bwssb presentation - water supply realities
DESCRIPTION
Presentation made by BWSSB in the Water Workshop for Apartment Communities, organized on Dec-6, 2009 by ApartmentADDA.comTRANSCRIPT
Water Supply Scenario in Water Supply Scenario in BangaloreBangalore
- A presentation by BWSSB - A presentation by BWSSB
Presented in Water Workshop organized by Presented in Water Workshop organized by ApartmentADDA.comApartmentADDA.com
Dec-6 2009Dec-6 2009
Bangalore Water Supply and Bangalore Water Supply and Sewerage BoardSewerage Board
A statutory organization set up in 1964 under the BWSSB Act whose core functions & responsibilities include :
Providing water supply & sewerage network and sewage disposal systems
Ensuring sufficient of domestic water supply to the required standards.
Levying & collecting water/sanitation charges on a no loss/no profit basis.
BWSSB’s jurisdiction covers the Bangalore Metropolitan Area (1306 Sq. Kms out of which 455 Sq.Km is Green Belt)
BMRDA area is 8005 Sq. Kms.
Population as per 2001 Censes : 53,79,000
Population as on 2005 (As per BDA) : 62,95,000
Population as on 2025 : 94,28,000
(Projected using Graphical Method)
Population as per 2001 Censes : 53,79,000
Population as on 2005 (As per BDA) : 62,95,000
Population as on 2025 : 94,28,000
(Projected using Graphical Method)
Sl. Sl. No.No. BoundariesBoundaries Sq. Sq.
Km.Km.
11 BMABMA 12751275
22 CDPCDP 594594
33Core Area Sewerage Catchments Core Area Sewerage Catchments
(BMP Area)(BMP Area) 229229
44Peripheral Drainage Zones (8 Nos) Peripheral Drainage Zones (8 Nos) a)a) CMCCMC’’s, TMC Area - 248 Sq.Kms, TMC Area - 248 Sq.Kmb)b) Village Panchayaths Village Panchayaths –– 117 Sq.Km 117 Sq.Km
365365
Area :Area :
Bangalore Area and Bangalore Area and PopulationPopulation
Bangalore Area and Bangalore Area and PopulationPopulation
Source of Water SupplySource of Water Supply
PLAN SHOWING
THREE SOURCES
OF WATER SUPPLY
TO BANGALORE
CITY
WATER RESOURCES TO BANGALORE CITY
HESSARGHATA
CHAMRAJA SAGAR
CAUVERY WATER
PLANT
About Bangalore water About Bangalore water supplysupply
1890-19001890-1900 1896- Hesargatta WSS – untreated 1896- Hesargatta WSS – untreated waterwater
1900-19301900-1930 Hesargatta – Combined jewel filtersHesargatta – Combined jewel filters
1930-19401930-1940 T G Halli Arkavathi WSS-27 MLD T G Halli Arkavathi WSS-27 MLD
1950-19601950-1960 1952-T G Halli – 45 MLD added1952-T G Halli – 45 MLD added
1960-19701960-1970 1964 – T G Halli – 135 MLD 1964 – T G Halli – 135 MLD
1970-19801970-1980 1974 – CWSS I Stage – 135 MLD 1974 – CWSS I Stage – 135 MLD
1980-19901980-1990 1882- CWSS Stage II – 135 MLD 1882- CWSS Stage II – 135 MLD
1990-20001990-2000 1993- CWSS Stage III – 270 MLD 1993- CWSS Stage III – 270 MLD
2000-20102000-2010
2010-20202010-20202002 – CWSS Stage IV phase I -270 2002 – CWSS Stage IV phase I -270 MLD MLD
Proposed CWSS Stage IV Phase II – 500 Proposed CWSS Stage IV Phase II – 500 MLD MLD
Hessarghatta LakeHessarghatta Lake
Built in 1896
Chamaraja Sagar Reservoir
Built in 1933
Water Treatment Plant at Water Treatment Plant at T.G.HalliT.G.Halli
Built in 1933
Present Water SupplyPresent Water Supply
ProjectsProjects Year of Year of commissioningcommissioning
Installed Installed Capacity Capacity
(MLD)(MLD)
Present Present Supply Supply (MLD)(MLD)
Arkavathy (TG Halli)Arkavathy (TG Halli) 19331933 149149 6060
Cauvery Stage ICauvery Stage I 19741974 135135 135135
Cauvery Stage IICauvery Stage II 19831983 135135 135135
Cauvery Stage IIICauvery Stage III 19931993 270270 300300
Cauvery Stage IV, Cauvery Stage IV, Phase – IPhase – I 20022002 270270 270270
Total SupplyTotal Supply 959959 900900
CAUVERY RIVER - SHIVA ANICUT
WATER RESOURCES TO BANGALORE CITY
Intake Gate at NBR
Filter House at T.K.Halli
Pump House at T.K.Halli
CWSS - III Stage Pump House
Pipe Lines
Present Water Supply Scenario
Service Area Service Area : 800.29 SqKm : 800.29 SqKm
Population as on 2008 Population as on 2008 : 7.5Million : 7.5Million
Present Demand Present Demand : 1125 MLD: 1125 MLD
Present Supply Present Supply : 900 MLD: 900 MLD
The Per Capita Supply The Per Capita Supply : 110 to 120 ltrs: 110 to 120 ltrs
Water allocation from Cauvery : 19 TMCWater allocation from Cauvery : 19 TMC
Already utilised : 12 TMCAlready utilised : 12 TMC
Complete utilisation by : 2012-13Complete utilisation by : 2012-13
ALTERNATIVE SOURSES
• Recycle and reuse of wastewater for non potable uses
• Dual piping system in all new layouts
• Rain water harvesting
• Restoration of lakes to improve ground water table
City Distribution System:
• The city has about 5638 kms of distribution network ranging from 50 mm to 600 mm dia.
• Rechlorination is done at city reservoirs to maintain residual chlorine of 0.2ppm at consumer end.
• Chlorine plants installed in the city - 46 Nos
City Distribution System:
• The city has about 5638 kms of distribution network ranging from 50 mm to 600 mm dia.
• Rechlorination is done at city reservoirs to maintain residual chlorine of 0.2ppm at consumer end.
• Chlorine plants installed in the city - 46 Nos
WATER QUALITY MANAGEMENTWATER QUALITY MANAGEMENT
• Testing physical, chemical and bacteriological Testing physical, chemical and bacteriological parameters of raw water and treated water at parameters of raw water and treated water at treatment plants.treatment plants.
• Testing samples from distribution system in the Testing samples from distribution system in the city.city.
• More than 60 water samples are collected More than 60 water samples are collected every day from the distribution system and every day from the distribution system and tested.tested.
• Two mobile labs with portable testing kit collect Two mobile labs with portable testing kit collect samples from the city distribution system every samples from the city distribution system every day.day.
Customer friendly initiativesCustomer friendly initiatives– Advanced Interactive Voice Response Advanced Interactive Voice Response
System for booking complaints is functional.System for booking complaints is functional.(155313)(155313)
– Electronic Clearance System is introduced.Electronic Clearance System is introduced.
– Customer Charter launched.Customer Charter launched.
– e-Tenderinge-Tendering
– Informative Website in position.Informative Website in position.(www.bwssb.org)(www.bwssb.org)
Customer friendly initiatives
Total No. of KIOSK installed – 74 Nos
24x7 multi-utility fully automated Water bill payment KIOSK KaverEcom - with facilities for collecting cash, cheques and DDs is in operaton.
KaverEcom
Customer friendly initiatives
GEOGRAPHICAL INFORMATION GEOGRAPHICAL INFORMATION SYSTEM (GIS)SYSTEM (GIS)
• All the information of water and All the information of water and sewerage pipeline network, and all sewerage pipeline network, and all other assets of BWSSB has been other assets of BWSSB has been incorporated in GIS.incorporated in GIS.
• It is going to become a major tool It is going to become a major tool for the management of the entire for the management of the entire water supply and sanitation water supply and sanitation system, including revenue billing. system, including revenue billing.
SERVICE TO URBAN POORSERVICE TO URBAN POOR
• 10% of the urban population are living in 10% of the urban population are living in slumsslums
• Water for these slums is supplied through Water for these slums is supplied through public taps free of costpublic taps free of cost
• Few slums are provided with individual Few slums are provided with individual connections which are exempted from access connections which are exempted from access charges except for Rs. 550 towards meter charges except for Rs. 550 towards meter costcost
• The lowest tariff adopted is Rs.6/KL The lowest tariff adopted is Rs.6/KL
Initiatives 1. Unaccounted for water – Pilot project
completed in central part of Bangalore.
2. Setting of Recycling and Reuse of Waste water for potable purpose.
3. Rain water harvesting to meet demand in domestic and industrial buildings.
4. Dual pipe supply of Potable and Non-Potable water in New layouts.
Improving AccountabilityImproving Accountability
• Installation of bulk flow meters on Installation of bulk flow meters on feeder mains in the city feeder mains in the city
• Hand held terminals for spot meter Hand held terminals for spot meter readingreading
• Installation of SCADA to all the main Installation of SCADA to all the main valves, controlling point at Cauvery valves, controlling point at Cauvery BhavanBhavan
Future Water SupplyFuture Water Supply
Projected Population by 2011 : 7.34 MILLIONFuture Demand : 1576 MLDPresent Supply : 900 MLDDeficit : 676 MLD
Proposals:
Augmentation in Phase I : 100 MLDPhase – II Project : 500 MLDTotal Supply After Phase-II Project : 1500 MLD
Augmenting Water Supply to Bangalore City by 270 Million Liters Per Day
Project Started during January 1997
Water Components Commissioned during July 2002
Sewerage Components Completed Except 0.90 Kms Trunk Sewer Works out of 54 Km – completion by September 2006
Expenditure as on MAY 2006 – Rs. 1332.07 Crores
Augmenting Water Supply to Bangalore City by 270 Million Liters Per Day
Project Started during January 1997
Water Components Commissioned during July 2002
Sewerage Components Completed Except 0.90 Kms Trunk Sewer Works out of 54 Km – completion by September 2006
Expenditure as on MAY 2006 – Rs. 1332.07 Crores
Cauvery Stage – IV Phase - 1Cauvery Stage – IV Phase - 1
Bangalore Water Supply & Sewerage Project Stage – IV, Phase – II
Bangalore Water Supply & Sewerage Project Stage – IV, Phase – II
Objective of the Project is to Augment Water Supply by 500 MLD
To provide Sewerage System & Treatment Facility in the peripheral areas of Bangalore city
Distribution improvement (UFW)
Slum development, e-governance and HRD
Objective of the Project is to Augment Water Supply by 500 MLD
To provide Sewerage System & Treatment Facility in the peripheral areas of Bangalore city
Distribution improvement (UFW)
Slum development, e-governance and HRD
Cost Rs. 1759 Crores
Implementation period from 2005 – 06 to 2011 – 2012
Raw Water Transmission : 6.2 km – 2600 mm & 9.6 km – 2200 mm
Water Treatment Plant (WTP) of 500 Mld
Clear Water Pumping Stations : 3 Stages of 14 nos. each to pump 500 Mld of water
Clear water transmission system : WTP to City about 68 Kms - 2700 mm
Trunk mains to ground level service reservoirs in city 115 kms
Supervisory control and data acquisition system (SCADA)
Cost Rs. 1759 Crores
Implementation period from 2005 – 06 to 2011 – 2012
Raw Water Transmission : 6.2 km – 2600 mm & 9.6 km – 2200 mm
Water Treatment Plant (WTP) of 500 Mld
Clear Water Pumping Stations : 3 Stages of 14 nos. each to pump 500 Mld of water
Clear water transmission system : WTP to City about 68 Kms - 2700 mm
Trunk mains to ground level service reservoirs in city 115 kms
Supervisory control and data acquisition system (SCADA)
Water Supply ComponentWater Supply Component
Bangalore Water Supply & Sewerage Project Stage – IV, Phase – II
Bangalore Water Supply & Sewerage Project Stage – IV, Phase – II
Total Estimated Cost of Project
ItemsItems Amount (Rs. Crores)Amount (Rs. Crores)
Water Supply ComponentWater Supply Component 14151415
Sewerage ComponentSewerage Component 667667
Distribution Improvement ComponentDistribution Improvement Component 249249
Management ImprovementManagement Improvement 2525
Slum DevelopmentSlum Development 4949
Price EscalationPrice Escalation 184184
Physical ContingenciesPhysical Contingencies 123123
Interest During ConstructionInterest During Construction 119119
Sub-Total – JBIC Financed PortionSub-Total – JBIC Financed Portion 28312831
Land AcquisitionLand Acquisition 6161
AdministrationAdministration 202202
Taxes and DutiesTaxes and Duties 290290
Total Project CostTotal Project Cost 33843384
Funding For the Phase-2 Project
Total Estimated Cost of the Project – Rs.3384 Crores
JBIC Portion – Rs. 2831 Crores
BWSSB/GoK Portion – Rs. 553 Crores
Bangalore SanitationBangalore Sanitation
Bangalore is blessed with undulated terrain having natural gradient
Wastewater generated flows out of the city in all the four directions
Wastewater generated is collected and conveyed through the sewerage network to the treatment plants for treatment up to Secondary level and disposed to the natural course
BWSSB has setup 12 treatment plants of secondary level of various capacities all-round the city – 718 MLD Capacity
Two Tertiary treatment plants of total capacity 70 MLD has been established and treated water is reused for non potable purposes
About Bangalore sanitary About Bangalore sanitary systemsystem
1920-1920-19501950
Sewerage system existedSewerage system existed
1950-1950-19601960
Major sewerage system constructedMajor sewerage system constructed
1970-1970-19801980
K & C Valley wastewater treatment K & C Valley wastewater treatment plant ( Primary) & V- Valley STP plant ( Primary) & V- Valley STP (Primary)(Primary)
1980-1980-20002000
K & C and V Valley and Hebbal K & C and V Valley and Hebbal upgraded to secondary upgraded to secondary
2000-2000-20102010
CWSS Stage IV Phase I – 7 treatment CWSS Stage IV Phase I – 7 treatment plants & sewerage systemplants & sewerage system
Core Area Sewerage Net work
Major Valleys1 – K & C Valley2 – V Valley3 – Hebbal Valley
#
#
#
%
%
%
%
%
Hebbal Valley
Arkavathi Valley
Vrishbhavathi Valley
Challaghatta Valley
Koramangala Valley
Tavarakere Valley
Katriguppe Valley
Hebbal Minor Valley-1 Hebbal
Minor Valley-2
Agaram SPS
V-Valley STP
Madivala Mini-STP
K&C Valley STPKempambudhi
Mini-STP
Hebbal Valley STP
(38)
(36)
(35)
Area in Sq.Km. (32)
(31)
(19)(16)
(6)
(11)(5)
K-MinorValley
To Mailasandra STP
To Raja CanalSTP
Bellandur Lake
$
Major and Minor Major and Minor ValleysValleys
Area in Sq Area in Sq KmsKms
HebbalHebbal 4848
ChallaghattaChallaghatta 3636
KoramangalaKoramangala 3737
TaverekereTaverekere 1919
KathariguppeKathariguppe 1616
VrishabhavathiVrishabhavathi 3838
ArkavathiArkavathi 3535
TotalTotal 229229
Abstract of sewer statistics Abstract of sewer statistics >400mm>400mmCore AreaCore Area
ZonesZones Total Length Total Length in Km in Km
Existing Existing inside SWD inside SWD
in Kmin Km
No of No of manholes in manholes in
NosNos
HebbalHebbal 4545 99 16501650
K&CK&C 113113 3535 28572857
V ValleyV Valley 8585 1818 17461746
TotalTotal 243243 6262 62536253
Sewers less than 400 mm dia
Length – 3367 KMs
Number of Manholes – 1,21,364
Locations of existing STP`sLocations of existing STP`s
Yelahanka TTP
Jakkur STP
Hebbal STP
KR Puram STP
Kadabeesanahalli STP
K & C Valley STP
Madiwala STP
Kempambudhi STP
Mylasandra STP
V Valley STP & TTP
Nagasandra STP
Rajacanal STP
Wastewater Treatment Plants Wastewater Treatment Plants
Sl. Sl. No.No. LocationLocation
CapacitCapacity in y in MLDMLD
Treatment FacilityTreatment Facility
Under CWSS I, II, III stagesUnder CWSS I, II, III stages
1.1. Vrishabhavathi Vrishabhavathi ValleyValley 180180 Secondary – Trickling Secondary – Trickling
filters filters
2.2. K & C Valley IK & C Valley I 163163 Secondary: Activated Secondary: Activated sludge process sludge process
3.3. Hebbal ValleyHebbal Valley 6060 Secondary: Activated Secondary: Activated sludge process sludge process
4.4. MadivalaMadivala 0404Secondary: UASB + Secondary: UASB + oxidation ponds+ oxidation ponds+ constructed wetlandsconstructed wetlands
5.5. KempambudhiKempambudhi 0101 Secondary: extended Secondary: extended Aeration Aeration
6.6. YelahankaYelahanka 1010Activated sludge process Activated sludge process + filtration+ chlorination + filtration+ chlorination (Tertiary)(Tertiary)
Wastewater Treatment PlantsWastewater Treatment Plants
Sl. No.Sl. No. LocationLocationCapacity Capacity
in MLDin MLDTreatment FacilityTreatment Facility
1.1. MylasandraMylasandra 7575 Secondary – Extended Secondary – Extended aerationaeration
2.2. NagasandraNagasandra 2020Secondary -Extended Secondary -Extended aerationaeration
3.3. JakkurJakkur 1010 Secondary – UASB +Extended Secondary – UASB +Extended aerationaeration
4.4. K. R. PuramK. R. Puram 2020 Secondary – UASB +Extended Secondary – UASB +Extended aerationaeration
5.5. KadabeesanahalliKadabeesanahalli 5050Secondary-Extended aerationSecondary-Extended aeration
6.6. K & C Valley IIK & C Valley II 3030Secondary - Extended Secondary - Extended aerationaeration
7.7. K & C Valley IIIK & C Valley III 5555 Secondary – CMASSecondary – CMAS
8.8. RajacanalRajacanal 4040Secondary- Extended Secondary- Extended aerationaeration
Grand TotalGrand Total 718718Note : V. Valley 60 MLD Tertiary treatment plant is fed by 180 MLD STP
Under CWSS Stage IV Phase IUnder CWSS Stage IV Phase I
Wastewater Treatment PlantsWastewater Treatment Plants
Raw sewage characteristics
Raw sewage BOD : Average 350 mg/lit
Raw sewage suspended solids: Average 400-500 mg/lit
Treated effluent standards ( Secondary)
Treated effluent BOD : < 20 mg/lit
Treated effluent suspended solids : < 30 mg/lit
Tertiary standardsTreated effluent BOD : < 5 mg/lit Treated effluent suspended solids : < 5 mg/lit
Coliforms : < 2.2/100ml
– – Diffused Aeration SystemDiffused Aeration System
– – Diffused Aeration SystemDiffused Aeration System
– – Diffused Aeration SystemDiffused Aeration System
– – Effluent qualityEffluent quality
– – Effluent QualityEffluent Quality
Effluent Quality
V. Valley Sewage treatment Plant - Recycling Plant
V. Valley Sewage treatment Plant - Recycling Plant
V. Valley Sewage treatment Plant - Recycling Plant
VIEW OF V. VALLEY TERTIARY TREATMENT PLANT
YELAHANKA Tertiary Treatment plant (Conventional ASP followed with filtration by
Chlorination)
WATER SUPPLY TO APARTMENTS• Housing complexes having more than 50 apartment ,
_ Dual piping system is mandatory
_ STP is mandatory
_ RWH is mandatory
• GBWAS Charges in CMC areas,
_ 0 to 600 Sft-----Rs.4000/-
_ 600 to 1200 -----Rs. 8000/-
_ 1200 to 2400 -----Rs.16000/-
_ 2400 and above ---- Rs.24000/-
• Prorata charges ---- Rs.200/- Sft
Rain Water Harvesting
•Mandatory for all existing buildings on
40 X 60
•Mandatory for all new buildings on
30 X 40 and above
Population in BBMP Area
YearYear PopulatioPopulation in Lakhsn in Lakhs
Water Water Demand Demand in MLDin MLD
Water Water supply supply in MLDin MLD
Short Short fall in fall in MLDMLD
20012001 53.7953.79 870870 540540 330330
20072007 75.0075.00 12191219 870870 349349
20152015 88.0088.00 17201720 14701470 250250
20212021 100.00100.00 21252125 14701470 655655
20362036 125.00125.00 25502550 14701470 10801080