case study: simplified la of uildings with … · 1 case study: simplified la of uildings with...

4
1 Case Study: SIMPLIFIED LCA OF BUILDINGS WITH “PASSIVHAUS” STANDARD, by CONSTRUCCIONES URRUTIA Construcciones URRUTIA S.A. is a construction company, constituted in Vitoria – Gasteiz in 1972, although its origins date back to 1939. For over seven decades it has participated in all kinds of constructing projects. The keys to its long history and the satisfaction of its clients, have been the professionalism of its staff, its flexibility and adaptability. URRUTIA has specialized in advising and constructing ”Passivhaus” or passive houses, becoming the first developer in the Basque Country and Spain to build on this standard. Description of the company For these two indicators an analysis of the existing tools in the market was carried out, then the staff was trained in the chosen tool: E2CO2cero. After an initial application of the tool to a pilot project from the PASSIV buildings portfolio allowing to analyze different constructing solutions. Short description of the project Key Objectives of the Project The project consisted of the evaluation of the environmental impact generated by the predevelopment of USE and MAINTENANCE of a set of buildings from which we already knew the impact during the use and maintenance through the PASSIVHAUS standard. URRUTIA had a portfolio of buildings which met this demanding standard, and its interest was to expand the analysis to other phases of the life cycle of the building. It was decided that they were going to address the two most significant phases – election of material and execution of work – by studying two indicators: EMBEDDED ENERGY and CARBON FOOTPRINT Timeline Simplified LCA to estimate energy efficiency, reduction of energy use through every stage of the building’s life cycle. LC Approach used in the Project Sector 1 st July 2015 - 31 st March 2016 Aware of the environmental responsibility that causes the development of its activities, URRUTIA has been certified by international standard ISO 14001 pledging to work for continuous improvement, through the identification and assessment of environmental objectives in its projects. Motivation Factors Adelina Uriarte Construcciones URRUTIA, S.A (SME) Estibaliz Uriarte - Construcciones URRUTIA, S.A (SME) Ana Belen de Isla – LKS Ingenieria (Coach) Eugenia Atin – Prospektiker (LCiP Project) Olatz Errazkin Prospektiker (LC Champion Project team

Upload: lamdang

Post on 11-May-2018

219 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Case Study: SIMPLIFIED LA OF UILDINGS WITH … · 1 Case Study: SIMPLIFIED LA OF UILDINGS WITH “PASSIVHAUS” STANDARD, by CONSTRUCCIONES URRUTIA Construcciones URRUTIA S.A. is

1

Case Study: SIMPLIFIED LCA OF BUILDINGS WITH “PASSIVHAUS” STANDARD, by CONSTRUCCIONES URRUTIA

Construcciones URRUTIA S.A. is a construction company, constituted in Vitoria –

Gasteiz in 1972, although its origins date back to 1939. For over seven decades it

has participated in all kinds of constructing projects.

The keys to its long history and the satisfaction of its clients, have been the

professionalism of its staff, its flexibility and adaptability. URRUTIA has specialized

in advising and constructing ”Passivhaus” or passive houses, becoming the first

developer in the Basque Country and Spain to build on this standard.

Description of

the company

For these two indicators an analysis of the existing tools in the

market was carried out, then the staff was trained in the chosen

tool: E2CO2cero. After an initial application of the tool to a pilot

project from the PASSIV buildings portfolio allowing to analyze

different constructing solutions.

Short

description of

the project

Key

Objectives of

the Project

The project consisted of the evaluation of the

environmental impact generated by the

predevelopment of USE and

MAINTENANCE of a set of buildings from

which we already knew the impact during the

use and maintenance through the

PASSIVHAUS standard.

URRUTIA had a portfolio of buildings which

met this demanding standard, and its interest

was to expand the analysis to other phases

of the life cycle of the building. It was decided

that they were going to address the two most

significant phases – election of material and

execution of work – by studying two

indicators: EMBEDDED ENERGY and

CARBON FOOTPRINT

Timeline

Simplified LCA to estimate energy efficiency,

reduction of energy use through every stage

of the building’s life cycle.

LC Approach

used in the

Project

Sector 1st July 2015

-

31st March 2016

Aware of the environmental responsibility

that causes the development of its activities,

URRUTIA has been certified by international

standard ISO 14001 pledging to work for

continuous improvement, through the

identification and assessment of

environmental objectives in its projects.

Motivation

Factors

• Adelina Uriarte – Construcciones

URRUTIA, S.A (SME)

• Estibaliz Uriarte - Construcciones

URRUTIA, S.A (SME)

• Ana Belen de Isla – LKS Ingenieria

(Coach)

• Eugenia Atin – Prospektiker (LCiP Project)

• Olatz Errazkin – Prospektiker (LC

Champion

Project team

Page 2: Case Study: SIMPLIFIED LA OF UILDINGS WITH … · 1 Case Study: SIMPLIFIED LA OF UILDINGS WITH “PASSIVHAUS” STANDARD, by CONSTRUCCIONES URRUTIA Construcciones URRUTIA S.A. is

2

Case Study: SIMPLIFIED LCA OF BUILDINGS WITH “PASSIVHAUS” STANDARD, by CONSTRUCCIONES URRUTIA

The main difficulty of the project has been the

necessity to identify a tool which allows to obtain these

indicators from the materials incorporated into work.

The buildings incorporate several thousand materials

and it was vital to locate and handle an extensive

database of building materials and to give information

about the embedded energy and carbon footprint of

each material and each construction process. Once

E2CO2cero was chosen as the tool to use, the staff

was trained on its use and they started to apply it to

URRUTIA’s construction projects.

Implementation

challenges /

lessons learnt

Expected

Impact

Results of the

project

Throughout the project three meetings have been held with the coach to define the targets, the tool and the

methodology. We have obtained CO2 and embedded energy indicators of six PASSIV buildings, allowing URRUTIA

to identify the chapters and materials of greatest environmental impact. It has also allowed to compare between

different key materials in the energy performance of the building, for instance thermal insulation materials or exterior

carpentry.

The project has extended URRUTIA’s LCA methodology, focused on use and maintenance phase, to other phases

with a significant potential impact to extend the energy efficiency policy and commitment to sustainable development

at the entire life cycle of the building. Two basic indicators ware chosen: EMBEDDED ENERGY and CARBON

FOOTPRINT. By embedded energy we understand the total amount of energy consumed for the construction of the

building. It contemplates the energy used in the manufacturing process, the energy used for the transportation of

materials and the energy used by the machinery in the execution of the different work units. The carbon footprint of a

building quantifies the total of greenhouse gasses (GHG) emitted as a result of the construction of said building

measured as the equivalent CO2 mass.

Description of

the Project

Environmental Impact

The pilot application of the tool in the real PASSIV projects allowed

to prove that the embedded energy and carbon footprint in a

passive building were larger, but it is more than compensated in

the use and maintenance phase.

When we were starting the project, we got the information from an

international study of the carbon footprint and embedded energy in

buildings and the result was the same. Passive buildings have a

greater carbon footprint and embedded energy during

construction, but it compensates during the use of said building.

Page 3: Case Study: SIMPLIFIED LA OF UILDINGS WITH … · 1 Case Study: SIMPLIFIED LA OF UILDINGS WITH “PASSIVHAUS” STANDARD, by CONSTRUCCIONES URRUTIA Construcciones URRUTIA S.A. is

3

Case Study: SIMPLIFIED LCA OF BUILDINGS WITH “PASSIVHAUS” STANDARD, by CONSTRUCCIONES URRUTIA

Description of

maturity in LC

approaches

before the

project

CONSTRUCCIONES URRUTIA is ISO

14001 certified and sustainability has

always been important, that is why they

have a line of work with “passiv” housing.

However, before the project they had

never quantified the energy savings nor

the life cycle of the “passiv” projects vs.

traditional projects.

Description of

maturity in LC

approaches

after the

project

Maturity and Strategy

Following the completion of the pilot

project, CONSTRUCCIONES URRUTIA

has access to a tool for simplified LCA

(E2CO2cero), 2 people have been trained

to use the tool and now they are able to

quantify the benefits of certain materials

and activities that make a house "passiv".

Page 4: Case Study: SIMPLIFIED LA OF UILDINGS WITH … · 1 Case Study: SIMPLIFIED LA OF UILDINGS WITH “PASSIVHAUS” STANDARD, by CONSTRUCCIONES URRUTIA Construcciones URRUTIA S.A. is

4

Case Study: SIMPLIFIED LCA OF BUILDINGS WITH “PASSIVHAUS” STANDARD, by CONSTRUCCIONES URRUTIA

This project is a step forward in URRUTIA’s path, which serves to strengthen the path chosen in 2003 with the

certification ISO 14001 and later with the PASSIV project analyzing the environmental impact of these projects in the

entire life cycle of the building.

Environmental Standpoint

The results show that the embedded energy and carbon footprint of a passive building is greater than that of a usual

building, but it compensates during the using phase of the life cycle. However, that does not mean that every effort

made to reduce that environmental impact is useless. EDPs can be a very useful tool as they allow comparisons and

not just make energy efficient buildings, but also use products which will cause a lesser environmental impact.

Evaluation of

the project

Economic

feasibility:

expected ROI

and payback

periods

The software tool used has an annual cost of under 100€ and the time needed for each analysis and study of each

project can be of around 4-5 hours, which means we are talking about an investment so small in quantity that there

is no need for a payback study.

Adelina Uriarte

Estibaliz Uriarte

[email protected]

www.construccionesurrutia.com

Coach:

Ana Belén de Isla. LKS INGENIERIA

[email protected]

LCiP Project: Eugenia Atin

([email protected])

LC Champion: Olatz Errazkin

([email protected])

LCiP website:

www.lifelcip.eu

Planned follow

up activities CONSTRUCCIONES URRUTIA is going to

do the simplified LCA of all the construction

projects of dwellings, not only “passivhaus”

houses but all of them. The more projects we

have to compare, the better, and then

URRUTIA can make informed decisions

concerning materials (insulation, carpentry,

etc.) taking into account the complete life

cycle of those materials and the building

itself.

Links and

contacts for

further

information

This project has been funded with support from the LIFE+ Programme of the EU. The views expressed here

are purely the authors’ own and the Commission cannot be held responsible for any use which may be made

of the information contained herein.

Icons made by Freepik from www.flaticon.com