley Road. The site is immediately adjacent to the
heritage listed ‘Bloomfield’ gates off Forest Road and the Bloomfield Health Service precinct.
A Masterplan for the site was prepared by Premise Consulting (‘Orange Sporting Precinct Masterplan – Sir
Jack Brabham Park’, Project Number 219058, Set 1F). A copy of the Masterplan is included in Appendix A
and was used to support a Tree Removal Development Application for the site that is currently under
assessment by Council.
The preliminary civil engineering design by BRS adopted the site Masterplan layout as adjusted through
discussions with NSW Heritage Council. The layout and finished surface levels proposed as part of the
main civil works package have been used to inform this bulk earthworks design.
This design report summarises the design approach and methodology for the preliminary bulk earthworks
design of The Project.
This report should be read in conjunction with the bulk earthworks drawings included in Appendix F.
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 6
2 Project Start Up and Existing Site Description
2.1 Start Up Inspection and Meeting
A site start-up meeting was held on site on 8 March 2021. The site inspection was undertaken during
daylight hours to observe existing site conditions, project opportunities and project constraints.
The inspection was attended by representatives from:
a. Public Works Advisory of NSW;
b. Barker Ryan Stewart.
Following the inspection, a project kick-off meeting was held in Council’s offices. This meeting was
attended by representatives from:
a. Orange City Council;
b. Public Works Advisory of NSW;
c. Premise Consultants;
d. Barker Ryan Stewart.
2.2 Existing Site Description
The proposed Orange Regional Sporting Precinct at Jack Brabham Park is located approximately 3km
south of the Orange town centre. The site is bound to the north by existing sports fields at Jack Brabham
Park, to the east by Huntley Road, to the south by Bloomfield Health Services and to the west by Forest
Road. The site is known as 1502 Forest Road, Orange and is legally defined as Lot 209 DP42900.
The site has an area of approximately 21.5ha and generally grades from south to north. The site comprises
of a disused golf course with the former fairways and greens overcome with weed and associated
vegetation growth. A number of site improvements remain on the site including structures, paths and
piped channel crossings.
The site includes a large number of trees that line the former fairways. The trees are a mixture of native and
exotic species.
Small dams exist upstream of the site and at the northern boundary of Jack Brabham Park. The dams are
linked by a semi-formal channel that flows north through the proposed site and existing Jack Brabham
Park. The semi-formal channel is not a mapped watercourse.
A number of local and trunk utility services traverse the site. These services primarily comprise of
communications and Council water and sewer assets. Other public utilities are located in the Forest Road
and Huntley Road verges.
Bloomfield Hospital heritage gates are located off Forest Road and form part of State Heritage Register
SHR: 01745. The gates provide access to Bloomfield Hospital and are located beyond the Sports Precinct
boundary.
The existing site is presented in Figure 1 to Figure 10.
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 7
Figure 1 – Plan view of site (via SixMaps)
Figure 2 – Aerial image of site (via SixMaps)
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 8
Figure 3 – Aerial image of site (via NearMap)
Figure 4 – View looking north along former fairway parallel to Forest Road
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 9
Figure 5 – View looking south over former golf green toward Forest Road and Bloomfield heritage gates
Figure 6 – View looking east with proposed site on the right and existing Jack Brabham Park on the left
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 10
Figure 7 – Semi-formal channel through centre of site and path crossing
Figure 8 – View looking west from eastern portion of site
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 11
Figure 9 – Maintenance compound at interface of proposed site and Jack Brabham Park
Figure 10 – Bloomfield heritage gates adjoining Forest Road
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 12
3 Scope of Bulk Earthworks
Bulk earthworks at the site are proposed to be undertaken ahead of the main civil works package.
The scope of works for the proposed bulk earthworks package broadly includes:
a. Removal of trees and vegetation;
b. Demolition of a disused structure and associated infrastructure near future Car Park 1;
c. Demolition of minor site improvements (piped channel crossing, etc) to facilitate bulk earthworks
operations;
d. Management of stormwater around and through the site as appropriate to suit the contractor’s
staging;
e. Adjustment of utility services that will be impacted by the bulk earthworks operations;
f. Relocation of site maintenance compound (if required);
g. Stripping and stockpiling of topsoil;
h. Bulk earthworks cutting, filling, compaction and testing operations;
i. Hydromulch stabilisation of the finished bulk earthworks surface.
The proposed bulk earthworks package does not include:
a. Permanent connections to existing public roads;
b. Construction of road and car park pavements, kerbs, wearing course, etc;
c. Adjustment to existing utility services that are not impacted by bulk earthworks operations;
d. Adjustment of retained utility service pits and surface fittings to suit revised site levels;
e. Installation of new utility infrastructure to service the future sports fields (ie electrical, comms,
water and sewer, etc);
f. Installation of stormwater drainage pits, pipes and culverts;
g. Construction of any structures, including grandstands;
h. Construction of athletics track;
i. Installation of sports field playing surface, including import of specialist growing medium and
amelioration/improvement of site won topsoil;
j. Spreading of topsoil.
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 13
4 Detailed Site Survey
Premise Consultants were engaged by Orange City Council to undertake a detailed topographical
survey of the site and the immediately surrounding area. The survey was undertaken in August 2020 is
presented over 6 sheets as part of Job Number 220366.
The survey was undertaken on MGA2020 co-ordinates with levels to AHD. A screen capture of the survey
extents is presented in the Figure below. A full copy of the survey is included in Appendix B.
Figure 11 – Extent of Topographical Survey
The Premise Consulting survey has been adopted as the site’s existing surface for the bulk earthworks
design.
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 14
5 Utilities Services
5.1 Dial Before You Dig Information
Dial Before You Dig (DB4YD) plans for the site were requested on 22 March 2021 (Job No 21303286). Utility
assets in the vicinity of the works were identified from the following authorities:
a. AARNet
b. APT Management Services
c. NBN Co
d. Optus
e. Telstra
f. Essential Energy
g. Jemena Gas
5.2 Communications (AARNet, APT, NBN, Optus and Telstra)
Significant copper and fibre optic communications assets exist in both the Forest Road and Huntley Road
verges. Communication assets are also located within the site parallel to Huntley Road. It is noted that
the existing maintenance compound does not appear to have an underground communications
service.
Assets located within the site parallel to Huntley Road will be partially located within future Car Park 3, 4
and 5. It is anticipated communications cabling will be retained and the communication pits will be
adjusted to suit proposed car park levels as part of the future main civil works package.
5.3 Essential Energy
Aerial HV, LV and street lighting assets exist along Forest Road and Huntley Road. Underground HV and
LV assets are located along Forest Road. Aerial assets are not expected to be impacted by the
proposed works.
Underground LV assets exist within the site to service a small building located within the footprint of future
Car Park 1 and the amenities building near future Car Park 5.
Any impacts to underground assets are expected to be limited to future car park connections to Forest
Road and Huntley Road. Any assets that will become redundant as a result of the bulk earthworks (such
as the one servicing the small building at future Car Park 1) will be capped and removed.
5.4 Jemena Gas
A network of DN110 210kPa gas mains exist along Forest Road and Huntley Road. No known gas assets
are present within the site.
Any impacts to existing gas assets are expected to be limited to future car park connections to Forest
Road and Huntley Road.
5.5 Orange City Council (Water and Sewer)
A utility services plan showing stormwater, potable water and sewer assets was provided by Orange City
Council. The plan showed:
a. Stormwater drainage assets to the north of Jack Brabham Park to drain the existing dam near
Huntley Road. Other stormwater assets did not appear to be present on the site.
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 15
b. Multiple potable water services traversing the site, generally in a north-south orientation. Assets
included DN200, DN250 and DN375 assets. Portions of these mains will need to be adjusted or
relocated to facilitate the proposed bulk earthworks.
c. A number of sewer assets traverse the site including a DN375 main that discharges north near the
centre of the site and a DN150/DN225 network that runs parallel to Huntley Road. Portions of the
sewer network will need to be adjusted or relocated to facilitate the proposed bulk earthworks.
It is understood that a feeder pipe from the Gosling Creek dam (located about 1.5km south-east of the
site) is located near the future athletics stadium and future Car Park No 3. It is understood that Council is
undertaking investigations as to the viability of utilising the Gosling Creek Feeder pipe as the primary
source of irrigation water for the proposed sporting fields.
5.6 Proposed Orange City Council Water and Sewer Works
It is understood that significant augmentation and adjustments are proposed to Council's water and
sewer assets on and adjoining the sports field site as part of Council’s Bloomfield Precinct service
infrastructure redevelopment. These adjustments and augmentation will relocate a large portion of
Council's assets away from the sports field site.
Timing of the proposed utility adjustment and augmentation works are yet to be confirmed. Following
further discussion with Council, the final utility adjustment strategy will be included on the 100% bulk
earthworks documents.
A copy of the proposed utility strategy is included in Appendix E.
5.7 Utility Potholing
Utility potholing to physically locate assets using non-destructive investigation techniques may be
undertaken as part of future design stages of the project, or as part of the bulk earthworks. Any
potholing works should be undertaken by accredited specialists.
5.8 Summary of Services
A summary of known services is presented in the table below.
Utility Service Information Source Assets Comment
Communications Dial Before You Dig, site
survey
AARNet, APT, NBN, Optus
and Tesltra - fibre and
copper network
Pit adjustment to suit
future car park works
Essential Energy Dial Before You Dig, site
survey
Aerial and underground
HV, LV, street lighting,
Zone Substation
Potentially impacted at
future car park access
points
Jemena Dial Before You Dig, site
survey
DN110 Potentially impacted at
future car park access
points
Water and Sewer Dial Before You Dig, site
survey, Council data
Potable water and sewer Adjustment and
relocations required to
suit bulk earthworks
Table 1 - Summary of Known Utility Services
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 16
6 Geotechnical Works
6.1 Geotechnical and Pavement Investigation
Macquarie Geotech was engaged by Orange City Council to undertake geotechnical site investigations
and reporting. Results are presented in the Macquarie Geotech report ‘Sporting Precinct – Geotechnical
Investigation, Report number B20292, Rev 02, dated 04/01/2021.
Pavement thickness recommendations for the future internal roads and car parks have been considered
in the bulk earthworks design.
A copy of the report is included in Appendix C.
6.2 Contamination Investigation
Envirowest Consulting was engaged by Orange City Council to undertake a preliminary contamination
investigation. Results are presented in the Enirowest Consulting report ‘Preliminary Contamination
Investigation - Proposed New Sporting Precinct, Forest Road, Orange’, Report number R12205C, Rev 0,
dated 21/9/2020.
A copy of the report is included in Appendix D.
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 17
7 Bulk Earthworks Design
7
7.1 Bulk Earthworks Design
A preliminary site earthworks model was prepared that considered the proposed site grading including:
a. Main fields with grandstands;
b. Main sports fields;
c. Car parks and internal access roads;
d. Adjoining regrade areas.
The earthworks model was prepared in 12D Model software (version 14) with the following assumptions:
a. Existing site surface per Premise Consultants detailed site survey (refer Section 4);
b. Average 150mm topsoil strip across the bulk earthworks footprint based upon the Macquarie
Geotech report (refer Section 6.1);
c. Site layout per BRS concept civil engineering drawing set 210090-01 Rev B;
d. Future finished site levels per BRS concept civil engineering drawing set 210090-01 Rev B;
e. Bulk earthworks levels a specific depth below the future finished surface level as summarised in
Table 2 below. Note BEW = bulk earthworks and FSL = finished surface level.
Location BEW Level
Below
Future FSL
Comment
a. Main League Field -300mm Allows for future import of growing medium
b. 8 Centre Fields and
Athletics Track
-250mm Allows for future placement of ameliorated/improved, site
won topsoil. Stripped topsoil to be stockpiled by BEW
contractor for improvement/placement by main civil
contractor.
c. Athletics Track -500mm Allows for future treatment/import to address reactive
subgrade
d. Car Park 1 and Roads -330mm Allows for future import of pavement materials
e. Car Park 2 N/A Retain existing
f. Car Park 3 and Roads -430mm Allows for future import of pavement materials
g. Car Park 4 and Roads -330mm Allows for future import of pavement materials
h. Car Park 5 and Roads N/A Nil BEW proposed. Undertake as part of main civil works
i. Areas other than those
listed above
-140mm Allows for placement of site won topsoil (typically on
mounds, batters, landscape areas, etc)
Table 2 – Bulk Earthworks Volume Summary
A summary of site topsoil volumes is presented below:
Topsoil Element Value
Strip Volume at 150mm Average Depth 30,800m³
Assumed Stockpile Dimensions (nom.) 110mL x 110mW x 2.5mH
Future Respread Volume by Main Civil
Contractor Over Item b and i Table 2
30,800m³
Table 3 – Topsoil Volume Summary
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 18
A summary of the site bulk earthworks volumes, excluding topsoil, is presented below.
Volume
Cut -116,275m³
Fill +116,287m³
Net -12m³ (export)
Table 4 – Bulk Earthworks Volume Summary
The above volumes are preliminary and make no allowance for:
a. Bulking factors;
b. Trench spoil;
c. Grandstand foundation spoil;
d. Unsuitable material.
7.2 Maintenance Compound
A maintenance compound that services the existing Jack Brabham Park is located between the proposed
sports fields and Jack Brabham Park. The compound currently has vehicle access from Huntley Road.
It is preferred to retain maintenance compound without adjustment or relocation. The current bulk
earthworks design shows an earth batter encroaching the fenced compound area. Further, the existing
vehicle access off Huntley Road is likely to require relocation to utilise part of future Car Park No 4.
Impacts to the maintenance compound can not be avoided without installation of a retaining wall about
3m high, or adjustment to the future sports field layout and/or runoff areas.
If the maintenance compound is to be relocated, consideration is required to the timing of the relocation
and if this is undertaken by Council ahead of the bulk earthworks operations, or if its relocation is included
in the bulk earthworks contract.
7.3 Tree Removal
The site includes a large number of trees that line the former fairways. The trees are a mixture of native and
exotic species.
The site Masterplan included in Appendix A included tree removal drawings that were used as part of a
Tree Removal Development Application that is currently under assessment by Council. Trees that are
proposed for removal as part of the Development Application have been duplicated on Sheet 102 and
102 in the bulk earthworks drawing set included in Appendix F.
7.4 Heritage
Bloomfield Hospital heritage gates are located off Forest Road and form part of State Heritage Register
SHR: 01745. The gates provide access to Bloomfield Hospital and are located beyond the Sports Precinct
boundary.
The Bloomfield gates and adjoining heritage precinct that form part of SHR: 01745 are not expected to be
impacted by the proposed bulk earthworks.
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
Page 19
8 Items for Further Discussion/Consideration
The engineering drawings included in Appendix F present a 80% complete concept design for the bulk
earthworks design of the project. The list below presents a summary of items that require further discussion
and consideration as part of the next stage of the design:
a. Further adjustment and refinement to the bulk earthworks design to accommodate the design
development of the main civil works package.
b. Further consideration to relocation of existing maintenance compound or adjustment to suit layout
(fields, runoff, retaining walls etc).
c. Confirmation of timing of Bloomfield Precinct service infrastructure redevelopment.
d. Finalisation of utility adjustments to be undertaken as part of the bulk earthworks package, following
completion of Item c above.
e. Consideration to timing of potholing of utility services.
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
APPENDIX A
Site Masterplan
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
APPENDIX B
Detailed Site Survey
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
APPENDIX C
Geotechnical Report
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
APPENDIX D
Preliminary Contamination Report
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
APPENDIX E
Bloomfield Precinct Service Infrastructure Redevelopment
210090 – Orange Regional Sporting Precinct Bulk Earthworks Design Report
APPENDIX F
Bulk Earthworks Engineering Drawings