cadarache: a site for iter

14
J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 2001 1 Euratom Cadarache: a Site for ITER

Upload: others

Post on 03-Feb-2022

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 20011

Euratom

Cadarache:a Site for ITER

Page 2: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 20012

Euratom

Lay out

• ITER: the right step to be started during the 6th

European Research Programme (FP6, 2002-2006)– Consensus both at the scientific and political level

• Cadarache: well equipped with both fusion and fission nuclear installations

• European site studies– First phase recently completed

• Summary

Page 3: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 20013

Euratom

Existing infrastructure• CEA (16000persons)

– Complete range of fundamental and applied research

• Cadarache nuclear Centre (4000persons)– 18 nuclear installations– Strong base for fusion science with TORE-SUPRA

(Exp, theory, technology), participation to JET, ITER technologies

• Provence– Strong growth area with heavy industry, high tech and

universities– Wonderful socially

Page 4: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 20014

Euratom

TORE SUPRAThe largest Tokamak with superconductors

Page 5: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 20015

Euratom

TORE SUPRAback into operation in the CIEL configuration

Page 6: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 20016

Euratom

Socio-economic Infrastructure

• In the heart of Provence

Marseille, 800 000 p, 40’ to Cadarache

Aix, 134 000 p, 30’

University, festival, hospitals

Manosque, Pertuis, 20 000 p, 10’

• Network of Motorways

• High speed train TGV since June 2001

• Airport (Marseille-Provence, 40’)

Page 7: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 20017

Euratom

European ITER Site Studies (EISS)• EISS (2001, 5 M€)

– Technical assessment (seismic, electrical and water supplies, transport, costs, etc.)

– Licensing procedure started

– Socio-economic studies

• EISS (2002, ~ 10 M€)– Licensing procedure continued

– ITER/site adaptation studies with CTA

– Design of infrastructure

èè All demands fulfilled, costs 1~2 %, strong support from regional authorities

Page 8: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 20018

Euratom

A European site study group is assessing

Cadarache as a potential site for ITER.

A first batch of 13 taskshas been completed this

summer.

A second batch (Licensing + site design) is foreseen

for 2002 – 03No insurmountable

difficulties identified

Task Description of the 13 tasks

TR1 Land

TR2 Seismic Issues and External Hazard Safety

TR3 Heat Sink and Water Supply

TR4 Electrical Supply

TR5 Transport and Shipping

SL1 Review of Accidental and Normal Operation Safety Analysis

SL2 Definition of a Quality Assurance Procedure

SL3 Effluents and releases

SL4 Waste Management and Decommissioning

SL5 Tritium Transport and Control

SE1 Socio-economic Infrastructure

GAC1 Cost Estimate

GAC2 EISS Documentation and Synthesis

Page 9: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 20019

Euratom

Transport of large loads

Page 10: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 200110

Euratom

Planning

'Options de Sûreté’ reportReport preparation

Examination by ASF

ASF adviceRapport Préliminaire de Sûreté

Seismic analysis

Wastes

EffluentsSafety analysis

Transmission to ILE

Public debate

Information

Preparation

Debate

Conclusion

Technical studies

Overall studies

Building designDetailed implantation on site

European site proposal

Setting up of ITER Legal Entity

30/06

27/06

30/06

01/07

01/06

Tri 1 Tri 2 Tri 3 Tri 4 Tri 1 Tri 2 Tri 3 Tri 4 Tri 1 Tri 2 Tri 3 Tri 42001 2002 2003

Page 11: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 200111

Euratom

LayoutITER 40ha

Fence

Durance

A51 Motorway

Tore Supra 11ha

Existing

400kV line

Page 12: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 200112

Euratom

ITER, seen from Cadarache castle

ITER Tore Supra

Page 13: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 200113

Euratom

SUMMARY• Cadarache provides the required nuclear

infrastructure including a large fusion centre with experience of international project construction (JET & Tore-Supra)

• Cost effectiveness– Electricity, full tendering practice, low site

adaptation costs, no extra charge for seismic

• Wonderfully hospitable and attractive region:top class international participation guaranteed!

Page 14: Cadarache: a Site for ITER

J Jacquinot, Fusion Power Associates Annual Meeting and Symposium, Washington 25-26/ 09/ 200114

Euratom

NEXT

• In-depth site studies and licensing are underway. No show stoppers identified

• Official European site designation expected in a few month

• We would love to welcome the world fusion community in Provence