OZ MINERALS • PAGE 2
ACQUISTION OF THE CARRAPATEENA
COPPER – GOLD DEPOSIT IN SOUTH AUSTRALIA
• Agreement to purchase Carrapateena
IOCG copper project in March.
• US$250 million, plus US$50 million on
production of copper and uranium,
gold or silver.
Benefits for OZ Minerals:
• Meets strategy: copper, appropriate
production scale potential, favourable
mining jurisdiction, long-life potential.
• Development could be funded from
anticipated Prominent Hill cash flows.
• Offers development, operations,
exploration, logistics and management
synergies.
OZ MINERALS • PAGE 3
-
10
20
30
40
50
60
70
80
90
EV
c/lb
Cu
Eq
Advanced Projects / Producers
COMPETITIVE ACQUISTION
Exploration / Development Construction / Production
OZ
Min
era
ls/
Carr
ap
ate
en
a
OZ MINERALS • PAGE 4
GAWLER IOCG PROVINCE
ANDAMOOKA COMPLEX
• 150km north of industrial centre Port
Augusta
• 100km south-east of Olympic Dam
• Outside Woomera Prohibited Area
• 1,070 sqkm tenements (838 sqkm main)
• Olympic Dam – Total Mineral Resource
9,080 Mt at 0.87% Cu, 0.027% U3O8, 0.32
g/t Au and 1.5 g/t Ag (PIRSA)
• Prominent Hill – Total Mineral Resource
285 Mt at 0.90% Cu, 0.8 g/t Au (ASX
release 09/11/2010)
-27 °
13
2 °
13
5 °
-30 °
-36 °
-33 °
13
8 °
Coober Pedy
Inferred margin of the
Gawler Craton
Marla
CHALLENGERCHALLENGERCHALLENGERCHALLENGERCHALLENGERCHALLENGERCHALLENGERCHALLENGERCHALLENGER
Streaky Bay
Ceduna
Tarcoola
Marree
Oodnadatta
PROMINENT HILLPROMINENT HILLPROMINENT HILLPROMINENT HILLPROMINENT HILLPROMINENT HILLPROMINENT HILLPROMINENT HILLPROMINENT HILL
Leigh Creek
OLYMPIC DAMOLYMPIC DAMOLYMPIC DAMOLYMPIC DAMOLYMPIC DAMOLYMPIC DAMOLYMPIC DAMOLYMPIC DAMOLYMPIC DAM
Port Augusta
Kangaroo Is.
Port Lincoln
ADELAIDE
Moonta
Wallaroo
Port PirieWhyalla
Port Wakefield
CARRAPATEENA
OZ MINERALS • PAGE 5
DISCOVERY IN 2005
DISCRETE MAGNETIC AND GRAVITY ANOMALY
200km
CAR01
CAR02
CAR01 -
no significant mineralization
CAR02 -
68m @ 3.0%Cu, 0.4g/t Au
from 476m
OZ MINERALS • PAGE 6
CARRAPATEENA CROSS SECTION –
BASIC GEOLOGY
• 500m of sedimentary cover
• IOCG system extending to 1500m below surface:
• Complex hematite breccias hosted in sericite-
chlorite altered granites
• Two high grade bornite dominated pods surrounded
by a lower grade chalcopyrite dominated shell
OZ MINERALS • PAGE 7
CARRAPATEENA CROSS SECTION –
6543300N LOOKING NORTH • CAR051W1 – 903m @ 2.15% Cu, 0.66 g/t Au from 608m
(incl. 169m @ 4.30% Cu, 0.74 g/t Au from 1174m).
• CAR050 – 905m @ 2.08% Cu, 0.98 g/t Au from 487m (incl.
75m @ 4.63% Cu, 1.10 g/t Au from 1203m).
±50m view
Bornite shell in blue
Chalcopyrite shell in yellow
0.5 – 1% Cu
1 – 2% Cu
2 – 3% Cu
>3% Cu
Cu values
PLAN N
-500
-1000
-1500
OZ MINERALS • PAGE 8
• CAR073 – 905m @ 2.17% Cu, 0.89g/t Au from 506m
(incl. 82m @ 4.78% Cu, 1.13 g/t Au from 518m)
• CAR031W1 – 410m @ 1.88% Cu, 1.20 g/t Au from
582m (incl. 134m @ 2.85% Cu, 1.48g/t Au from 858m)
-500
-1000
-1500
CARRAPATEENA CROSS SECTION –
6543400N LOOKING NORTH
PLAN N ±50m view
Bornite shell in blue
Chalcopyrite shell in yellow
0.5 – 1% Cu
1 – 2% Cu
2 – 3% Cu
>3% Cu
Cu values
OZ MINERALS • PAGE 9
CARRAPATEENA - CORE PHOTOS
CAR051 Chalcopyrite Mineralisation CAR061 Bornite Mineralisation
OZ MINERALS • PAGE 10
INITIAL INFERRED RESOURCE TO SOUTH
0m 250m
Mineralisation not well
understood, potential for
extension to the east
Exploration &
Inferred Resource
status area
Exploration area
Chalcopyrite shell
in yellow
Exploration & Inferred
Resource status area
Exploration area
Historic drillhole collar
Historic drillhole trace
N
0m 250m
Main deposit
Potential for
extension at depth Mineralisation
open to the east
Target range:
25-45Mt @ 1% Cu,
0.4g/t Au, 140ppm
U3O8, 4g/t Ag
Inferred resource:
203Mt @ 1.31% Cu,
0.56g/t Au, 270ppm
U3O8, 6g/t Ag
OZ MINERALS • PAGE 11
CARRAPATEENA DEPOSIT LOOKING WEST
Chalcopyrite shell
in yellow
Exploration & Inferred Resource status area
Exploration area
0m 250m
Mineralisation
deepens to the
south
Exploration & Inferred
Resource status area Exploration area
Target range:
25-45Mt @ 1% Cu,
0.4g/t Au, 140ppm
U3O8, 4g/t Ag
Inferred resource:
203Mt @ 1.31% Cu,
0.56g/t Au, 270ppm
U3O8, 6g/t Ag
OZ MINERALS • PAGE 12
CURRENT STATUS
• Native title agreement reached
for exploration activity.
• Exploration drilling
commenced.
• Exploration camp construction
underway.
• Northern target-area first
exploration priority.
• Infill of southern area.
• Scoping studies commencing.
OZ MINERALS • PAGE 14
SCOPING STUDY – MINING CONCEPTS
• Scoping studies commencing.
‒ Mining options: sublevel open
stoping, sublevel caving, block
caving and hybrid.
‒ Mining inventories and rates being
developed.
‒ Production schedules/early stage
costs being investigated
‒ Infrastructure options
Lower mining costs
Lower development costs
<$10/t $10-20/t $20-50/t
Block caving
Sublevel caving
Sublevel open stoping
OZ MINERALS • PAGE 15
CONCEPTUAL PROJECT TIMELINE
2011 2012 2013 2014 2015 2016 2017
Exploration drilling to complete initial
Inferred Resource, 10,000m
Option studies for mining
Phase II exploration drilling to move to
Indicated Resource
Geotechnical drilling
Pre-feasibility
Exploration shaft
Feasibility study
Construction