caltrain electrification project update
TRANSCRIPT
Caltrain Electrification Project Update
Spring 2009
General History of ElectrificationInitial Concept Introduced 1998• Caltrain Rapid Rail Study• Caltrain Strategic PlanProject Planning Started 1999• Systems Analysis• Technical Support DocumentationEnvironmental/Conceptual Engineering from 2000-2005• EIR and Alternatives Planning• Preliminary Engineering Studies and DesignsProgram Milestone Update 2006• Amended Scope, Schedule & Budget based upon conceptual
engineering • Caltrain Board presentation April 2006: Reaffirmation of
program priority • Proceeded to Preliminary Engineering phase of project
Electrification Project Characteristics Supports Caltrain’s future operational growth• System will have sufficient power capacity for longer consists on
5-minute headway operations – a primary goal of Caltrain 2025Compatible with regional interfaces• Will enable projects such as Transbay Terminal to be served by
rail• Sufficient clearances for freights and other diesels to operate
normally under the wiresSupports statewide initiatives• Overhead wires will be designed to allow 90 mph operations, with
ability to adjust for 125 mph (California High Speed Rail)
Main Components of ElectrificationTraction Power Supply (TPS)• 25kV ac auto-transformer configuration• 2 main substations at SSF and SJ (115kV utility supply)• 7 paralleling stations, 1 switching station
Overhead Catenary System (OCS)• 4 wire system (messenger, contact, feeder, static)• 30 to 40 ft. high located on outside of tracks (150-200ft apart)• Cantilevers for 2-track areas and headspan arrangements in
multi-track areasCommunications System• Fiber optics to provides communication link for operation of the
electrification system (96 fiber secure ring)• Provides support network for existing and future control and
information systems (10Gb bandwidth and 100 access points)
OCS: two tracks - cantilever arrangement
Minimal visual impact from outside of right of way
OCS: station configuration
Poles integrated into station design to minimize impacts
Terminal Area: multi-track design
Headspan arrangement
OCS: multi-track design
Headspan arrangement
Some right of way modifications and vegetation clearing required
OCS: in open route areas
OCS: on elevated section
Poles integrated into structure or embankment
Electrical Substation
Noise at facility: less than 68 dBA EMF: 5 to 9 mG at perimeter of facility
115kV Utility supply is transformed to 25kV for Railroad use
Fiber Optic network links Control Center with field devices
Integrated SCADA and Communications
Traction Power Site and Catenary System
TPS, OCS and Communications within one system design
Rolling Stock Options – Two AlternativesElectric Multiple Unit (EMU) • Every unit self-propelled • Performance not affected by length
of train • Unaffected by > 2% gradients
Electric Locomotive• One motor unit / 8 coaches• Train lengths affect performance
(acceleration and braking)
Key Impacts and Benefits of ProjectNo Adverse Impacts (EA/EIR)• Visual effect not out of character with existing land uses
Reduced Noise and Vibration• Beneficial to current residents as well as Transit-oriented
Development and the Grand Boulevard vision
Substantially Lower Air Pollutant Emissions• Electric trains are zero emission vehicles• Reduction of up to 90% of particulate and gaseous emissions
Lower Energy Consumption (electric vs. diesel)• Approx 30% savings per year in energy consumed• Regenerative braking provides opportunity for additional savings
of 15-20%
Key Impacts and Benefits of ProjectTravel time reduction due to enhanced acceleration / deceleration characteristics of electric vehicles• Modern, efficient system• Operational flexibility • Stimulates ridership which reduces automobile miles, and
reduces parking demands in SF, SJ and Peninsula cities
Positive Employment Impact• Approximately 1,700 direct construction jobs created and 2,000
additional indirect and induced positions
Electrification Progress to Date• TPS study and electrical simulations completed• OCS conceptual drawings and standards completed• Technical Specs and design criteria completed• Operations and Maintenance analysis report and
estimate completed• Preliminary safety and construction impact analyses
completed• PG&E feasibility study completed• 35% Designs of TPS, OCS, Signals and Communications
plans and specifications completed
Electrification Current Activities
• Coordinating with PG&E for connection to 115kV supply • Request for exemption from existing CPUC General
Orders for 25kV electrification • Updating project schedule and budget based on
35% design• Preparing design packages (OCS, TPS, Signals and
Crossings, Comms) for advancement to RFP for next phase
• Interface of project components with current and futureinfrastructure projects
• Coordinating design with UPRR, VTA, Transbay,CaHSR
Project ScheduleElectric Revenue Service in 2015• Completion of 35% preliminary engineering – Mar 2008• EA/EIR sign off and release to public – early 2009• CPUC exemption for Caltrain 25kV electrification – mid 2009• Coordination of utility supply – late 2008 to early 2010• Detailed design phase – 2009 to 2010 • Construction (OCS, TPS, Signal and Crossing mods, Comms
network) – 2011 to 2013• Testing / Commissioning / System Integration & Start-up –
late 2014• Revenue Service – 2015
Project Estimate (2008 dollars)
San Francisco to Tamien Electrification Systems (TPS and OCS)
– TPS, OCS, Control, Utilities = $452 million
Signal, communications, grade crossing, infrastructure
– Compatibility modifications = $156 million
Total Infrastructure Installation= $608 million
Project Risks and Challenges
• Funding constraints potential to cause project delays • Regulatory support (CPUC, FTA, etc.)• Development pressures along Caltrain RoW• Managing construction under live operations and
community constraints• Coordination with other capital projects and
maintenance activities• Regional agencies and public support