capacity addition planning in the power sector- india

Upload: nitish102

Post on 10-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    1/24

    Capacity Addition Planningin the Power Sector

    Shantanu Dixitwww.prayaspune.org

    [email protected]

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    2/24

    Prayas2

    Interaction plan

    Capacity addition plans e.g Konkan region

    Climate friendly, economic options for meetingenergy services needs

    Indias current capacity addition plans

    Key shortcomings and implications for climate

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    3/24

    ~7,600 MW of new

    generation planned in

    Shahapur Taluka, Dist.

    Raigadh

    ~6,600 MW of new

    generation planned

    in Ratnagiri district

    ~19,000 MW of new

    generation planned in

    the Konkan strip ofMaharashtra

    ~4000 MW of

    existing generation

    in Konkan

    Raigadh : 9,558 km

    Ratnagiri : 8,208 km

    Sindhudurg : 5207 km

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    4/24

    Prayas4

    Interaction plan

    Capacity addition plans e.g Konkan region

    Climate friendly, economic options formeeting energy services needs

    Indias current capacity addition plans

    Key shortcomings and implications for climate

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    5/24

    Prayas5

    Integrated Resource Planning: Case

    studies from India

    DEFENDUS (Karnataka 1990)

    Development Focused End Use oriented ScenarioAmulya Kumar N. Reddy et.al.

    Least Cost Plan (Maharashtra 1994)

    P

    rayas Energy Group

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    6/24

    Prayas6

    Typical Energy Saving Potential(based on Karnataka IRP by Reddy et. Al.)

    End use efficiency savings

    Industry modernisationefficient drives etc: 15-25%

    CFL for lighting : 14-58%

    Solar Water heaters: 28%

    LPG instead of electric stoves: 18%

    Frictionless foot-valves and HDP

    E piping foragirculture pumps: 30%

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    7/24

    Prayas7

    Conclusions of Integrated Plan for

    Maharashtra (Prayas 1993)

    0

    5,000

    10,000

    15,000

    20,000

    0% 20% 40% 60% 80% 100%PLFn (at Bus-bar)

    R

    s/KW(

    Bus-bar)/Yr

    Ind.Co-gen

    Gasifier

    Small hydro

    SugerCo-gen

    CFL

    Loadshift

    CL-light

    T&D impro.

    SWH

    IPS

    Refri.

    HT/LT industry

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    8/24

    Prayas8

    Typical Benefits of IRP

    Typically: efficiency can meet 25-40% andrenewable generation can meet 20-25% ofincremental needs at lower economic costs.

    Maharashtra IRP while meeting same level ofenergy services

    Financial saving - ~ 33% Reduction in incremental fossil fuel consumption - ~

    55%

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    9/24

    Prayas9

    Interaction plan

    Capacity addition plans e.g Konkan region

    C

    limate friendly, economic options for meetingenergy services needs

    Indias current capacity addition plans

    Key shortcomings and implications for climate

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    10/24

    Prayas10

    Capacity Addition: 11th Plan targets

    Projection to add ~ 600 GW in next 25 years

    11

    th P

    lan (2007-12) - 68869 MW 48010 Coal & Lignite, 15585 Hydro, 3160 Nuclear, 2114Gas

    53% Central, 33% State, 14 Private

    + 13,500 MW Renewable, Captive

    Transmission & Distribution to carry this power

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    11/24

    Prayas11

    Drivers

    Growing economy GDP growth from ~ 5 - 6% to 8 - 9%

    Continuing shortages Peak shortage - ~ 12% and energy shortage ~ 8%

    Only 40-50% of targets met in 8,9,10th plans

    Need for greater reliability

    Target of 5% spinning reserves Need to electrify all houses

    44% houses do not have electricity

    About 12000 MW of capacity addition

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    12/24

    Prayas12

    Approach towards meeting energy

    needs

    We do not enjoy the luxury of an either-or choice: Indianeeds energy from all known and likely sources. PrimeMinister of India (Speech at Tarapur Automic Station 31st August 2007, -http://www.rediff.com/news/2007/aug/31guest.htm)

    Ambitious projections for 10 years 100,000 MW Thermal

    50,000 MW Hydro

    11,000 MW Nuclear

    Expanding fuel supply and sources

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    13/24

    Prayas13

    Policy changes to meet capacity

    addition needs

    De-licensing of generation projects

    Merchant plants Captive power plants

    Ultra mega power plants

    Encourage capacity addition through all means

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    14/24

    Prayas14

    Ultra Mega Power Projects

    4000 MW super critical coal thermal plants (5 7plants expected)

    Federal government lead Fiscal incentives, conducting competitive bidding, helped

    evolve power purchase agreement and payment securitymechanism

    Encouraging results for first two projects

    Half a dozen bids for each project Highly competitive tariff

    US cents 2.7 / kWh for pithead project and US cents 5 / kWh forimported coal based project (levalised tariff)

    Both projects won by private sector

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    15/24

    Prayas15

    Ultra Mega Power Projects

    Key Features of UMPPCompetitive Bidding Process Transparent process

    Well laid out procedures and timetable Anonymous comparison of all bids to be made public

    All contracts signed with winning bidder (including PPA) will bepublic

    No uncertainty and little scope for post bid negotiations

    All required inputs and clearances to be provided by specialpurpose vehicle (govt. owned shell company)

    Project contract formats finalized before bidding

    Simple criteria for selection of winner

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    16/24

    Prayas16

    Interaction plan

    Capacity addition plans e.g Konkan region

    Climate friendly, economic options for meetingenergy services needs

    Indias current capacity addition plans

    Key shortcomings and implications for

    climate

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    17/24

    Prayas17

    Capacity addition planning Oblivious

    of key challenges

    Significant over projection

    Even though capacity addition is 40 50% less,shortages have reduced or increased very moderately

    Cap dd Pea Shortage %5 year pla Projected ctual Projected ctual

    0540 4 0 % %

    40 50 0 5 % %

    0 4 0 0 0 % 4%

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    18/24

    Prayas18

    Capacity addition planning Oblivious

    of key challenges

    Economic implications

    11th five yr. plan

    Projected investment need US $ 255 Billion

    Fixed cost of US cents 15 / unit of incrementalsales!

    (v/s current total tariff of around US cents 8 / unit)

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    19/24

    Prayas19

    Social and Environmental issues -1

    Electricity Policy Environment

    Appropriate advance action through EIA and Environment Action Program

    Streamline procedures including setting up of Land Bank and Forest Bank Coal washeries, full compliance with environmental norms

    Demand Side Management, Energy Conservation

    Hydro Policy Proper implementation of National Policy on Rehabilitation and

    Resettlement to ensure that the concerns of project-affected families

    are addressed adequately. Adequate safeguards for environmental protection with suitable

    mechanism for monitoring of implementation of Environmental ActionPlan and R&R Schemes

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    20/24

    Prayas20

    Environment issues -2

    Plans have little details on environment & social impacts Emphasis on speeding up clearance of environmental obstacles No analysis on: How much land required? How many people

    displaced? Livelihood impact? No focus on enhancing the effectiveness through democratisation

    (participatory R&R mention in Transmission Chapter of11th Plan)

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    21/24

    Prayas21

    Salient observations

    Over projection of demand and poorimplementation performance

    Shortage psychosis and exaggerated capacityaddition plans

    Integrated resource planning is avoided

    Climate friendly options, even thougheconomical, are ignored

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    22/24

    Prayas22

    Lesson

    To address climate change issues, improvementin national level planning process is critical.

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    23/24

    The vicious circle

  • 8/8/2019 Capacity Addition Planning in the Power Sector- India

    24/24

    Prayas24

    Indias Capacity Addition Plans

    Year PeakDemand

    GW

    Inst.Cap

    GW

    Remarks

    2007 104 132 14% peak shortage; Coal (54%),Hydro(26),Gas (11), Nuclear(3), Renewable(6)

    2012 158 220

    2022 323 425

    2032 592 778 ~Coal (50%),Hydro (29),Gas (6),Nuclear(12), Renewable (5)

    Source: Integrated Energy Policy, 8% GDP Growth Scenario