Cabazon Elementary School Construction Schedule Activity Description MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL Off-Site Utilities & Street Work On-Site Rough & Finish Grading Building A, Classrooms Building B, Administive Offices & Cafateria Building C, Library Relocatable Classrooms & Restroom Buildings Parking Lot Lighting, Pavement & Signage Landscape & Irrigation Work SUB-TOTAL BASED ON ORIGINAL CONTRACT 243 DAYS TIME EXTENTION DUE TO CHANGES IN SCOPE OF WORK 109 DAYS TOTAL DURATION 352 DAYS 2000 2001

Upload: jon-zuber

Post on 16-Aug-2015

23 views

Category:

Documents


0 download

TRANSCRIPT

Cabazon Elementary School Construction ScheduleActivity Description MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL

Off-Site Utilities & Street Work

On-Site Rough & Finish Grading

Building A, Classrooms

Building B, Administive Offices & Cafateria

Building C, Library

Relocatable Classrooms & Restroom Buildings

Parking Lot Lighting, Pavement & Signage

Landscape & Irrigation Work

SUB-TOTAL BASED ON ORIGINAL CONTRACT 243 DAYS

TIME EXTENTION DUE TO CHANGES IN SCOPE OF WORK 109 DAYS

TOTAL DURATION 352 DAYS

2000 2001