cable rehabilitation at oncor
DESCRIPTION
Cable Rehabilitation at Oncor. by Richie Harp – Distribution Standards Data provided by Mark Darilek – Maintenance Planning. SWEDE 2009 – Tulsa, OK – Thursday, May 7, 2009. Cable Rehabilitation Overview. Rehabilitated cable Cable repairs to facilitate future rehabilitation - PowerPoint PPT PresentationTRANSCRIPT
Cable Rehabilitation at Oncorby Richie Harp – Distribution StandardsData provided by Mark Darilek – Maintenance Planning
SWEDE 2009 – Tulsa, OK – Thursday, May 7, 2009
Cable Rehabilitation Overview
Rehabilitated cable
Cable repairs to facilitate future rehabilitation
Oncor requirements for rehabilitation
Further considerations
2nd Responder process
Another technology
Amount of Rehabilitated Cable
Began in 1995
420 cbl-mi rehabilitated
8,000 cbl-mi in service – Pre-1993 cable
22,000 cbl-mi total cable
Amount of Rehabilitated Cable
URD
Cable size – Less than #4/0 AWG(#2 and #1/0 AWG, and minimalamount of #2/0 AWG)
Began in 1995
405 cbl-mi rehabilitated
17,000 cbl-mi in service
2% of URD cables
Amount of Rehabilitated Cable
Feeder
Cable size – #4/0 AWG and larger (up to 1000 kcmil)
Began in 2008
15 cbl-mi rehabilitated
3,400 cbl-mi in service
0.4% of feeder cable
Cable Repairs
Standard cable (Began purchasing in 1990)
#1/0 Al 19-Strands
Strand-filled conductors
25 kV, 260-mil TRXLPE
16-#14 AWG Concentric Neutral Wires (Full neutral)
Jacketed
Cable Repairs (Cont)
Only for cable repairs (2-ft pieces) for future injection
#1/0 Al 19-Strands
Strands not filled
25 kV, 260-mil TRXLPE
8-#14 AWG concentric neutral wires(1/2 neutral)
Unjacketed
On 1000-ft composite reel
Oncor Requirements for Rehabilitation
Do not rehabilitate:
Cable installed in conduit
175-mil or 220-mil cable operating at 14.4 kV
Butyl rubber cable
Cable with tape conductor shield
Corroded concentric neutral
Do not rehabilitate cable if…
Corroded center conductor
Loss of insulation shield conductivity
Insulation shield with no adhesion
Failures due to dig-ins or debris in trench
There is a chance the cable will be converted to 14.4 kV in the future
Oncor Requirements for Rehabilitation (cont)
Other Requirements
There must be more than 25% concentric neutral remaining.
There cannot be more that one joint per 100 feet of cable.
The faulted cable section must not have been de-energized more than six months.
Comments:
We tried to rehabilitate some open loops that had been de-energized for up to 2 years
Very little success
We quit rehabilitating open loops that had been de-energized for more than 6 months.
More comments:
2006 and 2007 Processes
Left URD loops open after failures (direct buried cables)
Only repaired cable to get customers’ lights back on.
More comments:
Dec 2007 Process
Began repairing failed loops again.
Caught up with open loops (Feb 2009)
–Inject cables or
–Replace cable if not able to inject
More comments:
Dec 2008 Process Change
Install joint to repair cable
Try to inject the cable
After the repair, if the cable is not able to be injected, then just leave energized.
Defer replacement of the cable until the next fault.
2nd Responder Process
System-Wide Process
Repair failures on direct buried cable (not in conduit)
Must be able to switch around to get lights back on.
Not normally feeder exits (Only non-critical cables)
2nd Responder Decision Process Flow Chart
Available by request
2nd Responder Process
1868 sections of failed cables came through the process since 2008
749 sections of cable were injected
1119 sections were not able to be injected
922 due to process requirements
197 not related to the process (already energized when arrived, in conduit, etc.)
2nd Responder Process – Injected/Not Injected
922
749 Injected
Non-Injected
2nd Responder Process
12 cause codes for not being able to inject the 1119 sections of cable
Age of fault (> 6 months)
Could not flow (Blocked strands or joints)
Inaccessible fault or joint location
Deteriorated neutral (< 25% remaining)
Previously injected, non-warranty or other
Previously injected, warranty
2nd Responder Process
12 cause codes for not being able to inject the cable (Cont)
Corroded conductor
Number of joints (> than 1 joint per 100 ft)
Unknown
Cable is in conduit
Already energized upon arrival
Other
–These last three represent the 197.
2nd Responder Process – Causes
11%
11%
20%
16%
5%
18%
1%
3%
1%
2%
4%8%
Age of fault
Could not flow
Inaccessible fault or joint
Deteriorated neutral
Number of splices
Previously injected, non-warrantyPreviously injected,warrantyCorroded conductor
Unknown
Cable in conduit
Energized upon arrival
Other
Another technology
Different formulations for injection fluid
Formulation tailored to operating environment
Tailored more for feeder cables with higher operating temperatures (»45°C)
No soak tanks required
Put back into service immediately after injection
Another technology (Cont)
Must replace all joints
Higher pressures for injection